February 21, 1980SANITARY DISTRICT OF DECATUR,Petitioner, PCB 79~250ENVIRONMENTAL PROTECTION AGENCY,Respondent.
Reasonably consistent operation of the
equipment was achieved in 1979,Heavy industrial overloading of the main treatmentplant caused or contributed to operational odors and BODand suspended solid levels exceeded those levels containein Petitioner~sNPDES permit.
It is estimated that Step
2 funding will not be received for at least a year.
However, because of the problems in getting the UNOX system
to operate correctly, the Board will grant the variancerequested for HOD5 and suspended solids.
4, The Petitioner shall dili...