  • ILLINOIS POLLUTION CONTROL BOARD
December 20, 1990INDIAN REFINING, ) Petitioner, ) v.
  • ) PCB 90—241
(Provisional Variance)ILLINOIS ENVIRONMENTAL ) PROTECTION AGENCY, ) Respondent.
  • This provisional
variance follows one granted the Petitioner on November 8, 1990for the same matter from November 15, 1990 to December 15, 1990.
  • Each day of
delay in startup would cost Indian Refining an economic loss of$130,000.
  • Upon receipt of the request, the Agency issued its
recommendation, finding that due to unforeseen, temporary anduncontrollable circumstances, failure to grant the requested 30—d...
Allowed