1. PRE-FILED TESTIMONY OF JOHN MASTRACCHIO
      2. INTRODUCTION
      3. PURPOSE
      4. COST SUMMARY
      5. CONCLUSION
      6. Testimony Attachments
      7. Attachment 1
      8. Summary of Costs to Meet Newly Proposed Effluent Standards in the Chicago Area
      9. Waterways
    1. John M. Mastracchio
      1. I
      2. Introduction
      3. Infrastructure Cost Summary
      4. Financial Summary
      5. Financial Limitations
      6. Baseline Financial Forecast
      7. Table 3 - Capital Improvement Plan (Other Projects)
      8. Scenario 1 (Chlorination/Dechlorination Disinfection)
      9. Scenario 2 (Ultraviolet Disinfection)
      10. Scenario 3 (Dissolved Oxygen)
      11. Scenario 4 (Chlorination I Dechlorination and Dissolved Oxygen)
      12. Scenario 5 (UV Disinfection and Dissolved Oxygen)
  1. Appendix A
  2. Backup Tables and Calculations
      1. Table A-tOTax Revenue Requirement Forecast Summary - Scenario 3
    1. Table A-ll
      1. Property Tax Extension Limitation - Scenario 3
      2. PRE-FILED TESTIMONY OF JOHN MASTRACCHIO
      3. INTRODUCTION
      4. PURPOSE
      5. ECONOMIC ASSESSMENT
      6. CONCLUSION
      7. Testimony Attachments
      8. Attachment 2
      9. Baseline Financial Results Compared to Financial Limitations and Restrictions
      10. Attachment 4
      11. Financial Results Including Dissolved Oxygen and ChlorinationlDechlorination
      12. Disinfection Costs Compared to Financial Limitations and Restrictions
      13. Economic Assessment
      14. July 2008
      15. Introduction
      16. Infrastructure Cost Summary
      17. Financial Summary
      18. Financial Limitations
      19. Baseline Financial Forecast
      20. Table 3 - Capital Improvement Plan (Other Projects)
      21. Scenario 1 (Chlorination/Dechlorination Disinfection)
      22. Scenario 2 (Ultraviolet Disinfection)
      23. Scenario 3 (Dissolved Oxygen)
      24. Scenario 4 (Chlorination I Dechlorination and Dissolved Oxygen)
      25. Scenario 5 (UV Disinfection and Dissolved Oxygen)
      26. ."".""'-
      27. Table A-7Tax Revenue Requirement Forecast Summary - Scenario 2
      28. Table A-8
      29. Property Tax Extension Limitation - Scenario 2
      30. Table A-16Tax Revenue Requirement Forecast Summary - Scenario 5
      31. Table A-17
      32. Property Tax Extension Limitation - Scenario 5
      33. John M. Mastracchio

BEFORE THE ILLINOIS POLLUTION CONTROL BOARD
IN THE MATTER OF:
WATER QUALITY STANDARDS AND
EFFLUENT LIMITATIONS FOR THE
CHICAGO AREA WATERWAY SYSTEM
AND
THE LOWER DES PLAINES RIVER:
PROPOSED AMENDMENTS TO 35 Ill.
Adm. Code Parts 301, 302, 303 and 304
)
)
)
)
)
)
)
)
R08-9
(Rulemaking - Water)
PRE-FILED TESTIMONY OF JOHN MASTRACCHIO
Economic Assessmentfor Disinfection Facilities
INTRODUCTION
My name
is John Mastracchio. I am a senior associate with Malcolm Pirnie and have
been a financial management, engineering, and rate consultant since 1994. My experience
includes completing studies involving municipal
utility economics and financial analysis. I hold
a Master
of Business Administration degree with a concentration in finance from Cornell
University, a Masters
of Engineering degree with a concentration in Civil and Environmental
Engineering from Clarkson University, and a Bachelor
of Arts degree from the State University
of New York. I am a Registered Professional Engineer and have received the Chartered
Financial Analyst designation from the Chartered Financial Analyst Institute. I am an active
member
of the American Water Works Association, the Water Environment Federation, and serve
on the Finance, Accounting, and Management Controls Committee
of the American Water Works
Association. A resume detailing my education and experience is presented in Attachment
6.
PURPOSE
The purpose
of my testimony is to explain the potential economic impacts of
implementing either chlorination/dechlorination or ultraviolet disinfection processes at the
Electronic Filing - Received, Clerk's Office, August 4, 2008

Metropolitan Water Reclamation District of Greater Chicago (District) water reclamation plants
that would
be necessary to meet an effluent limitation for fecal coliform of 400 colony forming
units (CFU)/100 mL, which is the treatment standard proposed
by the Illinois Environmental
Protection Agency for discharges to the Chicago Area Waterway System. The results
of this
assessment are summarized in this testimony, and are documented in greater detail in the report
entitled Economic Assessment
of Infrastructure to Meet Proposed Water Quality Standards for
Dissolved Oxygen and Plant Effluent Standards for Bacteria (Attachment 7). The economic
impacts were assessed in terms
of the District's statutory taxing authority and financial
capabilities.
COST SUMMARY
The economic assessment of implementing chlorination/dechlorination processes at the
Stickney, Calumet and Northside water reclamation plants was based
on the District spending
approximately $419 million in capital infrastructure and annual maintenance and operations
(M&O) costs
of approximately $26.0 million (expressed in 2008 dollars). The economic
assessment
of implementing ultraviolet disinfection processes was based on the District spending
approximately $491 million in capital infrastructure and annual
M&O costs of approximately
$22.1 million (expressed in 2008 dollars). A summary
of these costs are provided as Attachment
1.
The basis for these costs is documented in ChlorinationlDechlorination Cost Study
(ChlorinationlDechlorination Disinfection Cost Study for Stickney, Calumet and North Side
Water Reclamation Plants,
May 2008) and Ultraviolet Disinfection Cost Study reports
(UV
Disinfection Cost Study
-
North Side Water Reclamation Plant,
January 2008; working results of
the
Draft Stickney Water Reclamation Plant UV Cost Study
and the
Draft Hydraulic Evaluation
Technical Memorandum,
June 2008) prepared by CTE and the testimony of David
R.
Zenz.
2
Electronic Filing - Received, Clerk's Office, August 4, 2008

ECONOMIC
ASSESSMENT
The District generates revenue to fund its operations through an ad valorem property tax,
a personal property replacement tax, user charges, interest income, and other miscellaneous fees
and charges. The District'sprimary source
of operating revenue is the ad valorem property tax.
Personal property replacement tax
is primarily a tax on corporate income. User charge revenues
are collected from large commercial and industrial customers and tax-exempt customers. A
summary
of the District's revenues and expenditures for the period 2002 through 2006 is
provided as Attachment
2.
The District has several financial limitations and restrictions that directly impact its
ability to take on additional projects or programs. First, in 1995, the Property Tax Extension
Limitation Law was passed by the Illinois General Assembly, which limits the ability
of the
District to adopt future increases in the aggregate tax levy. In accordance with this Act,
increases to the District's property tax levy are limited to the lesser of: (1) five percent
or (2) the
change in the national consumer price index plus allowable increases for new property. The
aggregate levy
is the total levy of all funds except the Bond Redemption and Interest Fund and
the Stormwater Management Fund. In other words, debt service and stormwater management
costs are not included under this limitation.
Second, the District's initial Tax Cap legislation restricted the District's non-referendum
bond authority to only apply to projects initiated prior to October
1, 1991. There was a specific
exemption, essentialy to exclude Tunnel and Reservoir Plan projects from the more restrictive
provisions
of the Act which require referendum approval of all new debt. Public Act 89-385
provides the District with the authority to issue non-referendum "limited bonds" for capital
projects initiated after October
1, 1991 at the same debt service level as it did in 1994. Limited
bonds can
be issued to the extent that the total debt service requirements of any new debt, when
3
Electronic Filing - Received, Clerk's Office, August 4, 2008

combined with existing debt service, does not exceed the 1994 debt service extension base of
$141,463,920. Public Act 90-485 has provided a further modification by authorizing the
exclusion
of debt for Tunnel and Reservoir Plan projects from this debt service extension base.
Third, in 2003, the District received authority under Public
Act 93-279 to issue $150
million (previously
$100 million) of non-referendum bonds during any budget year plus
authoritzed,
but unissued bonds, during the previous three budget years through 2016.
A baseline scenario was prepared, which includes the District's currently planned capital
projects that the District feels is necessary in order to maintain and upgrade its aging facilities
and infrastructure,
but excludes the costs associated with this proposed rulemaking. The
estimated cost of the District's planned capital improvement projects were provided to Malcolm
Pimie in February 2008, and a discussion of these projects is provided in the testimony of Mr.
Tom Kunetz of the District's Engineering Department. The baseline scenario indicates that the
District would
be able to generate sufficient revenues to satisfy the District'sprojected revenue
requirements within the constraints
of the legal limitations I just discussed. In addition, the
District's debt financing needs will not exceed the Tax
Cap legislation limits or the District's
non-referendum bonding authority through fiscal year 2015. A summary
of the District's
projected results compared to the financial limitations and restrictions are provided as
Attachment 3 (Figures 3-1, 3-2 and 3-3).
However, the District does not have sufficient financial resources to fund the capital
expenditures and operation and maintenance costs necessary to disinfect its discharges to meet
the IEPA proposed bacterial effluent standard, either through chlorination and dechlorination
or
through ultraviolet disinfection. The District cannot generate sufficient revenues within the
constraints
of the Property Tax Extension Limitation Act, and the remaining funds needed would
4
Electronic Filing - Received, Clerk's Office, August 4, 2008

exceed the District'sTax Cap and non-referendum bonding authority. A summary of the
District's projected financial results as compared to the financial limitations and restrictions is
provided in Attachment 4 (Figures 4-1, 4-2 and 4-3) for the chlorination/dechlorination option
and in Attachment 5 (Figures 5-1, 5-2 and 5-3) for the ultraviolet disinfection option.
It should be noted that effluent limits for phosphorus and total nitrogen may be imposed
on the District's treatment plants in the future. The District'scurrently planned capital projects,
which were used in the baseline analysis, do not include the costs to implement nutrient removal
processes. As documented in a District cost summary table provided in Attachment
8, a
rudimentary, order-of-magnitude cost estimate prepared
by the District indicates that the capital
costs to construct nutrient removal processes could be approximately $2.8 billion dollars.
CONCLUSION
Full funding of the activities necessary to achieve compliance with IEPA's proposed rule
would require an act
of the state Legislature to amend the Property Tax Extension Limitation Act
and provide additional non-referendum bonding authority; a voter referendum in support
of
additional bonding authority; or drastic reductions in the funding of other District programs.
Furthermore,
if implemented, disinfection would leave no financial capacity to fund other
programs not currently included in the District'scapital plan. One such project not currently
included
in the District's capital plan is nutrient removal facilities at its treatment plants, which
could cost approximately $2.8 billion
if nutrient effluent limits are imposed in the future.
5
Electronic Filing - Received, Clerk's Office, August 4, 2008

Respectfully submitted,
fld~
By:
John Mastracchio
Electronic Filing - Received, Clerk's Office, August 4, 2008

Testimony Attachments
1.
Summary of Costs to Meet Newly Proposed Water Quality Standards in the Chicago
Area Waterways
2.
MWRD Summary of Financial Results
3.
Baseline Financial Results Compared to Financial Limitations and Restrictions
4.
Financial Results Including Chlorination/Dechlorination Disinfection Costs
Compared to Financial Limitations and Restrictions
5.
Financial Results Including Ultraviolet Disinfection Costs Compared to Financial
Limitations and Restrictions
6.
John Mastracchio Resume
7.
Report entitled Economic Assessment of Infrastructure to Meet Proposed Water
Quality Standards for Dissolved Oxygen and Plant Effluent Standards for Bacteria,
prepared by Malcolm Pimie, Inc.
8.
Rudimentary, Order-of-Magnitude Cost Estimates for Nutrient Removal at District
Water Reclamation Plants prepared
by the District
6
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 1
Summary
of Costs to Meet Newly Proposed Effluent Standards in the Chicago Area
Waterways
AnnualO&M
Total Present
Project Description
Capital Cost
Cost
Value Cost
SWRP
ChlorinationlDechlorination Disinfection
$225,700,000
$15,900,000
$533,500,000
Ultraviolet Disinfection
267,200,000
12,600,000
511,200,000
CWRP
ChlorinationlDechlorination Disinfection
$79,100,000
$5,020,000
$176,500,000
Ultraviolet Disinfection
112,300,000
4,600,000
201,600,000
NSWRP
ChlorinationlDechlorination Disinfection
$114,200,000
$5,040,000
$212,000,000
Ultraviolet Disinfection
111,600,000
4,900,000
206,800,000
Total
ChlorinationlDechlorination Disinfection
Ultraviolet Disinfection
$419,000,000
491,100,000
$25,960,000
22,100,000
$922,000,000
919,600,000
All costs in 2008 dollars.
Source:
Chlorination/Dechlorination Disinfection Cost Study for Stickney, Calumet and North Side Water Reclamation Plants
(CTE,
May 2008);
UV Disinfection Cost Study
-
North Side Water Reclamation Plant
(CTE, January 2008); working results of the
Draft
Stickney Water Reclamation Plant
UV Cost Study
and the
Draft Hydraulic Evaluation Technical Memorandum
(CTE, June 2008).
Subsequently updated to June 2008 dollars. Present value costs over 20 years based on a 3.0% interest rate and a 3.0 percent inflation
rate.
7
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 2
- MWRD Summary
of Financial Results
(in $ Thousands, Modified Accrual Basis)
2002
2003
2004
2005
2006
Revenues
Property Taxes
$
362,036
$
397,751
$
360,326
$ 423,941
$
380,675
Personal Property Replacement Tax
22,285
24,048
25,961
36,031
37,743
User Charges
48,890
50,222
47,757
45,983
52,504
Interest on Investments
15,693
13,163
9,943
19,693
43,659
Other Revenues
14,759
16,203
16,495
16,309
17,691
Total Revenues
$ 463,663 $
501,387
$
460,482 $ 541,957
$
532,272
Expenditures
General Administration
$
14,318
$
14,987
$
15,538
$
17,259
$
16,974
Personnel
27,610
30,916
35,877
32,900
35,162
Pension Costs
27,044
29,511
27,372
31,561
30,071
Research and Development
23,838
24,172
24,030
24,787
24,985
Information Technology
11,204
11,417
10,574
10,811
11,034
Maintenance and Operations
160,326
159,079
160,299
157,612
155,899
Other
32,843
22,563
27,637
31,522
26,931
Construction Costs
157,076
164,865
127,155
133,599
164,157
Debt Service
145,831
158,626
156,025
169,019
171,869
Total Expenditures
$
600,090
$
616,136
$
584,507 $ 609,070
$
637,082
Revenues Over (Under) Expenditures
$ (136,427) $ (114,749) $ (124,025)
$ (67,113) $ (104,810)
Other Financing Sources (Uses)
222,622
223,613
52,720
15,973
383,448
Net Change in Fund Balance
$
86,195 $ 108,864
$
(71,305) $ (51,140) $ 278,638
Source: Comprehensive Annual Financial Reports (2003-2006).
8
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 3
Baseline Financial Results Compared to Financial Limitations
and Restrictions
Figure 3-1 - Capital Improvement Plan - Baseline
CAPITAL PROGRAM EXPENDITURES
_Sewer
$600,000
$500,000
$400,000
.fl
c
$300,000
..
"
0to
$200,000
.c
...
I-
$100,000
$0
~
0
5
'"
Plant
_TARP
-CIBFCash Balance
Figure 3-2
Forecasted Aggregate Tax Levy Requirement Compared to Tax
Cap Limitation - Baseline
$410,000 ..,------------------------------,
$390,000
+--------------------------::------j
'" $370,000
-t------------------------~"""F::....-_1
'I:l
I
$350,000
~
$330,000
+-----------------:::;_.-=~
~
$310,000
+--------------,,~....,
<it $290,000
t-----:=---'f'-r---l
$270,000 .<--...-1=---I
$250,000 +-J'--'--r-.L---'---.---'--'-.,..-L..-.1--,--I.--I.--r--l--l--.--.L-..I...-,---J........I-,-....L..-L.-,-..L--'---j
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
~
Projected Tax Levy Requiremenl(ExcludingSt:lrmwaterCostand DebtService)
-
Tax Levy extension Limitation (CPJ + New Property)
Figure 3-3
Forecasted Debt Service Compared to Debt Service Extension Base - Baseline
$160,000
$140,000
$120,000
",$100,000
'I:l
; $80,000
:>
,g
$60,000
~
$40,000
$20,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
...Projected Amountof Limited Debt8ervlce
9
-
DebtService EXSEmsion limitation
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 4
Financial Results Including ChlorinationJDechlorination Disinfection Costs Compared to
Financial Limitations
and Restrictions
Figure 4-1 - Capital Improvement Plan
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-s..-
$600,000
Plant
_Tarp
,,',./'.Projects to Meel Proposed Standards
-CIBF Cash Balance
$500,000
$400,000
.fl
:
$300,000
:::l
..
~
$100,000
$200,000
$0_.-
Figure 4-2
Forecasted Aggregate Tax Levy Requirement Compared to Tax
Cap Limitation
$430,000 .,...------------------------------,
$410,000
+-------------------------~
$390,000
+-----------------------1
III
~
$370,000 +-------------------------:::::oo__'F--1
~
$350,000
+-----------------------::::;ortf/ll'r
l-
,g
$330,000 +-----------------=_rtf"2q
o
.E $310,000
+-------------=:::::;;;;1,.,....,.-
$290,000
+------::::::::~~"F_____l
$270,000 -1--"'-":::;'---1
$250,000 +-'--J..-,,---'-----L---,-...........-'----.--'---'-......-''-'--T-L.---L---,--'-
...........
,...-.L...-..L..-...........---'---,---'--'----l
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
c::::::::J
Projected Tax Levy Requirement(Excluding StonnwaterCostand Debt Service)
-
Tax Levy Extension
limitation (CPI + New Property)
Figure 4-3
Forecasted Debt Service Compared to Debt Service Extension Base
$200,000
$160,000
$160,000
$140,000
~$12O,000
=$100,000
5 $60,000
.c
~
$60,000
.E $40,000
$20,000
$0
2006
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Amountof Limited DebtService
10
-
DebtService Extension Limitation
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 5
Financial Results Including Ultraviolet Disinfection Costs Compared to Financial
Limitations
and Restrictions
Figure 5-1 - Capital Improvement Plan
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Se\YElr
$600,000
$500,000
$400,000
-B
..
III
c:
$300,000
::l
0
.c:
$200,000
I-
<It
$100,000
$0
CD
~
Plant
_Tarp
.~;._;
Projects to Meet Proposed Standards
-
aBF
Cash
Balance
:."':-:.:-:.:~~~
..'j, ••••••••••
"
~
",
",
..
..............•..........••
""
~~~~~~~~~~~~~~~~~~.
.
.
...
~
....:.:.l..
~':.~·;i;··~···
....
~~~~~S~~~~~~~~~~~~~~~~~~S~~~:
")T)······~
..
~··~··~··~$~$~m~:
Figure 5-2
Forecasted Aggregate Tax Levy Requirement
Compared to Tax Cap Limitation
$430,000 -r----------------------------,
$410,000 +---------------------------fr--1
$390,000 +--------------------------1
III
~
$370,000
+-------------------------=__
'F-----l
~
$350,000 +--------------------=.......
l-
~
$330,000
+------------------=:l_f"2~
.= $310,000 +--------------,=--....-
*
$290,000
+------=_-;~_1
$270,000 +--.....
-.=::.~
$250,000
+-'--.I-.,.................---,--'---'--,--'---'-,..-'--'-,----'---'----r-'--'--,--'---'-
..........
'---''--,---'----'---1
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
c::::==I
Projected Tax Levy Requirement(Excludlng StormwaterCostand Debt Service)
--Tax Levy Extension limitation (CPI + New Property)
Figure 5-3
Forecasted Debt Service Compared to Debt Service Extension Base
$250,000
$200,000
~$150,000
!I
5$100,000
.c
ti
.s $50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Amountof Limited DebtService
11
-
DebtService Extension
Limita~on
Electronic Filing - Received, Clerk's Office, August 4, 2008

ATTACHMENT 6
John
Mastracchio CV
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio. P.E .. CF A
Mr. Mastracchio
is a senior financial analyst specializing in municipal
utility economics, financial analysis, capital and financial planning, cost of
service evaluation, the design of rates, fees, and charges, and utility
valuation. Mr. Mastracchio is a member of the Finance, Accounting &
Management Controls
committee of the American Water Works
Association where he participates on
the capital financing and valuation
subcomittees, and
is a member of the Water Environment Federation and
the Chartered Financial Analyst Institute.
He is a contributing author of
the utility Capital Financing Manual of Practice (M29) and routinely
speaks at national and regional conferences and meetings on the topics
of regionalization, financial planning, rate-setting, and valuation.
REPRESENTATIVE EXPERIENCE
• Confidential Client: Due Diligence Review for Water System
Acquisition
I
New York City NY.
Task Leader for the financial analysis
as part of a due diligence investigation for the acquisition of a Water
Company
in the eastern U.S. Services included assistance in developing a
long-term capital improvement plan, review and development
of financial
modeling assumptions regarding supply
and demand, operation and
maintenance costs, capital expenditures
and general rate setting
methodology
in accordance with each state's rate setting requirements.
Recommendations regarding the acquisition and future capital and
operating requirements including projections of revenues and rate
of
return for each of five regulated utilities were presented.
City of Columbus: Comprehensive Rate and Charge Study
I
Columbus
OH.
Completed a cost-of-service evaluation and rate, fee, and charge
assessment
to assist the City of Columbus generate sufficient revenues
to pay
for upcoming water and sewer capital improvement and operation
and maintenance programs.
The project included completing a cost-of-
service evaluation to determine the cost responsibility of the city's
customers, water and sewer asset valuations to support connection fee
development, and a rate structure evaluation to identify water and sewer
rate structures
that were closely aligned with the cost of providing
service and developing rate formulas
for the city's future use. Based on
the results of this study, the city changed its water rates from a declining
block structure to a "lifeline" rate and
an inclining block structure for
residential customers. The city also implemented a separate charge to
customers to pay
for its upcoming $2.5 billion wet weather capital
program. This charge recovers the cost of the program based upon the
impervious surface area of the city's customers. Presented study results
to city staff, city council, and other stakeholders using interactive
financial modeling tools that were developed
for the client.
• Credit Suisse First Boston: Columbia, SC.
Acting on behalf of several
investment banking firms, reviewed of the estimates of environmental
liability reported to the Securities and Exchange Commission by a publicly
John M. Mastracchio
Title/Firm:
Senior Associate
Red Oak Consulting, A Division of
Malcolm Pirnie, Inc.
Years of Experience
13
Education
BA State University of New York at
Geneseo 1993
MS Civil and Environmental Engineering
Clarkson University 1994
MBA Finance Cornell University 2001
Licenses and Certifications
Professional Engineer
Chartered Financial Analyst
Societies
American Water Works Association,
F;inance, Accounting
&
Management
Controls Committee
Chartered Financial Analyst Society
of
Rochester
Government Financial Officers
Association
Water Environment Federation
Employment History
Red Oak Consulting, a Division of Malcolm
Pirnie, Inc.
2002 to present
Arthur Andersen, LLP. 2001 to 2002
Parsons Engineering Science. Inc. 1994 to
2000
A282007
I
WHI
Pathways to Lasting Solutions
:.:::
RHIDA K
'. • ••.
CONSULTING
• ••
A DIVISION or MALCOLM
PIRr~lE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
traded, national, environmental services company. This project
was
accomplished by reviewing pertinent SEC filings, environmental liability
reporting policies and procedures established
by the Company,
requirements of F
ASB Statement No.5 and SFAS Statement No. 143
related to reporting of environmental contingent liabilities and asset
retirement obligations, and information gathered through site visits,
interviews with regulators, site assessments, Superfund site reviews,
and
landfill useful life estimates provided by other Malcolm Pirnie team
members. This information
was assessed and used to form an opinion
about the reasonableness
of the estimates of environmental liability
prepared by the Company. Our clients, the investment banking firms,
relied
on our efforts as underwriters for the bonds to be issued by the
Company and
as agents and lenders with respect to a credit agreement
entered into
by the Company. In addition, other lenders participating in
the syndicate also relied on our report from a credit agreement
perspective.
• Countryside Village North. City of Anderson: Anderson utility
System Valuation
I
Anderson IN.
Completed a valuation of the
Countryside Village North sewer system to support the negotiated sale of
the system to the City of Anderson.
