ILLINOIS POLLUTION CONTROL BOARD
May 7, 2009
CITY OF JOLIET,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 09-25
(Permit Appeal - Water)
ROY M. HARSCH OF DRINKER BIDDLE & REATH LLP APPEARED ON BEHALF OF
PETITIONER; and
GERALD T. KARR, SENIOR ASSISTANT ATTORNEY GENERAL, APPEARED ON
BEHALF OF RESPONDENT.
OPINION AND ORDER OF THE BOARD (by G.T. Girard):
The City of Joliet (Joliet) has petitioned the Board for review of an Illinois
Environmental Protection Agency (IEPA) decision denying Joliet’s request to modify a permit
condition. Joliet’s current permit allows for the agricultural land application of Joliet’s sewage
sludge, subject to a condition that limits the increase in soil concentrations of radium resulting
from the addition of Joliet’s sludge. Specifically, Joliet sought to augment, from 0.4 picocuries
per gram (pCi/g) to 1.0 pCi/g, the permissible increase in soil radium concentrations above
background levels that may result from applying Joliet’s wastewater treatment plant sludge to
agricultural lands.
For the reasons below, the Board finds that Joliet has not met its burden of proof. Joliet
has failed to demonstrate that granting the modified permit would not result in a violation of the
water pollution prohibition of Section 12(a) of the Environmental Protection Act (Act) (415
ILCS 5/12(a) (2006)). The Board therefore affirms IEPA’s denial of Joliet’s permit application.
In this opinion, the Board first sets forth the procedural history of this case and rules on
Joliet’s motion to strike portions of an IEPA brief. Next, the Board makes its findings of fact.
The Board then summarizes the parties’ arguments, after which the Board discusses the issues
and renders its legal conclusions
2
PROCEDURAL MATTERS
Procedural History
On October 17, 2008, Joliet filed its petition for review of IEPA’s September 12, 2008
denial of Joliet’s requested permit modification. In an order of November 7, 2008, the Board
accepted Joliet’s petition for hearing. IEPA filed its 335-page administrative record (AR) on
December 11, 2008.
On January 2, 2009, Joliet filed the pre-filed testimony of the four witnesses it would
present at hearing: Harold Harty, Plant Operations Superintendent of the City of Joliet’s three
wastewater treatment plants; Dennis L. Duffield, Project Manager with Rogina & Associates,
Ltd. (RAL); Eli A. Port, a health physicist and President of Radiation Safety Services, Inc.
(RSSI); and Richard E. Toohey, Director of Dose Reconstruction Programs for Oak Ridge
Associated Universities. On January 7, 2009, the hearing officer granted Joliet’s January 5, 2009
motion to substitute pre-filed testimony for each of these four witnesses, correcting minor
typographical errors in the January 2, 2009 filing.
Hearing was held on January 13, 2009, in the Village of Bolingbrook. The Board cites
the hearing transcript as “Tr. at _.” Joliet offered ten hearing exhibits (Exh.), all of which were
admitted. The exhibits include the pre-filed testimony of Harty (Exh. 1), Duffield (Exh. 4), Port
(Exh. 8), and Toohey (Exh. 10). Joliet presented these four witnesses at hearing, and their pre-
filed testimony was entered into the record as if read (Tr. at 8, 15-16, 20, 28-29). IEPA offered
no hearing exhibits and presented no witnesses. On February 3, 2009, Joliet filed a motion to
correct the hearing transcript. The motion, to which IEPA did not respond, is granted.
With the parties’ agreement, post-hearing briefs were filed simultaneously. On February
20, 2009, Joliet filed its initial post-hearing brief (Joliet Br.) and IEPA filed its initial post-
hearing brief (IEPA Br.). On February 27, 2009, Joliet filed its response brief (Joliet Resp. Br.)
and IEPA filed its response brief (IEPA Resp. Br.).
On March 10, 2009, Joliet filed a motion to strike (Joliet Mot.) parts of IEPA’s response
brief. With the motion, Joliet filed a waiver of the Board’s statutory deadline for deciding this
case, waiving the deadline from April 3, 2009, to May 8, 2009. On March 23, 2009, IEPA filed
a response (IEPA Resp.) to Joliet’s motion to strike.
On May 1, 2009, after the hearing officer alerted counsel for the parties, Joliet filed, with
IEPA’s authorization, two replacement pages of IEPA’s administrative record. The replacement
pages (pp. 29 & 30 of a 2007 RAL report that had been submitted to IEPA) correspond to AR 72
and 73, which were miscopied in the administrative record filed by IEPA on December 11, 2008.
The Board accepts the two replacement pages as the parties request.
Motion to Strike
The Board declines IEPA’s request that the Board deny Joliet’s motion to strike portions
of IEPA’s response brief “without considering” the motion. IEPA Resp. at 1 (alleging the
3
motion is a “thinly veiled attempt to get in the last word”). The motion was timely filed and
accompanied by a waiver of the decision deadline.
See
35 Ill. Adm. Code 101.506.
The IEPA statements being challenged by Joliet concern: (1) the relocation of radium-
containing topsoil removed from beneath future slab-on-grade houses that may be constructed on
agricultural fields that received Joliet’s sludge; (2) the relationship between the treatment of
radium in Joliet’s drinking water supply to the issue of radium levels in Joliet’s sludge; and (3)
the Illinois Emergency Management Agency (IEMA) making determinations on the health
effects and bioaccumulative properties of radium. Joliet Mot. at 2-6. Joliet moves to strike these
three sets of statements made in IEPA’s response brief because they are allegedly unsupported
by the record and lack record citations.
Id
. at 1-2, 6. IEPA opposes Joliet’s motion, arguing that
IEPA’s statements are supported by the record and merely highlight Joliet’s misunderstanding of
the issue and burden of proof on appeal. IEPA Resp. at 2-3.
Parties to a permit appeal are expected to provide record citations to support factual
statements made in their briefs. The subjects addressed in the IEPA response brief statements
being contested, however, are not without mention in the administrative record before IEPA at
the time of IEPA’s determination. The Board declines to strike the IEPA statements as none of
them constitute extra-record evidence beyond the scope of Board review in a permit appeal.
See
Alton Packaging Corp. v. PCB, 162 Ill. App. 3d 731, 738, 516 N.E.2d 275, 280 (5th Dist. 1987).
The Board therefore denies Joliet’s motion to strike.
FACTS
Land Application of Radium-Bearing Sludge
Since the early 1980s, Joliet has operated a program for the land application of its
digested wastewater treatment plant sludge or “bio-solids.” AR at 6, 55; Exh. 1 at 1, 2. Joliet
operates three wastewater treatment plants: the Eastside Wastewater Treatment Plant (WWTP);
the Westside WWTP; and the Aux Sable Creek Basin WWTP. AR at 55. The bio-solids are
generated from treating sanitary sewage in the treatment plants. Exh. 1 at 2. Sludge settles in
plant clarifiers and is directed to digesters where bacteria reduce the amount of organic matter
and stabilize the sludge for land application.
Id
.
According to the June 2007 report entitled “
Land Application of Radium Bearing
Biosolids
,” prepared by RAL for Joliet, the “land application of biosolids at agronomic rates
allows growers to achieve desired crop yields without expenditures for commercial fertilizer.”
AR at 54. Nitrogen concentrations in the biosolids normally range between 1% and 6% on a dry
weight basis, while phosphorus concentrations typically range from 0.8% to 6.1%. AR at 54;
Exh. 4 at 12. The Joliet land application program results in bio-solids being applied to
approximately 1,000 acres per year. Exh. 1 at 2. To encourage farmers to accept the sludge in
the spring, they are paid $50 per acre for the right to apply the biosolids and up to an additional
$50 per acre if the crop yield is less than the five year average yield for the field. Exh. 1 at 2.
Radium is a radioactive element that occurs naturally in “rock and soil and may be found
in groundwater.” AR at 108. Radium 226 and radium 228 are “[t]he more common isotopes of
4
radium.” AR at 108. RSSI prepared an October 25, 2004 report for Joliet, entitled “
Report of
RESRAD Dose Modeling for Waste Water Treatment Plant Sludge Applied to Land Currently
Used for Agriculture
.” AR at 107-277. The RSSI 2004 report states:
The U.S. Environmental Protection Agency (USEPA) has established a maximum
contaminant level (MCL) of 5 picocuries per liter (pCi/l) for radium in public
water supplies.
1
Sludge resulting from the treatment of water and sewage and containing naturally
occurring radium from ground water may be disposed of in accordance with the
provisions of this Memorandum of Agreement and the requirements of IEPA and
the Rules and Regulations of the Illinois Pollution Control Board, as implemented
***
The radium concentration in the City of Joliet (Joliet) water supply is between 6
pCi/l and 10 pCi/l, exceeding the current MCL. Methods are available to Joliet’s
water supply system to remove radium from the water. The total amount of
radium remains unchanged and radium removed from the water remains in some
other form and must be disposed of. Depending upon the method, treatment may
result in the radium being concentrated in drinking water treatment waste or
wastewater (sewage treatment) sludge.
Joliet currently returns the radium initially in the water supply to sewage
treatment sludge. The sludge is made available for agricultural application to
exploit its nutrient content. The application of the sludge to land raises the
radium concentration in the soil. AR at 108-09; Exh. 8 at 2; Exh. 10 at 1; Tr. at
18-19.
The RAL addendum report of June 2008, prepared for Joliet, is entitled “
Addendum 1
Land Application of Radium Bearing Biosolids
.” AR at 9-22. That report refers to the bio-solids
from Joliet’s Westside WWTP as having “one of the highest concentrations of radium in
Illinois.” AR at 11.
1984 MOA
In September 1984, IEPA and the Illinois Department of Nuclear Safety (DNS, now the
Division of Nuclear Safety within IEMA), entered into a “Memorandum of Agreement” (MOA)
“for the purpose of delineating certain responsibilities of IEPA and IDNS regarding the disposal
of sludge resulting from treatment of water or sewage and containing radium occurring naturally
from ground waters.” AR at 336. The 1984 MOA states that many public water supplies in
Illinois “draw their raw water from deep wells which contain naturally occurring radium” and
such radium is “removed from the raw water during treatment thereby concentrating it in
sludge.” AR at 336. Paragraph 3 of the MOA provides:
1
“Picocurie” or “pCi” means “the quantity of radioactive material producing 2.22 nuclear
transformations per minute.” 35 Ill. Adm. Code 611.101. The Board’s primary drinking water
standards provide: “MCL for combined radium-226 and –228. The maximum contaminant
level for combined radium-226 and radium-228 is 5 pCi/ℓ.”
