  • ILLINOIS POLLUTION CONTROL BOARD
April 21, 1994STEWART WARNER, Petitioner,V.
  • ) PCB 94—130
(Provisional Variance)ILLINOIS ENVIRONMENTAL ) PROTECTION AGENCY, )) Respondent.
  • Pursuant
to Section 35(b) of the Act, the Board must issue the variancewithin two (2) days of this filing.
  • Upon receipt of the request, the Agency issued its
recommendation, notifying the Board that due to unforeseen,temporary and uncontrollable circumstances, failure to grant therequested thirty (30)-day provisional variance would impose anarbitrary or unreasonable hardship on the petitioner.
  • The Board’s responsibility
is to adopt a formal or...