January 8, 1976PEOPLE OF TIlE STATE OF ILLINOIS,Complainant,v.
) PCB 75-72
CITIZENS UTILITIES COMPANY OFILLINOIS, an Illinois corporation,Respondent.
A pre—hearing
conference was held July 29, 1975 at which time the partiesadvised the Hearing Officer that settlement negotiations werein progress.
As a result of the
inspection was a determination that a gravity-flow sewer mainbetween Westhaven and Fernway Subdivision was not in satisfactorycondition and it was replaced by a temporary fbrce main and liftstation during June 1973 (Stip.
p.
3); $33,000.00 for visual and
television inspection and cleaning of the system (Stip. ORDER1...