35 Ill. Adm. Code 611.330(b).
5
by IEPA. Any permit issued by the IEPA pursuant to this Agreement shall
contain conditions based on the technical criteria contained herein and in any
regulations which IEPA and DNS agree to adopt pursuant to this Agreement. AR
at 337, ¶3.
The MOA then sets forth ways in which sludge may be “disposed of” (landfilling, soil
conditioning) depending upon the level of radium in the sludge. AR 337-38, ¶¶4-6. These
provisions include the following language:
the sludge may be used for soil conditioning purposes on agricultural crop land
(e.g., corn, soy beans) but only if:
(1) such use is in accordance with IEPA procedures; and
(2) the level of radium in the sludge is such that after the sludge is mixed with soil
(for agricultural use) the incremental increase of the radium concentration in the
soil does not exceed 0.1 picocurie per gram (dry weight). AR at 337.
Where the level of radium in the sludge exceeds 50 pCi/g, for example, the MOA
requires pre-disposal approval by DNS. AR at 338, ¶6. Paragraph 7 of the MOA provides a
process for receiving prior DNS approval of “[a]lternative methods of sludge disposal” in
specified circumstances. AR at 338-39. The MOA also states that DNS agrees to “provide IEPA
with technical support in any proceeding in which the technical criteria contained in this
Memorandum are at issue.” AR at 339, ¶11.
Joliet’s Permit and Application to Modify
Joliet’s current permit for applying sewage sludge to agricultural lands was issued by
IEPA on February 16, 2007, and is set to expire on September 30, 2011. AR at 5, 6. Special
condition No. 2 of the permit limits the “total accumulative increase” in the amount of radium
226 and radium 228 in soil to 0.4 pCi/g above background levels. AR at 8; Exh. 1 at 3; Exh. 4 at
8-9; Tr. at 16-17. The permit had previously contained a limit of 0.1 pCi/g. AR at 29; Exh. 1 at
3; Exh. 4 at 5, 8.
Joliet applied with IEPA for a permit modification on July 30, 2008. AR at 1; Exh. 4 at
21. The application states:
Special Condition 2 should be modified to provide for a total accumulative
increase of Radium 226 and Radium 228 in the soil of 1.0 pCi/g. There is no
scientific basis for a limit of 0.4 pCi/g to be imposed on the City. A limit of 1.0
pCi/g meets all applicable guidelines in regard to the safe disposal of sludge
materials. The enclosed report “Land Application of Radium Bearing Biosolids”
prepared for the City of Joliet by Rogina and Associates, Ltd. supports this
position. AR at 8.
6
Joliet’s Technical Reports
The RAL addendum report of June 2008, prepared for Joliet, is entitled “
Addendum 1
Land Application of Radium Bearing Biosolids
.” AR at 9-22. The addendum report concludes:
Joliet has employed a health physicist to determine the annual exposure to
radiation by future residents on land receiving biosolids. The results of Joliet’s
work are that the soil concentration of radium can be increased by 1.0 pico-curies
per gram without exceeding a dose of 10 milli-rems per year. AR at 11; Exh. 10
at 6.
More specifically, the RAL June 2008 addendum report sets forth these conclusions and
recommendations:
The current Joliet Program of 10 applications of biosolids from the Joliet
Westside Wastewater Treatment Plant does not result in the exposure of future
residents of homes that follow the local building codes to radiation doses
greater than 10 mill-rems per year.
The anticipated dose to a resident of a home that was not constructed following
local building codes and has received 10 applications of Joliet Westside
biosolids is 15.35 milli-rems.
***
Programs that do not remove the topsoil from beneath the house should be
limited to 0.4 pico-curies per gram increase in soil concentration.
***
It is recommended that the City of Joliet be allowed to continue their current program of
land application of biosolids.
The cumulative increase in soil concentration should be limited to 1.0 pico-curies
per gram. The cumulative increase should be calculated as the sum of the
increase resulting from each application.
Joliet should continue to monitor the building code requirements that may
potentially apply to sites receiving biosolids to assure that topsoil must be
removed prior to the construction of a home. AR at 12; Exh. 4 at 15, 21; Tr. at
18.
Joliet’s February 28, 2005 cover letter submitting to IEPA the October 25, 2004 RSSI
report (“
Report of RESRAD Dose Modeling for Waste Water Treatment Plant Sludge Applied to
Land Currently Used for Agriculture
” (AR at 107-277)) summarized the report:
The dose models were prepared using the radium concentrations for the Joliet
Eastside and Joliet Westside Wastewater Treatment Plants. The models were
based on the application of sludge eight separate times over 20 years and nine
separate times over 22 years. The models were prepared by RSSI, Inc. a
7
consulting health physics firm, and used the program RESRAD 6.22. This is the
same model that was used by the Interagency Steering Committee on Radiation
Standards (ISCORS) in their review of biosolids.
The program was run by RSSI, Inc, a consulting health physics firm, at the
direction of the City of Joliet. The inputs to the model are in the written report
and output material. The future land use was based on single family homes with 3
units to the acre who do not have a dairy cow or grow their own vegetables.
Water was to be supplied by the City of Joliet after installation of the radium
removal equipment. The applied radium concentrations were based on Joliet
experience. One model with 8 applications over 20 years and another model for 9
applications over 22 years were used. All models conclude that the dose to
residents is less than 10 milli-rems per year. AR at 105; Exh. 4 at 6.
The “RESidual RADioactivity” or “RESRAD” model and computer code was developed
at Argonne National Laboratory for the United States Department of Energy to evaluate the
“dose or risk associated with residual radioactive material.” AR at 110;
see also
AR at 50; Exh.
8 at 2 (“for evaluating human health risk from residual contamination.”). RESRAD computes
“potential annual doses or lifetime risks resulting from exposure to radioactive material in soil,
and concentrations of radionuclides in air, surface water, and ground water resulting from the
activity in the soil.” AR at 110; Exh. 8 at 2. The “significant exposure pathways” available in
RESRAD modeling are:
direct external dose from the contaminated soil, and internal dose from inhalation
of airborne radionuclides including radon progeny, and from ingestion of fruits
and vegetables grown in the contaminated soil and irrigated with contaminated
water, from meat and ingestion of milk from live stock fed with contaminated
fodder and water, from drinking water drawn from a contaminated well or pond,
from ingestion of fish from a contaminated pond, and from ingestion of
contaminated soil. AR at 110;
see also
AR at 50; Exh. 8 at 3.
RESRAD modeling conducted by RSSI for Joliet’s sludge application considered
external exposure, inhalation, and radon. AR at 74, 110, 133, 158, 185, 212, 238, 265; Exh. 8 at
3. RSSI did not include ingestion of plant food, meat, milk, aquatic foods, soil, or drinking
water. AR at 74, 110, 133, 158, 185, 212, 238, 265. RSSI explained that “the planned use of
land is resident with no option of growing livestock or significant plant food,” adding that the
modeling assumed “[m]unicipal water supply will be used for drinking, bathing and irrigation
purposes” and that “the new homes will be served by a public water supply providing water that
complies with the Safe Drinking Water Act.” AR at 110, 112; AR at 74, 78; Exh. 8 at 3. RSSI
determined the annual radon dose and annual total dose resulting from two application patterns
using sludge from Joliet’s Eastside WWTP and two application patterns using sludge from
Joliet’s Westside WWTP. AR at 112. RSSI states that the “maximum annual dose from the total
of all applications in any application pattern is less than 9 mrem [millirems] per year.” AR at
114; Exh. 8 at 3; Exh. 10 at 2.
8
The June 2007 RAL report (“
Land Application of Radium Bearing Biosolids
” (AR at 41-
91)) states that RESRAD has “predetermined inputs” or “default values” to be used “if the actual
conditions are not known.” AR at 51. The RAL report purportedly described IEMA’s modeling,
though IEMA modeling documentation is not in the record:
The Illinois Emergency Management Agency, Division of Nuclear Safety has
modeled the radiation dose using a model configured to demonstrate construction
of the home on the radium bearing topsoil. The model also used input values
indicating that the resident would drink water from wells on site, grows
vegetables for consumption on the site, and consumes dairy products and seafood
impacted by the biosolids application on the site. The input values are identified
as default values in the model.
The results of the model indicated that a single radionuclide soil guideline or 0.23
pico-curies per gram for radium 226 and 1.50 pico-curies per gram for radium
228. Since both radionuclides are present in biosolids, the sum of fractions was
applied based on equal proportions of radium 226 and 22[8]. The resulting soil
guideline calculated to 0.4 pico-curies per gram.
0.4 pico-curies per gram soil concentration was recommended by the IEMA-
IDNS as the allowable increase in soil concentration that would comply with the
10 milli-rems per year dose limit. AR at 50; Exh. 4 at 8, 10; Exh. 8 at 3; Tr. at 17,
21-22.
The RAL June 2007 report states that Joliet’s modeling inputs were adjusted from those
used by IEMA. For example, “[o]ne of the primary inputs to the RESRAD model is the
concentration of radium in the topsoil below the house.” AR at 51. The inputs proposed by
Joliet are based on removing the topsoil under the house “as this is the normal construction
practice.” AR at 51; Exh. 4 at 11. The report states:
The primary local regulation of home building is through the local building code.
Since Joliet has historically applied biosolids on land in four counties, variations
in the building code requirements exist. Land that has received biosolids has also
been incorporated into a number of cities and villages.
***
Joliet requested RAL to survey the communities. The results of the survey
indicate that building codes in the areas receiving biosolids from Joliet require the
removal of topsoil prior to construction of the home or building.
***
The inputs to the RESRAD model are based on purchased vegetables, dairy
products and seafood instead of the use of items produced on site using
contaminated soil. This is consistent with the life style in a subdivision in the
Joliet area.
***
9
The RESRAD program was to run with inputs for the radium bearing topsoil to be
removed from beneath the future house, but remain in the area surrounding the
home. AR at 51-52.