The sewer system consisted of
approximately
3,000 linear feet of sewer, one lift station, 4,000 linear
feet
of force main, and associated appurtenances.
City of
Delaware: Financial Services
I
Delaware OH.
Provided expert
advice to the city
in support of financing wastewater capital
infrastructure improvements
in anticipated future city growth. Reviewed
and evaluated wastewater impact fee methodologies and fee levels.
Recommended changes to the existing wastewater fee structure to
address the city's concerns about rate equitability
for multifamily and
single-family residential customers, and
to ensure that growth pays for
itself.
Erie County Dept. of Environment and Planning: utility Merger
Feasibility Study
and Asset Management Evaluation
I
Buffalo NY.
Managed the evaluation of the feasibility of consolidating three adjacent
wastewater systems into Erie County Sewer Districts. Managed the
financial evaluation of the impacts
of consolidating included potential
cost savings and impacts
on customer taxes and user fee rates. Managed
the completion of a financial impact analysis and sewer rate plan
as part
of an overall asset management program for the County. The project
included evaluation
of capital improvement program alternatives using an
interactive financial model that supported the creation of an asset
management plan.
• Erie County Dept. of Environment and Planning: ECDEP Asset/Finac
I
Buffalo NY.
Managed the completion of a financial impact analysis and
sewer rate plan
as part of an overall asset management program for the
County.
The project included evaluation of capital improvement program
alternatives using
an interactive financial model, supporting the creation
of
an asset management plan, developing a baseline condition
A282007 / WHI
Pathways to Lasting Solutions
..
:::
RElIDAK
....0
0
••
CONSULTING
• ••
'" DIVISION
or
MALCOLM PIRt41(
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
assessment
of major plant and buried assets, evaluation of strategic
business drivers, development of project prioritization methodologies,
and preparation
of the final CIP document, including a detailed financial
impact analysis and
utility rate plan.
• City of Fort Wayne: Valuation in Support of utility Acquisition! Fort
Wayne IN.
Completed a valuation of a private water and wastewater
utility regulated by the Indiana Utilities Regulatory Commission using
asset- and market-based valuation approaches. The valuation estimate
was provided to the City's attorney to support settlement negotiations
and condemnation.
• City of Grand Forks: Rate Study and Cost-of-Service Evaluation!
Grand Forks. NO.
Completed a financial evaluation of the city's water,
wastewater, solid waste, and stormwater utilities. The evaluations were
conducted
to ensure that the costs associated with planned capital
infrastructure investment and the operations of each utility were
allocated equitably
to each customer class based on its service
requirements. Evaluated the financial affordability of capital
improvement plans. Developed cost allocation methodologies using sound
engineering, financial, and rate-making practice. Developed
nonproprietary revenue adequacy models
to provide the city with a basis
for the evaluation of alternative rate structures and to ensure that all of
the appropriate costs
of operating the utility were reflected in the rates.
• Greene County: Capital Planning Study! Dayton OH.
Provided capital
investment decision-making support and planning assistance for county
municipality
in Dayton, Ohio. Developed an affordable financial plan for
paying for the capital infrastructure investments that were identified in
the study. Developed an interactive financial model that was used during
the project
to assess the impact various capital improvement programs
and financing alternatives on the County's wastewater rates. Conducted
an in-depth evaluation of the parameters that impacted affordability,
developed a financial plan that identified the most cost effective project
financing alternatives, and presented 20-year pro forma financial
projections
for the County under several different scenarios and
assumptions.
• Borough of Haledon: Valuation in Support of Utility Acquisition!
Haledon NJ.
Completed a valuation of a municipal water system in New
Jersey
to assist the client in making acquisition decisions. The valuation
was completed to establish a baseline for the utility system and its
negotiated sale.
• The Harrisburg Authority: Financial Capability Assessment!
Harrisburg PA.
Completed a Financial Capability Assessment to measure
the impact
that the Authority's Long-Term Control Plan will have on both
the current and
future financial health of the service area. Determined
the service area's average wastewater
treatment and CSO
implementation cost per household, and evaluated debt. socioeconomic,
and financial management indicators of financial capability,
A282007
I
WHI
Pathways to Lasting Solutions
:.:::
REIIDAK
" • •• ,
CONSULTING
• ••
A DIVISION or MALCOLM PIRNIE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CFA
I
Recommended a capital improvement implementation schedule that
would minimize the financial impact
to customers, based on the results of
the assessment.
• Henrico County: Water and Sewer Rate Study / Richmond VA.
Completed a cost of service evaluation and rate, fee, and charge study to
assist Henrico County develop a sustainable financial management plan,
determine revenue requirements over the next ten years,
and ensure
equitable recovery of costs. The study also consisted of completing
an
asset valuation to support the development of impact fees to ensure that
growth pays
for itself over the planning period. The financial
management plan
was developed using an interactive forecast model that
allowed alternative scenarios to be easily evaluated. Connection fees, fire
protection charges, and local facility fees were established by
determining the costs of providing these services and developing fees
to
equitably recover these costs from customers utilizing the services. Rate,
fee, and charge formulas were developed
for the County's $80 million
operating budget.
City
of
Kingston: Wastewater Rate Study / Kingston, NY.
Completed a
wastewater rate study
to assist the City pay for its capital improvement
program, develop a sustainable financial management plan,
and
determine future revenue requirements. Developed an interactive rate
model
for forecasting revenue requirements and user rates. Presented
rate recommendations
to City officials.
• Kinderhook Industries, LLC: Environmental Liability Assessment /
Berwyn, PA.
Completed a financial evaluation in support of an
environmental compliance/liability assessment to support acquisition of a
firm
in the remedial construction and Resource Conservation and
Recovery Act
(RCRA) hazardous waste management business with three
RCRA treatment, storage, or disposal facilities (TSDFs). Financial
evaluation consisted of reviewing the reporting requirements of F
ASS 5
and
SFAS 143 to ensure environmental liability estimates prepared by
Malcolm Pirnie satisfied accounting and reporting requirements. Utilized
the expected cash flow approach
for calculating environmental liabilities,
compared liability estimates with those reported
on the company's
financial statements, and prepared cost and cash flow estimates.
• City of Lorain: Wastewater Regionalization Study / Lorain, OH
Managed the completion of a wastewater regionalization study to
evaluate the feasibility of constructing a regional wastewater treatment
plant and conveyance system to serve customers throughout Lorain
County. Assessed the capital and
O&M costs associated with the regional
entity, developed financial models
to project revenue requirements and
rates under the regional approach and under status quo. Facilitated
discussions with stakeholders pertaining
to the costs and benefits of
regionalization.
• LS Power, LLC: Economic Impact Assessment / West Deptford, NJ.
Assessed the potential economic impact of the construction and
operation
of a modern coal-fired power plant in West Deptford Township,
A282007
I
WHI
Pathways to Lasting Solutions
:0:::
RHIDAK
....
•• ,
CONSULTING
• ••
14. DIVISION
or
MALCOLM PIRNI(
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
New Jersey. Utilized IMPLAN® software to assess the economic impacts
of a
500 MW coal fired power plant on an 11 county region. Examined the
direct and indirect economic benefits
to the region, effects of the project
on local employment and economic output. during construction and post
construction, and evaluated the potential peak economic stimulus.
Prepared report that provided information
to elected officials and other
stakeholders
to support a decision to proceed with the project.
• City of Lancaster: Engineer's Feasibility Report
and Rate Study
I
Lancaster OH.
Completed an Engineer's Feasibility Report to support the
release of bond disclosure documentation
for the issuance of $8 million
waterworks revenue bonds. Subsequently completed a sewer rate study
consisting of projections of rate revenue requirements considering
various capital improvement programs, and growth scenarios,
development
of sewer rate and connection fee recommendations,
evaluation of customer affordability, and comparison of sewer rates
in
nearby communities.
Completed a comprehensive water rate and charge study
to support the
client's capital investment planning process. The project included
assessing alternatives
for financing water system capital investments and
completing a cost-of-service evaluation
to equitably recover utility costs
from rate payers.
In addition, a nonproprietary financial planning and rate
design model
was developed to assist in the pricing of utility services.
Detailed analyses of customer costs, usage characteristics, capital
improvement program costs,
and neighboring utility rate comparisons
were conducted
to support the design of the rate components.
• Macomb County: Wastewater Treatment Plant Acquisition Evaluation
I
Mt Clemens, MI
Managed the completion of a preliminary evaluation of
wastewater treatment plant ownership and
joint use options for Macomb
County. Completed a financial evaluation of alternatives that provided a
projection of future capital and
O&M costs, and assessed the future rate
implications
of each option. Estimated the value of wastewater system
assets and evaluated asset transfer pricing
that would result in a win-win
for all involved parties. Served as a financial and technical resource for
assessing asset transfer and deal structure alternatives.
• Maricopa Water District: Wholesale Water Service Agreement
Development
I
Phoenix AZ.
Assisted in the development and
negotiation of a water treatment plant financing agreement with
an
investor-owned water company. Developed water and water rate and
pricing formulas
for inclusion into the capital lease and other supporting
documentation. The capital lease agreement provided the client with a
reasonable rate of return and ensured
that financing requirements, such
as legal debt service coverage and capital reserve requirements would be
met under many foreseeable future scenarios. Developed and provided
an interactive rate-setting and financial planning model for use during the
development and negotiation of the agreements. Worked with the client's
legal council
in developing the terms and conditions of the agreement.
Provided expert testimony before the Arizona Corporation Commission
A282007
I
WHI
Pathways to Lasting Solutions
:.;::
REIIDAK
•• •
0".
CONSULTING
••
A DIVISION
or
MALCOLM
PIRr~lE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio. P.E.. CF A
regarding the financial impact of the District constructing
and operating
its own water treatment plant.
• Milwaukee Metropolitan Sewerage District: MMSD O&M Options
Analysis
I
Milwaukee WI. Assisted MMSD in evaluating the feasibility of
continued contract operations or the feasibility of District operation of
their wastewater
treatment facilities. Assisted in the evaluation of
alternative forms of privatization as applied to a number of its service
areas including wastewater treatment and sludge disposal. Assisted
in
the efforts to establish submittal requirements relating to financial
capability and cost bids and participated
in the review and evaluation of
these areas
for the submitted proposals.
• City of Marysville: Wastewater Master Study
I
Marysville OH.
Completed financial planning studies in support of the development of
water and wastewater capital investment plans and the issuance of
revenue bonds. Analyzed the affordability of recommended capital
investment alternatives and associated impacts
to the city's long-term
financial position. Developed
an interactive financial planning model to
guide the planning process and assist the city in making capital
investment decisions. Completed a wastewater pricing evaluation
to
develop wastewater rates for the city that reflected the cost of providing
service and ensured adequate funding
for the city's upcoming $200
million capital improvement program. Prepared a bond feasibility report
supporting the issuance
of approximately $150 million in revenue bonds
and bond anticipation notes.
• Metropolitan Distrct Commission: Valuation Assessments
I
Hartford
CT. Completed valuations of publicly-owned and investor-owned water
utilities regulated by the Connecticut Department
of Public Utility Control
to assist our client
in making utility acquisition decisions. The target
utilities provide water service to more than
200,000 people in the
northeastern
US. The estimates of value were determined utilizing
different valuation techniques
to estimate the potential value of the
water systems, including the asset and income approaches. Mr.
Mastracchio's efforts and experience
in valuating public utilities
supported the client's strategic expansion objectives.
• Metropolitan District Commission: Financial Analysis and Pricing for
the Development of Inter-jurisdictional Agreements
I
Hartford CT.
Completed financial analyses and pricing of water service for
intergovernmental water service agreements to allow the Metropolitan
District Commission
to maximize its utilization of its excess water supply
capacity and generate additional revenues by selling this capacity
to
neighboring private water companies. The project involved developing
terms and conditions of the agreement.
as well as developing and
recommending a wholesale water rate and capacity charge structure. The
wholesale rate
was developed by evaluating the costs of operating the
water utility using a financial model. The capacity charge
was based on
the net value
of the Commissions fixed assets and available water supply
A282007
I
WHI
Pathways to Lastlll,lJ SolutIons
:.::: REIIDAK
.. ".". CONSULTING
• ••
A DIVISION
or
MALCOLM PIRtlJ(
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
capacity and
was designed to recognize the value of the additional water
supply capacity, which would
be dedicated to the private water company.
City of Miamisburg: Bond Engineering Report and Rate study!
Miamisburg OH. Completed a bond feasibility report to support the
issuance of
$2 million in 2004 waterworks revenue bonds. Bond
feasibility analysis included a description of the system and the
improvements, summary of historic and projected system demands, a
cash flow analysis, a comparison of water rates with those of other cities,
and
an opinion of the adequacy of the rates and cash flows of the city.
Completed a water and sewer rate study
for the City consisting of
projecting revenue requirements over a five year period, assessing the
impact
of various capital improvement program scenarios, developing
cost justified water and sewer rates, and completing a survey of water
and sewer rates
of nearby communities.
• Nassau County: Water
Utility Consolidation Study! Mineola, NY.
Evaluated the feasibility
of consolidating 46 water systems within Nassau
County into one or more management organizations. Assessed the
potential
for cost savings and the impact on residential ad valorem taxes
and user fees. Assessed the environmental benefits of a regional
approach to water resources. Prepared reports and presented findings to
the County Executive of
Nassau County.
state of New Jersey, Department of the Public Advocate: Water
Utility Valuation / Newark, NJ. Served as a valuation expert and
provided testimony
in the matter of the Joint Petition of the City Trenton,
New Jersey and New Jersey American Water Company, Inc. for
authorization of the purchase and sale of the assets of the outside water
utility system of the City of Trenton,
New Jersey.
• Newark Watershed Conservation and Development Corporation:
Wasewater
Asset Condition Assessment and Valuation! Newark, NJ.
Supported efforts to complete an asset condition assessment and
valuation of the City
of Newark's wastewater system to assist the Newark
Watershed Conservation
and Development Corporation (NWCDC) and the
City of Newark
in their consideration of the formation of a Municipal
Utilities Authority.
City of Newark: Wastewater Rate Study! Newark, OH. Project
Manager
for a wastewater rate and charge study. The project included an
evaluation of the City's rate structure, development of a nonproprietary
rate model, detailed analyses of customer costs, usage characteristics,
and capital improvement program costs, and presentation
of rate
recommendations to City Council.
In addition, neighboring utility rate
comparisons were completed to support the design of the rate
components.
City of Norwalk: Financial Planning and Rate Study! Norwalk CT.
Completed a financial planning study in support of a long-term
wastewater master plan. Analyzed capital investment alternatives and
associated impacts to City wastewater rates. Developed
an interactive
A282007
I
WHI
'Pathways to Lastlnq Solutions
: .; :: RErIDA K
" •• ". CONSULTING
• ••
A DIVISION
or
to4ALCOL~
PIRtJI[
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
financial planning model
to utilize throughout the planning process and
assisted the City
in making capital investment decisions. Completed
system asset valuation estimates
to support connection fee development.
Presented rate recommendations at budget hearings with the City
Commission.
• City of Painesville: Pricing of Utility Services
I
Painesville OH.
Developed an intergovernmental wastewater service agreement to allow
the City of Painesville
to maximize its utilization of its excess wastewater
treatment capacity
to neighboring county customers. The project
involved developing terms and conditions of the agreement.
as well as
developing and recommending a wholesale rate and capacity charge
structure. The wholesale rate
was developed by evaluating the costs of
operating the city's wastewater
utility using a financial model. The
capacity charge
was based on the net value of the city's fixed assets and
available wastewater treatment capacity and
was designed to recognize
the value of the city's additional system capacity, which will
be sold to the
county.
• City of Reno: Wastewater Cost of Service Evaluation and Rate Study
I
Reno, NV. Developed a financial plan and wastewater utility pricing
schedules
for the City of Reno. Project helped to ensure the funding and
financing of the City's wastewater
utility capital investment needs.
Developed
an interactive financial model that was used to evaluate future
rate revenue requirements, determine the cost
of providing wastewater
service, and determine equitable connection fees based on the estimated
value of fixed assets and the cost of wastewater system expansion.
Advised the City
in the design a rate structure that was aligned with the
City's needs and financial objectives. Presented study results
to City staff,
city council and other stakeholders using interactive financial modeling
tools that were developed
for the client.
• Saratoga County Water Authority: Water Bond Feasibility Report
I
Saratoga, NY. Prepared an engineering and financial feasibility report for
the issuance of $40 million in water system revenue bonds to finance the
construction of water treatment plant. raw water pipeline, pump station,
and distribution mains.
• Summit County: Comprehensive Rate and Charge Study
I
Akron OH.
Completed a cost of service evaluation and rate, fee, and charge
assessment
to assist the County to generate sufficient revenues to pay
for upcoming sewer capital improvement and operation and maintenance
programs. The project included completing a cost
of service evaluation to
determine the cost responsibility of the County customers, wastewater
asset valuation estimates
to support capacity fee development, and a
rate structure evaluation
to identify sewer rate structures that were
closely aligned with the cost of providing service, and developing rate
formulas
for the County's future use.
• U.S. Air Force Material Command: Hill AFB EUL
I
Ogden UT. Senior
Analyst
for the valuation and financial analysis of a proposed Enhanced
:
A282007
I
WHI
Pathways to Lasting Solutions
:.;;: RE[[)AK
'. • ee.
CONSULTING
... "
A DIVISION
or
MALCOLM
PIRr~lE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CFA
Use Lease (EUL) at Hill Air Force Base. The analysis included evaluating
real estate market conditions and land sales data, completing a life cycle
cost analysis of Air Force office space procurement options and
developing valuation models
for potential site development scenarios.
Other activities included developing the financial portion of the Business
Case analysis, supporting presentations to leadership, responding to
technical questions and developing potential site development scenarios.
• Utilities Inc: Strategic Financial Consulting
I
Northbrook, IL.
Managed
the completion of financial assessments, and projections of performance
and value
for more than 90 operating companies of an investor-owned
utility located in Arizona, Florida, Georgia, Illinois, Indiana, Kentucky,
Louisiana, Maryland, North Carolina, New Jersey, Nevada, Pennsylvania,
South Carolina, Tennessee, and Virginia. Provided analysis results to the
senior leadership team of Utilities, Inc.
• City of Virginia Beach: Financial Services
I
Virginia Beach VA.
Served
as project manager for a multi-year financial services contract for the
City of Virginia Beach that included true-up evaluation, developing
an
interactive financial planning model, and completing a cost of service
evaluation.
The true-up evaluation consisted of reviewing the City of
Norfolk's cost allocation model
for allocating operation and maintenance
expenses, reviewing the rate model
for allocation of fixed assets, and the
rate
of return on rate base for reasonableness. The cost of service
evaluation consisted of assessing
future capital funding needs for the
water and sewer utilities due
to aging infrastructure, system expansion,
and new regulations, determining revenue requirements over a five
to ten
year period, and developing rates, fees and charges to meet revenue
requirements and other City rate-setting goals and objectives.
• Virgin Islands Public Services Commission: Expert Testimony
I
St
Thomas, VI.
Served as financial and rate expert for the U.S Virgin Islands
Public Services Commission regarding Waste Management Authority's
solid waste and wastewater
utility rate cases. Reviewed financial and rate
aspects
of the Authority's filings, prepared written testimony, and
presented oral testimony before the Public Services Commission.
Application involved establishment of new Authority Environmental User
Fees and Wastewater User Fees. Technical issues reviewed involved
reasonableness of the rate revenue requirements, fairness and
equitability of the rate structure, and affordability issues.
• Westchester Joint Water Works: Water Rate Study
I
Westchester,
NY.
Completed a comprehensive rate study for Westchester Joint Water
Works and its member municipalities. Evaluated revenue requirements
and the cost
to serve wholesale and retail customers, developed rate
models, and worked with Client and member municipalities
to evaluate
water rate structure alternatives.
Wayne County, Department of Environment: Comprehensive
Assessment
and Master Plan
I
Detroit MI,
Completed a financial
evaluation
in support of a comprehensive utility assessment and master
A282007
I
WHI
Pathways to Lasting Solutions
:.:::
RE[[)AK
'.0
0
°.
CONSULTING
• ••
,., DIVISION Of h4ALCOLIo4 PIRtll[
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
plan. Assessed the client's level of competitiveness, vulnerability
to
privatization, and degree of organizational alignment from a financial
perspective. Developed a cost allocation model that
was used throughout
the project. Evaluated many aspects of the client's financial operations
including a detailed evaluation of
DOE's rate and fee structure, as well as
a critical review of administration, finance, accounting, and general
management policies and procedures. Based on the evaluation,
recommended revising and consolidating
DOE's fee structure.
EXPERT TESTIMONY
Valuation Expert in the Matter of the Joint Petition of the City Trenton, New
Jersey and New Jersey American Water Company, Inc. for Authorization of
the Purchase and Sale
of the Assets of the Outside Water utility System of
the City
of Trenton, New Jersey,BPU Docket No. WM08010063.
Municipal Utility Rate Expert
in the Application for Approval of
Environmental User
Fee and Wastewater User Fee in the United States Virgin
Islands by the Virgin Island Waste Management Authority, Docket Number
554, before the Governement
of the Virgin Islands Public Services
Commission.
Rate Expert
In the Matter of the Application of Arizona-American Water
Company,
Inc. for Approvals Associated with a Proposed Transaction with
Maricopa Water Conservation District Number
One To Allow the Construction
of a Surface Water Treatment Facility Known
as the White Tanks Project,
Docket
No. W-01303A-05-0718, before the Arizona Corporation Commission.
PUBLICATIONS AND PRESENTATIONS
Mastracchio, J.M..
Capital Project Funding, Improving Your Success Rate,
presented at the Greater Buffalo Environmental Conference, Buffalo, NY, March 18, 2008.
Mastracchio, J.M., et. al.
Water Capital Financing, Manual of Practice M29,
contributing author and workshop presenter at the American Water Works Association
Annual Conference and Exposition, Toronto, Canada. June 23, 2007.
Mastracchio, J.M.,
"Economic and Financial Elements of Water utility
Facilities Master Planning,"
presented at the Spring Meeting of the American Water
Works Association, New York Section, Saratoga Springs
NY, April 24-27, 2007.
Mastracchio, J.M.,
"Budget Forecasting in the New Construction Cost Era -
It's Not as Simple
as the ENR Anymore,"
presented at the Conference of the
United States Society
of Dams, Pittsburgh PA, March 7, 2007.
Gangemi,
A.N, Mastracchio, J.M.,
"Dynamic utility Financial Modeling - A Utility
Manager's Crystal Ball,"
presented at the Annual Conference of the New England
Water Works Association, Danvers
MA, September 17-20,2006.
Mastracchio, J.M.,
"The Next Challenge in Eliminating Sewer Overflows: Who
Pays?,"
C1earwaters,
Vol. 35, p. 26-27, Winter 2005. New York Water Environment
Association, Inc.
Lockridge,
R.L., Mastracchio, J.M.,
"Dynamic Financial Modeling for Local
Governments,"
Proceedings,
91st Annual Conference of the International City/County
Management Association (ICMA), Minneapolis
MN, September 25-28, 2005.
A2820011
WHI
Pathways to Lasting Solutions
:.:::
RElIDAK
'.
••
••. CONSULTI
A DIVISION
or
MALCOLM
NG
PIR~'l(
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
Mastracchio, J.M.,
"Interactive Financial Modeling: An Effective Tool for
utility Management and Planning,"
Proceedings,
68th Annual Conference of the
Indiana Water Environment Association, Indianapolis
IN, November 15-17, 2004.
Mastracchio, J.M.,
"The Use of Financial Modeling to Support Utility
Management
and Planning,"
presented at the 78th Annual Conference of the Ohio
Water Environment Association, Columbus
OH, June 21-24, 2004.
Mastracchio, J.M.,
"Using Financial Models to Establish and Update Water
and Sewer Rates,"
presented at the Winter Conference of the County Commissioners
Association of Ohio, Columbus
OH, December 1,2003.
A282007
I
WHI
Pathways to Lasting Solutions
:.:;:
RElIDAK
'. Cl 0..
CONSULTING
• ••
A DIVISION
or
MALCOLM PIPtllE.
Electronic Filing - Received, Clerk's Office, August 4, 2008

ATTACHMENT 7
Economic Assessment of
Infrastructure to Meet Proposed Water Quality
Standards for Dissolved Oxygen and Plant Emuent Standards for Bacteria
(Malcolm Pirnie, Inc.,
July 2008)
Electronic Filing - Received, Clerk's Office, August 4, 2008

METROPOLITAN WATER RECLAMATION DISTRICT OF GREATER CHICAGO
ECONOMIC ASSESSMENT OF INFRASTRUCTURE TO MEET PROPOSED WATER
QUALITY STANDARDS FOR DISSOLVED OXYGEN AND PLANT EFFLUENT
STANDARDS FOR BACTERIA
Economic Assessment
July 2008
Introduction
The purpose of this study is to examine the potential economic impacts of implementing
processes at the Metropolitan Water Reclamation District of Greater Chicago (District)
facilities and in the waterways necessary to meet the proposed water quality and plant
effluent standards as proposed by the Illinois Environmental Protection Agency (IEPA)
under R08-9. The assessment
is composed of two sections; environmental and economic.
