  • ILLINOIS POLLUTION CONTROL BOARD
January 9, 1992THE PUMPER, INC., )) Petitioner, ) V.
  • ) PCB 91—262
) (Underground StorageILLINOIS ENVIRONMENTAL ) Tank Reimbursement)PROTECTION AGENCY, ) Respondent.
  • Any briefing schedule shall provide for final filings as
expeditiously as possible and in no event later than 70 days fromthe date of this Order.
  • That Order shall set a date certain
for each aspect of the case including: briefing schedule,hearing date(s), completion of discovery (if necessary) and prehearing confere...