PCB 00-088 11/18/99 Order
CATERPILLAR, INC, (Mossville Engine Center) v. ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-3274
Owner: Site Administrator (User-2, admin:DocuShare)DS
Thursday, April 5, 2001 08:42:34 AM CDT
Monday, January 7, 2002 12:40:59 PM CST
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
November 18, 1999CATERPILLAR, INC, (Mossville EngineCenter),Petitioner,v.
  • ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
  • In making
its recommendation, the Agency states that failure to grant the requested provisional variance for 45days will result in an arbitrary or unreasonable hardship on the petitioner.
  • The provisional variance is granted, subject to the following conditions:
1.
  • The variance shall begin on the date (on or about January 10, 2000) when petitioner
begins bypassing the existing tertiary gravity filters and shall continue for 45 days or untilthe installation of the new Gravisand Traveling Bridge filters is completed,...
Allowed