This report presents the economic portion of the assessment. The environmental portion
is provided under a separate cover.
The District's approach is to take a "holistic" view
of the environmental impacts of the
alternatives, including the potential economic impacts in terms
of the District's statutory
taxing authority and financial capability. A summary of the infrastructure costs, financial
condition and limitations
of the District, and financial forecast results under several
alternatives is provided below. These alternatives consist of:
Disinfection (Ultraviolet and ChlorinationlDechlorination) technology;
Dissolved Oxygen technology;
• A combination
of disinfection and dissolved oxygen technology.
Infrastructure Cost Summary
This study evaluates the costs and overall environmental impacts of potentially
implementing processes to disinfect plant effluent and increase dissolved oxygen in the
Chicago Area Waterway System (CAWS). Costs associated with several alternatives,
including implementing chlorination/dechlorination disinfection, and ultraviolet
disinfection at the three water reclamation plants is summarized in Table 1 below.
1
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table 1 - Summary of Costs to Meet Newly Proposed Water Quality and Emuent Standards in the
Chicago Area Waterway System
Project Description
Capital Cost
AnnualO&M
Cost
Total Present
Value Cost
SWRP
ChlorinationlDechlorination Disinfection
$225,700,000
$15,900,000
$533,500,000
Ultraviolet Disinfection
267,200,000
12,600,000
511,200,000
CWRP
ChlorinationlDechlorination Disinfection
$79, I00,000
$5,020,000
$176,500,000
Ultraviolet Disinfection
112,300,000
4,600,000
20 1,600,000
NSWRP
ChlorinationlDechlorination Disinfection
$114,200,000
$5,040,000
$212,000,000
Ultraviolet Disinfection
111,600,000
4,900,000
206,800,000
Total
ChlorinationlDechlorination Disinfection
$419,000,000
$25,960,000
$922,000,000
Ultraviolet Disinfection
491,100,000
22,100,000
919,600,000
Dissolved Oxygen Infrastructure
$524,800,000
$6,870,000
$656,600,000
All costs in 2008 dollars. Present value costs based on a 3.0% interest rate, and a 3% inflation rate for 20 years.
Sources:
Report entitled ChlorinationlDechlorination Disinfection Cost Study for Stickney, Calumet, and North Side Water Reclamation
Plants" prepared by CTE and dated May 12,2008. Costs subsequently updated to 2008 dollars.
Report entitled
UV Disinfection Cost Study - Northside Water Reclamation Plantprepared by CTE and dated January 31, 2008. Costs
subsequently updated to 2008 dollars.
Dissolved Oxygen Infrastructure costs provided by CTE.
Financial Summary
The District generates revenue to fund its operations from ad valorem property taxes,
personal property replacement tax (PPRT), user charge revenue, interest income, and
other revenues. The District's primary source
of operating revenue is ad valorem
property taxes. PPRT revenue is primarily a tax on corporate income. The PPRT
revenue
is first distributed to fully fund the District'sRetirement Fund, and subsequent
receipts are distributed to other non-debt funds. User charge revenues are collected from
large commercial and industrial classes, and tax-exempt customers. A summary
of the
District's revenues and expenditures for the period 2002 through 2006 is provided in
Table 2 below.
2
Economic Assessment
Report
8~
1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table 2 - MWRD Summary of Financial Results - All Governmental Funds
(in $ Thousands, Modified Accrual Basis)
2002
2003
2004
2005
2006
Revenues
Property Taxes
$ 362,036 $ 397,751 $ 360,326 $ 423,941 $ 380,675
Personal Property Replacement Tax
22,285
24,048
25,961
36,031
37,743
User Charges
48,890
50,222
47,757
45,983
52,504
Interest on Investments
15,693
13,163
9,943
19,693
43,659
Other Revenues
14,759
16,203
16,495
16,309
17,691
Total Revenues
$ 463,663 $ 501,387
$ 460,482 $ 541,957 $ 532,272
Expenditures
General Administration
$ 14,318
$ 14,987
$ 15,538 $ 17,259 $ 16,974
Personnel
27,610
30,916
35,877
32,900
35,162
Pension Costs
27,044
29,511
27,372
31,561
30,071
Research and Development
23,838
24,172
24,030
24,787
24,985
Information Technology
11,204
11,417
10,574
10,811
11,034
Maintenance and Operations
160,326
159,079
160,299
157,612
155,899
Other
32,843
22,563
27,637
31,522
26,931
Construction Costs
157,076
164,865
127,155
133,599
164,157
Debt Service
145,831
158,626
156,025
169,019
171,869
Total Expenditures
$ 600,090 $ 616,136 $ 584,507 $609,070 $
637,082
Revenues Over (Under) Expenditures $ (136,427) $(114,749) $ (124,025)
$ (67,113) $ (104,810)
Other Financing Sources (Uses)
222,622
223,613
52,720
15,973
383,448
Net Change in Fund Balance
$ 86,195 $ 108,864 $ (71,305) $ (51,140)
$ 278,638
Source: Comprehensive Annual Financial Reports (2003-2006).
The expenditures shown in Table 2 were appropriated to the Corporate Fund,
Construction Fund, Stormwater Fund, Capital Improvement Bond Fund, Bond
Redemption and Interest Fund, Retirement Fund, and the Reserve Claim Fund. These
funds are briefly summarized below:
The Corporate Fund is the District's General Fund and includes appropriation
requests for all day-to-day operational costs.
The Construction Fund
is utilized as a pay-as-you-go capital rehabilitation and
modernization program, and to fund operations-related projects, where the useful
life
of the improvement is less than 20 years or when the values are less than $1
million. Capital projects are financed by a tax levy sufficient to pay for project
costs as they are constructed.
The Stormwater Management Fund is used to minimize flooding damage by
coordinating, planning, implementing, financing, and operating regional
stormwater management projects, to foster stormwater improvements, and to
educate the public with respect to sustainable growth concepts.
The Capital Improvement Bond Fund includes major capital infrastructure
projects whose useful lives extend beyond 20 years, and which will be financed
by long-term debt, Federal and State grants, and State Revolving Fund loans.
3
Economic Assessment Report 8-1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

The Bond Redemption and Interest Fund is the District's debt service fund.
Principal and interest payments on District general obligation bonds and SRF
loans require an annual levy and appropriation.
The Retirement Fund
is used to account for pension costs as provided by
specifically levied annual property taxes. The taxes are collected and recorded in
this fund prior to their payment to the MWRD Retirement Fund.
The Reserve Claim Fund acts as the District's Insurance Fund. The District
is
primarily self-insured and utilizes this fund for repair or replacement of damaged
District property and claims implied against the District.
Financial Limitations
The District has several financial limitations and restrictions that directly impact its
ability to take on additional projects or programs. When considering the potential
economic impacts that the projected water quality improvement costs will have on the
District's funding and bonding authority, several financial limitations were considered.
First, in 1995, the Property Tax Extension Limitation Law (PTELL) was passed by the
Illinois General Assembly, which limits the ability
of the District to adopt future
increases in the aggregate tax levy. In accordance with this Act, increases to the
District's aggregate tax levy are limited to the lesser of: (1) five percent or (2) the change
in the national consumer price index (CPI) plus allowable increases for new property.
The aggregate levy is the total
of all funds except the Bond Redemption and Interest and
the Stormwater Management Funds.
Second, the District's initial Tax Cap legislation restricted the District's non-referendum
bond authority to only apply to projects initiated prior to October
1, 1991. There was a
specific exemption, essentially to exclude TARP projects from the more restrictive
provisions
of the Act which require referendum approval of all new debt. Public Act 89-
385 provides the District with the authority to issue non-referendum "limited bonds" for
capital projects initiated after October
1, 1991 at the same level as it did in 1994. Limited
bonds can be issued to the extent that the total debt service requirements of any new debt
when combined with existing debt service does not exceed the 1994 debt service
extension base
of $141,463,920. Public Act 90-485 has provided a further modification
by authorizing the exclusion
of debt for Tunnel and Reservoir Plan (TARP) projects from
this debt service extension base.
Third, in 2003, the District received authority under Public Act 93-279 to issue $150
million (previously $100 million)
of non-referendum bonds during any budget year plus
authorized but unissued bonds during the previous three budget years through 2016.
These financial limitations and restrictions directly impact the District's ability to take on
additional projects and/or programs, and the District is currently very near these limits
without considering the implementation
of disinfection or dissolved oxygen processes.
4
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Baseline Financial Forecast
A baseline long-term financial forecast was prepared for the District based on its current
estimated requirements to be used as a comparison with financial forecasts associated
with meeting the proposed water quality and effluent standards. Revenue and
expenditure projections were made based on the five-year forecast information contained
within the 2008 budget, the capital improvement program information provided by the
District, and discussions with the District's Administrative Services Manager. A
summary
of the current capital improvement plan, which does not include a disinfection
program or projects needed to meet the newly proposed water quality standards,
is
provided in Table 3 below. The estimated cost of the District's planned capital
improvement projects were provided to Malcolm Pimie in February 2008.
Table 3 - Capital Improvement Plan (Other Projects)
Yearly Dlspersement Projection (In $ Thousands)->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Corporate Fund Program
$
In
$
329
$
189
$
206
$
219
$
386
$
399
$
413
$
427
$
441
Construction Fund Program
14,651
14,547
11,818
6,720
4,927
5,949
6,849
7,796
9,249
10,512
Limited Bond Fund Projects
Plant
158,023
161,419
247,995
287,760
242,858
205,403
134,662
133,876
120,859
76,173
Sewer
23,668
53,703
73,934
61,605
2,618
7,979
TARP
1,016
3,668
10,822
8,524
4,838
Unspecnied
25,000
Unlimited Bond Fund Projects (TARP)
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited SRF Projects
Plant
29,453
24,654
29,049
Sewer
28,680
2,125
1,831
1,705
Unlimited SRF Projects (TARP)
1,553
Stormwater Fund Projects
10,008
2,490
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Total
$2n,584
$ 330,470 $ 437,454 $ 426,721 $ 324,680 $ 272,119 $ 214,824
$
204,638
$180,695 $ 179,807
Source: The estimated cost of the District's planed capital improvement projects were provided to Malcolm
Pirnie in February 2008.
It
is important to note that the current CIP does not include future Stormwater
Management fund projects as Detail Watershed Plans (DWPs) are not expected to be
completed until 2010.
In
addition, the District's currently planned projects do not include
the costs of implementing nutrient removal processes. As documented in a District
summary cost table (provided as Table 4 below), a rudimentary order-of-magnitude cost
estimate prepared
by the District indicates that the capital costs to construct nutrient
removal processes could be approximately $2.8 billion.
5
Economic Assessment Report 8-1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table 4 - Rudimentary, Order-of-Magnitude Cost Estimates for Nutrient Removal
at District Water Reclamation Plants
PLANT
CAPITAL COST
ANNUALM&O
Stickney
$1,666,000,000
$100,000,000
Calumet
$605,000,000
$29,000,000
North Side
$408,000,000
$4,700,000
Kirie
$83,000,000
$1,000,000
Egan
$38,000,000
$2,500,000
Hanover Park
$17,000,000
$1,000,000
Total
$2,817,000,000
$138,200,000
NOTES:
I. Cost Estimate prepared by engineering department
of MWRDGC.
2. Under the Master Plans for the Calumet and North Side WRPs, conceptual level cost estimates
were performed for various nutrient removal processes. The purpose
of the cost estimates was to
compare various nutrient removal processes relative to each other. These estimates were used to
generate a rudimentary, order-of-magnitude cost estimate for all seven WRPs. In short, North Side
and Calumet estimates were used
to arrive at capital and annual operating costs on a flow basis
(Le. dollars per million gallons
of sewage treated). These ratios were used to extrapolate costs for
the other four WRPs. The cost estimates that were derived assumed hypothetical effluent limits
of
0.5 mg/L for total phosphorus and between 6 to 8 mg/L for total nitrogen.
3. All costs are given in 2008 dollars.
4. Lemont Water Reclamation Plant
is not included as it is planned to be converted to a sewage
pumping station.
The baseline capital improvement plan and projected cash balance in the Capital
Improvement Bond Fund is shown graphically in Figure 1 below. As shown in this
figure, the cash balance in the Capital Improvement Bond Fund
is expected to gradually
decrease as a result of funding these capital projects until 2016 when the District's
authority to issue non-referendum bonds expires.
6
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 1
Capital Improvement Plan - Baseline
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
Plant -
Tarp -
CIBF Cash Balance
$600,000
$500,000
'C
..
$400,000
..
:::I
c
to
$300,000
0
.r:.
$200,000
...
t-
$100,000
$0
~
0
C\l
'<t
co
0
C\l
0
C\l
0
C\l
0
C\l
0
C\l
to
o
C\l
In
addition to these planned capital expenditures, maintenance and operations (M&O)
costs were projected over the forecast period. The projection was based on historical
results, the District's existing five-year forecast projections, and discussions with District
staff. The projections
of M&O costs are included in the forecasted property tax levy
increases summarized below. Additional details are provided in the tables and
calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements (for the years 2008 through
2017) was developed to provide a baseline scenario of current estimated requirements in
which to compare scenarios incorporating capital and M&O costs that would be
necessary to meet proposed water quality standards. The baseline financial projection
results are summarized in Figures 2 and 3 below and detailed in Appendix A. Figure 2
shows the annual increase in the property tax levy necessary to fund projected capital and
M&O costs, excluding those costs necessary to meet the proposed water quality
standards, as compared to the property tax levy limitation. The property tax limitation
limits the property tax levy increase to the lessor
of (1) five percent or (2) the change in
CPI plus the increase in new property. The baseline scenario results indicate that the
District will stay at or below the tax levy limitation over the forecast period.
Figure 3 shows the projected annual "limited" debt service associated with existing and
proposed District debt, excluding debt that would be necessary to fund capital projects
associated with the proposed water quality standards, as compared to the debt service
limitation. The baseline analysis indicates that the District will stay at or below the debt
service extention base limitation through fiscal year 2015 and exceed the limitation
slightly in fiscal years 2016 and 2017. This means that in 2016, the District'snon-
referendum bond authority, which expires at the end
of 2016, will be further limited so as
not to exceed the debt service extension base.
7
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 2
Forecasted Aggregate Tax Levy Requirement Compared to Tax
Cap Limitation - Baseline
$410,000 ,------------------------------,
$390,000 +----------------------------::::------i
$370,000
+---------------------------:::;,.,.-;;----;1
~
lij $350,000 +-------------------------::::;..,,1IIi"
!l
o
$330,000
+----------------......
---=---j
~
l-
e
$310,000 +------------=-"".,q'
0-
$290,000
+-------::::;o~_r-_j
$270,000 -1-r-"'I:------J
$250,000
+-L=L-,..-I~~--....k~___r_-L---L-.---..L--l-,--L-..L...-,___.L----lL.,---L--L___._--L.=L-r--'--...L.......j
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
=
ProjeetedTax Levy Requirement(Excluding StormwaterCostand Debt Service)
--Tax Levy Extension Limitation (CPI+ New Property)
Figure 3
Forecasted Debt Service Compared to Debt Service Extension Base
$160,000
$140,000
$120,000
III $100,000
'C
m
$80,000
::::l
,g
$60,000
l-
E
$40,000
$20,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
_
ProjeetedAmountof
Lim~ed
Debt Service
--Debt Service Extension Lim itation
8
Economic Assessment Report 871-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Scenario 1 (Chlorination/Dechlorination Disinfection)
Scenario 1 consists of adding the capital and annual M&O costs associated with
chlorination / dechlorination disinfection (as shown in Table 1) to the baseline financial
forecast. For the purposes
of this scenario, it was assumed that design of the disinfection
processes would occur in 2011 through 2013 and construction would occur in 2014
through 2016.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 1
is shown graphically in Figure 4 below. As shown in this
figure, additional capital costs would be incurred to meet the proposed water quality
standards, and the cash balance in the Capital Improvement Bond Fund would decrease
more rapidly than the baseline forecast
as a result of funding these capital projects until
2016 when the District's authority to issue non-referendum bonds expires. The analysis
indicates that the projected cash balance in the Capital Improvement Bond Fund would
be insufficient to fund current projects and the projects associated with the proposed
water quality standards due to the District's current authority and limitation
of issuing no
more than $150 million of non-referendum bonds during any budget year. Furthermore,
in order to fund the capital projects, the District would have to receive additional non-
referendum bonding authority
or issue a voter referendum.
Figure 4
Capital Improvement Plan - Scenario 1
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$600,000
$500,000
$400,000
~
....
c:
::l
$300,000
0
.c
$200,000
I-
CIt
$100,000
$0
ClJ
8
C\l
Plant
-
Tarp
......" Projects to Meet Proposed Standards
-
CIBF Cash Balance
In addition to the capital expenditures associated with Scenario 1, M&O costs associated
with this scenario were projected over the forecast period. The projections of M&O costs
associated with implementing the chlorination / dechlorination disinfection processes are
included in the forecasted property tax levy increases summarized below. Additional
details are provided in the tables and calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
plant effluent standards was developed for Scenario
1. The results are summarized in
9
Economic Assessment Report 8.1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figures 5 and 6 below and detailed in Appendix
A.
Figure 5 shows the annual aggregate
property tax levy requirement necessary to fund projected capital and M&O costs,
including those costs necessary to meet the proposed plant effluent standards,
as
compared to the aggregate tax levy limitation. The Scenario 1 results indicate that the
District will exceed the aggregate tax levy limitation once the disinfection processes have
been constructed and operations commence in 2016. Furthermore, in order to fund the
improvements, the District would have to request an amendment to the Property Tax
Extension Limitation Law or obtain voter approval via referendum to increase the
aggregate extension limitation and/or the limiting rate.
Figure 5
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Scenario 1
$430,000 .,..------------------------------,
$410,000 +-----------------------------1
$390,000 +-------------------------1
~
$370,000
!!l
$350,000 +-------------------==-........-
r=
o
$330,000 +------------------:-".,.",.=:........j
.5 $310,000 +-----------::::;;;00",...,
0-
$290,000 +-----=::;;;;0""",-,:'------1
$270,000
4--...-=.----1
$250,000
+-~"'--.--l-..JL......,---l.:"-""-__._.....l.-....L--r--'--....l-...,.-.L.-.l-r---..l-L_,.--L.
.......__._-k......L--r-....i=::..I.-l
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
=
Projected Tax Levy Requirement(Excluding Storm water Cost and Debt Service)
-
Tax Levy Extension
Limitation (CPI + New Properly)
Figure 6 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund capital
projects associated with the proposed plant effluent standards, as compared to the debt
service extension base. The Scenario 1 analysis indicates that the District would
significantly exceed the debt service extension base beginning in fiscal year 2014 if the
Scenario 1 projects associated with meeting the proposed plant effluent standards were
implemented.
Figure 6
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 1
$200,000 .,..-------------------------,
$180,000 +---------------------
$160,000 +------------------
{j$120,ooO$140,000
-t------------------
+----------------
Ii
OJ
$100,000 +------
5 $BO,OOO
+---
.s::.
t;
$60,000
+---
.=
$40,000
$20,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Amountof limited DebtService
-
DebtServlce extension Limitation
L..---------------~_------------~........I1ic
Assessment Report
8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Scenario 2 (Ultraviolet Disinfection)
Scenario 2 consists of adding the capital and annual M&O costs associated with
ultraviolet disinfection (as shown in Table
1) to the baseline financial forecast. For the
purposes of this scenario, it was assumed that design of the disinfection processes would
occur in 2011 through 2013 and construction would occur in 2014 through 2016.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 2
is shown graphically in Figure 7 below. As shown in this
figure, additional capital costs would be incurred to meet the proposed water quality
standards, and the cash balance in the Capital Improvement Bond Fund would decrease
more rapidly than the baseline forecast as a result
of funding these capital projects until
2016 when the District's authority to issue non-referendum bonds expires. The analysis
indicates that the projected cash balance in the Capital Improvement Bond Fund would
be insufficient to fund current projected projects and the projects associated with the
proposed water quality standards due to the District's current authority and limitation
of
issuing no more than $150 million of non-referendum bonds during any budget year.
Furthermore, in order to fund the capital projects, the District would have to receive
additional non-referendum bonding authority or issue a voter referendum.
Figure 7
Capital Improvement
Plan - Scenario 2
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$600,000
$500,000
$400,000
~
..
III
c
0
,.
$300,000
.c
$200,000
...
I-
$100,000
$0
<Xl
8
C\I
Plant
-
Tarp
••-.••-". Projects to Meet Proposed Standards
-
CIBF Cash Balance
In addition to the capital expenditures associated with Scenario 2, M&O costs associated
with this scenario were projected over the forecast period. The projections of M&O costs
associated with implementing the ultraviolet disinfection processes are included in the
forecasted property tax levy increases summarized below. Additional details are
provided in the tables and calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
plant effluent standards was developed for Scenario 2. The results are summarized in
Figures 8 and 9 below and detailed in Appendix
A.
Figure 8 shows the annual aggregate
property tax levy requirement necessary to fund projected capital and M&O costs,
11
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

including those costs necessary to meet the proposed plant effluent standards, as
compared to the aggregate property tax levy limitation. The Scenario 2 results indicate
that the District will exceed the aggregate tax levy limitation once the disinfection
processes have been constructed and operations commence in 2016. Furthermore, in
order to fund the improvements, the District would have to request an amendment to the
Property Tax Extension Limitation Law or obtain voter approval via referendum to
increase the aggregate extension limitation and/or the limiting rate.
Figure 8
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Scenario 2
$430,000 .,------------------------------,
$410,000 +-----------------------------1--.---l
$390,000 +-------------------------1;
III
'g $370,000
+-------------------------,~III"""F=----r
~
$350,000
+-------------------~........._
I-
,g
$330,000
+---------------,...",..~
fI)
c:: $310,000 +------------:::;;o",,_.I"f'
$290,000 +------:::::;;;o.....-J=---1
$270,000
-l--"'-'I==--l
$250,000
+-"--.L-.--'-"--T--'-"""--l---.,-~--'-___,_-'--'-_r_
........
""'---.,_"--.L-.__"---'~--'--.L__r
.........--'---l
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
=
Projected Tax Levy Requirement(Excluding StormwaterCostand Debt Service)
-
Tax Levy Extension Umitation (CPI
+ New Property)
Figure 9 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund capital
projects associated with the proposed plant effluent standards, compared to the debt
service extension base. The Scenario 2 analysis indicates that the District would
significantly exceed the debt service extension base beginning in fiscal year 2014 if the
Scenario 2 projects associated with meeting the proposed plant effluent standards were
implemented.
Figure 9
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 2
$250,000
$200,000
~$150,000
I:
III
III
5$100,000
..c::
~
.5 $50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
_
Projected Amountof Limned DeblServlce
12
-
DebtService Extension Limitation
&onomic Assessmenl Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Scenario 3 (Dissolved Oxygen)
Scenario 3 consists of adding the capital and annual M&O costs that are anticipated to be
required to meet the proposed Dissolved Oxygen Water Quality Standards in the CAWS
(as shown in Table 1) to the baseline financial forecast. While it is possible that the
dissolved oxygen enhancement facilities would be required in addition to either the
ultraviolet
or chlorination/dechlorination disinfection processes, the costs associated with
the dissolved oxygen processes are shown herein as a stand alone scenario in order to
demonstrate its financial impact separately from the other scenarios. For the purposes
of
this scenario, it was assumed that design of the dissolved oxygen enhancement facilities
would occur in 2010 through 2012 and construction would occur in 2013 through 2015.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 3 is shown graphically in Figure 10 below. As shown in this
figure, additional capital costs would
be incurred to implement the processes, and the
cash balance in the Capital Improvement Bond Fund would decrease more rapidly than
the baseline forecast as a result
of funding these capital projects until 2016 when the
District's authority
to issue non-referendum bonds expires. The analysis indicates that
the projected cash balance in the Capital Improvement Bond Fund would
be insufficient
to fund current projects and the projects associated with the proposed water quality
standards due to the District's current authority and limitation
of issuing no more than
$150 million
of non-referendum bonds during any budget year. Furthermore, in order to
fund the capital projects, the District would have to receive additional non-referendum
bonding authority
or issue a voter referendum.
