  • ILLINOIS POLLUTION CONTROL BOARD
September 23, 1999COMMONWEALTH EDISON COMPANY (DresdenPower Station),Petitioner,v.
  • ILLINOIS ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
  • The Board grants petitioner a provisional variance from: (1) 35 Ill.
  • 2.
  • During the term of this provisional variance petitioner’s maximum temperature rise at the edge
of the mixing zone shall be limited to 10.6 degrees Fahrenheit and the maximum temperaturedischarge at the outfall to the river shall not exceed 112 degrees Fahrenheit.
  • A written summary of this data shall be submitted to the
2Agency within 30 days after the variance period is completed. Section 41 of the Environmental Protection Act (41...