  • ILLINOIS POLLUTION CONTROL BOARD
August 8, 1974WEBER MARKING SYSTEMS, INC.,Petitioner,v.
  • PCB 74—172
ENVIRONMENTAL PROTECTION AGENCY,Respondent.
  • A letter of April 29, 1974, from the
installation contractor, Hydronics Piping Corporation, indicatesthat the delay in completion date is caused by slow delivery ofessential materials.
  • The Agency Motion to Dismiss was based on their belief, stated
in item 3, that “to date, no stipulation has been filed” by thePetitioner in response to the Board Order of May 9, 1974.
  • On August 7 the Agency filed a Motion to Dismiss,
stating “Petitioner’s solvent recovery system was operating byJuly 15, 1974, and has brought Petitioner’s facility ...