Figure 10
Capital Improvement Plan - Scenario 3
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$600,000
$500,000
$400,000
-ll
c
01
$300,000
III
::s
0
s::.
$200,000
I-
0
$100,000
$0
8
C\I
Plant
-
Tarp
r..;..;;" Projects to Meet Proposed Standards
-
CIBF Cash Balance
In
addition to the capital expenditures associated with Scenario 3, M&O costs associated
with this scenario were projected over the forecast period. The projections
of M&O costs
associated with implementing the dissolved oxygen processes are included in the
13
Economic Assessment Repon 8-1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

forecasted property tax levy increases summarized below. Additional details are
provided in the tables and calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
water quality standards was developed for Scenario 3. The results are summarized in
Figures
11 and 12 below and detailed in Appendix
A.
Figure 11 shows the annual
property tax levy requirement necessary to fund projected capital and M&O costs,
including those costs necessary to meet the proposed water quality standards,
as
compared to the aggregate property tax levy limitation. The Scenario 3 results indicate
that the District will exceed the tax levy limitation once the dissolved oxygen
enhancement facilities have been constructed and operations commence in 2016.
Furthermore, in order to fund the improvements, the District would have to request an
amendment to the Property Tax Extension Limitation Law or obtain voter approval via
referendum to increase the aggregate extension limitation and/or the limiting rate.
Figure 11
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Scenario 3
$410,000 .------------------------------.,
$390,000
i---------------------------r~____i
$370,000 i-------------------------::::ol!......,F----f
~
Ii
$350,000
,g
::J
$330,000 i---------------...,.,.",.=--t
~
$310,000
+-----------="",-Ef
(b
$290,000
-t------=...-t!-J----i
$270,000
.L.-r-~--1
$250,000
i-~J..-...---J-L.....,----I==1____r---L-~-,--'---'-_,_..L.-.....l-..,.----.L-...L.-.__L..-.-'--..---J""""-olL.....,---'==1____i
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
=
Projected Tax Levy Requirement(Exciuding StormwaterCostand Debt Service)
-
Tax Levy Extension Lim ilalion (CPI
+ New Property)
Figure 12 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund current
projected projects and capital projects associated with the proposed water quality
standards, compared to the debt service extension base. The Scenario 3 analysis indicates
that the District would significantly exceed the debt service extension base beginning in
fiscal year 2014 if the Scenario 3 projects associated with the proposed water quality
improvements were implemented.
14
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 12
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 3
$250,000
$200,000
~$150,000
c:
III
5$100,000
.s::
~
c: $50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
.-Projected Amount of
Lim~ed
Debt Service
-
Debt Service Extension LimitatiCll
Scenario 4 (Chlorination
I
Dechlorination and Dissolved Oxygen)
Scenario 4 consists of adding the capital and annual M&O costs associated with both
chlorination
I
dechlorination and dissolved oxygen (as shown in Table 1) to the baseline
financial forecast.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 4 is shown graphically in Figure
13 below. As shown in this
figure, additional capital costs would be incurred to implement the processes, and the
cash balance in the Capital Improvement Bond Fund would decrease more rapidly than
the baseline forecast and the scenarios showing either disinfection or dissolved oxygen
processes, as a result
of funding these capital projects until 2016 when the District's
authority to issue non-referendum bonds expires. The analysis indicates that the
projected cash balance in the Capital Improvement Bond Fund would be insufficient to
fund the current projected projects and projects associated with the proposed plant
effluent and water quality standards due to the District'scurrent authority and limitation
of issuing no more than $150 million of non-referendum bonds during any budget year.
Furthermore, in order to fund the capital projects, the District would have to receive
additional non-referendum bonding authority or issue a voter referendum.
15
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 13
Capital Improvement Plan - Scenario 4
ESTIMATED CAPITAL PROGRAM EXPENDITURES
_Sewer
$700,000
$600,000
$500,000
-tl
$400,000
CIl
..
:>
c
$300,000
0
s::
...
I-
$200,000
$100,000
$0
co
8
(\J
Plant
-
Tarp
:'.'.~:,
Projects to Meet Proposed Standards
-
CIBF Cash Balance
.............
........................
....................................................
..Jmm~mmmmn
"' ;>
"'."'•••• ,
iiI
.-
"' "' "' "'
"'..
~~iiiIii~~~···~···~·~~·~~···:·
~
~~~~~~~~~~~~~mmmmmmmnmmi
......
·········:S5S~$~~~~5~~~5~~~~~~~:.~5~~:::.)~:·::
......"'...."'.................
rrrrr
t;"y'y';"y':mmim
(\J
o
(\J
In addition to the capital expenditures associated with Scenario 4, M&O costs associated
with this scenario were projected over the forecast period. The projections
of M&O costs
associated with implementing the dissolved oxygen and chlorination/dechlorination
disinfection processes are included in the forecasted property tax levy increases
summarized below. Additional details are provided in the tables and calculations
provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
plant effluent and water quality standards was developed for Scenario 4. The results are
summarized in Figures 14 and
15 below and detailed in Appendix
A.
Figure 14 shows
the annual aggregate property tax levy requirement necessary to fund projected capital
and M&O costs, including those costs necessary to meet the proposed standards, as
compared to the aggregate property tax levy limitation. The Scenario 4 results indicate
that the District will exceed the tax levy limitation once the dissolved oxygen processes
and chlorination / dechlorination disinfection improvements have been constructed and
operations commence in 2016. Furthermore, in order to fund the projects, the District
would have to request an amendment to the Property Tax Extension Limitation Law
or
obtain voter approval via referendum to increase the aggregate extension limitation
and/or the limiting rate.
16
Economic Assessment Repon 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 14
Forecasted Aggregate Tax Levy Requirement Compared to Tax
Cap Limitation - Scenario 4
$450,000 .,.-----------------------------,
$430,000
+-------------------------------==---1
$410,000 +--------------------------i-r----l
~
$390,000
~
$370,000 +-----------------------=::ooIIIII'""F=------l
.2 $350,000
+---------------------=-.,.,.~
I- $330,000
+-----------------=:;;0...,..,,::...;,
fit
.=
$310,000
+--------------=._-r-
$290,000 +---------:::::;;;;;;II."",,-,=-----j
$270,000
.).......;....-~~-
$250,000 +-.......
..&...-...--'........:::'__r---'-..........
--,---"---'---.--'---'-...,..--"-""'----~'--..&...-
..........
-'__r----l:.---"----.----"----.L~
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
=
Projected Tax Levy Requirement(Excluding StormwaterCostand Debt Service)
-
Tax Levy Extension Limitation (CPI
+ New Property)
Figure 15 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund current
projected projects and capital projects associated with the proposed plant effluent and
water quality standards, compared to the debt service extension base. The Scenario 4
analysis indicates that the District would significantly exceed the debt service extension
base beginning in fiscal year 2014
if the Scenario 4 projects associated with meeting the
proposed standards were implemented.
Figure 15
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 4
$250,000
$200,000
~$150,000
c
III
5$100,000
.c
th
.= $50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
-
Projected
Am
ount of Lim
~ed
Debt Service
17
-
Debt Service Extension Limitation
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Scenario 5 (UV Disinfection and Dissolved Oxygen)
Scenario 5 consists of adding the capital and annual M&O costs associated with both UV
disinfection and dissolved oxygen (as shown in Table 1) to the baseline financial forecast.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 5
is shown graphically in Figure 16 below. As shown in this
figure, additional capital costs would be incurred to implement the processes, and the
cash balance in the Capital Improvement Bond Fund would decrease more rapidly than
the baseline forecast and the scenarios showing either disinfection or dissolved oxygen
processes, as a result
of funding these capital projects until 2016 when the District's
authority to issue non-referendum bonds expires. The analysis indicates that the
projected cash balance in the Capital Improvement Bond Fund would be insufficient to
fund current projected projects and the projects associated with the proposed water
quality standards due to the District's current authority and limitation
of issuing no more
than $150 million of non-referendum bonds during any budget year. Furthermore, in
order to fund the capital projects, the District would have to receive additional non-
referendum bonding authority or issue a voter referendum.
Figure 16
Capital Improvement Plan - Scenario 5
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$700,000
$600,000
$500,000
~
$400,000
c
'"'"
:::I
$300,000
0
.c
<It
I-
$200,000
$100,000
$0
8
C\I
Plant
-
Tarp
':.':;. Projects to Meet Proposed Standards
-
CIBF Cash Balance
In
addition to the capital expenditures associated with Scenario 5, M&O costs associated
with this scenario were projected over the forecast period. The projections
of M&O costs
associated with implementing the dissolved oxygen and ultraviolet disinfection processes
are included in the forecasted property tax levy increases summarized below. Additional
details are provided in the tables and calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
plant efluent and water quality standards was developed for Scenario
5. The results are
summarized in Figures 17 and 18 below and detailed in Appendix A. Figure 17 shows
the annual aggregate property tax levy requirement necessary to fund projected capital
18
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

and M&O costs, including those costs necessary to meet the proposed standards, as
compared to the aggregate property tax levy limitation. The Scenario 5 results indicate
that the District will exceed the tax levy limitation once the dissolved oxygen processes
and ultraviolet disinfection improvements have been constructed and operations
commence in 2016. Furthermore, in order to fund the projects, the District would have
to request an amendment to the Property Tax Extension Limitation Law
or obtain voter
approval via referendum to increase the aggregate extension limitation and/or the limiting
rate.
Figure 17
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Scenario 5
$450,000 .,.--------------------------------,
$430,000 +-------------------------------j
$410,000 +------------------------=------j
~
$390,000 +---------------------------i
c::
~
$370,000
o $350,000 +----------------------=.--r
..c::
~
$330,000
+-----------------=:;_~~
o
$310,000
+--------------::=---,.....-
$290,000 +---------:==-....
-,=-.----l
$270,000
~"""'~~I
$250,000
+-.L.-..L.-.......-JL.-.L.......,,......-L---"-'L......,.----II.=--r......L----L----r--'-......L-,---4--'--r-..L.-.....L-....---.L.-..L.-...--l"'=oL.......j
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
c:::::I
Projected Tax Levy Requirement (Exduding Storm waterCostand Debt Service)
-
Tax Levy Extension Limitation (CPl. New Property)
Figure 18 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund current
projected projects and capital projects associated with the proposed plant effluent and
water quality standards, compared to the debt service extension base. The Scenario 5
analysis indicates that the District would significantly exceed the debt service extension
base beginning in fiscal year 2014
if the Scenario 5 projects associated with meeting the
proposed standards were implemented.
19
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 18
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 5
$300,000
$250,000
$200,000
III
'C
m$150,000
:::s
o
t: $100,000
CIt
.E
$50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Amounlof
Lim~ed
Debt Service
20
--DeblService Extension Limitation
Economic Assessment
Report
8.1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Back to top


Appendix A

Back to top


Backup Tables and Calculations
21
Economic Assessment
Report
8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-I
Tax Levy Requirement Forecast Summary - Baseline Scenario
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$
239,262
$
243,031
$
251,304
$
268,826
$
278,106
$
286,957
$
297,344
$
309,412
$
321,991
$
334,848
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
31,204
55,313
79,422
92,888
106,555
120,223
133,890
147,558
150,583
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (in
$
thousands)
$
428,814
$
454,481
$
480,642
$
516,489
$
548,031
$
576,473
$
589,851
$
617,489
$
639,442
$
656,823
Table A-2
Property Tax Extension Limitation - Baseline Scenario
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)':
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
370,744
386,237
(Excluding Debt Service and Stormwater)
Projected Increase in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
4.20%
4.18%
Estimated Change in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
~
~
1.20%
1.20%
1.20%
1.20%
1.20%
~
1.20%
Total Allowable Increase in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
22
Economic Assessment Report K. J.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-3 - Debt Service Projection and Debt Service Extention Limitation - Baseline Scenario
Historical
Projection (in
$
Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040 $ 220,164 $ 337,931
$ 369,596
$ 260,514
$ 223,362
$
148,729
$
146,689
$
135,726
$ 106,446
Unlimited Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited Bond and SRF
15,276
8,357
58,133
26,779
30,881
1,705
Unlimited Bond and SRF
1,201
1,553
Future sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab
Projects
27,072
CIBF
Compliance
Program
with
Expenditures
Proposed Water Quality Standards
---
75,204
63,520
$
253,081
$ 314,478
---
$ 430,627
---
$ 431,501
---
$ 329,734 $ 275,764
$ 221,642
$
209,243
$
185,886
$
174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150,000
$
$
150,000 $ 300,000
$ 150,000
$ 150,000
$
100,000
$
150,000
$
150,000
$
150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
--....1&1!!.
14,297
27,767
18,602
25,908
22,772
19,436
13,671
10,316
9,500
9,262
10,181
Bond Fund Revenues
344,618
206,297
$
69,767
$ 460,602 $ 367,908
$ 364,772
$ 214,436
$ 208,671 $ 205,316 $ 204,500 $ 204,262
$
50,181
CIBF Cash Balance
285,935
555,349
372,035
518,159
455,440
388,711
273,412
206,318
189,992
185,249
203,625
79,680
Debt Service
Existing limited
31,632
46,800
51,228
$
66,463 $ 63,894 $ 60,792 $ 38,331
$
26,574
$
37,302
$
36,183
$
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930.
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond DS for Water Quality Projects
Proposed Unlimited Bond and SRF
Debt service
133,427
135,730
141,601
153,613
175,142
196,149
214,681
229,707
230,016
242,565
248,571
250,176
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
101,469
111,833
102,838
101,201
125,596
138,145
148,849
150,104
Debt service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
23
Economic Assessment ReJX>rt 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-4
Tax Revenue Requirement Forecast Summary - Scenario 1
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$
239,262
$
243,031
$
251,304
$
268,826
$
278,106
$
286,957
$
297,344
$
309,412
$
355,511
$
366,886
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
31,204
55,313
80,141
95,045
110,152
138,205
166,258
187,118
190,143
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (in
$
thousands)
$
428,814
$
454,481
$
480,642
$
517,208
$
550,189
$
580,069
$
607,832
$
649,856
$
712,521
$
728,421
Table A-5
Property Tax Extension Limitation - Scenario 1
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)':
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
404,264
418,275
(Excluding Debt Service and Stormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
13.62%
3.47%
Estimated Change
in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
0.90%
1.20%
1.20%
~
1.20%
1.20%
1.20%
1.20%
1.20%
Total Allowable Increase
in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
9.02%
8.25%
--
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
24
Economic A"essment Report H-I-OH
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-6 - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 1
Historical
Projection (In
$
Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Lim~ed
Bond Funds
8,862
31,250
$
183,040 $ 220,164 $ 337,931 $ 369,596 $ 260,514 $ 223,362
$
148,729
$
146,689
$
135,726
$ 106,446
Unlimited Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited Bond and SRF
15,276
8,357
58,133
26,n9
30,881
1,705
Unlimited Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
-
___ --.1Q.!R
20,275
20,275
202,748
CIBF Program Expenditures
---
75,204
202,748
101,374
63,520
$
253,081 $ 314,478 $ 430,627 $ 441,639 $ 350,009 $ 296,039
$ 424,390
$ 411,991 $ 287,260
$ 174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150,000
$
$
150,000
$ 300,000
$ 150,000
$ 150,000
$
100,000
$ 150,000
$
150,000
$ 150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment Income
~
14,297
27,767
18,602
25,908
22,n2
18,929
12,125
7,679
(3,407)
(14,427)
(19,761)
Bond Fund Revenues
344,618
206,297
$
69,767 $ 460,602 $ 367,908
$ 364,n2
$ 213,929 $ 207,125 $ 202,679
$
191,593
$
180,573
$
20,239
CIBF Cash Balance
285,935
555,349
372,035
518,159
455,440
378,573
242,493
153,579
(68,133)
(288,530)
(395,217)
(549,104)
Debt Service
Existing limited
31,632
46,800
51,228
$
66,463 $ 63,894 $ 60,792 $ 38,331 $
26,574
$
37,302 $
36,183 $
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,5n
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond DS for Water Quality Projects
719
2,158
3,596
17,982
32,367
39,560
39,560
Proposed Unlimited Bond and SRF
---
---
---
---
-
Debt service
133,427
135,730
141,601
153,613
175,142
196,868
216,839
233,303
247,998
274,932
288,131
289,736
Debt Issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
101,469
112,552
104,996
104,797
143,578
170,512
188,409
189,664
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
25
Economic Assessment Repon 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-7
Tax Revenue Requirement Forecast Summary - Scenario 2
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$ 239,262
$
243,031 $ 251,304 $ 268,826 $ 278,106 $ 286,957
$ 297,344 $ 309,412 $ 350,527 $ 362,122
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
-
31,204
55,313
80,265
95,417
110,770
141,299
171,827
193,925
196,950
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (in
$
thousands)
$ 428,814
$
454,481 $ 480,642
$ 517,332
$ 550,560 $ 580,688
$ 610,927 $ 655,426 $ 714,344 $ 730,464
Table A-8
Property Tax Extension Limitation - Scenario 2
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)l:
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
399,280
413,511
(Excluding Debt Service and Stormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
12.22%
3.56%
Estimated Change in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
0,90%
1.20%
1.20%
~
1.20%
1.20%
1.20%
1.20%
~
Total Allowable Increase in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
7.68%
7.02%
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
26
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Historical
Projection (In $ Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040
$ 220,164 $ 337,931
$ 369,596
$ 260,514 $ 223,362
$ 148,729
$
146,689
$
135,726
$
106,446
Unlim~ed
Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited Bond and SRF
15,276
8,357
58,133
26,779
30,881
1,705
Unlimited Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
---
---
11.882
23,764
23,764
237,636
237,636
118,818
CIBF Program Expenditures
75,204
63,520 $
253,081
$ 314,478 $ 430,627 $ 443,383 $ 353,498 $ 299,528
$ 459,279 $ 446,879 $ 304,704 $ 174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150,000
$
$ 150,000 $ 300,000 $ 150,000
$ 150,000
$
100,000
$
150,000 $ 150,000
$
150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
~
14,297
27,767
18,602
25,908
22,772
~
11,859
7,225
(5,628)
(18,503)
(24,913)
Bond Fund Revenues
344,618
206,297
$
69,767 $ 460,602 $ 367,908 $ 364,772
$213,841 $ 206,859
$ 202,225
$
189,372
$
176,497 $
15,087
CIBF Cash Balance
285,935
555,349
372,035
518,159
455,440
376,829
237,172
144,503
(112,550)
(370,057)
(498,263)
(657,303)
Debt Service
Existing limited
31,632
46,800
51,228
$
66,463
$ 63,894 $ 60,792
$
38,331
$
26,574
$
37,302
$
36,183
$
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond
OS for Water Quality Projects
843
2,529
4,215
21,076
37,937
46,367
46,367
DebtProposedserviceUnlimited
Bond and SRF
---
133,427
135,730
141,601
153,613
--- ---
-
---
175,142
196,992
217,210
233,922
251,092
280,502
294,938
296,544
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total
Lim~ed
Bond Debt Service
31,632
46,800
51,228
79,929
101,469
112,676
105,367
105,416
146,672
176,082
195,216
196,472
Debt Service Exlenslon Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
Table A-9 - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 2
27
Economic Assessment Report K.!.OK
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-tO
Tax Revenue Requirement Forecast Summary - Scenario 3
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$
239,262
$
243,031
$
251,304
$
268,826
$
278,106
$
286,957
$
297,344
$
309,412
$
330,862
$
343.326
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
-
31,204
56,771
82,337
97,261
125,506
153,751
181,996
195,664
198,689
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (in
$
thousands)
$
428,814
$
454,481
$
482,100
$
519,405
$
552,404
$
595,423
$
623,379
$
665,595
$
696,418
$
713,407
Table A-ll
Property Tax Extension Limitation - Scenario 3
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation
Law)1:
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
379,615
394,715
(Excluding Debt Service and Stormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
6.69%
3.98%
Estimated Change in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
~
~
1.20%
1.20%
1.20%
1.20%
1.20%
~
1.20%
Total Allowable Increase in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
2.37%
2.15%
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for
new property.
28
Economic
A~sessment
Report 8-1-0K
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-12 - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 3
Historical
Projection (in
$
Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040
$ 220,164
$ 337,931 $ 369,596 $ 260,514 $ 223,362
$
148,729
$
146,689
$
135,726
$
106,446
Unlimited Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Lim~ed
Bond and SRF
15,276
8,357
58,133
26.779
30.881
1.705
Unlim~ed
Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9.229
22,511
36,503
37,489
38,501
39,541
40.608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
---
20.546
20,546
20,546
205,456
205,456
205,456
CIBF Program Expenditures
75.204
63.520 $
253.081
$ 314,478 $ 451,173 $ 452,047
$ 350.280 $ 481,220 $ 427,098 $ 414,698
$ 185.886
$
174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150.000
$
$
150,000 $ 300,000 $ 150,000 $ 150,000
$
100,000
$
150,000 $ 150.000
$
150,000
Proposed unlimited
250,000
150.000
50.000
Proposed SRF
40,000
42,000
42.000
42,000
42,000
42.000
45,000
45,000
45.000
45,000
45,000
40,000
Investment Income
~
14.297
27.767
18,602
25.908
21,745
17.330
10.432
(3.357)
(15.130)
(26.871)
(27,759)
Bond Fund Revenues
344.618
206.297 $
69.767
$ 460,602 $ 367,908
$ 363.745
$ 212,330 $ 205,432
$ 191.643 $ 179,870 $ 168,129
$
12,241
CIBF Cash Balance
285,935
555,349
372,035
518.159
434,894
346,592
208,642
(67,146)
(302.601)
(537,429)
(555,186)
(717,073)
Debt Service
Existing
Iim~ed
31.632
46,800
51,228
$
66,463 $ 63,894 $ 60,792 $ 38,331
$
26,574
$
37,302
$
36,183 $
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed
Lim~ed
Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed
Unlim~ed
Bond Funds
17.738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed
Lim~ed
Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond OS for Water Quality Projects
1,458
2,916
4,373
18,951
33,528
48,106
48,106
48,106
Proposed Unlimited Bond and SRF
---
---
---
Debt service
133,427
135,730
141,601
153,613
176,600
199,065
219,054
248,658
263.544
290,671
296,677
298,282
Debt issuance capacity unissued
600,000
400,000
550,000
300.000
150.000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
102.926
114,748
107,211
120.152
159,125
186,251
196.955
198.210
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141.464
141,464
29
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-13
Tax Revenue Requirement Forecast Summary - Scenario 4
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$
239,262
$
243,031
$
251,304
$
268,826
$
278,106
$
286,957
$
297,344
$
309,412
$
364,381
$
375,364
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt
Service. Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
-
31,204
56,771
83,056
99,419
129,102
171,733
214,364
235,224
238,249
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (in
$
thousands)
$
428,814
$
454,481
$
482,100
$
520,124
$
554,562
$
599,020
$
641,361
$
697,962
$
769,498
$
785,005
Table A-14
Property Tax Extension Limitation - Scenario 4
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)':
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
413,134
426,753
(Excluding Debt Service and 8tormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
16.11%
3.30%
Estimated Change
in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
~
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
Total Allowable Increase in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
11.41%
10.45%
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
30
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-IS - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 4
Historical
Projection (in
$
Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040
$
220,164
$
337,931
$
369,596
$
260,514
$ 223,362
$
148,729
$
146,689
$
135,726
$
106,446
Unlim~ed
Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Lim~ed
Bond and SRF
15,276
8,357
58,133
26,779
30,881
1,705
Unlim~ed
Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
---
20,546
30,683
40,820
225,730
408,204
408,204
lOt ,374
CIBF Program Expenditures
75,204
63,520
$
253,081
$
314,478 $451,173
$
462,184
$
370,555
$
501,494
$
629,846
$
617,446
$
287,260
$
174,127
Bond Fund Revenues (Debt Sizing)
Proposed
lim~ed
Bonds
300,000
150,000
$
$
150,000
$ 300,000 $ 150,000
$
150,000
$
100,000
$ 150,000
$
150,000
$
150,000
Proposed
unlim~ed
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
~
14,297
27,767
18,602
25,908
21,745
~
8,886
(5,994)
(28,036)
(50,560)
(57,701)
Bond Fund Revenues
344,618
206,297
$
69,767
$
460,602
$
367,908
$
363,745 $ 211,823
$
203,886
$
189,006
$
166,964
$
144,440
$
(17,701)
CIBF Cash Balance
285,935
555,349
372,035
518,159
434,894
336,455
177,723
(119,885)
(560,726) (1,011,208)
(1,154,028) (1,345,857)
Debt Service
Existing limited
31,632
46,800
51,228
$
66,463
$
63,894
$
60,792
$
38,331
$
26,574
$
37,302
$
36,183
$
33,219
$
3t,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,2t4
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,3t7
17,342
20,366
23,39t
26,416
Proposed Limited Bond
OS for Water Quality Projects
1,458
3,635
6,531
22,547
51,510
80,473
87,666
87,666
Proposed Unlimited Bond and SRF
Debt service
133,427
135,730
141,601
153,613
176,600
199,784
221,212
252,254
281,526
323,038
336,237
337,842
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
102,926
115,468
109,369
123,748
177,106
218,618
236,515
237,770
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
31
Economic Assessment Repon 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-16
Tax Revenue Requirement Forecast Summary - Scenario 5
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$ 239,262
$
243,031 $ 251,304 $ 268,826 $ 278,106 $ 286,957
$ 297,344 $ 309,412
$ 359,397 $ 370,600
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
31,204
56,771
83,180
99,790
129,721
174,827
219,933
242,031
245,056
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (in
$
thousands)
$ 428,814 $
454,481
$ 482,100 $ 520,248 $ 554,934 $ 599,639
$ 644,455 $ 703,532 $ 771,321 $ 787,049
Table A-17
Property Tax Extension Limitation - Scenario 5
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)1:
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
408,150
421,989
(Excluding Debt Service and Stormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
14.71%
3.39%
Estimated Change in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
M!lli
1.20%
1.20%
~
1.20%
1.20%
1.20%
1.20%
1.20%
Total Allowable Increase in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
10.07%
9.21%
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
32
Economic Assessment Report M-I-0H
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-IS - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 5
Historical
Projection (in
$
Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040
$ 220,164 $ 337,931
$ 369,596
$ 260,514 $ 223,362
$
148,729 $ 146,689
$
135,726
$ 106,446
Unlimited Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited Bond and SRF
15,276
8,357
58,133
26,779
30,881
1,705
Unlimited Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
---
20,546
32,427
44,309
229,219
443,092
443,092
118,818
CIBF Program Expenditures
75,204
63,520
$
253,081 $ 314,478 $451,173 $ 463,929 $ 374,044 $ 504,983
$ 664,734
$ 652,335 $ 304,704
$
174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150,000 $
$ 150,000
$ 300,000 $ 150,000
$ 150,000
$
100,000
$
150,000
$
150,000
$
150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
~
14,297
27,767
18,602
25,908
21,745
16,736
8,620
(6,448)
(30,257)
(54,637)
(62,854)
Bond Fund Revenues
344,618
206,297
$
69,767
$ 460,602
$ 367,908 $ 363,745
$ 211,736
$ 203,620
$
188,552
$
164,743
$
140,363
$
(22,854)
CIBF Cash Balance
285,935
555,349
372,035
518,159
434,894
334,710
172,402
(128,961)
(605,143) (1,092,735) (1,257,075)
(1,454,056)
Debt Service
Existing limited
31,632
46,800
51,228
$
66,463 $ 63,894
$ 60,792
$ 38,331
$
26,574
$
37,302
$
36,183
$
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond DS for Water Quality Projects
1,458
3,759
6,902
23,166
54,605
86,043
94,473
94,473
DebtProposedserviceUnlimited
Bond and SRF
---
133,427
--- ---
135,730
141,601
153,613
176,600
199,908
221,583
252,873
284,620
328,608
343,044
344,650
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
102,926
115,591
109,740
124,367
180,201
224,188
243,322
244,578
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
33
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 8
Rudimentary, Order-of-Magnitude Cost Estimates for Nutrient Removal
at District Water
Reclamation Plants
Rudimentary, Order-at-Magnitude Cost
Estimates
tor Nutrient Removal at District
Water Reclamation Plants
PLANT
CAPITAL COST
ANNUAL M&O
Stickney
$1,666,000,000
$100,000,000
Calumet
$605,000,000
$29,000,000
North Side
$408,000,000
$4,700,000
Kirie
$83,000,000
$1,000,000
Egan
$38,000,000
$2,500,000
Hanover Park
$17,000,000
$1,000,000
Total
$2,817,000,000
$138,200,000
NOTES:
