  • ILLINOIS POLLUTION CONTROL BOARD
May 7, 2009UNION ELECTRIC COMPANY d/b/aAMERENUE and KINMUNDY POWERPLANT,Petitioner,v.
  • ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
  • Adm.
  • Code 105.Subpart C.
  • In this case, the Agency granted a CAAPP renewal permit, subject to
conditions, for Union Electric’s Raccoon Creek Power Plant.
  • 35 Ill. Adm. Code 101.500(d).
The Board accepts the petition for hearing. 6, 2001), aff’d sub nom. Unless the Board or the hearing officer orders otherwise, the Agency must file an answer,including the entire record of its determination within 30 days after it is served with the petition.