  • ILLINOIS POLLUTION CONTROL BOARD
May 9, 1991JOHN DEERE TECHNICAL CENTER,Petitioner,V.
  • ) PCB 91—76
(Provisional Variance)ILLINOIS ENVIRONMENTALPROTECTION AGENCY, Respondent.
  • Adm.
  • Code 722.134(b).
  • Upon receipt of the request the Agency issued its
recommendation, finding that the hazardous wastes must remain on—site for longer than 90 days due to unforeseen, temporary anduncontrollable circumstances and failure to grant the requested30—day provisional variance would impose an arbitrary orunreasonable hardship on Petitioner.
  • lll~,pars. 1035(b) & (C). In provisional variances it
is the responsibility of the Agency to make the technicaldeterminations and findin...