1. Cost Estimate prepared by engineering department of MWRDGC.
2. Under the Master Plans for the Calumet and North Side WRPs, conceptual level cost estimates
were performed for various nutrient removal processes. The purpose of the cost estimates was to
compare various nutrient removal processes relative to each other. These estimates were used to
generate a rudimentary, order-of-magnitude cost estimate for all seven WRPs.
In short, North
Side and Calumet estimates were used to arrive at capital and annual operating costs
on a flow
basis
(Le. dollars per million gallons of sewage treated). These ratios were used to extrapolate
costs for the other four WRPs. The cost estimates that were derived assumed hypothetical
effluent limits of 0.5
mg/L
for total phosphorus and between 6 to 8
mg/L
for total nitrogen.
3. All costs are given in 2008 dollars.
4. Lemont Water Reclamation Plant is not included as it is planned to be converted to a sewage
pumping station.
12
Electronic Filing - Received, Clerk's Office, August 4, 2008

BEFORE THE ILLINOIS POLLUTION CONTROL BOARD
IN THE MATTER OF:
WATER QUALITY STANDARDS AND
EFFLUENT LIMITATIONS FOR THE
CHICAGO AREA WATERWAY SYSTEM
AND THE LOWER DES PLAINES RIVER:
PROPOSED AMENDMENTS TO 35 Ill.
Adm. Code Parts 301, 302, 303 and 304
)
)
)
)
)
)
)
)
R08-9
(Rulemaking - Water)
PRE-FILED TESTIMONY OF JOHN MASTRACCHIO
Economic Assessmentfor Dissolved Oxygen Enhancement Facilities
INTRODUCTION
My name
is John Mastracchio. I am a senior associate with Malcolm Pirnie and have
been a financial management, engineering, and rate consultant since 1994. My experience
includes completing studies involving municipal utility economics and financial analysis. I hold
a Master
of Business Administration degree with a concentration in finance from Cornell
University, a Masters
of Engineering degree with a concentration in Civil and Environmental
Engineering from Clarkson University, and a Bachelor
of Arts degree from the State University
of New York. I am a Registered Professional Engineer and have received the Chartered
Financial Analyst designation from the Chartered Financial Analyst Institute. I am an active
member
of the American Water Works Association, the Water Environment Federation, and serve
on the Finance, Accounting, and Management Controls Committee
of the American Water Works
Association. A resume detailing my education and experience is presented in Attachment 7.
Electronic Filing - Received, Clerk's Office, August 4, 2008

PURPOSE
I was asked to examine the potential economic impacts of constructing and operating
dissolved oxygen enhancement facilities that would be necessary to meet the Illinois
Environmental Protection Agency'sproposed water quality standards in the Chicago Area
Waterway System. The results
of this assessment are summarized in this testimony and are
documented in greater detail in the report entitled Economic Assessment
of Infrastructure to
Meet Proposed Water Quality Standards for Dissolved Oxygen and Plant Effluent Standards for
Bacteria (Attachment 6). The economic impacts were assessed in terms
of the District's
statutory taxing authority and financial capability.
COST
SUMMARY
The economic assessment of implementing dissolved oxygen enhancement processes was
based on the District spending approximately $525 million in capital infrastructure and annual
maintenance and operations (M&O) costs
of approximately $6.9 million (expressed in 2008
dollars) to construct and implement dissolved oxygen enhancement facilities that would increase
the dissolved oxygen levels in the Chicago Area Waterway System (CAWS) in order to achieve
compliance with the IEPA proposed standards. The basis for these costs
is documented in the
testimony
of David R. Zenz. As discussed in his testimony, these are rough, order-of-magnitude
cost estimates that are based upon a variety
of assumptions, and there are still concerns and
unknowns with respect to the facilities that would be required to meet the proposed standards.
2
Electronic Filing - Received, Clerk's Office, August 4, 2008

ECONOMIC ASSESSMENT
The District generates revenue to fund its operations through an ad valorem property tax,
a personal property replacement tax, user charges, interest income, and other miscellaneous fees
and charges. The District's primary source
of operating revenue is the ad valorem property tax.
The personal property replacement tax
is primarily a tax on corporate income. User charge
revenues are collected from large commercial and industrial customers and tax-exempt
customers. A summary
of the District's revenues and expenditures for the period 2002 through
2006
is provided as Attachment 1.
The District has several financial limitations and restrictions that directly impact its
ability to take on additional projects or programs. First, in 1995, the Property Tax Extension
Limitation Law was passed by the Illinois General Assembly, which limits the ability
of the
District to adopt future increases in the aggregate tax levy. In accordance with this Act,
increases to the District's property tax levy are limited to the lesser of:
(1) five percent or (2) the
change in the national consumer price index plus allowable increases for new property. The
aggregate levy is the total levy
of all funds except the Bond Redemption and Interest Fund and
the Stormwater Management Fund. In other words, debt service and stormwater management
costs are not included under this limitation.
Second, the District's initial Tax Cap legislation restricted the District'snon-referendum
bond authority to only apply to projects initiated prior to October
1, 1991. There was a specific
exemption, essentially to exclude Tunnel and Reservoir Plan projects, from the more restrictive
provisions
of the Act which require referendum approval of all new debt. Public Act 89-385
provides the District with the authority to issue non-referendum "limited bonds" for capital
projects initiated after October
1, 1991 at the same debt service level as it did in 1994. Limited
bonds can be issued to the extent that the total debt service requirements of any new debt, when
3
Electronic Filing - Received, Clerk's Office, August 4, 2008

combined with existing debt service, does not exceed the 1994 debt service extension base of
$141,463,920. Public Act 90-485 has provided a further modification by authorizing the
exclusion
of debt for Tunnel and Reservoir Plan projects from this debt service extension base.
Third, in 2003, the District received authority under Public Act 93-279 to issue $150
million (previously $100 million)
of non-referendum bonds during any budget year, plus
authorized, but unissued bonds, during the previous three budget years through 2016.
A baseline scenario was prepared, which includes the District's currently planned capital
projects that the District feels is necessary in order to maintain and upgrade its aging facilities
and infrastructure, but excludes the costs associated with this proposed rulemaking. The
estimated cost
of the District's planned capital improvement projects were provided to Malcolm
Pirnie in February 2008, and a discussion
of these projects is provided in the testimony of Mr.
Tom Kunetz
of the District's Engineering Department. The baseline scenario indicates that the
District would be able to generate sufficient revenues to satisfy the District's projected revenue
requirements within the constraints
of the legal limitations r just discussed.
In
addition, the
District's debt financing needs will not exceed the Tax Cap legislation limits or the District's
non-referendum bonding authority through fiscal year 2015. A summary
of the District's
projected results compared to the financial limitations and restrictions are provided
as
Attachment 2 (Figures 2-1, 2-2 and 2-3).
However, the District does not have sufficient financial resources to fund the capital
expenditures and operation and maintenance costs necessary to meet the rEPA proposed
dissolved oxygen standards. The District cannot generate sufficient revenues within the
constraints
of the Property Tax Extension Limitation Act, and the remaining funds needed would
exceed the District'sTax Cap and non-referendum bonding authority. A summary of the
4
Electronic Filing - Received, Clerk's Office, August 4, 2008

District's projected financial results under this scenario, as compared to the financial limitations
and restrictions,
is provided in Attachment 3 (Figures 3-1, 3-2 and 3-3).
I also completed an evaluation
of the economic impact of the combined costs of the IEPA
proposed dissolved oxygen standards and disinfection requirements (chlorination/dechlorination
or ultraviolet disinfection). Disinfection costs were summarized in Attachment 1
of my previous
testimony.
If the District is required to move forward with both processes, it is anticipated that
the Property Tax Extension Limitation Act, the District'sTax Cap, and the non-referendum
bonding authority would be greatly exceeded. A summary
of the District's projected financial
results, including the dissolved oxygen enhancement and chlorination / dechlorination
disinfection processes, as compared to the financial limitation and restrictions
is provided in
Attachment 4 (Figures 4-1, 4-2 and 4-3). Similarly, a summary
of the District's projected
financial results, including the dissolved oxygen and ultraviolet disinfection processes, as
compared to the financial limitation and restrictions is provided in Attachment 5 (Figures 5-1, 5-
2, and 5-3).
It
should be noted that effluent limits for phosphorus and total nitrogen may be imposed
on the District's treatment plants in the future. The District's currently planned capital projects,
which were used in the baseline analysis, do not include the costs to implement nutrient removal
processes. As documented in a District cost summary table provided in Attachment 8, a
rudimentary, order-of-magnitude cost estimate prepared by the District indicates that the capital
costs to construct nutrient removal processes could be approximately $2.8 billion dollars.
CONCLUSION
Fully funding the activities necessary to achieve compliance with IEPA's proposed rule
would require an act
of the state Legislature to amend the Property Tax Extension Limitation Act
5
Electronic Filing - Received, Clerk's Office, August 4, 2008

and provide additional non-referendum bonding authority; a voter referendum in support of
additional bonding authority; or drastic reductions in the funding of other District programs.
Furthermore, adding the combined costs of implementing both the dissolved oxygen and
disinfection processes that would be required by this rulemaking to the wastewater system costs
currently planned by the District would result in the District'sfinancial limitations and
restrictions to
be greatly exceeded.
In
addition, if implemented, these processes would leave no
financial capacity to fund other programs not currently included in the Distrct's capital plan.
One such project, not currently included in the District'scapital plan, is nutrient removal
facilities at its treatment plants, which
couldcost approximately $2.8 billion if nutrient effluent
limits are imposed in the future.
6
Electronic Filing - Received, Clerk's Office, August 4, 2008

Respectfully submitted,
fld~
By:
John Mastracchio
Electronic Filing - Received, Clerk's Office, August 4, 2008

Testimony Attachments
1.
MWRD Summary of Financial Results
2.
Baseline Financial Results Compared to Financial Limitations and Restrictions
3.
Projection of Financial Results Including Cost of Dissolved Oxygen Processes
Compared to Financial Limitations and Restrictions
4.
Financial Results Including Dissolved Oxygen and ChlorinationlDechlorination
Disinfection Costs Compared to Financial Limitations and Restrictions
5.
Results Including Dissolved Oxygen and Ultraviolet Disinfection Costs Compared to
Financial Limitations and Restrictions
6.
Report entitled Economic Assessment of Infrastructure to Meet Proposed Water
Quality Standards for Dissolved Oxygen and Plant Effluent Standards for Bacteria,
prepared by Malcolm Pirnie, Inc.
7.
John Mastracchio Resume
8.
Rudimentary, Order-of-Magnitude Cost Estimates for Nutrient Removal at District
Water Reclamation Plants prepared by the District
7
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 1
-
MWRD Summary of Financial Results
(in $ Thousands, Modified Accrual Basis)
2002
2003
2004
2005
2006
Revenues
Property Taxes
$
362,036
$
397,751
$
360,326 $ 423,941
$
380,675
Personal Property Replacement Tax
22,285
24,048
25,961
36,031
37,743
User Charges
48,890
50,222
47,757
45,983
52,504
Interest on Investments
15,693
13,163
9,943
19,693
43,659
Other Revenues
14,759
16,203
16,495
16,309
17,691
Total Revenues
$
463,663
$
501,387
$
460,482 $ 541,957
$
532,272
Expenditures
General Administration
$
14,318
$
14,987
$
15,538
$
17,259
$
16,974
Personnel
27,610
30,916
35,877
32,900
35,162
Pension Costs
27,044
29,511
27,372
31,561
30,071
Research and Development
23,838
24,172
24,030
24,787
24,985
Information Technology
11,204
11,417
10,574
10,811
11,034
Maintenance and Operations
160,326
159,079
160,299
157,612
155,899
Other
32,843
22,563
27,637
31,522
26,931
Construction Costs
157,076
164,865
127,155
133,599
164,157
Debt Service
145,831
158,626
156,025
169,019
171,869
Total Expenditures
$
600,090 $
616,136
$
584,507 $ 609,070
$
637,082
Revenues Over (Under) Expenditures
$ (136,427)
$ (114,749)
$ (124,025) $ (67,113) $ (104,810)
Other Financing Sources (Uses)
222,622
223,613
52,720
15,973
383,448
Net Change in Fund Balance
$
86,195 $ 108,864
$
(71,305) $ (51,140) $ 278,638
Source: Comprehensive Annual Financial Reports (2003-2006).
8
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 2
Baseline Financial Results Compared to Financial Limitations and Restrictions
Figure 2-1 - Capital Improvement Plan - Baseline
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
Plant _
Tarp -
CIBF Cash Balance
$600,000
$500,000
$400,000
.fl
....
"
c
0
$300,000
.c
$200,000
..
l-
$100,000
$0
co
0
C\l
.q-
<0
co
8
C\l
5
C\l
5
C\l
~
5
C\l
~
Figure 2-2
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Baseline
$410,000 r------------------------------,
$390,000 +--------------------------==---1
$370,000 +-------------------------==--""'f-----1
-ll
m $350,000
6
$330,000
+-----------------=:;_"r.:=.....j
~
l-
.5 $310,000
+----------~"",."1
<It
$290,000
+-------=_~l_____l
$270,000
.J.-~=-----l
$250,000
+-""""--,r--"""""...,............
"-'-...,--"--"'----,---'----'---,---'--'--,--'--...L..-,....-I.........'---r---'-.........-,-...L..-""---j
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
c:::=:J
Projected Tax
Levy Requirement(Excluding SkmnwaterCostand Debt Service)
-
Tax Levy Extension limitation (CPI+ New Property)
Figure 2-3
Forecasted Debt Service Compared to Debt Service Extension Base - Baseline
$160,000
$140,000
$120,000
CIl$100,000
'0
m$80,000
::J
,g $60,000
tit
.5
$40,000
$20,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
_
Projected Amountof Limited DebtService
9
-
DebtService Extension Limitation
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 3
Projection
of Financial Results Including Cost of Dissolved Oxygen Processes
Compared to Financial Limitations and Restrictions
Figure 3-1 - Capital Improvement Plan
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$600,000
$500,000
$400,000
-8
II
c
$300,000
II
"
0
..
...
z:
$100,000$200,000
$0
~
Plant
_Tarp
;~;~.
ProJoctsto Meet Proposed Standards
-CIBF Cash Balance
Figure 3-2
Forecasted Aggregate Levy Requirement
Compared to Tax Cap Limitation
$410,000 ,..--------------------------------,
$390,000
+--------------------------~t----l
III $370,000 +-------------------------c:::oII.....,'------j
'C
c
$350,000
+--------------------~
........
III
.t::
g $330,000 -1----------------=-"""""""...,
I-
.5 $310,000
+------------=_-r
... $290,000 +--------::::;;;;01""",-,.-..,
$270,000
-1--'--'1'----1
$250,000
+-J'-=-L.,----'---'-__._--'--'--,..-'-~----'--J..__._--'-....I-..,.-'-~----'---'-___._--'--'--_,__""""y
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
~
Projected Tax levy Requirement(Excluding StmnwaterCostand DebtSerYlce)
-
Tax Levy Extension Limitation (CPI + New Property)
Figure 3-3
Forecasted Debt Service Compared to Debt Service Extension Base
$250,000
$200,000
~$150,OOO
c
III
g$100,000
.t::
~
.5
$50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Amountof Limited DebtSelVlce
10
-
Debt Service Extension Limitation
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 4
Financial Results Including Dissolved Oxygen and ChlorinationlDechlorination
Disinfection Costs Compared to Financial Limitations and Restrictions
Figure 4-1 - Capital Improvement Plan
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
Plant
-Tarp
••••••• Projects to Meet Proposed Standards
-
aBF cash Balance
~
c
:I
"
o
.c
I-
lit
$700,000
$600,000
$500,000
$400,000
$300,000
$200,000
$100,000
$O-~.
o
@
CD
@
Figure 4-2
Forecasted Aggregate Levy Requirement Compared to Tax Cap Limitation
$450,000
$430,000
$410,000
-a $390,000
!
c
$370,000
,g $350,000
I- $330,000
.!:
... $310,000
$290,000
$270,000
$250,000
-
I........
,..-
....
"",-
-
-"..,.
r--
-
-
-
-~
f-- -
-
-
-
f-- f-----
f--
-
f-----
-
9:RF
----
-
f--
f-----
f--
-
f-----
-
II
-
f--
f-----
f--
-
f-
-
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
$250,000
$200,000
-a $150,000
c
III
5$100,000
.c
~
.5
$5O,OCK>
$0
c:::::::l Projected Tax Levy Requirement(ExCluding
StmnwaterCostand
Debt Service)
--
Tax Levy Extension Limitation (CPI + New Property)
Figure 4-3
Forecasted Debt Service Compared to Debt Service Extension Base
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
....Projected Amountof Limited DebtService
11
-
DebtService Extension Umitatial
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 5
Financial Results Including Dissolved Oxygen
and Ultraviolet Disinfection Costs
Compared to Financial Limitations
and Restrictions
Figure 5-1 - Capital Improvement Plan
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$700,000
$600,000
$500,000
{!j
$400,000
.,
..
l:
$300,000
"
0
...
...
.l:
$200,000
$100,000
$0
8
C\I
Plant
-
Tarp
.,-,. Projects to Meet Proposed Standards
-
CIBF Gash Balance
o
@
Figure 5-2
Forecasted Aggregate Levy Requirement
Compared to Tax Cap Limitation
$450,000
$430,000
$410,000
Ul
$390,000
i
$370,000
.2
$350,000
I-
$330,000
.!:
o $310,000
$290,000
$270,000
$250,000
r--
I-
~
~
I-
-~
I-
.-.-,.".
~
t---
I-- I-
--~
t-- t--
I-- l-
I--
t-- t---
I-- I-
----
,...
1--rlf1.
F
I-- I-- I--
t-- t--
t--- l-
t--- t--- t---
t-- t--
I-- I-
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
~
Projected Tax Levy Requirement(Excluding StormwaterCostand Debt Service)
--Tax Levy Extension Limitation (CPI + New Property)
Figure 5-3
Forecasted Debt Service Compared to Debt Service Extension Base
$300,000
$250,000
$200,000
~
:$150,000
~
o
~$1oo,000
c
.- $50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Am Duntof Lim iled Debt Service
12
--DebtService Extension Limitation
Electronic Filing - Received, Clerk's Office, August 4, 2008

ATTACHMENT 6
Economic Assessment of Infrastructure to Meet Proposed
Water Quality
Standards for Dissolved Oxygen
and Plant Effluent Standards for Bacteria
(Malcolm Pirnie, Inc.,
July 2008)
Electronic Filing - Received, Clerk's Office, August 4, 2008

METROPOLITAN WATER RECLAMATION DISTRICT OF GREATER CHICAGO
ECONOMIC ASSESSMENT OF INFRASTRUCTURE TO MEET PROPOSED WATER
QUALITY STANDARDS FOR DISSOLVED OXYGEN AND PLANT EFFLUENT
STANDARDS FOR BACTERIA
Economic Assessment
July 2008
Introduction
The purpose of this study is to examine the potential economic impacts of implementing
processes at the Metropolitan Water Reclamation District of Greater Chicago (District)
facilities and in the waterways necessary to meet the proposed water quality and plant
effluent standards as proposed by the Illinois Environmental Protection Agency (IEPA)
under R08-9. The assessment
is composed of two sections; environmental and economic.
This report presents the economic portion of the assessment. The environmental portion
is provided under a separate cover.
The District's approach is to take a "holistic" view of the environmental impacts of the
alternatives, including the potential economic impacts in terms
of the District's statutory
taxing authority and financial capability. A summary of the infrastructure costs, financial
condition and limitations
of the District, and financial forecast results under several
alternatives is provided below. These alternatives consist of:
Disinfection (Ultraviolet and ChlorinationlDechlorination) technology;
Dissolved Oxygen technology;
• A combination
of disinfection and dissolved oxygen technology.
Infrastructure Cost Summary
This study evaluates the costs and overall environmental impacts of potentially
implementing processes to disinfect plant effluent and increase dissolved oxygen in the
Chicago Area Waterway System (CAWS). Costs associated with several alternatives,
including implementing chlorination/dechlorination disinfection, and ultraviolet
disinfection at the three water reclamation plants is summarized in Table 1 below.
1
Economic Assessment ReJXlft 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table 1 - Summary of Costs to Meet Newly Proposed Water Quality and Effiuent Standards in the
Chicago Area Waterway System
Project Description
Capital Cost
AnnualO&M
Cost
Total Present
Value Cost
SWRP
ChlorinationlDechlorination Disinfection
$225,700,000
$15,900,000
$533,500,000
Ultraviolet Disinfection
267,200,000
12,600,000
511,200,000
CWRP
ChlorinationlDechlorination Disinfection
$79, 100,000
$5,020,000
$176,500,000
Ultraviolet Disinfection
112,300,000
4,600,000
201,600,000
NSWRP
ChlorinationlDechlorination Disinfection
$114,200,000
$5,040,000
$212,000,000
Ultraviolet Disinfection
111,600,000
4,900,000
206,800,000
Total
ChlorinationlDechlorination Disinfection
$419,000,000
$25,960,000
$922,000,000
Ultraviolet Disinfection
491,100,000
22,100,000
919,600,000
Dissolved Oxygen Infrastructure
$524,800,000
$6,870,000
$656,600,000
All costs in 2008 dollars. Present value costs based on a 3.0% interest rate, and a 3% inflation rate for 20 years.
