February 7, 1980IN THE MATTER OF: R77—15, R78—14,SULFUR DIOXIDE AND PARTICULATES ) R78—15, R78~16,REGULATIONS, RULES 204(c)(1)(A) ) R78—17AND (D) AND RULE 203(g) (1) OFCHAPTER 2ORDER OF THE BOARD (by Mr.
The limitation happens to be the same one
sought by Bemis Company, Inc.
Therefore, although the motion is granted, the requested
relief of considering the limitation Celotex seeks for itsPeoria facility as a “regulatory proposal” is not given j~ se.
But the INR is not required to conduct a study for every
site—specific limitation sought thereafter within the same proceeding.