)) ENVIRONMENTAL PROTECTION AGENCY ) ORDER OF THE BOARD (BY SAMUEL T.
LAWTON, JR.):
IT IS THE ORDER of the Pollution Control Board:1.
Petitioner, RR.
11. This variance is in contemplation of a further petition
for variance based upon said schedule indicating completion and compliance by July 30, 1974. 2. Petitioner is granted variance from the project completionschedule requirements of Rule 103(b) (6) (e) of the Air Pollution ControlRegulations, to allow application for instal...