R 92-017 12/02/93 Opinion and Order
IN THE MATTER OF: PETITION OF THE U. S. ARMY ENGINEER DISTRICT, ROCK ISLAND, FOR A DREDGED MATERIAL PLACEMENT REGULATION APPLICABLE TO THE ILLINOIS RIVER/ WATERWAY BETWEEN LA GRANGE LOCK AND DAM (MILE 80.2) AND LOCKPORT LOCK (MILE 291) : 35 ILL. ADM. CODE 303.400
Handle: Document-19600
Owner: Site Administrator (User-2, admin:DocuShare)DS
Friday, April 26, 2002 02:18:18 PM CDT
Monday, October 18, 2004 01:49:48 PM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
December 2, 1993IN THE MATTER OF: ) PETITION OF THE U.S.
  • ARMY ENGINEER ) R92-17
DISTRICT, ROCK ISLAND, FOR A DREDGED ) (Rulemaking)MATERIAL PLACEMENT REGULATIONAPPLICABLE TO THE ILLINOIS RIVER! 1 The “Illinois Waterway” is defined statutorily in theIllinois Waterway Act at 615 ILCS 10/1 as a waterway fromLockport to a point on the Illinois River near Utica.
  • Public hearings were held before Hearing Officer Michelle C.
  • Dresdow on June 22, 1993 in Peoria, Illinois, and on June 23,
1993 in Morris, Illinois5.
  • ~ The Agency’s response was submitted as one of the
documents w...
Allowed
scantmp1
Adobe Portable Document Format (.pdf) - application/pdf
R 92-017 12_02_93 Opinion and Order.pdf
4
1232433
No
Appears In: R 92-017
Preferred Version: R 92-017 12/02/93 Opinion and Order