September 13, 1990PETER ARENDOVICHPATRICIA LISTEPNANNComplainants,V.
) PCB 88—127
(Enforcement)KOPPERS COMPANY, INC., ) Respondent.
Repairs and modifications that have been completed include the
repair or replacement of hatches and vents on a number ofsystems, the renovation of the distillation vacuum system, andthe installation of inert gas purge systems to reduce vaporemissions during the cleaning of transmission lines.
This Final
Order does not preclude other enforcement actions being broughtagainst Koppers if the violations continue.
Coat Tar Feed Tanks Investigated feasibility of connecting
tanks ...