June 18, 1976LEHIGH PAVING COMPANY, )) Petitioner,V.
) PCB 76—94
ENVIRONMENTAL PROTECTION AGENCY, ) Respondent.
Koch Engineering Company (Koch) is the
manufacturer of the control equipment to be installed.
The production schedule is limited due
to weather conditions (Agency Recommendation at 2).
As
Lehigh cannot install the equipment and make asphalt pavingat the same time, timing in July, a good weather month,would be critical to Petitioner’s business.
This allows
Petitioner time to install the equipment and guarantee itsoperation for the 1977 season. The Board finds that such a limitation would be inappro...