The RAL June 2007 adds that the proposed drinking water treatment technology is not expected
to increase the amount of radium in the sludge, noting:
Since the mass loading of radium is not expected to change, the quantity of
radium in the waste sludge from the plant is not expected to change from the
current levels. Therefore, the amount of radium currently being applied with the
biosolids to farm fields will not be increased due to the installation of new water
treatment technology. AR at 86.
Memoranda and Correspondence
Jeff Hutton of IEPA’s Division of Water Pollution Control, Permit Section, prepared a
memorandum on January 24, 2007. As documented in that memorandum, representatives of
IEPA, IEMA, and Joliet met on January 24, 2007, “to discuss the appropriate model to be used in
determining the allowable increase in radium above background.” AR at 92. The memorandum
continues:
All present agreed that a dose of 10 mrem/yr was acceptable.
***
The question then devolved to what parameters were appropriate for modeling the
10 mrem/yr exposure limit. Specifically, Joliet wanted the model based on the
idea that the top 12 inches of soil was removed from under the house. Roy
Harsch [on behalf of Joliet] indicated that the City had done a survey of the
counties in northern Illinois and all had adopted the International Building Code
standard which required the removal [of] “expansive soils” prior to construction.
The use of this parameter would allow a much higher application rate of radium to
the soil.
Gary McCandless (IEMA) asked how the city or [IEPA] could guarantee that the
building codes were followed. Rich Allen [of IEMA] asked if [IEPA] was willing
to assume the risk associated with an individual not following building codes.
Toby [Frevert of IEPA] said that [IEPA] wouldn’t dictate building codes at the
local level.
Roy Harsch said that [IEPA] should realize the constraints of working with the
general population.
***
Eli Port [of RSSI] indicated that the modeling needed to be based on a reasonable
assurance of public protection. This seems to me to be the primary question.
Does requiring people to adhere to the County building codes constitute a
reasonable level of protection? AR 92-94; Exh. 4 at 9; Tr. at 16, 21.
10
In a July 18, 2007 memorandum, Hutton of IEPA documented his observations after
completing his review of “Joliet’s radium proposal, IEMA’s proposed MOA and RESRAD
Manual 6.0.” AR at 35. According to Hutton:
The biggest factor impacting exposure is the question[] of whether the topsoil is
removed before construction of the residence. Joliet has presented a chart
indicating that building codes in the area require removal of topsoil prior to
building. In addition common home construction practice is to remove the topsoil
prior to laying either foundations or concrete pads. I contacted several builders
selected at random from the phone book and all said the same thing. The top 3
feet of soil is removed prior to construction so that the footings of the structure
are below the frost line.
***
IEMA’s pathways and Joliet’s pathways differ in that IEMA included factors
assuming the subdivision resident drank water from an on site well, drank milk
produced on site, ate meat produced on site, ate fish contaminated with radium,
and consumed vegetables produced on site. According to table 2.2 [of RESRAD
Manual 6.0] only the vegetables should have been used for the suburban resident
scenario. I have real problems with the concept of suburbanites drinking milk
directly from the cow and raising their own meat and poultry onsite.
***
Joliet assumed that the drinking water used by the resident came from public
water supply system rather than a well which would increase the amount of
radium allowed on site. Given that many of the areas being developed in northern
Illinois are outlying areas where the residents use well and septic systems the use
of the drinking water in IEMA’s model is a valid pathway. AR at 35-36.
Hutton then states his conclusions and discusses a “presentation to IEMA”:
If [IEPA] allows an increase of 1.0 pCi/g above background and assumes removal
of the topsoil under the structure, it will be protective of human health. This is the
same increase above background as is allowed under Wisconsin’s rules and
results in less than 10 mrem/year exposure based on Joliet’s model.
***
[IEPA] should propose an allowable increase of 1.0 pCi/g in soil radium based on
the RESRAD scenario where the exposed individual is a suburban dweller living
in a house where the topsoil has been removed during the construction of that
house.
Presentation to IEMA:
Mike Klebe [of IEMA] indicated to me that IEMA has
gone as far as they believe they can by allowing an increase of 0.4 pCi/g above
background. However, that 0.4 pCi/g increase is based on extremely conservative
factors in their modeling that do not appear to reflect the real world situation.
[IEPA] should argue that the assumptions in the model need reflect the actual
11
situation with regard to the conversion of farmland to subdivisions. The
assumptions in the model should assume 1) removal of the topsoil under the
structure, 2) the individual is not consuming meat, milk and poultry grown onsite
and 3) be based on the change above background rather than total radium. We
can accept the use of well water by the individual.
[IEPA] should request that the RESRAD model should be re-run by both Joliet
and IEMA using the above constraints to determine just how many mrem/year are
produced by an increase in soil radium of 1.0 pCi/yr. The two models should
show similar results. The Agencies could review the proposal after these new
models are completed. AR at 37; Exh. 4 at 16-17.
In a letter of August 13, 2007, from IEMA’s Gary McCandless, Acting Chief, Bureau of
Environmental Safety, Division of Nuclear Safety, to IEPA’s Toby Frevert, Manager, Division
of Water Pollution Control, McCandless refers to the RAL report of June 2007 and states:
Joliet misinterpreted [IEMA’s] computer modeling. They claim [IEMA] used
input parameters that indicate ingestion exposure pathways. While [IEMA] left
certain ingestion related input parameters as the default values, the pathways were
turned off. This is an easier way to accomplish the same effect.
Joliet also took issue with [IEMA] not taking into consideration that topsoil would
be removed prior to construction of any buildings. Other than statements that
building code requires removal of topsoil, Joliet provided no documentation
stating this requirement. Neither did Joliet provide any documentation of
procedures used by building inspectors to verify this or documentation regarding
the use of the soil removed from the site.
In their study, Joliet discussed the results of the computer modeling used to
support their proposed radium concentration increase limit. Joliet did not provide
any input or output files so [IEMA] could verify their results.
At our last meeting where we agreed to a 300% increase in the radium soil
concentration increase limit, we agreed that Joliet would have to adapt their
procedures to meet their operational needs for biosolids management. It appears
from [IEMA’s] review of Joliet’s submittal, they remain steadfast in their quest to
maintain the status quo for their biosolids land application program, and, remain
unsatisfied with [IEMA’s] efforts and willingness to increase the previous limit
by 300%. AR at 33; Exh. 4 at 18.
In a December 3, 2007 memorandum from Hutton of IEPA to Mike Klebe of IEMA,
Hutton states:
[IEPA] would like to know what is the level of exposure, expressed in
mrem/yr, for an increase in background of 1.0 pCi/g based on the following cases:
12
The exposed individual is a suburban home owner where the top foot of
soil was removed from underneath the house during construction. No
inputs from food occur for this individual.
The exposed individual is a suburban home owner where the top foot of
soil was not removed under the house. No inputs from food occur for this
individual.
[IEPA] has been operating under the assumption that the City of Joliet and
[IEMA] were in consultation over the inputs to be used in running RESRAD
models. However, [IEPA] has not received a response from the City with regard
to the status of such consultation at this time. AR at 32; Exh. 4 at 19.
A December 22, 2007 letter from James Eggen, Director of Public Utilities for Joliet, to
IEPA’s Allen Keller, Manager, Permit Section, Division of Water Pollution Control, provides:
The radium is naturally occurring in the water supply and its presence in the
biosolids had been overlooked until such time that treatment from the water
supply became mandatory. Initially a limit of 0.1 pCi/g was imposed based on a
long standing Memorandum of Agreement (MOA) between the Department of
Nuclear Safety (DNS) and Illinois Environmental Protection Agency (IEPA). As
a result of an objection from the City of Joliet, a new permit was issued with the
radium limit revised to 0.4 pCi/g. This allowed Joliet’s program to proceed while
the matter was reviewed further. It was always Joliet’s intention that the 0.4
pCi/g limit was an interim limit while we allowed the science to justify a higher
limit.
***
The Division of Nuclear Safety (DNS) has been unwilling to accept the City’s
analysis on the premise that new homes will be built on top of the topsoil layer
which has been amended with biosolids. By building above this topsoil layer, the
natural decay products will be trapped inside the building providing for a greater
risk to its inhabitants. Joliet’s analysis maintains that the topsoil layer is disturbed
and removed from the building site during the construction process.
The current use of the land is for agricultural purposes. It is reasonable to
presume that the land would remain as agricultural until developed or left to grow
wild for conservation or nature preserve purposes, in which case there would be
no future buildings on the land.
The Department of Nuclear Safety has not demonstrated their argument on how a
future building may be constructed on a subject site. The two major defects with
their argument are that any professional builder will remove unsuitable materials
from beneath a structure and that all current building codes require organic
material (i.e. topsoil) to be removed from beneath a structure.
***
13
Joliet’s argument is a simple one. The land is tilled two or more times a year.
The topsoil layer has absolutely no structural bearing capacity and must be
removed prior to building any type of structure.
The City of Joliet with its consultants has attempted to work with the DNS to find
a common ground which would be agreeable to both parties. While they gave us
the impression they agreed with our calculations and would further review the
data, they proceeded to complete a Memorandum of Agreement (MOA) with the
EPA to set the standard at 0.4 pCi/g.
2
2
No such MOA is in the record.
From this we can conclude that the City
and the DNS will not be able to come to an agreement. AR 29-30; Exh. 4 at 20.
A February 26, 2008 memorandum of IEPA’s Hutton describes a meeting of that date
between representatives of IEPA and IEMA. AR at 23. Hutton states that the meeting was held
to discuss, among other things, the “status of MOA” and “technical issues.” AR at 23.
According to the memorandum, Klebe of IEMA indicated that when topsoil is assumed to be
“removed,” “IEMA’s model results in 5.8 mrem/yr exposure.” AR at 23. Klebe also indicated
that “0.4 pCi/g is IEMA’s comfort number.” AR at 23; Exh. 4 at 20.
