PCB 77-349 04/13/78 Opinion and Order
CENTRAL ILLINOIS UTILITY COMPANY v. ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-32336
Owner: Site Administrator (User-2, admin:DocuShare)DS
Monday, January 6, 2003 03:50:39 PM CST
Wednesday, May 28, 2003 02:20:58 PM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
April 13, 1978CENTRAL ILLINOIS UTILITY COMPANY,Petitioner,V.
  • ) PCB 77—349
ENVIRONMENTAL PROTECTION AGENCY,Respondent.
  • Oak Run is projected to contain 2500 lots
and is expected to grow at the rate of 25 houses per year.
  • Consequently a delayed
compliance date of January 1, 1978 was adopted to giveaffected communities enough time to evaluate alternativesfor compliance.
  • The record in this proceeding, however,
justifies a diversion from the Board’s position.
  • Consequently, the January 1, 1981 date
will be honored in this Variance since it represents theextent of Federal authority.
Allowed