Sources:
Report entitled ChlorinationlDechlorination Disinfection Cost Study for Stickney, Calumet, and North Side Water Reclamation
Plants" prepared by CTE and dated May 12, 2008. Costs subsequently updated to 2008 dollars.
Report entitled UV Disinfection Cost Study - Northside Water Reclamation Plantprepared by
CfE and dated January 31, 2008. Costs
subsequently updated to 2008 dollars.
Dissolved Oxygen Infrastructure costs provided by erE.
Financial Summary
The District generates revenue to fund its operations from ad valorem property taxes,
personal property replacement tax (PPRT), user charge revenue, interest income, and
other revenues. The District's primary source of operating revenue is ad valorem
property taxes.
PPRT revenue is primarily a tax on corporate income. The PPRT
revenue is first distributed to fully fund the District'sRetirement Fund, and subsequent
receipts are distributed to other non-debt funds. User charge revenues are collected from
large commercial and industrial classes, and tax-exempt customers. A summary
of the
District's revenues and expenditures for the period 2002 through 2006
is provided in
Table 2 below.
2
Economic Assessment
Report
8-1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table 2 - MWRD Summary of Financial Results - All Governmental Funds
(in $ Thousands, Modified Accrual Basis)
2002
2003
2004
2005
2006
Revenues
Property Taxes
$
362,036
$
397,751 $ 360,326
$ 423,941
$
380,675
Personal Property Replacement Tax
22,285
24,048
25,961
36,031
37,743
User Charges
48,890
50,222
47,757
45,983
52,504
Interest on Investments
15,693
13,163
9,943
19,693
43,659
Other Revenues
14,759
16,203
16,495
16,309
17,691
Total Revenues
$
463,663
$
501,387 $ 460,482
$ 541,957
$
532,272
Expenditures
General Administration
$
14,318
$
14,987
$
15,538
$
17,259
$
16,974
Personnel
27,610
30,916
35,877
32,900
35,162
Pension Costs
27,044
29,511
27,372
31,561
30,071
Research and Development
23,838
24,172
24,030
24,787
24,985
Information Technology
11,204
11,417
10,574
10,811
11,034
Maintenance and Operations
160,326
159,079
160,299
157,612
155,899
Other
32,843
22,563
27,637
31,522
26,931
Construction Costs
157,076
164,865
127,155
133,599
164,157
Debt Service
145,831
158,626
156,025
169,019
171,869
Total Expenditures
$ 600,090
$
616,136 $ 584,507
$ 609,070
$
637,082
Revenues Over (Under) Expenditures
$ (136,427) $ (114,749) $ (124,025)
$ (67,113) $ (104,810)
Other Financing Sources (Uses)
222,622
223,613
52,720
15,973
383,448
Net Change in Fund Balance
$
86,195 $ 108,864
$ (71,305) $ (51,140) $ 278,638
Source: Comprehensive Annual Financial Reports (2003-2006).
The expenditures shown in Table 2 were appropriated to the Corporate Fund,
Construction Fund, Stormwater Fund, Capital Improvement Bond Fund, Bond
Redemption and Interest Fund, Retirement Fund, and the Reserve Claim Fund. These
funds are briefly summarized below:
The Corporate Fund
is the District's General Fund and includes appropriation
requests for all day-to-day operational costs.
The Construction Fund
is utilized as a pay-as-you-go capital rehabilitation and
modernization program, and to fund operations-related projects, where the useful
life
of the improvement is less than 20 years or when the values are less than $1
million. Capital projects are financed by a tax levy sufficient to pay for project
costs as they are constructed.
The Stormwater Management Fund is used to minimize flooding damage by
coordinating, planning, implementing, financing, and operating regional
stormwater management projects, to foster stormwater improvements, and to
educate the public with respect to sustainable growth concepts.
The Capital Improvement Bond Fund includes major capital infrastructure
projects whose useful lives extend beyond 20 years, and which will be financed
by long-term debt, Federal and State grants, and State Revolving Fund loans.
3
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

The Bond Redemption and Interest Fund is the District's debt service fund.
Principal and interest payments on District general obligation bonds and SRF
loans require an annual levy and appropriation.
The Retirement Fund
is used to account for pension costs as provided by
specifically levied annual property taxes. The taxes are collected and recorded in
this fund prior to their payment to the MWRD Retirement Fund.
The Reserve Claim Fund acts
as the District's Insurance Fund. The District is
primarily self-insured and utilizes this fund for repair or replacement of damaged
District property and claims implied against the District.
Financial Limitations
The District has several financial limitations and restrictions that directly impact its
ability to take on additional projects or programs. When considering the potential
economic impacts that the projected water quality improvement costs will have on the
District's funding and bonding authority, several financial limitations were considered.
First, in 1995, the Property Tax Extension Limitation Law (PTELL) was passed by the
Illinois General Assembly, which limits the ability
of the District to adopt future
increases in the aggregate tax levy. In accordance with this Act, increases to the
District's aggregate tax levy are limited to the lesser of: (1) five percent or (2) the change
in the national consumer price index (CPI) plus allowable increases for new property.
The aggregate levy is the total
of all funds except the Bond Redemption and Interest and
the Stormwater Management Funds.
Second, the District's initial Tax Cap legislation restricted the District's non-referendum
bond authority to only apply to projects initiated prior to October
1, 1991. There was a
specific exemption, essentially to exclude TARP projects from the more restrictive
provisions
of the Act which require referendum approval of all new debt. Public Act 89-
385 provides the District with the authority to issue non-referendum "limited bonds" for
capital projects initiated after October
1, 1991 at the same level as it did in 1994. Limited
bonds can be issued to the extent that the total debt service requirements
of any new debt
when combined with existing debt service does not exceed the 1994 debt service
extension base
of $141,463,920. Public Act 90-485 has provided a further modification
by authorizing the exclusion
of debt for Tunnel and Reservoir Plan (TARP) projects from
this debt service extension base.
Third, in 2003, the District received authority under Public Act 93-279 to issue $150
million (previously $100 million)
of non-referendum bonds during any budget year plus
authorized but unissued bonds during the previous three budget years through 2016.
These financial limitations and restrictions directly impact the District's ability to take on
additional projects and/or programs, and the District is currently very near these limits
without considering the implementation
of disinfection or dissolved oxygen processes.
4
Economic Assessment
Report
8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Baseline Financial Forecast
A baseline long-term financial forecast was prepared for the District based on its current
estimated requirements to be used as a comparison with financial forecasts associated
with meeting the proposed water quality and effluent standards. Revenue and
expenditure projections were made based on the five-year forecast information contained
within the 2008 budget, the capital improvement program information provided by the
District, and discussions with the District's Administrative Services Manager. A
summary
of the current capital improvement plan, which does not include a disinfection
program or projects needed to meet the newly proposed water quality standards,
is
provided in Table 3 below. The estimated cost of the District's planned capital
improvement projects were provided to Malcolm Pimie in February 2008.
Table 3 - Capital Improvement Plan (Other Projects)
Yearly Dlspersement ProJection (In $ Thousands)->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Corporate Fund Program
$
177
$
329
$
189
$
206
$
219
$
386
$
399
$
413
$
427
$
441
Construction Fund Program
14,651
14,547
11,818
6,720
4,927
5,949
6,849
7,796
9,249
10,512
Limited Bond Fund Projects
Plant
158,023
161,419
247,995
287,760
242,858
205,403
134,662
133,876
120,859
76,173
Sewer
23,668
53,703
73,934
61,605
2,618
7,979
TARP
1,016
3,668
10,822
8,524
4,838
Unspecffied
25,000
Unlimited Bond Fund Projects (TARP)
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited SRF Projects
Plant
29,453
24,654
29,049
Sewer
28,680
2,125
1,831
1,705
Unlimited SRF Projects (TARP)
1,553
Stormwater Fund Projects
10,008
2,490
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Total
$ 277,584 $ 330,470
$
437,454
$
426,721 $ 324,680
$ 272,119 $ 214,824 $
204,638
$180,695
$
179,807
Source: The estimated cost of the District's planed capital improvement projects were provided to Malcolm
Pirnie in February 2008.
It
is important to note that the current CIP does not include future Stormwater
Management fund projects
as Detail Watershed Plans (DWPs) are not expected to be
completed until 2010.
In
addition, the District'scurrently planned projects do not include
the costs of implementing nutrient removal processes. As documented in a District
summary cost table (provided
as Table 4 below), a rudimentary order-of-magnitude cost
estimate prepared by the District indicates that the capital costs to construct nutrient
removal processes could be approximately $2.8 billion.
5
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table 4 - Rudimentary, Order-of-Magnitude Cost Estimates for Nutrient Removal
at District Water Reclamation Plants
PLANT
CAPITAL COST
ANNUALM&O
Stickney
$1,666,000,000
$100,000,000
Calumet
$605,000,000
$29,000,000
North Side
$408,000,000
$4,700,000
Kirie
$83,000,000
$1,000,000
Egan
$38,000,000
$2,500,000
Hanover Park
$17,000,000
$1,000,000
Total
$2,817,000,000
$138,200,000
NOTES:
I. Cost Estimate prepared by engineering department
of MWRDGC.
2. Under the Master Plans for the Calumet and North Side WRPs, conceptual level cost estimates
were performed for various nutrient removal processes. The purpose
of the cost estimates was to
compare various nutrient removal processes relative to each other. These estimates were used to
generate a rudimentary, order-of-magnitude cost estimate for all seven WRPs. In short, North Side
and Calumet estimates were used
to arrive at capital and annual operating costs on a flow basis
(i.e. dollars per million gallons
of sewage treated). These ratios were used to extrapolate costs for
the other four WRPs. The cost estimates that were derived assumed hypothetical effluent limits
of
0.5 mg/L for total phosphorus and between 6 to 8 mg/L for total nitrogen.
3. All costs are given in 2008 dollars.
4. Lemont Water Reclamation Plant is not included as it is planned to be converted to a sewage
pumping station.
The baseline capital improvement plan and projected cash balance in the Capital
Improvement Bond Fund is shown graphically in Figure 1 below. As shown in this
figure, the cash balance in the Capital Improvement Bond Fund is expected to gradually
decrease as a result
of funding these capital projects until 2016 when the District's
authority to issue non-referendum bonds expires.
6
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 1
Capital Improvement
Plan. Baseline
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
Plant -
Tarp -
CIBF Cash Balance
$600,000
$500,000
'0
..
$400,000
"
..
c
0to
$300,000
.r:.
$200,000
I-
tI>
$100,000
$0
~
0
C\l
.q-
co
0
C\l
0
C\l
0
C\l
0
C\l
0
C\l
(Xl
o
C\l
In addition to these planned capital expenditures, maintenance and operations (M&O)
costs were projected over the forecast period. The projection was based on historical
results, the District's existing five-year forecast projections, and discussions with District
staff. The projections
of M&O costs are included in the forecasted property tax levy
increases summarized below. Additional details are provided in the tables and
calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements (for the years 2008 through
2017) was developed to provide a baseline scenario of current estimated requirements in
which to compare scenarios incorporating capital and M&O costs that would be
necessary to meet proposed water quality standards. The baseline financial projection
results are summarized in Figures 2 and 3 below and detailed in Appendix
A.
Figure 2
shows the annual increase in the property tax levy necessary to fund projected capital and
M&O costs, excluding those costs necessary to meet the proposed water quality
standards, as compared to the property tax levy limitation. The property tax limitation
limits the property tax levy increase to the lessor
of (1) five percent or (2) the change in
CPI plus the increase in new property. The baseline scenario results indicate that the
District will stay at
or below the tax levy limitation over the forecast period.
Figure 3 shows the projected annual "limited" debt service associated with existing and
proposed District debt, excluding debt that would
be necessary to fund capital projects
associated with the proposed water quality standards, as compared to the debt service
limitation. The baseline analysis indicates that the District will stay at
or below the debt
service extention base limitation through fiscal year 2015 and exceed the limitation
slightly in fiscal years 2016 and 2017. This means that in 2016, the District'snon-
referendum bond authority, which expires at the end
of 2016, will be further limited so as
not to exceed the debt service extension base.
7
Economic Assessment
Report
8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 2
Forecasted Aggregate Tax Levy Requirement Compared to Tax
Cap Limitation - Baseline
$410,000 ,-------------------------------,
$390,000
$370,000
~
111
$350,000
!l
o
$330,000
.c
l-
e
$310,000
0-
$290,000
+-------::::;;o~_r_-__l
$270,000
-1-.-"'------1
$250,000
+--'--...L-,-'-..L.-,............_'---,,..--L---''---,----'---L-,--'----'--,-'----'----.---'----'----.----'''---...l..---r-...L-....I-.j
=
Projected Tax Levy Requirement(Excluding Storm water Costand Debt Service)
--Tax Levy Extension Limitation (CPI + New Property)
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Figure 3
Forecasted Debt Service Compared to Debt Service Extension Base
$160,000
$140,000
$120,000
1/1
$100,000
'tJ
IX
$80,000
:J
,g
$60,000
I-
~
$40,000
$20,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
_
Projected
Am
ount of Limited Debt Service
8
--Debt Service Extension Lim itatial
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Scenario 1 (Chlorination/Dechlorination Disinfection)
Scenario 1 consists of adding the capital and annual M&O costs associated with
chlorination / dechlorination disinfection (as shown in Table 1) to the baseline financial
forecast. For the purposes
of this scenario, it was assumed that design of the disinfection
processes would occur in 2011 through 2013 and construction would occur in 2014
through 2016.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 1
is shown graphically in Figure 4 below. As shown in this
figure, additional capital costs would be incurred to meet the proposed water quality
standards, and the cash balance in the Capital Improvement Bond Fund would decrease
more rapidly than the baseline forecast as a result
of funding these capital projects until
2016 when the District's authority to issue non-referendum bonds expires. The analysis
indicates that the projected cash balance in the Capital Improvement Bond Fund would
be insufficient to fund current projects and the projects associated with the proposed
water quality standards due to the District's current authority and limitation
of issuing no
more than $150 million of non-referendum bonds during any budget year. Furthermore,
in order to fund the capital projects, the District would have to receive additional non-
referendum bonding authority or issue a voter referendum.
Figure 4
Capital Improvement Plan - Scenario 1
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$600,000
$500,000
$400,000
{l
..
In
c:::
$300,000
:J
0
~
$200,000
.,.
I-
$100,000
$0
CXl
0
0
C\l
Plant
-
Tarp
••
':~"
Projects to Meet Proposed Standards
-
CIBF Cash Balance
In addition to the capital expenditures associated with Scenario 1, M&O costs associated
with this scenario were projected over the forecast period. The projections
of M&O costs
associated with implementing the chlorination / dechlorination disinfection processes are
included in the forecasted property tax levy increases summarized below. Additional
details are provided in the tables and calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
plant effluent standards was developed for Scenario
1. The results are summarized in
9
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figures 5 and 6 below and detailed in Appendix
A.
Figure 5 shows the annual aggregate
property tax levy requirement necessary to fund projected capital and M&O costs,
including those costs necessary to meet the proposed plant effluent standards,
as
compared to the aggregate tax levy limitation. The Scenario 1 results indicate that the
District will exceed the aggregate tax levy limitation once the disinfection processes have
been constructed and operations commence in 2016. Furthermore, in order to fund the
improvements, the District would have to request an amendment to the Property Tax
Extension Limitation Law or obtain voter approval via referendum to increase the
aggregate extension limitation and/or the limiting rate.
Figure 5
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Scenario 1
$430,000 .,.--------------------------------,
$410,000 +-----------------------------.1
$390,000
-f-------------------------j
III
'g
$370,000
+--------------------------,~~------l
~
$350,000 +-------------------c=-.........-
~
$330,000
-f-------------------,_"..,~
.5 $310,000 +----------..."....""...,
o
$290,000 +------::::::;0""""-,:=----1
$270,000
+---<__=----1
$250,000 +-.L..-.L-T-'=-'----,---"=......,..........
'-'---r--'-........,.--.......
..I.--,----''---L-.,---&.-"'''......,...-L..--'---r--'''''''=L-..i
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
=
Projected Tax Levy Requiremenl(Excluding SlormwalerCosland Debt Service)
-
Tax Levy Extension Limitation (CPI
+ New Property)
Figure 6 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund capital
projects associated with the proposed plant effluent standards, as compared to the debt
service extension base. The Scenario 1 analysis indicates that the District would
significantly exceed the debt service extension base beginning in fiscal year 2014
if the
Scenario 1 projects associated with meeting the proposed plant effluent standards were
implemented.
Figure 6
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 1
$200,000 ,-------------------------------,
$180,000 +---------------------
$160,000 +------------------
~$120,OOO
$140,000
+-----------------
+----------------
m
$100,000
.c
S $80,000 +---
t; $60,000
+---
.5 $40,000
$20,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
I:I:::J
Projected Amountof Limited DebtService
-
DebtServlce Extension Limitation
l.---
~------------
__ic Assessmenl Repon 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Scenario 2 (Ultraviolet Disinfection)
Scenario 2 consists of adding the capital and annual M&O costs associated with
ultraviolet disinfection (as shown in Table
1) to the baseline financial forecast. For the
purposes of this scenario, it was assumed that design of the disinfection processes would
occur in 2011 through 2013 and construction would occur in 2014 through 2016.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 2 is shown graphically in Figure 7 below. As shown in this
figure, additional capital costs would be incurred to meet the proposed water quality
standards, and the cash balance in the Capital Improvement Bond Fund would decrease
more rapidly than the baseline forecast as a result
of funding these capital projects until
2016 when the District's authority to issue non-referendum bonds expires. The analysis
indicates that the projected cash balance in the Capital Improvement Bond Fund would
be insufficient to fund current projected projects and the projects associated with the
proposed water quality standards due to the District's current authority and limitation
of
issuing no more than $150 million of non-referendum bonds during any budget year.
Furthermore, in order to fund the capital projects, the District would have to receive
additional non-referendum bonding authority or issue a voter referendum.
Figure
7
Capital Improvement Plan - Scenario 2
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$600,000
$500,000
$400,000
'0
..
....
::>
c
$300,000
0
.r:.
$200,000
...
I-
$100,000
$0
!Xl
8
C\l
Plant
-
Tarp
.;..'b
Projects to Meet Proposed Standards
-
CIBF Cash Balance
In
addition to the capital expenditures associated with Scenario 2, M&O costs associated
with this scenario were projected over the forecast period. The projections of M&O costs
associated with implementing the ultraviolet disinfection processes are included in the
forecasted property tax levy increases summarized below. Additional details are
provided in the tables and calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
plant effluent standards was developed for Scenario 2. The results are summarized in
Figures 8 and 9 below and detailed in Appendix
A.
Figure 8 shows the annual aggregate
property tax levy requirement necessary to fund projected capital and M&O costs,
11
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

including those costs necessary to meet the proposed plant effluent standards, as
compared to the aggregate property tax levy limitation. The Scenario 2 results indicate
that the District will exceed the aggregate tax levy limitation once the disinfection
processes have been constructed and operations commence in 2016. Furthermore, in
order to fund the improvements, the District would have to request an amendment to the
Property Tax Extension Limitation Law or obtain voter approval via referendum to
increase the aggregate extension limitation and/or the limiting rate.
Figure 8
Forecasted Aggregate Tax Levy Requirement
Compared to Tax Cap Limitation - Scenario 2
$430,000 ,-----------------------------,
$410,000
-t----------------------------r---r---j
$390,000 -+------------------------1
III
'g $370,000
-+-----------------------",...~---l
~
$350,000
-t-------------------~
.......
~
$330,000
-t-----------------==-.,..~
:. $310,000
-t----------e::::::;;;"".,.~
$290,000
-t--------:::::;;;;;II....,.-}--i
$270,000
4-~':::::::'--1
$250,000
-t-'--.L.-,....-'---...J'-r--'-----L----,-'----'---r--'---'-...----..l...-....I.-,-'--"""""'''''''''''---...J'-r--'----'--,---'----'---j
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
I
I Projected Tax Levy Requiremenl(ExcludingStonnwaterCostand DeblServicej
-
Tax Levy Extension Limitation (CPI + New Properly)
Figure 9 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund capital
projects associated with the proposed plant effluent standards, compared to the debt
service extension base. The Scenario 2 analysis indicates that the District would
significantly exceed the debt service extension base beginning in fiscal year 2014
if the
Scenario 2 projects associated with meeting the proposed plant effluent standards were
implemented.
Figure 9
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 2
$250.000
$200,000
~
$150,000
m
S
$100,000
s::.
~
.: $50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
-
Projected Amount of Limned DebtServlce
12
-
Debt Service Extension Limitation
Economic Assessment Repol! 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Scenario 3 (Dissolved Oxygen)
Scenario 3 consists of adding the capital and annual M&O costs that are anticipated to be
required to meet the proposed Dissolved Oxygen Water Quality Standards in the CAWS
(as shown in Table 1) to the baseline financial forecast. While it
is possible that the
dissolved oxygen enhancement facilities would be required
in
addition to either the
ultraviolet or chlorination/dechlorination disinfection processes, the costs associated with
the dissolved oxygen processes are shown herein as a stand alone scenario in order to
demonstrate its financial impact separately from the other scenarios. For the purposes
of
this scenario, it was assumed that design of the dissolved oxygen enhancement facilities
would occur in 2010 through 2012 and construction would occur in 2013 through 2015.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 3
is shown graphically in Figure 10 below. As shown in this
figure, additional capital costs would be incurred to implement the processes, and the
cash balance in the Capital Improvement Bond Fund would decrease more rapidly than
the baseline forecast as a result
of funding these capital projects until 2016 when the
District's authority to issue non-referendum bonds expires. The analysis indicates that
the projected cash balance
in
the Capital Improvement Bond Fund would be insufficient
to fund current projects and the projects associated with the proposed water quality
standards due to the District's current authority and limitation
of issuing no more than
$150 million
of non-referendum bonds during any budget year. Furthermore, in order to
fund the capital projects, the District would have to receive additional non-referendum
bonding authority
or issue a voter referendum.
Figure 10
Capital Improvement Plan - Scenario 3
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$600,000
$500,000
$400,000
{j
II
c
$300,000
III
::2
0
~
$200,000
...
I-
$100,000
$0
§
N
Plant
-
Tarp
;.':.':~
Projects to Meet Proposed Standards
-
CIBF Cash Balance
In
addition to the capital expenditures associated with Scenario 3, M&O costs associated
with this scenario were projected over the forecast period. The projections
of M&O costs
associated with implementing the dissolved oxygen processes are included in the
13
Economic Assessment Report 8.1
~08
Electronic Filing - Received, Clerk's Office, August 4, 2008

forecasted property tax levy increases summarized below. Additional details are
provided in the tables and calculations provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
water quality standards was developed for Scenario
3. The results are summarized in
Figures 11 and 12 below and detailed in Appendix
A.
Figure 11 shows the annual
property tax levy requirement necessary to fund projected capital and M&O costs,
including those costs necessary to meet the proposed water quality standards,
as
compared to the aggregate property tax levy limitation. The Scenario 3 results indicate
that the District will exceed the tax levy limitation once the dissolved oxygen
enhancement facilities have been constructed and operations commence in 2016.
Furthermore, in order to fund the improvements, the District would have to request an
amendment to the Property Tax Extension Limitation Law or obtain voter approval via
referendum to increase the aggregate extension limitation and/or the limiting rate.
Figure 11
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Scenario 3
$410,000 ,---------------------------------,
$390,000
f----------------------------f-=
til
$370,000
+-------------------------:::;;;,I......f----I
"C
c::: $350,000
+-----------------------:::::;._.r
o
~
$330,000
+----------------::::II.-=___!
r.
~
$310,000
+------------=...-"""
.".
$290,000
+-------=.-If~I____i
$270,000
.1-"'-~---l
$250,000
+-.l...-~..---'L..-...I--..-,r__'_='___,_----""---L_.,._--'---'-__r_-'--'-...,.___--'---'-.,._.l...--'--..---''-----".I--..-,---''=-''''''O--i
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
,
I ProjeetedTax Levy Requirement (Excluding StormwaterCostand Debt Service)
-
Tax Levy Extension Lim itation (CPI
+ New Properly)
Figure 12 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund current
projected projects and capital projects associated with the proposed water quality
standards, compared to the debt service extension base. The Scenario 3 analysis indicates
that the District would significantly exceed the debt service extension base beginning in
fiscal year 2014 if the Scenario 3 projects associated with the proposed water quality
improvements were implemented.