In a Hutton memorandum of August 27, 2008, he states that Joliet’s requested permission
to “raise the radium to a level of 1.0 pCi/g above background levels” is “in violation of the
memorandum of agreement between IEPA and IEMA/Nuclear Safety.” AR at 5. Hutton’s
memorandum describes the “[a]ction” on Joliet’s request: “Deny supplemental request for
increase above background.” AR at 5. As documented in an August 28, 2008 memorandum
prepared by Hutton, representatives of IEPA and Joliet met on that date to discuss Joliet’s permit
modification application. AR at 3-4; Exh. 4 at 22. At the meeting, Hutton stated that the
“increase to 1.0 pCi/g increase was unlikely.” AR at 3; Exh. 4 at 22.
IEPA’s Denial Letter
On September 12, 2008, IEPA issued a letter denying Joliet’s request to modify special
condition No. 2 of Joliet’s sludge application permit. AR at 1. IEPA’s denial letter states that
IEPA must deny Joliet’s requested permit modification because:
The Memorandum of Agreement (MOA) between Illinois EPA and the Illinois
Emergency Management Agency limits the increase in soil radium to 0.1 pCi/g
above background levels. The proposed allowable increase in soil radium to 1.0
pCi/g exceeds the limit set in the MOA. AR at 1; Exh. 4 at 23.
The denial letter further states:
Sections 12 and 39 of the Environmental Protection Act (Act), 415 ILCS 5/12 and
39, prohibit the Agency from issuing a permit for any facility which would
threaten, cause or allow the discharge of contaminants which might cause or tend
to cause water pollution in Illinois.
14
In addition to the above cited Sections of the Act, the permit application does not
fulfill the requirements of 35 Ill. Adm. Code 309.241.
The following information, clarification or corrections must be provided for us to
complete our technical review and are to be considered specific reasons why the
Act and the regulations adopted pursuant to the Act will not be met:
The Agency will be pleased to reevaluate your permit application on receipt of
your written request and the necessary information and documentation to correct
or clarify the deficiencies noted above. AR at 1; Exh. 4 at 23.
PARTIES’ ARGUMENTS
Joliet’s Post-Hearing Brief
Joliet states that radium, a radioactive element found naturally in soil and groundwater, is
“also in the bio-solids that are produced by Joliet in the process of treating its wastewater.”
Joliet Br. at 1, n.1. According to Joliet:
Each application of bio-solids to a farm field is assumed to add a tiny incremental
amount of radium to the soil and, therefore, Special Condition 2 has the effect of
limiting the total number of applications of bio-solids that are allowed on any one
farm field.
Id
.
Joliet asserts that it sought to increase the special condition No. 2 radium limit of 0.4 pCi/g
because the limit restricts the number of land applications of sludge to “so few total applications
that farmers were reluctant to disrupt their standard fertilization programs for such a limited
benefit.” Joliet Br. at 1-2;
see also id
. at 19.
There is no disagreement, continues Joliet, that 10 millirems is the radiation dosage
considered protective, as “each party agrees that the 10 millirem exposure level is the appropriate
maximum level from which the land application limit (e.g., 0.4 pCi/g in the Permit, compared to
1.0 pCi/g as requested by Joliet) is derived.” Joliet Br. at 2, 5. Joliet explains that after
“extensive negotiations” with IEPA:
the only actual point of disagreement between Joliet and IEPA (which caused
IEPA to deny the modification request) was whether the standard and required
building practice of removing topsoil is a factor that may be considered in
determining the allowable increase of radium levels in the soils from Joliet’s bio-
solids program.
Id
. (emphasis in original).
Joliet maintains that the “legally-mandated building practice” of removing topsoil before
constructing a residence should be considered in arriving at the “theoretical allowable increase of
radium levels in the soils from Joliet’s bio-solids program.”
Id
.
Accordingly, the “real issue” in this appeal, Joliet asserts, is:
15
whether Joliet or IEPA is correct as to the proper exposure model input to use
when calculating the radium dosage based on the assumptions that are made
concerning whether topsoil is usually removed as part of residential construction.
Joliet Br. at 3.
Joliet maintains that building codes in the Joliet area require that topsoil be removed for
structural reasons prior to constructing slab-on-grade residences.
Id
. Joliet adds that topsoil
obviously must be removed to build below-grade-features, such as basements.
Id
., n.2.
According to Joliet, by removing the topsoil before construction, the “risk of radiation exposure
resulting from the elevated levels caused by previous bio-solid application on the land is greatly
reduced.” Joliet Br. at 3.
“IEMA does not accept that topsoil is almost always stripped before homes are built,”
according to Joliet, and so “IEMA’ s modeling assumes that the topsoil always remains
underneath a house.” Joliet Br. at 5. Joliet asserts that “the majority of building codes (as well
as standard building practices) require that the topsoil be removed prior to construction.”
Id
.
There is a “stark absence in the record of any evidence refuting” Joliet’s position.
Id
. at 25. It
appears from the record, continues Joliet, that IEPA “improperly gave deference” to IEMA’s
position on the “building code issue” instead of acknowledging Joliet’s evidence and the
“opinions of its own agency personnel.”
Id
. at 3-4, 23. Joliet argues that the record supports its
contention that increasing the current permit limit to 1.0 pCi/g is “safe and protective of human
health and the environment.”
Id
. at 5-6.
In addition, Joliet states that the “only justification IEPA provided” for denying Joliet’s
request is the 1984 MOA between IEPA and IEMA. Joliet Br. at 4. Joliet argues that the MOA
“cannot bestow upon IEPA any enforceable authority to set any specific limit.”
Id
. at 26. The
MOA limit of 0.1 pCi/g, Joliet continues, constitutes “an impermissible rulemaking without
following proper rulemaking procedures under the Administrative Procedure Act (‘APA’), 5
ILCS 100/5-40, or any specific authority to implement such a rule under the Act.”
Id
. at 4, 27.
The MOA comes within the APA’s definition of a “rule” and “no exceptions apply,”
according to Joliet. Joliet Br. at 27. Joliet explains that:
The APA defines a “rule” as each agency statement of general applicability that
implements, applies, interprets, or prescribes law or policy, but does not include
(i) statements concerning only the internal management of an agency and not
affecting private rights or procedures available to persons or entities outside the
agency, (ii) informal advisory rulings issued under Section 5-150, (iii) intra-
agency memoranda, (iv) the prescription of standardized forms, or (v) documents
prepared or filed or actions taken by the Legislative Reference Bureau under
Section 5.04 of the Legislative Reference Bureau Act. Joliet Br. at 27.
Joliet then asserts:
16
The MOA is of general applicability as it does not specify any specific entity, and
it provides for the implementation of a standard regarding the disposal of sludge
resulting from treatment of water or sewage and containing radium occurring
naturally from ground waters. (R336). Furthermore, the MOA prescribes the
policies to be taken based on the content of the radium-containing sludge. (R337
- R339). Moreover, the MOA, on its face, does not fall within any of the
exceptions provided above. The fact that this MOA is between IEMA and IEPA,
two separate and distinct governmental agencies, is dispositive that no exceptions
apply and, therefore, the MOA clearly falls within the definition of a rule as
defined in the APA.
Id
. at 27.
Joliet maintains that IEMA and IEPA entered into the MOA “without giving the public
and those affected by this rule notice or an opportunity to comment on such rule, thereby
violating the rulemaking requirements to which both agencies are subject.” Joliet Br. at 4.
Consequently, Joliet argues, the rule is invalid and IEPA has “no legal basis for denying Permit
Condition 2 in reliance on a MOA which is not legally binding.”
Id
. at 28. The facts of this
case, according to Joliet, “exemplify the very reason why the APA requires that proper
rulemaking procedures be followed”:
The issues and concerns identified by IEMA would have been resolved had
proper rulemaking procedures been followed, because the regulated community
would have had notice and the opportunity to comment. Moreover, because this
MOA is of general applicability it affects other communities that have similar bio-
solid land application programs.
Id
.
Further, Joliet notes, IEPA “has already disregarded the MOA” by issuing the permit on
February 16, 2007, with a limit of 0.4 pCi/g, “a limit that is clearly in excess of what it is allowed
under the same MOA.”
Id
. IEPA “obviously did not consider itself bound by the MOA at that
time.”
Id
. at 4-5.
Joliet acknowledges that IEPA “has also generally cited to Sections 12 and 39 of the Act”
in the denial letter, but Joliet argues that:
these sections of the Act simply concern enforcement of the general prohibitions
on causing water pollution and IEPA fails to offer any evidence that granting the
Permit modification from 0.4 pCi/g to 1.0 pCi/g, as requested, would have caused
a violation of these sections. Nor is any evidence concerning this issue set forth
in the record. Joliet Br. at 4, n.4.
Joliet notes that there is no specific numeric limit for radium in the Act or Board regulations, but
Joliet makes clear that it is “not challenging IEPA’s authority to regulate radium levels under the
Permit.” Joliet Br. at 16.
Joliet adds that the permit denial will negatively affect farmers who rely on the sludge
and will cost Joliet over four times as much to dispose of the sludge:
17
the program is beneficial to the environment because the only other alternative for
dealing with the radium containing bio-solids would be to dispose of the material
in a landfill. The current present value of the cost associated with the existing
land application program is about $10,265,000. However, the cost for disposal of
such to a landfill would be more than four times the current cost, and totals
$48,083,408. Joliet Br. at 6.
IEPA’s Post-Hearing Brief
IEPA argues that its denial letter “is very specific in the reason” for denying the
requested permit modification:
The denial letter provides that Sections 12 and 39 of the Act prohibit the Agency
from issuing a permit to a facility which would threaten, cause or allow the
discharge of contaminants which might cause or tend to cause water pollution in
Illinois. (R-1). Even more specifically, the causing, threatening or allowing
of the discharge of contaminants which might cause or tend to cause water
pollution will occur because the Petitioner is seeking an increase in soil radium
from 0.1 pCi/g above background levels to 1.0 pCi/g above background levels,
which will exceed the limit set in the Memorandum of Agreement (“MOA”)
between Illinois EPA and Illinois Emergency Management Agency. (R-l, R-8 &
R-336-339). IEPA Br. at 2.
IEPA further asserts that in denying Joliet’s request for permit modification, IEPA was
“fulfilling the mandate” of the Illinois Constitution and the Act of “ensuring all citizens enjoy the
right to a healthful environment.” IEPA Br. at 4. Joliet’s proposed activities, according to IEPA,
would contravene this purpose, as those activities “will increase the radium concentrations in the
soil above what is already there” and that increase in concentration “leads to an increase in risk.”
