PCB 00-226 08/24/00 Order
EQUILON ENTERPRISES L.L.C. v. ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-2439
Owner: Site Administrator (User-2, admin:DocuShare)DS
Wednesday, April 4, 2001 04:09:53 PM CDT
Wednesday, December 26, 2001 03:01:22 PM CST
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
August 24, 2000EQUILON ENTERPRISES L.L.C.,Petitioner,v.
  • ILLINOIS ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
  • The Board accepts this matter
for hearing.
  • Hearings shall be scheduled and completed in a timely manner pursuant to the applicable statutory decision
deadline or as extended by waiver.
  • Unless otherwise ordered by the hearing officer, the Agency shall file the record of its review of the CAAPP permit
application within 30 days after service of the petition.
  • I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that the above order was
adopted on the 24th day of August 2000 by a vote of 7-0.Dorothy M. Gun...
Allowed
Adobe Portable Document Format (.pdf) - application/pdf
00-226082400.pdf
4
8509
No
Appears In: PCB 00-226
Preferred Version: PCB 00-226 08/24/00 Order