July 23, 2009AMEREN ENERGY GENERATINGCOMPANY and VENICE POWER PLANT,Petitioners,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
Pet.
at 3-8.
Ameren challenges the inclusion of these conditions and
asks the Board to stay their effect until ultimately ruling on the merits.
at 3, see Exh.
2. Exhibit 2 to the petition is a “redlined” version of the permit that indicates the conditions orparts of the conditions Ameren seeks to stay. 2In Community Landfill Co. and City of Morris v. IEPA, PCB 01-48, 01-49, slip op. 2.The Board grants the requested partial stay and permit conditions 3.2.1, 4.0, 5.6.2, 5.7.2,5.9.2, 7.1.3(f), 7.2.3( e)...