Id
. IEPA maintains that Joliet’s arguments about how the increased risk would be
“insignificant” is “beside the point.”
Id
. IEPA argues that:
the standard for issuing a permit is whether the Act will be violated not whether
the activity will not lead to a significant risk of harm to the general population.
Petitioner has failed in its burden of showing that the Act will not be violated.
Id
.
at 5.
Finally, as for Joliet’s argument that it will be more expensive to landfill the sludge,
IEPA counters that “cost is not a basis for allowing a violation of the Act.” IEPA Br. at 5.
Joliet’s Response Brief
Joliet states that IEPA’s brief fails to address, or “even acknowledge,” what Joliet
considers the only actual point of controversy in this appeal: “whether the standard and required
building practice of removing topsoil before constructing a slab-on-grade residence is a factor
that should be considered in determining the allowable increase of radium levels in the soils from
Joliet’s bio-solids program.” Joliet Resp. Br. at 1. Instead, Joliet continues, IEPA appears to be
18
arguing that “any increase” in soil radium levels is a “
per se
violation” of the Act.
Id
. at 2
(emphasis in original). Joliet responds that IEPA, IEMA, and Joliet have already agreed that “an
increase in radium concentration in the soil in farm fields is acceptable and permissible pursuant
to Special Condition 2 of Joliet’s Permit,” and therefore “it is simply not the case that any
increase is a violation of the Act.”
Id
. (emphasis in original).
According to Joliet, because neither the Act nor any regulations under the Act contain
any specific limitations on radium levels in soils, IEPA “relies heavily” on the 1984 MOA
between IEPA and IEMA “that set a limit of 0.1 pCi/g of radium for land applications of sewage
sludge.” Joliet Resp. Br. at 2. Joliet maintains that when IEPA argues that “anything in
excess of that level ‘causes water pollution’ and is a violation of the Act,” IEPA “loses sight of
the fact” that IEPA itself has already issued a permit to Joliet allowing a level of 0.4 pCi/g.
Id
.
Accordingly, in addition to the MOA limit being unenforceable, Joliet continues, land
application resulting in an increase “in excess of 0.1 pCi/g of the background level is not a
violation of the Act as asserted by Respondent in its denial because the Permit already allows for
this.”
Id
.
Joliet stresses that the current limit of 0.4 pCi/g “was a level that was derived from
modeling the acceptable radiation dose—10 millirems—that all concerned (Joliet, IEPA and
IEMA) agreed is protective.” Joliet Resp. Br. at 3 (emphasis in original). The analytical model
used is “specifically designed to determine what is protective of human health” when setting the
“appropriate soil application limit as to radium.”
Id
., n.3. Joliet continues:
The limitation of 0.4 pCi/g in Special Condition 2 was not a level that was chosen
because radium at that level (0.4 pCi/g or below) did not cause “water pollution”
under Section 12 of the Act. This fundamental point must be understood before
one can consider the ultimate question of whether granting the requested
modification would cause a violation of the Act.
***
[T]he real issue in this appeal . . . is whether Joliet or IEPA is correct as to the
proper exposure model inputs to use when calculating the radiation dosage. The
only material difference in the modeling is the assumption made as to whether
topsoil is usually removed as part of slab-on-grade residential construction (which
then determines whether 0.4 pCi/g or 1.0 pCi/g is the appropriate radium
limitation). Joliet Resp. Br. at 3.
Joliet asserts that IEPA, IEMA, and Joliet agreed that the increase above soil radium
background concentrations from land applying sludge should be limited to a concentration that
would not result in “an unacceptable level of risk to those who might reside in houses that might
subsequently be built on these lands where Joliet’s bio-solids had been applied.” Joliet Resp. Br.
at 9-10. The three entities further agreed, according to Joliet, that this risk would be determined
by “evaluating the increased exposure to radon gas from the decay of the radium that would not
produce an increased dose of more than 10 millirems.”
Id
. at 10. They agreed still further,
continues Joliet, on using “the RESRAD computer model to calculate this increased radiation
exposure.”
Id
.
19
Joliet’s modeling predicted that an increase in soil radium concentration of 1.0 pCi/g
above background would result in less than a 10 millirem dose for a resident of a house built
using “the legally required and accepted building practice of removing the topsoil when building
an on-grade slab house.” Joliet Resp. Br. at 10;
see also
Tr. at 30. Joliet maintains that IEMA,
however, would not agree to this assumption when modeling the increased risk “because some
individual might proceed to violate building codes and ignore sound construction practices by
building a house with the slab poured on top of the topsoil.”
Id
. “This,” according to Joliet, is
the “sole controversy at issue,” not “whether any increase in radium will cause water pollution or
violations of the Act or regulations, as argued by Respondent, or as cited in the boilerplate IEPA
permit denial letter.”
Id
. (emphasis in original).
IEPA’s Response Brief
IEPA asserts that Joliet’s arguments “have nothing to do with the standard of review for a
permit appeal hearing.” IEPA Resp. Br. at 1. IEPA argues that the burden of proof rests with
Joliet, and Joliet has not met the burden. Under Section 39(a) of the Act, continues IEPA, a
permit is to issue only “upon proof of the applicant that the permitted activity or facility will not
cause a violation of the Act or regulations.”
Id
. According to IEPA, this is this standard that
must be met, not, as Joliet argues, whether the activity will cause harm or undue risk.
Id
.
IEPA maintains that Joliet’s arguments about whether the record supports Joliet’s
position on building codes requiring topsoil removal “misses the point of what standard is
required to be met for issuance of a permit.” IEPA Resp. Br. at 2. IEPA states:
Compliance with building codes is not at issue before the Board. The denial letter
issued by the Agency framed the issue and it relates to the increase of
concentration of radium in the soil above background, not the removal of topsoil.
Id
.
IEPA argues that Joliet waived the argument about the 1984 MOA being an
impermissible rulemaking by not putting this argument in Joliet’s petition for review. IEPA
Resp. at 4-5. If Joliet is not foreclosed by waiver, IEPA argues that the MOA between it and
IEMA is not an impermissible rulemaking. IEPA cites Section 4 of the Act for the IEPA
Director’s authority to “by agreement secure such services as he or she may deem necessary
from any other department, agency, or unit of the State Government . . . as may be required.”
Id
., quoting 415 ILCS 5/4 (2006). Further, IEPA quotes Section 3 of the Illinois
Intergovernmental Cooperation Act: “Any power . . . which may be exercised by a public
agency of this State may be exercised . . . and enjoyed jointly with any other public agency of
this State.” IEPA Resp. Br. at 5, quoting 5 ILCS 220/3 (2006). Based on these statutory
provisions, IEPA maintains that governmental agencies may enter into a memorandum of
agreement “to memorialize a joint exercise of power,” adding that IEPA and IEMA “did so in
this case to combine areas of expertise on radium contamination.” IEPA Resp. Br. at 5.
IEPA concedes that it does not derive authority to set permit limits from the 1984 MOA,
but rather from Section 39 of the Act. IEPA Resp. Br. at 5-6. IEPA asserts that Section 12 of
the Act, cited in the denial letter, provides:
20
the prohibition against causing or threatening to cause water pollution through
certain activities or means. It is this Section coupled with the Agency’s duty
contained in Section 39 of the Act when issuing permits that gives the Illinois
EPA the authority to act in this case. The Petitioner’s proposal to increase the
allowable concentration of radium in the soil above background by 1000% are the
types of activities that the Illinois EPA must consider when fulfilling its duty of
ensuring that permit applicants have proven their activities will not lead to a
violation of the Act.
Id
. at 6.
IEPA concludes that Joliet failed to prove that its proposed activity will not cause a
violation of the Act, and Joliet’s arguments about (1) the activity being “safe,” (2) alternatives
being more costly, (3) building codes, and (4) the IEPA permit writer disagreeing with IEMA,
“are all diversions.” IEPA Resp. Br. at 6.
DISCUSSION
Legal Framework
Under the Act (415 ILCS 5 (2006)), IEPA is the permitting authority. The Act requires
IEPA to issue a permit if the permit applicant proves that the requested permit will not cause a
violation of the Act or the Board’s regulations.
See
415 ILCS 5/39(a) (2006). If IEPA denies a
requested permit, the applicant may appeal IEPA’s decision to the Board within 35 days.
See
415 ILCS 5/40(a)(1) (2006); 35 Ill. Adm. Code 105.204, 105.206. The petitioner has the burden
of proof on appeal.
See
415 ILCS 5/40(a)(1) (2006); 35 Ill. Adm. Code 105.112.
The Board’s review of permit appeals is generally limited to information before IEPA
during IEPA’s statutory review period, and is not based on information developed by the permit
applicant or IEPA after IEPA’s decision. Alton Packaging, 162 Ill. App. 3d at 738, 516 N.E.2d
at 280; Panhandle, PCB 98-102, slip op. at 2; American Waste Processing v. IEPA, PCB 91-38,
slip op. at 2 (Oct. 1, 1992). However, it is the proceeding before the Board that affords the
petitioner the opportunity to challenge the information relied upon by, and the reasons given by,
IEPA for denying the permit. Alton Packaging, 162 Ill. App. 3d at 738, 516 N.E.2d at 280,
citing IEPA v. PCB, 115 Ill. 2d 65, 70, 503 N.E.2d 343, 345 (1986).
On appeal, the question before the Board is “whether the applicant proves that the
application, as submitted to the Agency, demonstrated that no violation of the Act would occur if
the permit was granted.” Panhandle Eastern Pipe Line Co. v. IEPA, PCB 98-102, slip op. at 10
(Jan. 21, 1999),
aff’d sub nom
Panhandle Eastern Pipe Line Co. v. PCB and IEPA, 314 Ill. App.
3d 296, 734 N.E.2d 18 (4th Dist. 2000), quoting Centralia Environmental Services, Inc. v. IEPA,
PCB 89-170, slip op. at 9 (Oct. 25, 1990);
see also
Browning-Ferris Industries of Illinois, Inc. v.
PCB, 179 Ill. App. 3d 598, 601-602, 534 N.E.2d 616, 619 (2d Dist. 1989); Joliet Sand & Gravel
Co. v. PCB, 163 Ill. App. 3d 830, 833, 516 N.E.2d 955, 958 (3d Dist. 1987), citing IEPA v. PCB,
118 Ill. App. 3d 772, 455 N.E.2d 188 (1st Dist. 1983). IEPA’s denial letter frames the issues on
appeal.
