August 3, 1978COMMONWEALTH EDISON COMPANY,Petitioner,v.
) PCB 77—201
ENVIRONMENTAL PROTECTION AGENCY,Respondent.
(B) Edison shall execute the revised compliance
plan for Powerton Station asoutlined in its March 17, 1978 amendedpetition for variance, which p~titionisincorporated by reference as if fullyset forth herein.
CE) Within 45 days of the adoption of this
Order, the Commonwealth Edison Companyshall execute and forward to the IllinoisEnvironmental Protection Agency, 2200Churchill Road, Springfield, Illinois62706 a Certification of Acceptance andAgreement to be bound to all terms andconditions of this Order.
SIGNED____...
Allowed