14
Economic Assessment Repon 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 12
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 3
$250,000
$200,000
-l------------------------
~$150,OOO
c
III
6$100,000
.c
~
C $50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
_
Projected Hnount of
Lim~ed
Debt Service
-
Debt Service Extension Limitation
Scenario 4 (Chlorination
I
Dechlorination and Dissolved Oxygen)
Scenario 4 consists of adding the capital and annual M&O costs associated with both
chlorination / dechlorination and dissolved oxygen (as shown in Table 1) to the baseline
financial forecast.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 4
is shown graphically in Figure 13 below. As shown in this
figure, additional capital costs would be incurred to implement the processes, and the
cash balance in the Capital Improvement Bond Fund would decrease more rapidly than
the baseline forecast and the scenarios showing either disinfection or dissolved oxygen
processes,
as a result of funding these capital projects until 2016 when the District's
authority to issue non-referendum bonds expires. The analysis indicates that the
projected cash balance in the Capital Improvement Bond Fund would be insufficient to
fund the current projected projects and projects associated with the proposed plant
effluent and water quality standards due to the District'scurrent authority and limitation
of issuing no more than $150 million of non-referendum bonds during any budget year.
Furthermore, in order to fund the capital projects, the District would have to receive
additional non-referendum bonding authority or issue a voter referendum.
15
Economic Assessment
Report
8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 13
Capital Improvement Plan - Scenario 4
ESTIMATED CAPITAL PROGRAM EXPENDITURES
_Sewer
$700,000
$600,000
$500,000
.tJ
$400,000
..
Ul
:::I
c
$300,000
0
~
...
I-
$200,000
$100,000
$0
00
0
0
C\l
Plant
-
Tarp
:~~~~.;
Projects to Meet Proposed Standards
-
CIBF Cash Balance
In
addition to the capital expenditures associated with Scenario 4, M&O costs associated
with this scenario were projected over the forecast period. The projections of M&O costs
associated with implementing the dissolved oxygen and chlorination/dechlorination
disinfection processes are included in the forecasted property tax levy increases
summarized below. Additional details are provided in the tables and calculations
provided in Appendix
A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
plant effluent and water quality standards was developed for Scenario 4. The results are
summarized in Figures 14 and
15 below and detailed in Appendix
A.
Figure 14 shows
the annual aggregate property tax levy requirement necessary to fund projected capital
and M&O costs, including those costs necessary to meet the proposed standards, as
compared to the aggregate property tax levy limitation. The Scenario 4 results indicate
that the District will exceed the tax levy limitation once the dissolved oxygen processes
and chlorination / dechlorination disinfection improvements have been constructed and
operations commence in 2016. Furthermore, in order to fund the projects, the District
would have to request an amendment to the Property Tax Extension Limitation Law or
obtain voter approval via referendum to increase the aggregate extension limitation
and/or the limiting rate.
16
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 14
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Scenario 4
$450,000 .-------------------------------,
$430,000
+-----------------------------==----1
$410,000
+-------------------------r---,.----j
~
$390,000
+------------------------~
lJl
c
$370,000
;-------------------------::::00111-.:=-----1
5 $350,000
;---------------------::::;;;oo~­
.c
';;; $330,000
+----------------::::::;;o...
r-:=-f
* $310,000
;--------------=_-r-
$290,000
+--------:~
......-,'----___i
$270,000
.J-..........,~r
$250,000 ;--.......
----.--""--=:.J.-,--......
-'--,--'--"'--,....-J'--"'--r-'--L..-r-'-'--,----L----J'--,----L.--'---.----'="""'"'----l
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
=
Projected Tax Levy Requirement(Excluding StormwaterCostand Debt Service)
-
Tax Levy Extension Limitation (CPI
+ New Properly)
Figure 15 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund current
projected projects and capital projects associated with the proposed plant effluent and
water quality standards, compared to the debt service extension base. The Scenario 4
analysis indicates that the District would significantly exceed the debt service extension
base beginning in fiscal year 2014 if the Scenario 4 projects associated with meeting the
proposed standards were implemented.
Figure 15
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 4
$250,000
$200,000
~$150,000
c
III
5$100,000
.c
th
.!:
$50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
-
Projected
Am
ount of Limned Debt Service
17
-
Debt Service Extension Limitation
Economic Assessment
Report
8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Scenario 5 (UV Disinfection and Dissolved Oxygen)
Scenario 5 consists of adding the capital and annual M&O costs associated with both uv
disinfection and dissolved oxygen (as shown in Table 1) to the baseline financial forecast.
The capital improvement plan and projected cash balance in the Capital Improvement
Bond Fund for Scenario 5
is shown graphically in Figure 16 below. As shown in this
figure, additional capital costs would be incurred to implement the processes, and the
cash balance in the Capital Improvement Bond Fund would decrease more rapidly than
the baseline forecast and the scenarios showing either disinfection or dissolved oxygen
processes,
as a result of funding these capital projects until 2016 when the District's
authority to issue non-referendum bonds expires. The analysis indicates that the
projected cash balance in the Capital Improvement Bond Fund would be insufficient to
fund current projected projects and the projects associated with the proposed water
quality standards due to the District's current authority and limitation
of issuing no more
than $150 million
of non-referendum bonds during any budget year. Furthermore, in
order to fund the capital projects, the District would have to receive additional non-
referendum bonding authority or issue a voter referendum.
Figure 16
Capital Improvement Plan - Scenario 5
ESTIMATED CAPITAL PROGRAM EXPENDITURES
-Sewer
$700,000
$600,000
$500,000
~
$400,000
c
01
III::s
$300,000
0
r.
...
~
$200,000
$100,000
$0
~
0
C\I
Plant
-
Tarp
;:"•• Projects to Meet Proposed Standards
-
CIBF Cash Balance
In
addition to the capital expenditures associated with Scenario 5, M&O costs associated
with this scenario were projected over the forecast period. The projections of M&O costs
associated with implementing the dissolved oxygen and ultraviolet disinfection processes
are included in the forecasted property tax levy increases summarized below. Additional
details are provided in the tables and calculations provided
in
Appendix A.
A ten-year projection of funding and tax levy requirements necessary to meet proposed
plant efluent and water quality standards was developed for Scenario 5. The results are
summarized in Figures
17 and 18 below and detailed in Appendix A. Figure 17 shows
the annual aggregate property tax levy requirement necessary to fund projected capital
18
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

and M&O costs, including those costs necessary to meet the proposed standards, as
compared to the aggregate property tax levy limitation. The Scenario 5 results indicate
that the District will exceed the tax levy limitation once the dissolved oxygen processes
and ultraviolet disinfection improvements have been constructed and operations
commence
in
2016. Furthermore, in order to fund the projects, the District would have
to request an amendment to the Property Tax Extension Limitation Law or obtain voter
approval via referendum to increase the aggregate extension limitation and/or the limiting
rate.
Figure 17
Forecasted Aggregate Tax Levy Requirement Compared to Tax Cap Limitation - Scenario 5
$450,000
$430,000
$410,000
~
$390,000
I:
~
$370,000
o $350,000
s::.
';;; $330,000
.,. $310,000
$290,000
$270,000
$250,000
,....-
t--
t--
.-
"""",.
11-'
."".""'-
t--
~
-
e---
-
.---"'-
....,,"""""''''''
r--- r--- r---
-
-",...- .....
-
I-
r--- r--- r---
-
.-.-
!---
-
-
l-
e---
!---
-
I I II
!--- !--- -
-
r---
-
!---
-
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
=
Projected Tax Levy Requirement (Exduding StormwaterCostand Debt Service)
-
Tax Levy Extension Limitation (CPI+ NewProperty)
Figure 18 shows the projected annual "limited" debt service associated with existing and
proposed District debt, including debt service that would be necessary to fund current
projected projects and capital projects associated with the proposed plant effluent and
water quality standards, compared to the debt service extension base. The Scenario 5
analysis indicates that the District would significantly exceed the debt service extension
base beginning in fiscal year 2014
if the Scenario 5 projects associated with meeting the
proposed standards were implemented.
19
Economic Assessment
Report
8-1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Figure 18
Forecasted Debt Service Compared to Debt Service Extension Base - Scenario 5
$300,000
$250,000
$200,000
UI
'C
m
$150,000
:::I
o
(:. $100,000
fit
.:
$50,000
$0
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
IIII!!!!II
ProjecledAmounlof
lim~ed
DeblService
20
--DeblService Extension limitation
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Appendix A
Backup Tables and Calculations
21
Economic Assessment Repon 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-I
Tax Levy Requirement Forecast Summary - Baseline Scenario
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$ 239,262
$
243,031 $ 251,304 $ 268,826 $ 278,106 $ 286,957
$ 297,344 $ 309,412 $ 321,991 $ 334,848
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
-
31,204
55,313
79,422
92,888
106,555
120,223
133,890
147,558
150,583
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (In
$
thousands)
$ 428,814
$
454,481 $ 480,642
$ 516,489
$ 548,031
$ 576,473 $ 589,851 $ 617,489 $ 639,442
$ 656,823
Table A-2
Property Tax Extension Limitation - Baseline Scenario
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)':
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
370,744
386,237
(Excluding Debt Service and Stormwater)
Projected Increase in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
4.20%
4.18%
Estimated Change in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
0.90%
1.20%
~
1.20%
1.20%
1.20%
1.20%
~
1.20%
Total Allowable Increase in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1
The
Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
22
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-3 - Debt Service Projection and Debt Service Extention Limitation - Baseline Scenario
Historical
Projection (in
$
Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040 $ 220,164 $ 337,931 $ 369,596 $ 260,514 $ 223,362
$
148,729 $
146,689
$
135,726
$
106,446
Unlimited Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited Bond and SRF
15,276
8,357
58,133
26,779
30,881
1,705
Unlimited Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
---
---
CIBF Program Expenditures
75,204
63,520
$
253,081 $ 314,478 $ 430,627 $ 431,501 $ 329,734 $ 275,764
$ 221,642
$ 209,243
$
185,886
$
174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150,000
$
$ 150,000 $ 300,000 $ 150,000 $ 150,000
$
100,000
$ 150,000 $
150,000
$
150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
--1&1!!
14,297
27,767
18,602
25,908
22,772
19,436
13,671
10,316
9,500
9,262
10,181
Bond Fund Revenues
344,618
206,297
$
69,767
$ 460,602
$ 367,908 $ 364,772
$ 214,436
$ 208,671 $ 205,316 $ 204,500
$
204,262
$
50,181
CIBF Cash Balance
285,935
555,349
372,035
518,159
455,440
388,711
273,412
206,318
189,992
185,249
203,625
79,680
Debt Service
Existing limited
31,632
46,800
51,228 $
66,463
$ 63,894
$ 60,792 $ 38,331
$
26,574
$
37,302
$
36,183 $
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond OS for Water Quality Projects
Proposed Unlimited Bond and SRF
---
---
Debt service
133,427
135,730
141,601
153,613
175,142
196,149
214,681
229,707
230,016
242,565
248,571
250,176
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
101,469
111,833
102,838
101,201
125,596
138,145
148,849
150,104
Debt Service Ex1ension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
23
Economic
A~sessment
Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-4
Tax Revenue Requirement Forecast Summary - Scenario 1
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$
239,262
$
243,031
$
251,304
$
268,826
$
278,106
$
286,957
$
297,344
$
309,412
$
355,511
$
366,886
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
-
31,204
55,313
80,141
95,045
110,152
138,205
166,258
187,118
190,143
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (In
$
thousands)
$
428,814
$
454,481
$
480,642
$
517,208
$
550,189
$
580,069
$
607,832
$
649,856
$
712,521
$
728,421
Table A-5
Property Tax Extension Limitation - Scenario 1
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)':
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
404,264
418,275
(Excluding Debt Service and Stormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
13.62%
3.47%
Estimated Change
in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
0.90%
~
1,20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
Total Allowable Increase
in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
9.02%
8.25%
--
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
24
Economic Assessment Repun g.I-OK
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-6 - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 1
Historical
Projection (in
$
Thousands)-->
Descl1ptlon
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8.862
31.250
$
1B3.040 $ 220.164
$ 337,931
$ 369.596
$ 260,514
$ 223.362
$
14B.729 $ 146,6B9 $ 135,726
$
106,446
Unlimited Bond Funds
51.066
22,712
10.355
67,535
61,816
50.972
46,709
15.89B
35,425
24,053
10,619
Limited Bond and SRF
15.276
8,357
5B.133
26.n9
30,BBl
1,705
Unlim~ed
Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9.229
22,511
36,503
37,4B9
38,501
39.541
40,60B
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
---
___ ---.1.Q.ill
20.275
20,275
202,74B
202,74B
101,374
CIBF Program Expenditures
75.204
63.520
$
253.0B1
$ 314,478 $ 430,627 $441,639 $ 350,009
$ 296.039 $ 424,390 $ 411.991
$ 287,260
$
174.127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300.000
150,000
$
$ 150,000 $ 300,000 $ 150,000
$ 150,000 $ 100.000 $
150.000 $
150,000
$ 150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42.000
45,000
45,000
45,000
45,000
45.000
40,000
Investment income
~
14,297
27,767
lB,602
25,908
22.n2
18,929
12,125
7.679
(3,407)
(14,427)
(19,761)
Bond Fund Revenues
344,61B
206,297
$
69,767 $ 460.602
$ 367.908
$
364,n2
$ 213.929
$ 207,125
$ 202,679 $ 191.593 $ 1BO.573
$
20.239
CIBF Cash Balance
285,935
555,349
372,035
518.159
455.440
378,573
242,493
153,579
(68,133)
(288.530)
(395,217)
(549,104)
Debt Service
Existing limited
31,632
46,800
51,228
$
66,463
$ 63.894
$ 60,792
$ 38.331
$
26,574
$
37,302 $
36.183 $
33,219
$
31,450
Existing unlimited
(wi
SRF)
101,795
88.930
90,373
55,946
55.935
55,935
83,462
96,5n
72,491
72,491
67,794
68.143
Proposed Limited Bond Funds
10,643
31.929
42,571
53.214
60,310
70,952
81.595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31.929
31.929
31.929
31,929
31.929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14.317
17.342
20.366
23,391
26.416
Proposed Limited Bond DS for Water Quality Projects
719
2,15B
3.596
17.982
32,367
39,560
39,560
Proposed Unlimited Bond and SRF
---
---
-
--- ---
-
Debt service
133,427
135,730
141,601
153,613
175,142
196,868
216,839
233,303
247,998
274,932
288.131
289,736
Debt issuance capacity unissued
600,000
400,000
550.000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79.929
101,469
112,552
104.996
104,797
143,578
170.512
188,409
189.664
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141.464
141.464
141,464
141.464
25
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-7
Tax Revenue Requirement Forecast Summary - Scenario 2
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$ 239,262
$
243,031 $ 251,304 $ 268,826 $ 278,106 $ 286,957
$ 297,344 $ 309,412 $ 350,527
$ 362,122
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
-
31,204
55,313
80,265
95,417
110,770
141,299
171,827
193,925
196,950
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (in
$
thousands)
$ 428,814
$
454,481
$ 480,642 $ 517,332 $ 550,560 $ 580,688 $ 610,927 $ 655,426
$ 714,344 $ 730,464
Table A-8
Property Tax Extension Limitation - Scenario 2
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)
1
:
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
399,280
413,511
(Excluding Debt Service and Stormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
12.22%
3.56%
Estimated Change in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
0.90%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
Total Allowable Increase in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
7.68%
7.02%
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
26
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Historical
Projection (in
$
Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040
$
220,164
$
337,931
$
369,596
$
260,514
$
223,362
$
148,729
$
146,689
$
135,726
$
106,446
Unlimited Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited Bond and SRF
15,276
8,357
58,133
26,779
30,881
1,705
Unlimited Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
-
---
11,882
23,764
CIBF Program Expenditures
---
75,204
63,520
$
253,081
$
314,478
$
430,627
$
443,383
$
353,498
$
299,52823,764
$
237,636459,279
$
237,636446,879
$
304,704118,818
$
174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150,000
$
$
150,000
$
300,000
$
150,000
$
150,000
$
100,000
$
150,000
$
150,000
$
150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
~
14,297
27,767
18,602
25,908
22,772
~
11,859
7,225
(5,628)
(18,503)
(24,913)
Bond Fund Revenues
344,618
206,297
$
69,767
$
460,602
$
367,908
$
364,772
$
213,841
$
206,859
$
202,225
$
189,372
$
176,497
$
15,087
CIBF Cash Balance
285,935
555,349
372,035
518,159
455,440
376,829
237,172
144,503
(112,550)
(370,057)
(498,263)
(657,303)
Debt Service
Existing limited
31,632
46,800
51,228
$
66,463
$
63,894
$
60,792
$
38,331
$
26,574
$
37,302
$
36,183
$
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond DS for Water Quality Projects
843
2,529
4,215
21,076
37,937
46,367
46,367
Proposed Unlimited Bond and SRF
---
--- ---
---
Debt service
133,427
135,730
141,601
153,613
175,142
196,992
217,210
233,922
251,092
280,502
294,938
296,544
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
101,469
112,676
105,367
105,416
146,672
176,082
195,216
196,472
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
Table A-9 - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 2
27
Economic Assessment Report 8-1-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-IO
Tax Revenue Requirement Forecast Summary - Scenario 3
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$ 239,262
$
243,031 $ 251,304 $ 268,826 $ 278,106 $ 286,957
$ 297,344 $ 309,412 $ 330,862 $ 343,326
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
31,204
56,771
82,337
97,261
125,506
153,751
181,996
195,664
198,689
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (In
$
thousands)
$ 428,814 $
454,481 $ 482,100 $ 519,405 $ 552,404 $ 595,423
$ 623,379 $ 665,595 $ 696,418 $ 713,407
Table A-ll
Property Tax Extension Limitation - Scenario 3
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)1:
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
379,615
394,715
(Excluding Debt Service and Stormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
6.69%
3.98%
Estimated Change in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
~
1,20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
Total Allowable Increase in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
262,065
293,066
304,495
316,370
328,709
341,529
355,673
370,619
366,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
2.37%
2.15%
1
The
Property Tax Extension Limitation Act, Tax Cap limits future increases
in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
28
Economic Assessment Repon 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-12 - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 3
Historical
Projection (in $ Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040
$ 220,164
$
337,931
$
369,596
$ 260,514
$
223,362
$
148,729
$
146,689
$
135,726
$
106,446
Unlimited Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Lim~ed
Bond and SRF
15,276
8,357
58,133
26,n9
30,881
1,705
Unlim~ed
Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
---
20,546
20,546
20.546
205,456
205,456
205,456
CIBF Program Expenditures
75,204
63,520
$
253,081
$
314,478 $451,173
$
452,047
$ 350,280
$
481,220 $ 427,098
$
414,698
$
185,886
$ 174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150,000
$
$
150,000
$
300,000 $ 150,000
$
150,000
$
100,000
$
150,000
$
150,000
$
150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
~
14,297
27,767
18,602
25,908
21,745
17,330
10,432
(3,357)
(15.130)
(26,871)
(27,759)
Bond Fund Revenues
344,618
206,297
$
69,767
$
460,602 $ 367,908
$ 363,745
$
212,330
$
205,432
$
191,643
$
179,870
$
168,129
$
12,241
CIBF Cash Balance
285,935
555,349
372,035
518,159
434,894
346,592
208,642
(67,146)
(302,601)
(537,429)
(555,186)
(717,073)
Debt Service
Existing
Iim~ed
31,632
46,800
51,228
$
66,463 $ 63,894 $ 60,792
$
38,331
$
26,574
$
37,302
$
36,183
$
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31.929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond DS for Water Quality Projects
1,458
2,916
4,373
18,951
33,528
48,106
48,106
48,106
DebtProposedserviceUnlimited
Bond and SRF
---
133,427
135,730
141,601
153,613
---
176,600
---
199,065
---
219,054
248,658
263,544
290,671
296,6n
298,282
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
102,926
114,748
107,211
120,152
159,125
186,251
196,955
198,210
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
29
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-13
Tax Revenue Requirement Forecast Summary - Scenario 4
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$
239,262
$
243,031
$
251,304
$
268,826
$
278,106
$
286,957
$
297,344
$
309,412
$
364,381
$
375,364
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt
Service. Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt
Service. Proposed
-
31,204
56,771
83,056
99,419
129,102
171,733
214,364
235,224
238,249
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (In
$
thousands)
$
428,814
$
454,481
$
482,100
$
520,124
$
554,562
$
599,020
$
641,361
$
697,962
$
769,498
$
785,005
Table A-14
Property Tax Extension Limitation - Scenario 4
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)l:
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
413,134
426,753
(Excluding Debt Service and Stormwater)
Projected Increase
in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
16.11%
3.30%
Estimated Change
in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated
New Property (Growth)
0.80%
0.90%
~
~
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
Total Allowable Increase
in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate
Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
11.41%
10.45%
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for
new property.
30
Economic Assessment Report 8.1.08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-IS - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 4
Historical
Projection (in $ Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Capital Improvement Bond Fund Program Expenditures
limited Bond Funds
8,862
31,250
$
183,040 $ 220,164 $ 337,931
$ 369,596 $ 260,514 $ 223,362
$
148,729
$
146,689
$
135,726
$
106,446
Unlimited Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
limited Bond and SRF
15,276
8,357
58,133
26,779
30,881
1,705
Unlimited Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance
w~h
Proposed Water Quality Standards
---
20,546
30,683
40,820
225,730
408,204
408,204
101,374
CIBF Program Expenditures
75,204
63,520
$
253,081
$
314,478 $451,173 $ 462,184 $ 370,555
$ 501,494
$
629,846
$
617,446
$
287,260
$
174,127
Bond Fund Revenues (Debt Sizing)
Proposed lim
~ed
Bonds
300,000
150,000
$
$ 150,000
$
300,000
$
150,000 $150,000
$
100,000
$
150,000
$
150,000
$
150,000
Proposed unlimited
250,000
150,000
50,000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
~
14,297
27,767
18,602
25,908
21,745
~
8,886
(5,994)
(28,036)
(50,560)
(57,701)
Bond Fund Revenues
344,618
206,297
$
69,767 $ 460,602
$
367,908
$ 363,745
$
211,823
$ 203,886
$
189,006
$
166,964
$
144,440
$
(17,701)
CIBF Cash Balance
285,935
555,349
372,035
518,159
434,894
336,455
177,723
(119,885)
(560,726) (1,011,208) (1,154,028)
(1,345,857)
Debt Service
Existing limited
31,632
46,800
51,228 $
66,463
$ 63,894
$
60,792 $ 38,331
$
26,574
$
37,302
$
36,183
$
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed
limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed
limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,4t6
Proposed limited Bond OS for Water Quality Projects
1,458
3,635
6,531
22,547
51,510
80,473
87,666
87,666
DebtProposedserviceUnlimited
Bond and SRF
---
133,427
135,730
141,601
153,613
---
---
-
---
176,600
199,784
221,212
252,254
281,526
323,038
336,237
337,842
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total limited Bond Debt Service
31,632
46,800
51,228
79,929
102,926
115,468
109,369
123,748
177,106
218,618
236,515
237,770
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
31
Economic Assessment Report K.I.OK
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-16
Tax Revenue Requirement Forecast Summary - Scenario 5
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Projected Levy:
Corporate Fund
$
239,262
$
243,031
$
251,304
$
268,826
$
278,106
$
286,957
$
297,344
$
309,412
$
359,397
$
370,600
Construction Fund
1
5,523
8,385
1,272
2,830
5,213
6,561
7,635
8,747
10,090
Stormwater Fund
15,211
18,802
12,443
15,878
17,023
18,145
18,387
19,123
20,126
20,410
Debt Service - Existing
141,601
122,409
119,829
116,727
121,793
123,152
109,793
108,674
101,013
99,594
Debt Service - Proposed
31,204
56,771
83,180
99,790
129,721
174,827
219,933
242,031
245,056
Retirement Fund
25,665
26,450
26,023
26,726
27,447
28,188
28,949
29,818
30,712
31,634
Reserve Claim Fund
7,073
7,062
7,345
7,639
7,944
8,262
8,593
8,936
9,294
9,666
Total Projected Gross Levy (in
$
thousands)
$
428,814
$
454,481
$
482,100
$
520,248
$
554,934
$
599,639
$
644,455
$
703,532
$
771,321
$
787,049
Table A-17
Property Tax Extension Limitation - Scenario 5
Projection (in
$
Thousands)-->
Description
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Property Tax Levy Constraint (Property Tax Extension Limitation Law)1:
Adjusted Aggregate Gross Property Tax Levy
272,001
282,066
293,057
304,462
316,327
328,620
341,447
355,801
408,150
421,989
(Excluding Debt Service and Stormwater)
Projected Increase in Aggregate Tax Levy
0%
3.70%
3.90%
3.89%
3.90%
3.89%
3.90%
4.20%
14.71%
3.39%
Estimated Change
in Consumer Price Index
3.00%
2.80%
2.70%
2.70%
2.70%
2.70%
2.70%
3.00%
3.00%
3.00%
Estimated New Property (Growth)
0.80%
0.90%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
1.20%
Total Allowable Increase
in Adjusted Tax Levy
3.80%
3.70%
3.90%
3.90%
3.90%
3.90%
3.90%
4.20%
4.20%
4.20%
Total Allowable Aggregate Tax Levy
272,001
282,065
293,066
304,495
316,370
328,709
341,529
355,873
370,819
386,394
Gap between Allowable and Projected Tax levy Increase
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
10.07%
9.21%
'The Property Tax Extension Limitation Act, Tax Cap limits future increases in property tax levies, except debt service to the lesser of 5 percent or the change in the national consumer price
index plus allowable increases for new property.