See
Centralia, PCB 89-170, slip op. at 8; Pulitzer Community Newspapers, Inc. v. IEPA,
PCB 90-142, slip op. at 6 (Dec. 20, 1990).
21
IEPA’s Denial Letter
On September 12, 2008, IEPA denied Joliet’s request to modify special condition No. 2
of Joliet’s permit for applying WWTP sludge to agricultural fields. Joliet had requested that
IEPA change from 0.4 pCi/g to 1.0 pCi/g the allowable increase in soil radium concentrations
due to sludge application. IEPA’s denial letter states that IEPA must deny Joliet’s requested
permit modification because:
The Memorandum of Agreement (MOA) between Illinois EPA and the Illinois
Emergency Management Agency limits the increase in soil radium to 0.1 pCi/g
above background levels. The proposed allowable increase in soil radium to 1.0
pCi/g exceeds the limit set in the MOA. AR at 1; Exh. 4 at 23.
The denial letter also states:
Sections 12 and 39 of the Environmental Protection Act (Act), 415 ILCS 5/12 and
39, prohibit the Agency from issuing a permit for any facility which would
threaten, cause or allow the discharge of contaminants which might cause or tend
to cause water pollution in Illinois.
In addition to the above cited Sections of the Act, the permit application does not
fulfill the requirements of 35 Ill. Adm. Code 309.241. AR at 1; Exh. 4 at 23.
Accordingly, IEPA based its denial upon the MOA limit and various statutory and regulatory
provisions, including Section 12 of the Act. The Board will address these denial grounds in turn.
MOA Limit Denial Ground
IEPA’s denial letter specifically provides that Joliet’s request of 1.0 pCi/g would exceed
the limit of 0.1 pCi/g set forth in the 1984 MOA between IEPA and IEMA. The Board finds
several deficiencies with this denial ground. First, the MOA limit is neither a provision of the
Act nor a regulation promulgated under the Act. If an applicant fails to prove that permit
issuance would not violate
the Act or its regulations
, then denial is proper. Accordingly, that the
MOA limit may be exceeded is not, by itself, an appropriate ground for denying the permit
application.
See
415 ILCS 5/39(a) (2006). Second, IEPA’s reliance on the 0.1 pCi/g limit of the
MOA is incongruous with the fact that IEPA has already granted Joliet a permit with a limit of
0.4 pCi/g. IEPA has not adequately reconciled this denial reason with the limit set forth in
Joliet’s current permit. Third, the Board finds that this record provides no basis to equate
exceeding the MOA limit of 0.1 pCi/g (by 10 times or otherwise) with violating the water
pollution prohibition of Section 12 of the Act.
Further, Joliet argues that the 1984 MOA between IEPA and IEMA is an improperly
promulgated rule in violation of the APA. The Board finds initially that, contrary to IEPA’s
assertion, Joliet did not waive this specific argument by not explicitly articulating it in Joliet’s
petition for review. Joliet’s petition challenged IEPA’s decision as lacking any basis in law or
22
fact. IEPA never moved to challenge the pleading as insufficient, and the Board finds the
petition grounds broad enough to include Joliet’s argument that the MOA violates the APA.
The APA defines a “rule” as follows:
each agency statement of general applicability that implements, applies,
interprets, or prescribes law or policy, but does not include (i) statements
concerning only the internal management of an agency and not affecting private
rights or procedures available to persons or entities outside the agency, (ii)
informal advisory rulings issued under Section 5-150, (iii) intra-agency
memoranda, (iv) the prescription of standardized forms, or (v) documents
prepared or filed or actions taken by the Legislative Reference Bureau under
Section 5.04 of the Legislative Reference Bureau Act. 5 ILCS 100/1-70 (2006).
The MOA language at issue states in relevant part:
the sludge may be used for soil conditioning purposes on agricultural crop land
(e.g., corn, soy beans) but only if:
***
(2) the level of radium in the sludge is such that after the sludge is mixed with soil
(for agricultural use) the incremental increase of the radium concentration in the
soil does not exceed 0.1 picocurie per gram (dry weight). AR at 337, ¶4(b)(2);
see also
¶¶5(b), 6(b) (cross-referencing ¶4(b)).
IEPA does not argue that this MOA limit is a statement concerning only internal agency
management or otherwise qualifies for an exemption from the APA definition of “rule.” On its
face, the MOA limit is not restricted in its applicability to a specific entity. Under the terms of
the MOA, the 0.1 pCi/g limit is to apply when sludge of a given radium concentration is
proposed to be used as a soil conditioner. The denial letter simply states that Joliet’s request
“exceeds the limit set in the MOA.” AR at 1. IEPA’s use here of the MOA limit does not
constitute the construction of Section 12 of the Act or the application of that statutory provision
to this particular set of facts.
See
Sparks & Wiewel Construction Co. v. Martin
, 250 Ill. App. 3d
955, 968, 620 N.E.2d 533, 542-43 (4th Dist. 1993).
The Board in no way questions the ability of State agencies to enter into MOAs with each
other.
See
5 ILCS 220 (2006). The Board finds, however, that as the MOA limit of 0.1 pCi/g
has been used in this denial letter, the limit is a statement of general applicability that
implements policy affecting the rights of persons or entities outside the agencies and therefore
constitutes a “rule” under the APA (5 ILCS 100/1-70 (2006)). It is undisputed that the MOA
limit was never subjected to the APA’s rulemaking requirements of public notices, opportunity
for public comment, and filing with the Secretary of State.
See
5 ILCS 100/5-35, 5-40, 5-65
(2006). The Board finds that as applied by IEPA in the denial letter, the MOA limit is an
unpromulgated rule.
See
Illinois Ayers Oil Co. v. IEPA, PCB 03-214, slip op. at 15-16 (Apr. 1,
2004). Unless a rule is promulgated in conformity with the APA, “it is not valid or effective
against any person or party and may not be invoked by an administrative agency for any
23
purpose.”
See
Sparks, 250 Ill. App. 3d at 967, 620 N.E.2d at 542;
see also
5 ILCS 100/5-10(c)
(2006).
For all of these reasons, the Board finds that exceedence of the MOA limit is not a proper
ground for permit denial.
Section 12 Denial Ground
The Water Pollution Prohibition
As set forth above, IEPA’s denial letter also cites Sections 12 and 39 of the Act (415
ILCS 5/12, 39 (2006)). Section 12 of the Act is a substantive prohibition while Section 39
provides the procedures for IEPA permit determinations. Referring to Section 12, the denial
states that IEPA cannot grant a permit for a facility that “would threaten, cause or allow the
discharge of contaminants which might cause or tend to cause water pollution in Illinois.” AR at
1. Referring to Section 39, the denial letter states that an applicant must “submit proof to the
Agency that the proposed facility will not cause a violation of the Act.”
Id
. Whether or not this
passage of the denial letter is “boilerplate” as Joliet argues (Joliet Resp. Br. at 10), the Board
cannot simply ignore it, picking and choosing which words of the letter to give effect.
See
Centralia, PCB 89-170, slip op. at 8; Pulitzer, PCB 90-142, slip op. at 6.
In addition, the denial letter cites Section 309.241 of the Board’s water pollution
regulations (35 Ill. Adm. Code 309.241). Section 309.241(a) provides:
a)
The Agency shall not grant any permit required by this Subpart B . . .
unless the applicant submits adequate proof that the treatment works,
pretreatment works, sewer, or wastewater source will be constructed,
modified, or operated
so as not to cause a violation of the Act
or of this
Subtitle . . . . 35 Ill. Adm. Code 309.241(a) (emphasis added).
It must be presumed that IEPA referred to Section 309.241 based on its determination that
Section 12 of the Act may be violated. Neither the denial letter nor IEPA’s briefs provide any
other apparent explanation for the citation to this regulation.
Therefore, IEPA’s decision bases denial on Section 12 of the Act, and Joliet’s purported
failure to prove that issuance of the requested permit condition would not “threaten, cause or
allow the discharge of contaminants which might cause or tend to cause water pollution in
Illinois.” AR at 1. This language of the denial letter paraphrases a portion of Section 12(a) of
the Act:
No person shall:
(a)
Cause or threaten or allow the discharge of any contaminants into the
environment in any State so as to cause or tend to cause water pollution in
Illinois, either alone or in combination with matter from other sources . . . .
415 ILCS 5/12(a) (2006).
24
“Contaminant” is defined in the Act as “any solid, liquid, or gaseous matter, any odor, or any
form of energy, from whatever source.” 415 ILCS 5/3.165 (2006). Under the Act, “waters”
means “all accumulations of water, surface and underground, natural, and artificial, public and
private, or parts thereof, which are wholly or partially within, flow through, or border upon this
State.” 415 ILCS 5/3.550 (2006). The Act defines “water pollution” as:
such alteration of the physical, thermal, chemical, biological or radioactive
properties of any waters of the State, or such discharge of any contaminant into
any waters of the State, as will or is likely to create a nuisance or render such
waters harmful or detrimental or injurious to public health, safety or welfare, or to
domestic, commercial, industrial, agricultural, recreational, or other legitimate
uses, or to livestock, wild animals, birds, fish, or other aquatic life. 415 ILCS
5/3.545 (2006).
3
Central to Joliet’s arguments on appeal is the RESidual RADioactivity (RESRAD) model
and computer code. Joliet’s consultant, RSSI, relied upon the
User’s Manual for RESRAD
Version 6
, ANL/EAD (July 2001) (AR at 110, n.1), which the Board will refer to as the
“Manual.” RESRAD was created by the Argonne National Laboratory as a multi-functional tool
for developing cleanup criteria and assessing the dose or risk associated with residual radioactive
material.
RESRAD
4
The source analysis addresses the derivation of the source terms that determine the rate at
which residual radioactivity is released into the environment. In Joliet’s case, the source analysis
relates to the land application of sewage sludge that results in residual radioactivity. The
environmental transport analysis concerns the identification of “environmental pathways by
Manual at 1-3. RESRAD includes a detailed pathway analysis for deriving soil
concentration guidelines from a given dose limit.
