PCB 87-154 02/04/88 Opinion and Order
KING-SEELY THERMOS COMPANY v. ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-25764
Owner: Site Administrator (User-2, admin:DocuShare)DS
Wednesday, June 12, 2002 10:17:30 AM CDT
Wednesday, June 12, 2002 10:18:58 AM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
February 4, 1987KING-SEELY THERMOS COMPANY,Petitioner,v.
  • ) PCB 87—154
ILLINOIS ENVIRONMENTAL ) PROTECTION AGENCY, ) Respondent.
  • Petitioner seeks a variance from the 3.0 lb/gal.
  • The current system
utilizes a wet paint process whereby the transfer of paint isaccomplished using volatile organic materials.
  • The dry paint process will account for 57 of the
proposed new system; the remaining 43 will be applied with a VOMcompliant wet paint with final VOM emission levels less than 3.0lb/gal.
  • Petitioner considered combining new equipment with certain
existin...