November 15, 1979VILLAGE OF ROUND LAKE PARK,Petitioner,v.
) PCB 79—178
ENVIORNMENTAL PROTECTION AGENCY, ) Respondent.
Petitioner originally
had an agreement with Lake County in which the County was toconstruct an interceptor and trunk sewer to transport Petitioner’ssewage to a new regional treatment plant to be constructedby the Village of Fox Lake.
Without the variance, it is claimed that the Petitioner
and Unity Ventures, Inc.
Rather than grant relief for five years as
Petitioner has requested, the Board will limit the varianceto the same terms as Bloomingdale for consistency.
This 45 day period
shall be...
Allowed