PCB 03-027 Order 09/05/02
DYNEGY MIDWEST GENERATION (BALDWIN POWER STATION) v. ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
Upon receipt of an Illinois Environmental Protection Agency recommendation, the Board granted this facility, located in both St. Clair and Randolph Counties, a 45-day provisional variance, subject to conditions, from the effluent limits set forth in 35 Ill. Adm. Code 304.141(b) and its National Pollutant Discharge Elimination System permit number IL0000043.
Handle: Document-27446
Owner: Brown, Don (User-14, brownd:DocuShare)DS
Monday, September 9, 2002 02:41:59 PM CDT
Tuesday, September 10, 2002 01:06:08 PM CDT
Modified By:
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
September 5, 2002DYNEGY MIDWEST GENERATION(BALDWIN POWER STATION),Petitioner,v.
  • ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
  • Such provisional variances shall
be issued within 2 working days of notification from the Agency.
  • 2) During the provisional variance period, Dynegy shall meet a total suspended
solids limit of 50 mg/L monthly average and a sampling frequency of once perweek using a 24-hour composite.
  • IT IS SO ORDERED.
  • If Dynegy chooses to accept this provisional variance, it must execute a Certificate of
Acceptance of all terms and conditions of this provisional variance and, within 10 days afterthe date of the above o...