January 23, 1997ILLINOIS POWER COMPANY, an IllinoisCorporation (Unit 2 - Baldwin Power Station),Petitioner,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
On
October 24, 1996 the Agency filed a motion to extend time to file a cross-motion for summaryjudgment in response to Illinois Power's motion for summary judgment.
Therefore Illinois Power's amended motion for summary judgment is granted and the Agency'
cross-motion is denied.
This standard of review was discussed in
Browning-Ferris Industries of Illinois, Inc.
In
this case, petitioner has the burden of demonstrating that approval of the operating permitrevisions without the...