View Properties

PCB 79-101 08/09/79 Order
ALLIED CHEMICAL CORPORATION v. ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-31682
Owner: Site Administrator (User-2, admin:DocuShare)DS
Tuesday, December 24, 2002 03:07:18 PM CST
Monday, June 2, 2003 01:55:08 PM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
August 9, 1979ALLIED CHEMICAL CORPORATION,Petitioner,v.
  • ) PCB 79—101
ENVIRONMENTAL PROTECTION AGENCY,Respondent.
  • Under
Procedural Rule 406 the response was due on July 14, 1979.
  • However, the
waiver has extended the time for decision only from September 6to September 20.
  • The motion will be conditionally granted.
  • The
Board will consider the response if it is filed before August 16,1979 and if it is accompanied by a waiver of decision throughOctobcr 4, 1979.