February 7, 1980ARTHUR LIGHT, Petitioner, PCB 79—172ENVIRONMENTAL PROTECTION AGENCY, ) RespondentOPINION OF THE BOARD (by Mr.
No hearing was
held.
On January 24, 1980 the Board granted Petitioner a
variance from the 120 day requirement in PCB 78—30 providedthat cover be applied and an operating permit he obtained byMarch 31, 1980, If the March 31, 1980 deadline is missed,Petitioner shall cease operations.
As insurance to
force timely compliance, the Agency requested that a $5,000performance bond be posted.
While the Board has not seen fit to require a
performance bond, Petitioner should understand that he mus...