March 5, 1998COUNTY OF BOONE, a bodycorporate and politic, and the CITYOF BELVIDERE, a municipality,Petitioners,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
The Agency requested the extension “to April 15, 1998, or
any other date not more than a total of 90 days from the date of the Agency's finaldetermination.”Section 40(a)(1)of the Act, which governs the appeal process, provides:the 35-day period for petitioning for a hearing may be extendedfor a period of time not to exceed 90 days by written noticeprovided to the Board from the applicant and the Agency withinthe initial appeal period.