April 4, 1975UNION CARBIDE CORPORATION,Petitioner,vs.
Petitioner now seeks
variance from Rules 103(b) (2) and 203(a) until June 1, 1975.
Pursuant to the conditions expressed in the Board Order in
PCB 73-313, Union Carbide submitted and received Agency approvalof its Compliance Plan and Project Completion Schedule forbringing this facility into compliance.
The investigator was informed that
Unit #1 will tie into the settling chamber on March 20, 1975and Unit #2 will tie in on June 1, 1975.
ORDER
It is the Order of the Pollution Control Board that UnionCarbide Corporation is granted variance from Rules 103(b) (2)and 203(a) of the Air Pollu...