Id
. at 1-4, 2-3, 2-4. The soil guideline is the
radionuclide concentration in the soil that is acceptable if the site is to be used “without
radiological restrictions.”
Id
. at 3-1. The pathway analysis includes “source” analysis,
“environmental transport” analysis, “dose/exposure” analysis, and “scenario” analysis.
Id
. at 2-
1.
3
Section 12(a) of the Act also prohibits persons from causing, threatening, or allowing the
discharge of contaminants so as to violate “standards adopted by the Pollution Control Board
under the Act.” 415 ILCS 5/12(a) (2006). Under the Act, the Board has adopted groundwater
quality standards for radium 226 and 228 (35 Ill. Adm. Code 620.410(a)), drinking water quality
standards for radium (35 Ill. Adm. Code 611.330(b)), and surface water quality standards for
radium (35 Ill. Adm. Code 302.207(c), 302.307, 302.525(c)). IEPA’s denial letter, however,
does not state Joliet failed to prove that permit issuance would not violate any of these standards.
4
The Manual defines “radiation dose” as “the effective dose equivalent (EDE) from external
radiation and the committed effective dose equivalent (CEDE) from internal radiation.” Manual
at 1-3. The sum of the external radiation EDE and the internal radiation CEDE is referred to as
the “total effective dose equivalent” (TEDE).
Id
.
25
which radionuclides can migrate from the source to a human exposure location” and the
determination of “the migration rate along the pathways.” Manual at 2-1. The dose/exposure
analysis pertains to the derivation of dose conversion factors for the radiation dose that will be
incurred by the exposure to ionizing radiation. Finally, the scenario analysis concerns the pattern
of human activity that affects the rate of radionuclide release into the environment and the
severity and duration of exposure.
Id
.
The major pathways considered in RESRAD to derive site-specific soil guidelines are:
external radiation from direct exposure to contaminated soil; inhalation of dust and radon; and
ingestion of contaminated plants, meat, milk, aquatic foods, water, and soil. Manual at 2-4, 2-5.
The RESRAD model allows for consideration of some aspects of the Act’s definition of “water
pollution.”
5
patterns of human activity that can affect the release of radioactivity from the
contaminated zone and the amount of exposure received at the exposure location.
There are many potential exposure scenarios, such as subsistence farming and
industrial worker. The actual scenario of a site depends on numerous factors,
including the location of the site, zoning of the land, physical characteristics of
the site, etc. Soil guidelines are usually based on a resident farmer exposure
scenario. This scenario includes all environmental pathways for on-site or near-
site exposure and is expected to result in the highest predicted lifetime dose.
Other scenarios, such as the suburban resident, industrial worker, and
recreationist, can be taken into account by adjusting the scenario parameters in
The contamination of groundwater and surface water may be taken into account.
Ingestion exposure pathways include “food pathways” (plants, meat, milk, and aquatic foods),
“water pathway segments” (groundwater and surface water), and the “drinking water pathway”
(groundwater and surface water).
Id
. at 2-7 to 2-12.
The plant food pathway accounts for, among other things, root and foliar uptake of
irrigation water that has been contaminated. Manual at 2-7. A water pathway segment can
connect the contaminated zone with the point of water withdrawal for drinking or irrigation.
Id
.
at 2-9. The model can assume that irrigation or drinking water will be taken from a well that was
contaminated by precipitation or irrigation water infiltrating the contaminated zone and
transporting radionuclides through the vadose zone to the aquifer.
Id
. at 2-9, 2-10. Where an on-
site well is the source of drinking water, RESRAD determines the concentration factor that
characterizes the drinking water pathway through multiplication of the water/soil concentration
ratio by the annual quantity of contaminated drinking water consumed by an individual.
Id
. at 2-
12.
Under RESRAD, exposure scenarios are:
5
RESRAD assesses human exposure to radiation. The model does not consider, for example, the
separate effects of radiation rendering surface waters harmful to “wild animals, birds, fish, or
other aquatic life.” 415 ILCS 5/3.545 (2006). The Board addressed such concerns in setting
water quality standards for radium.
See
Revisions to Radium Water Quality Standards:
Proposed New 35 Ill. Adm. Code 302.307 and Amendments to 35 Ill. Adm. Code 302.207 and
302.525, R04-21, slip op. at 13 (Dec. 15, 2005).
26
formulas for calculating the transport of radionuclides through the pathways . . . .
Manual at 2-16.
The exposure scenario for a suburban resident can be considered by “suppressing” (
i.e.
, not
including) pathways believed to be inapplicable.
Id
. at 2-20. According to the Manual, in the
suburban resident scenario, the pathways considered are external radiation exposure, dust
inhalation, radon inhalation, and the ingestion of plant foods and soil.
Id
. at 2-21. The pathways
suppressed are the ingestion of contaminated meat, milk, fish, and water.
Id
. The following
table from the Manual is illustrative:
Pathways to be Considered for the Resident Farmer, Suburban Resident, Industrial
Worker, and Recreationist Scenarios
Pathway
Resident
Farmer
a
Suburban
Resident
b
Industrial
Worker
c
Recreationist
d
External gamma
exposure
Yes
Yes
Yes
Yes
Inhalation of dust Yes
Yes
Yes
Yes
Radon inhalation Yes
Yes
Yes
Yes
Ingestion of plant
foods
Yes
Yes
No
No
Ingestion of meat Yes
No
No
Yes
Ingestion of milk Yes
No
No
No
Ingestion of fish
Yes
No
No
Yes
Ingestion of soil
Yes
Yes
Yes
Yes
Ingestion of
water
Yes
No
No
No
a
Resident Farmer: water used for drinking, household purposes, irrigation, and
livestock watering is from a local well in the area.
b
Suburban Resident: no consumption of meat and milk obtained from the site, and
the water used for drinking is from offsite sources.
c
Industrial Worker: no consumption of water or food obtained on the site. Note: the
EPA’s industrial worker is assumed to drink water from an onsite well (EPA
1994). However, the drinking water ingestion rates for the industrial worker and
resident are different.
d
Recreationist: no consumption of food except meat (game animals) and/or fish
obtained from the onsite pond, and the water used for drinking is from offsite
sources. Manual at 2-21, Table 2.2;
see also
AR at 38.
The RESRAD model therefore can account for certain aspects of the Act’s definition of
“water pollution” by considering human exposure to radiation resulting from surface water and
groundwater impacts that arise out of radium-contaminated soil. The record indicates that Joliet
and IEPA agreed that the radium limit in the permit should be set based on the use of RESRAD,
that the modeling should address a suburban resident scenario, and that human exposure from the
sludge should be kept below a radiation dose of 10 millirems per year.
27
Joliet’s modeling estimated the dose of radiation to which a future suburban resident may
be exposed due to Joliet’s sludge application, assuming that a suburban house would eventually
be built on agricultural land that received Joliet’s sludge. As discussed below, based on its
modeling assumptions, Joliet calculated that an increase in soil radium concentration of up to 1.0
pCi/g above background levels would not subject a future suburban resident to a radiation dose
greater than 10 millirems per year.
Joliet’s Modeling
One of Joliet’s consultants, RSSI, conducted Joliet’s RESRAD modeling. RSSI used
radium concentrations in sludge from the Joliet Eastside and Joliet Westside WWTPs. AR at
105. The modeling was based on applying sludge eight separate times over 20 years and nine
separate times over 22 years.
Id
. Future land use was based on single-family homes with 3 units
to the acre.
Id
. RSSI considered “three pathways: external exposure, inhalation, and radon.”
AR at 110. RSSI did not include exposure from the ingestion of drinking water, plant food,
meat, milk, aquatic foods, or soil. AR at 110, 133, 158, 185, 212, 238, 265. RSSI determined
the annual radon dose and annual total dose resulting from varied sludge application patterns.
AR at 112. RSSI concluded that “the maximum annual dose from the total of all applications in
any application pattern is less than 9 mrem per year.” AR at 114.
Drinking Water.
In suppressing the drinking water pathway, RSSI stated that municipal
water supply was assumed for drinking, bathing, and irrigation purposes. AR at 110.
Accordingly, RSSI assumed, for purposes of Joliet’s RESRAD modeling, that the suburban
resident would not ingest drinking water from an on-site well. Drinking water would be
provided by an off-site source. This pathway assumption, as noted above, is consistent with the
Manual. However, the Manual elaborates:
In the suburban resident scenario, it is assumed that municipal water (i.e.,
uncontaminated water) is used for drinking and irrigation purposes. If well water
is used, however, these pathways can be activated in RESRAD. In an EPA
[United States Environmental Protection Agency] study (EPA 1994), an on-site
well is assumed for drinking in the suburban resident scenario. Manual at 2-20.
RESRAD considers water ingestion only for the rural resident, and the ingestion
rate is 510 L/yr. The EPA also considers water ingestion for the suburban
resident and industrial worker; the EPA
Exposure Factor Handbook
(EPA 1997)
recommends an average drinking water intake of 1.4 L/d.
Id
. at 2-22, Table 2.3,
n.g.
Hutton of IEPA’s Division of Water Pollution Control, Permit Section, expressed
concern about Joliet’s RESRAD modeling effort excluding the consumption of drinking water:
Joliet assumed that the drinking water used by the resident came from public
water supply system rather than a well which would increase the amount of
radium allowed on site. Given that many of the areas being developed in northern
Illinois are outlying areas where the residents use well and septic systems the use
28
of the drinking water in IEMA’s model is a valid pathway. AR at 36.
IEMA’s modeling, referenced by Hutton, is not in the record and it is unclear whether IEMA
used the drinking water ingestion pathway in assessing Joliet’s proposal. AR at 33; Exh. 4 at 18.
Joliet presented testimony at the Board hearing concerning the issue of modeling water ingestion.
Dennis L. Duffield, who is with Joliet’s consultant RAL and is the former Director of Joliet’s
Public Works and Utilities, testified before the Board about Hutton’s comment:
It should be noted that I am not aware of a single well and septic subdivision that
has developed on land that has received Joliet biosolids. All the development that
I recall has developed on the public water supply. Exh. 4 at 16.
The Board finds that Duffield’s testimony relates to past development and is not necessarily
predictive of future subdivision development on agricultural lands that have received Joliet’s
sludge.
RSSI’s report states:
Surface water usually has low radium concentrations, but groundwater
concentrations can be significant. Water drawn from deep bedrock aquifers may
contain concentrations of radium that exceed regulatory standards. In Northern
Illinois, high radium concentrations result from the presence of radium in the
granite bedrock that surrounds the aquifers from which water supplies are drawn.
Radium in drinking water may pose a radiological health hazard. About one-fifth
of ingested radium is taken up by the body and the balance is excreted in feces.
Some of the absorbed radium is subsequently excreted in urine. In the body,
radium, a group IIA alkali earth element, behaves like other elements in the
group, such as calcium, and is deposited primarily in bone cortex.
The internally deposited radium emits alpha particles that damage tissues adjacent
to the decaying atoms. AR at 108.
The Board finds that the record does not support Joliet’s exclusion of the water ingestion
pathway.
Plant Food.
RSSI stated that “the planned land use is resident” with “no option” of
growing “significant plant food.” AR at 110. RAL added that “purchased vegetables” are
“consistent with the life style in a subdivision in the Joliet area.” AR at 52. The Manual,
however, includes the ingestion of plant foods among the pathways to be considered for the
suburban resident scenario, noting that “[p]lanting vegetable gardens is common in urban and
suburban areas as well as rural areas . . . .” Manual at 2-8, 2-21.
This is noted by Hutton of IEPA:
29
IEMA’s pathways and Joliet’s pathways differ in that IEMA included factors
assuming the subdivision resident drank water from an on site well, drank milk
produced on site, ate meat produced on site, ate fish contaminated with radium,
and consumed vegetables produced on site.
According to table 2.2
[of the
Manual]
only the vegetables should have been used for the suburban resident
scenario
. I have real problems with the concept of suburbanites drinking milk
directly from the cow and raising their own meat and poultry onsite. AR at 36
(emphasis added), 38 (Table 2.2 of the Manual).
Like RESRAD, the USEPA study (1984) referred to in the Manual included a pathway for the
ingestion of home-grown produce in a suburban scenario.
Radiation Site Cleanup Regulations:
Technical Support Document for the Development of Radionuclide Cleanup Levels for Soil,
Review Draft
, USEPA, Office of Air and Radiation, EPA 402-R-96-011 A at 2-8 (Sept. 1994).
Though Joliet’s modeling approach is based on the claimed subdivision lifestyle in “the
Joliet area,” the record shows that historically, Joliet’s sludge has been received on crop lands in
four counties. Further, if municipal water is not assumed, as discussed above, the plant food
could be impacted by contaminated irrigation water from an on-site well. The Board finds that
the record does not support Joliet’s exclusion of the plant food ingestion pathway.
Topsoil.
Much of the record is devoted to the dispute over whether Joliet’s RESRAD
model properly assumed that topsoil would be removed before construction of the future
suburban residences on the agricultural fields that have received Joliet’s sewage sludge. In fact,
Joliet argues that the sole issue for the Board to decide on appeal is whether, for purposes of the
RESRAD model, it is more appropriate to assume that topsoil will be removed, or left in place,
when the suburban house is built.
In its RESRAD modeling, Joliet assumed the topsoil would be removed before any house
construction, based on what Joliet describes as common industry practice and the requirements
of local building codes. IEMA’s calculations were based on the assumption that the future
residence would be built on the topsoil, though, as noted, IEMA’s modeling documentation is
not in the record. Assuming the topsoil’s presence or absence beneath the house affects the
calculated radon entry into the house and thus the resident’s radiation dose estimated under the
model.
It is undisputed that removing topsoil before house construction is common industry
practice. Nor is there any dispute that numerous building codes in northern Illinois, including
those in areas that have received Joliet’s sludge, require the removal of topsoil before house
construction. AR at 51-52, 72-73, 92. Each of the following communities was surveyed by RAL
and found to have such a building code requirement: Will County,
6
6
Will County allows construction of pads without topsoil removal “only with proven 95%
compaction.” AR at 72.
Kendall County, Grundy
County, Kankakee County, Kane County, DeKalb County, LaSalle County, Joliet, Manhattan,
Channahon, Minooka, Shorewood, Plainfield, Oswego, Yorkville, Wilmington, Frankfort,
Mokena, Sugar Grove, Elburn, and Morris. AR at 72-73. These local codes are based on either
30
the International Building Code (IBC) and the International Residential Code (IRC) or the
Building Officials and Code Administrators (BOCA) National Building Code.
Id
. Joliet has
established that it is reasonable to assume, for purposes of RESRAD, the removal of topsoil from
beneath the future suburban house prior to construction.
While the record establishes that industry practice and local building codes call for the
topsoil
within the footprint of the house
to be removed, Joliet has not established that all topsoil
on a parcel is permanently removed from that property. In the record, IEMA raised a concern
about “the use of soil removed from the site.” AR at 33. Duffield testified on behalf of Joliet at
the Board hearing that:
Most new construction in the Joliet area is a part of a 40 acre or larger
subdivision. Common practice in developments of this size is to strip the topsoil
from the site and place it in stockpiles during the grading and construction of the
site. When the homes are ready for occupancy, the topsoil is spread on the lawn
areas around the home. Exh. 4 at 23.
Eli Port, a health physicist and President of RSSI, testified about modeling the removal of topsoil
before construction: “[i]n the model, the only interface with amended soil is where topsoil is
brought up against a basement wall or outside the home.” Exh. 8 at 3;
see also
AR at 52 (RAL
June 2007 report: “The RESRAD program was to run with inputs for the radium bearing topsoil
to be removed from beneath the future house, but remain in the area surrounding the home.”).
The Board finds that if radium-impacted soil remains on the property, albeit outside of
the building footprint, the soil could be an on-going source of groundwater contamination to the
detriment of an assumed on-site drinking water well.
Board Finding on Section 12 Denial Ground
The RESRAD model permits the use of the on-site drinking water well pathway in the
suburban resident scenario and calls for using the plant food ingestion pathway. The record does
not support Joliet’s exclusion of these pathways from its modeling. Had Joliet included the
pathways, the resulting dose would have taken into account the suburban resident’s additional
radiation exposure due to the migration of radionuclides from Joliet’s sludge to groundwater,
which in turn could be used for drinking water or irrigation of plant foods.
Radium 226 and 228 in WWTP sludge, as well as their decay products, are
“contaminants” (415 ILCS 5/3.165 (2006)) under the Act. “Waters” include groundwater (415
ILCS 5/3.550 (2006)). Section 12(a) of the Act provides in relevant part that no person shall
“[c]ause or threaten or allow the discharge of any contaminants into the environment in any State
so as to cause or tend to cause water pollution in Illinois, either alone or in combination with
matter from other sources” (415 ILCS 5/12(a) (2006)). “Water pollution” includes the
“discharge of any contaminant into any waters of the State, as will or is likely to . . . render such
waters harmful or detrimental or injurious to public health . . . .” 415 ILCS 5/3.545 (2006).
31
Joliet argues that “
IEPA fails to offer any evidence
that granting the Permit modification
from 0.4 pCi/g to 1.0 pCi/g, as requested, would have caused a violation” of Section 12(a). Joliet
Br. at 4, n.4 (emphasis added). Joliet, however, carries the burden of proof.
See
415 ILCS
5/40(a)(1) (2006). By not taking into account the human health effects of radiation exposure due
to ingesting contaminated water from an on-site well or ingesting plant foods irrigated with
contaminated water, Joliet did not demonstrate that permit issuance would not “[c]ause or
threaten or allow the discharge of any contaminants into the environment in any State so as to
cause or tend to cause water pollution.” 415 ILCS 5/12(a) (2006). After carefully reviewing the
record, the Board finds that IEPA correctly determined that Joliet failed to prove that issuance of
the requested permit would not result in a violation of Section 12(a) of the Act. The Board
accordingly affirms IEPA’s decision to deny Joliet’s requested permit modification.
CONCLUSION
On September 12, 2008, IEPA denied Joliet’s request to modify special condition No. 2
of Joliet’s sewage sludge land application permit. The denial was based on IEPA’s
determination that (1) Joliet’s proposal would exceed the 0.1 pCi/g radium limit of the 1984
MOA between IEPA and IEMA, and (2) Joliet did not prove that issuance of the modified
condition would not cause, threaten, or allow the discharge of contaminants so as to cause or
tend to cause water pollution in violation of Section 12(a) of the Act. The MOA limit is neither a
provision of the Act or Board regulation nor a proxy for water pollution under the Act. Further,
as applied by IEPA in the denial letter, the MOA limit is an invalid “rule,” contrary to the APA.
However, because Joliet’s modeling of residual radiation exposure from its sludge did not
account for the ingestion of water from an on-site well and the ingestion of plant food irrigated
with water from that well, Joliet did not meet its burden of proof with respect to the water
pollution prohibition of Section 12(a). On that ground, IEPA’s denial was proper, and the Board
therefore affirms.
This opinion constitutes the Board’s findings of fact and conclusions of law.
ORDER
1.
The Board denies Joliet’s motion to strike portions of IEPA’s response brief.
2.
The Board affirms IEPA’s September 12, 2008 denial of Joliet’s requested permit
modification for the reasons stated in the above opinion.
IT IS SO ORDERED.
Board Member T.E. Johnson dissented.
Section 41(a) of the Environmental Protection Act provides that final Board orders may
be appealed directly to the Illinois Appellate Court within 35 days after the Board serves the
order. 415 ILCS 5/41(a) (2006);
see also
35 Ill. Adm. Code 101.300(d)(2), 101.906, 102.706.
Illinois Supreme Court Rule 335 establishes filing requirements that apply when the Illinois
32
Appellate Court, by statute, directly reviews administrative orders. 172 Ill. 2d R. 335. The
Board’s procedural rules provide that motions for the Board to reconsider or modify its final
orders may be filed with the Board within 35 days after the order is received. 35 Ill. Adm. Code
101.520;
see also
35 Ill. Adm. Code 101.902, 102.700, 102.702.
I, John Therriault, Assistant Clerk of the Illinois Pollution Control Board, certify that the
Board adopted the above opinion and order on May 7, 2009, by a vote of 4-1 with Member
Johnson dissenting.
_________________________________
John T. Therriault
Assistant Clerk.