32
Economic
A~sesl'iment
Repon M.I-08
Electronic Filing - Received, Clerk's Office, August 4, 2008

Table A-1S - Debt Service Projection and Non-Referendum Bonding Authority Limitation - Scenario 5
Historical
Projection (in $ Thousands)-->
Description
2006
2007
2008
2009
2010
2011
2012
2013
2014
2016
2016
2017
Capital Improvement Bond Fund Program Expenditures
Limited Bond Funds
8,862
31,250
$
183,040
$ 220,164 $ 337,931
$ 369,596
$ 260,514
$ 223,362
$
148,729
$ 146,689 $
135,726
$ 106,446
Unlim~ed
Bond Funds
51,066
22,712
10,355
67,535
61,816
50,972
46,709
15,898
35,425
24,053
10,619
Limited Bond and SRF
15,276
8,357
58,133
26,779
30,881
1,705
Unlim~ed
Bond and SRF
1,201
1,553
Future Sewer Rehab Projects
9,229
22,511
36,503
37,489
38,501
39,541
40,608
Future Plant Rehab Projects
27,072
Compliance with Proposed Water Quality Standards
---
20,546
32,427
44,309
229,219
443,092
443,092
118,818
CIBF Program Expenditures
75,204
63,520
$
253,081 $ 314,478
$451,173 $ 463,929 $ 374,044 $ 504,983
$ 664,734 $ 652,335 $ 304,704
$
174,127
Bond Fund Revenues (Debt Sizing)
Proposed limited Bonds
300,000
150,000
$
$ 150,000 $ 300,000
$ 150,000
$150,000
$ 100,000
$
150,000 $ 150,000
$
150,000
Proposed unlimited
250,000
150,000
50.000
Proposed SRF
40,000
42,000
42,000
42,000
42,000
42,000
45,000
45,000
45,000
45,000
45,000
40,000
Investment income
~
14,297
27,767
18,602
25,908
21,745
16,736
8,620
(6,448)
(30,257)
(54,637)
(62,854)
Bond Fund Revenues
344,618
206,297
$
69,767
$ 460,602
$ 367,908 $ 363,745
$211,736
$ 203,620
$
188,552
$
164,743
$
140,363
$
(22,854)
CIBF Cash Balance
285,935
555,349
372,035
518,159
434,894
334,710
172,402
(128,961)
(605,143) (1,092,735)
(1,257,075) (1,454,056)
Debt Service
Existing limited
31,632
46,800
51,228
$
66,463 $ 63,894 $ 60,792 $ 38,331
$
26,574
$
37,302
$
36,183 $
33,219
$
31,450
Existing unlimited
(wI
SRF)
101,795
88,930
90,373
55,946
55,935
55,935
83,462
96,577
72,491
72,491
67,794
68,143
Proposed Limited Bond Funds
10,643
31,929
42,571
53,214
60,310
70,952
81,595
92,238
92,238
Proposed Unlimited Bond Funds
17,738
17,738
28,381
28,381
31,929
31,929
31,929
31,929
31,929
Proposed Limited Bond and SRF
2,823
5,646
8,469
11,292
14,317
17,342
20,366
23,391
26,416
Proposed Limited Bond DS for Water Quality Projects
1,458
3,759
6,902
23,166
54,605
86,043
94,473
94,473
Proposed Unlimited Bond and SRF
Debt service
133,427
135,730
141,601
153,613
176,600
199,908
221,583
252,873
284,620
328,608
343,044
344,650
Debt issuance capacity unissued
600,000
400,000
550,000
300,000
150,000
Debt Service Extension Limitation
Total Limited Bond Debt Service
31,632
46,800
51,228
79,929
102,926
115,591
109,740
124,367
180,201
224,188
243,322
244,578
Debt Service Extension Base
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
141,464
33
Economic Assessment Report K-
J
-OK
Electronic Filing - Received, Clerk's Office, August 4, 2008

ATTACHMENT 7
John
Mastracchio CV
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
Mr. Mastracchio
is a senior financial analyst specializing in municipal
utility economics, financial analysis, capital and financial planning, cost of
service evaluation, the design
of rates, fees, and charges, and utility
valuation. Mr. Mastracchio is a member of the Finance, Accounting &
Management Controls committee of the American Water Works
Association where
he participates on the capital financing and valuation
subcomittees, and
is a member of the Water Environment Federation and
the Chartered Financial Analyst Institute. He is a contributing author of
the utility Capital Financing Manual of Practice (M29) and routinely
speaks at national and regional conferences and meetings on the topics
of regionalization, financial planning, rate-setting, and valuation.
REPRESENTATIVE EXPERIENCE
• Confidential Client: Due Diligence Review for Water System
Acquisition
I
New York City NY.
Task Leader for the financial analysis
as part of a due diligence investigation for the acquisition of a Water
Company
in the eastern u.S. Services included assistance in developing a
long-term capital improvement plan, review
and development of financial
modeling assumptions regarding supply
and demand, operation and
maintenance costs, capital expenditures and general rate setting
methodology
in accordance with each state's rate setting requirements.
Recommendations regarding the acquisition
and future capital and
operating requirements including projections of revenues and rate of
return for
each of five regulated utilities were presented.
• City of Columbus: Comprehensive Rate and Charge Study
I
Columbus
OH.
Completed a cost-of-service evaluation and rate, fee, and charge
assessment to assist the City of Columbus generate sufficient revenues
to pay for upcoming water
and sewer capital improvement and operation
and maintenance programs. The project included completing a cost-of-
service evaluation to determine the cost responsibility of the city's
customers, water
and sewer asset valuations to support connection fee
development,
and a rate structure evaluation to identify water and sewer
rate structures that were closely aligned with the cost of providing
service
and developing rate formulas for the city's future use. Based on
the results of this study, the city changed its water rates from a declining
block structure to a "lifeline" rate
and an inclining block structure for
residential customers.
The city also implemented a separate charge to
customers to pay for its upcoming $2.5 billion wet weather capital
program. This charge recovers the cost of the program
based upon the
impervious surface
area of the city's customers. Presented study results
to city staff, city council,
and other stakeholders using interactive
financial modeling tools that were developed for the client.
• Credit Suisse First Boston: Columbia. SC.
Acting on behalf of several
investment banking firms, reviewed of the estimates of environmental
liability reported to the Securities and Exchange Commission
by a publicly
John M. Mastracchio
Title/Firm:
Senior Associate
Red Oak Consulting, A Division of
Malcolm Pirnie, Inc.
Years of Experience
13
Education
BA State University of New York at
Geneseo 1993
MS Civil and Environmental Engineering
Clarkson University 1994
MBA Finance Cornell University 2001
Licenses and Certifications
Professional Engineer
Chartered Financial Analyst
Societies
American Water Works Association,
Finance, Accounting
& Management
Controls Committee
Chartered Financial Analyst Society
of
Rochester
Government Financial Officers
Association
Water Environment Federation
Employment History
Red Oak Consulting, a Division of Malcolm
Pirnie, Inc.
2002 to present
Arthur Andersen, U':P. 2001 to 2002
Parsons Engineering Science, Inc. 1994 to
2000
A282007
I
WHI
Pathways to Lasting Solutions
:.:;:
RElIDAK
'. • 0..
CONSULTING
• ••
A DIVISION
or
MALCOLM PIRtJIE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
traded, national, environmental services company. This project
was
accomplished by reviewing pertinent SEC filings, environmental liability
reporting policies and procedures established
by the Company,
requirements
of FASS Statement NO.5 and SFAS Statement No. 143
related to reporting of environmental contingent liabilities and asset
retirement obligations, and information gathered through site visits,
interviews with regulators, site assessments, Superfund site reviews,
and
landfill useful life estimates provided by other Malcolm Pirnie team
members. This information
was assessed and used to form an opinion
about the reasonableness of the estimates of environmental liability
prepared by the Company. Our clients, the investment banking firms,
relied
on our efforts as underwriters for the bonds to be issued by the
Company and
as agents and lenders with respect to a credit agreement
entered into
by the Company. In addition, other lenders participating in
the syndicate also relied on our report from a credit agreement
perspective.
• Countryside Village North. City of Anderson: Anderson Utility
System Valuation / Anderson IN.
Completed a valuation of the
Countryside Village North sewer system to support the negotiated sale of
the system to the City
of Anderson. The sewer system consisted of
approximately 3,000 linear feet of sewer, one lift station, 4,000 linear
feet of force main, and associated appurtenances.
• City of Delaware: Financial Services / Delaware OH.
Provided expert
advice to the city in support
of financing wastewater capital
infrastructure improvements
in anticipated future city growth. Reviewed
and evaluated wastewater impact fee methodologies and fee levels.
Recommended changes to the existing wastewater fee structure to
address the city's concerns about rate equitability
for multifamily and
single-family residential customers, and to ensure that growth pays
for
itself.
• Erie County Dept. of Environment and Planning: Utility Merger
Feasibility Study
and Asset Management Evaluation / Buffalo NY.
Managed the evaluation of the feasibility of consolidating three adjacent
wastewater systems into Erie County Sewer Districts. Managed the
financial evaluation of the impacts
of consolidating included potential
cost savings and impacts
on customer taxes and user fee rates. Managed
the completion
of a financial impact analysis and sewer rate plan as part
of an overall asset management program for the County. The project
included evaluation of capital improvement program alternatives using
an
interactive financial model that supported the creation of an asset
management plan.
• Erie County Dept. of Environment and Planning: ECDEP Asset/Finac /
Buffalo NY.
Managed the completion of a financial impact analysis and
sewer rate plan
as part of an overall asset management program for the
County.
The project included evaluation of capital improvement program
alternatives using
an interactive financial model, supporting the creation
of an asset management plan, developing a baseline condition
A282007
I
WHI
Pathways to Lasting Solutions
:.:::
RElIDAK
.. 0...
CONSULTING
••
A DIVISION
or
~ALCOLI.l PIRr~lt
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
assessment of major plant and buried assets, evaluation of strategic
business drivers, development of project prioritization methodologies,
and preparation
of the final CIP document. including a detailed financial
impact analysis and utility rate plan.
• City of Fort Wayne: Valuation in Support of Utility Acquisition! Fort
Wayne IN.
Completed a valuation of a private water and wastewater
utility regulated by the Indiana Utilities Regulatory Commission using
asset- and market-based valuation approaches.
The valuation estimate
was provided to the City's attorney to support settlement negotiations
and condemnation.
• City of Grand Forks: Rate Study and Cost-of-Service Evaluation!
Grand Forks,
NO.
Completed a financial evaluation of the city's water,
wastewater, solid waste, and stormwater utilities.
The evaluations were
conducted
to ensure that the costs associated with planned capital
infrastructure investment and the operations
of each utility were
allocated equitably
to each customer class based on its service
requirements. Evaluated the financial affordability
of capital
improvement plans. Developed cost allocation methodologies using sound
engineering, financial, and rate-making practice. Developed
nonproprietary revenue adequacy models
to provide the city with a basis
for the evaluation of alternative rate structures and to ensure that all of
the appropriate costs
of operating the utility were reflected in the rates.
• Greene County: Capital Planning Study! Dayton OH.
Provided capital
investment decision-making support and planning assistance
for county
municipality
in Dayton, Ohio. Developed an affordable financial plan for
paying for the capital infrastructure investments that were identified in
the study. Developed an interactive financial model that was used during
the project
to assess the impact various capital improvement programs
and financing alternatives on the County's wastewater rates. Conducted
an in-depth evaluation of the parameters that impacted affordability,
developed a financial plan that identified the most cost effective project
financing alternatives, and presented 20-year pro forma financial
projections
for the County under several different scenarios and
assumptions.
• Borough of Haledon: Valuation in Support of Utility Acquisition!
Haledon NJ.
Completed a valuation of a municipal water system in New
Jersey
to assist the client in making acquisition decisions. The valuation
was completed to establish a baseline for the utility system and its
negotiated sale.
• The Harrisburg Authority: Financial Capability Assessment!
Harrisburg PA.
Completed a Financial Capability Assessment to measure
the impact that the Authority's Long-Term Control Plan will have on both
the current and future financial health of the service area. Determined
the service area's average wastewater treatment and
CSO
implementation cost per household, and evaluated debt, socioeconomic,
and financial management indicators of financial capability.
A282007
I
WHI
Pathways to Lasting Solutions
: .; :: RErIDA K
'.
"••.
CONSULTING
• ••
A DIVISION Of MALCOLM PIRrJIE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
Recommended a capital improvement implementation schedule that
would minimize the financial impact
to customers, based on the results of
the assessment.
• Henrico County: Water and Sewer Rate Study
I
Richmond VA.
Completed a cost of service evaluation and rate, fee, and charge study to
assist Henrico County develop a sustainable financial management plan,
determine revenue requirements over the next ten years, and ensure
equitable recovery of costs. The study also consisted of completing
an
asset valuation to support the development of impact fees to ensure that
growth pays for itself over the planning period.
The financial
management plan
was developed using an interactive forecast model that
allowed alternative scenarios
to be easily evaluated. Connection fees, fire
protection charges, and local facility fees were established by
determining the costs of providing these services and developing fees
to
equitably recover these costs from customers utilizing the services. Rate,
fee, and charge formulas were developed for the County's
$80 million
operating budget.
• City of Kingston: Wastewater Rate Study
I
Kingston, NY.
Completed a
wastewater rate study
to assist the City pay for its capital improvement
program, develop a sustainable financial management plan, and
determine future revenue requirements. Developed
an interactive rate
model
for forecasting revenue requirements and user rates. Presented
rate recommendations
to City officials.
• Kinderhook Industries, LLC: Environmental Liability Assessment
I
Berwyn, PA.
Completed a financial evaluation in support of an
environmental compliance/liability assessment to support acquisition of a
firm
in the remedial construction and Resource Conservation and
Recovery Act
(RCRA) hazardous waste management business with three
RCRA treatment, storage, or disposal facilities (TSDFs). Financial
evaluation consisted of reviewing the reporting requirements
of FASB 5
and
SFAS 143 to ensure environmental liability estimates prepared by
Malcolm Pirnie satisfied accounting and reporting requirements. Utilized
the expected cash flow approach
for calculating environmental liabilities,
compared liability estimates with those reported
on the company's
financial statements, and prepared cost and
cash flow estimates.
• City of Lorain: Wastewater Regionalization Study
I
Lorain, OH
Managed the completion of a wastewater regionalization study to
evaluate the feasibility of constructing a regional wastewater treatment
plant and conveyance system
to serve customers throughout Lorain
County. Assessed the capital and
O&M costs associated with the regional
entity, developed financial models
to project revenue requirements and
rates under the regional approach and under status quo. Facilitated
discussions with stakeholders pertaining to the costs and benefits of
regionalization.
LS Power, LLC: Economic Impact Assessment
I
West Deptford, NJ.
Assessed the potential economic impact of the construction and
operation of a modern coal-fired power plant
in West Deptford Township,
A282007
I
WHI
Pathways to Lasting Solutions
,
:,,:::
RHIDAK
•. 0.°.
CONSULTING
• ••
14. DIVISION
or
MALCOLM PIRtll[
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CFA
New Jersey. Utilized IMPLAN® software to
assess the economic impacts
of a
500 MW coal fired power plant on an 11 county region. Examined the
direct
and indirect economic benefits to the region, effects of the project
on local employment and economic output, during construction and post
construction, and evaluated the potential peak economic stimulus.
Prepared report that provided information
to elected officials and other
stakeholders
to support a decision to proceed with the project.
• City of Lancaster: Engineer's Feasibility Report
and Rate study
/
Lancaster
OH,
Completed an Engineer's Feasibility Report to support the
release of bond disclosure documentation for the issuance
of $8 million
waterworks revenue bonds. Subsequently completed a sewer rate study
consisting of projections
of rate revenue requirements considering
various capital improvement programs, and growth scenarios,
development of sewer rate and connection fee recommendations,
evaluation of customer affordability, and comparison
of sewer rates in
nearby communities.
Completed a comprehensive water rate and charge study
to support the
client's capital investment planning process. The project included
assessing alternatives
for financing water system capital investments and
completing a cost-of-service evaluation
to equitably recover utility costs
from rate payers.
In addition, a nonproprietary financial planning and rate
design model
was developed to assist in the pricing of utility services.
Detailed analyses of customer costs, usage characteristics, capital
improvement program costs, and neighboring
utility rate comparisons
were conducted to support the design
of the rate components.
• Macomb County: Wastewater Treatment Plant Acquisition Evaluation
/
Mt Clemens, MI
Managed the completion of a preliminary evaluation
of
wastewater treatment plant ownership and joint use options for Macomb
County. Completed a financial evaluation of alternatives
that provided a
projection
of future capital and O&M costs, and assessed the future rate
implications of each option. Estimated the value of wastewater system
assets and evaluated asset
transfer pricing that would result in a win-win
for all involved parties. Served as a financial and technical resource for
assessing asset transfer and deal structure alternatives.
• Maricopa Water District: Wholesale Water Service Agreement
Development / Phoenix
AZ.
Assisted in the development and
negotiation of a water
treatment plant financing agreement with an
investor-owned water company. Developed water and water rate and
pricing formulas
for inclusion into the capital lease and other supporting
documentation.
The capital lease agreement provided the client with a
reasonable rate of return and ensured that financing requirements, such
as legal debt service coverage and capital reserve requirements would be
met under many foreseeable future scenarios. Developed and provided
an interactive rate-setting and financial planning model for use during the
development and negotiation of the agreements. Worked with the client's
legal council
in developing the terms and conditions of the agreement.
Provided expert testimony before the Arizona Corporation Commission
A282007
I
WHI
Pathways to Lasting Solutions
:.:::
REJ])AK
" • .c>.
CONSULTING
• ••
A DIVISION
or
MALCOLM PIRfllE:
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
regarding the financial impact of the District constructing and operating
its own water treatment plant.
• Milwaukee Metropolitan Sewerage District: MMSD O&M Options
Analysis
I
Milwaukee WI.
Assisted MMSD in evaluating the feasibility of
continued contract operations
or the feasibility of District operation of
their wastewater treatment facilities. Assisted
in the evaluation of
alternative forms of privatization as applied to a number of its service
areas including wastewater treatment and sludge disposal. Assisted
in
the efforts to establish submittal requirements relating to financial
capability and cost bids and participated
in the review and evaluation of
these areas
for the submitted proposals.
• City of Marysville: Wastewater Master Study
I
Marysville OH.
Completed financial planning studies in support of the development of
water and wastewater capital investment plans and the issuance of
revenue bonds. Analyzed the affordability of recommended capital
investment alternatives and associated impacts to the city's long-term
financial position. Developed
an interactive financial planning model to
guide the planning process and assist the city
in making capital
investment decisions. Completed a wastewater pricing evaluation to
develop wastewater rates
for the city that reflected the cost of providing
service and ensured adequate funding for the city's upcoming $200
million capital improvement program. Prepared a bond feasibility report
supporting the issuance of approximately
$150 million in revenue bonds
and bond anticipation notes.
• Metropolitan Distrct Commission: Valuation Assessments
I
Hartford
CT.
Completed valuations of publicly-owned and investor-owned water
utilities regulated by the Connecticut Department
of Public utility Control
to assist our client
in making utility acquisition decisions. The target
utilities provide water service to more than
200,000 people in the
northeastern
US. The estimates of value were determined utilizing
different valuation techniques to estimate the potential value of the
water systems, including the asset and income approaches.
Mr.
Mastracchio's efforts and experience in valuating public utilities
supported the client's strategic expansion objectives.
• Metropolitan District Commission: Financial Analysis and Pricing for
the Development of Inter-jurisdictional Agreements
I
Hartford CT.
Completed financial analyses and pricing of water service for
intergovernmental water service agreements to allow the Metropolitan
District Commission to maximize its utilization of its excess water supply
capacity and generate additional revenues
by selling this capacity to
neighboring private water companies.
The project involved developing
terms and conditions
of the agreement. as well as developing and
recommending a wholesale water rate and capacity charge structure.
The
wholesale rate was developed by evaluating the costs of operating the
water utility using a financial model.
The capacity charge was based on
the net value of the Commissions fixed assets and available water supply
A282007
I
WHI
Pathways to Lasting Solutions
:.:::
RHIDAK
'. • 0-.
CONSULTING
• ••
A DIVISION
or
MALCOLM PIRtllE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
capacity
and was designed to recognize the value of the additional water
supply capacity, which would
be dedicated to the private water company.
City of Miamisburg: Bond Engineering Report and Rate Study!
Miamisburg OH. Completed a bond feasibility report to support the
issuance of
$2 million in 2004 waterworks revenue bonds. Bond
feasibility analysis included a description of the system and the
improvements, summary of historic
and projected system demands, a
cash flow analysis, a comparison of water rates with those of other cities,
and
an opinion of the adequacy of the rates and cash flows of the city.
Completed a water
and sewer rate study for the City consisting of
projecting revenue requirements over a five year period, assessing the
impact of various capital improvement program scenarios, developing
cost justified water
and sewer rates, and completing a survey of water
and sewer rates of nearby communities.
• Nassau County: Water
Utility Consolidation Study! Mineola, NY.
Evaluated the feasibility of consolidating
46 water systems within Nassau
County into one or more management organizations. Assessed the
potential for cost savings
and the impact on residential ad valorem taxes
and user fees.
Assessed the environmental benefits of a regional
approach to water resources. Prepared reports
and presented findings to
the County Executive of
Nassau County.
• State
of New Jersey, Department of the Public Advocate: Water
utility Valuation! Newark, NJ. Served as a valuation expert and
provided testimony in the matter of the Joint Petition of the City Trenton,
New Jersey and New Jersey American Water Company, Inc. for
authorization of the purchase and sale of the assets of the outside water
utility system of the City of Trenton,
New Jersey.
• Newark Watershed Conservation and Development Corporation:
Wasewater
Asset Condition Assessment and Valuation! Newark, NJ.
Supported efforts to complete an asset condition assessment and
valuation of the City of Newark's wastewater system to assist the Newark
Watershed Conservation
and Development Corporation (NWCDC) and the
City of Newark
in their consideration of the formation of a Municipal
Utilities Authority.
City of Newark: Wastewater Rate Study! Newark, OH. Project
Manager for a wastewater rate
and charge study. The project included an
evaluation of the City's rate structure, development of a nonproprietary
rate model, detailed analyses of customer costs, usage characteristics,
and capital improvement program costs, and presentation of rate
recommendations to City Council.
In addition, neighboring utility rate
comparisons were completed to support the design of the rate
components.
City of Norwalk: Financial Planning and Rate Study! Norwalk CT.
Completed a financial planning study in support of a long-term
wastewater master plan. Analyzed capital investment alternatives
and
associated impacts to City wastewater rates. Developed an interactive
A282007
I
WHI
Pathways to Lasting Solutions
:.~;:
RHIDAK
'.00°.
CONSULTING
• ••
A DIVISION
or
MALCOLM PIRrJIE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
financial planning model
to utilize throughout the planning process and
assisted the City
in making capital investment decisions. Completed
system asset valuation estimates
to support connection fee development.
Presented rate recommendations at budget hearings with the City
Commission.
• City of Painesville: Pricing of Utility Services
I
Painesville OH.
Developed an intergovernmental wastewater service agreement to allow
the City of Painesville
to maximize its utilization of its excess wastewater
treatment capacity to neighboring county customers.
The project
involved developing terms and conditions of the agreement,
as well as
developing and recommending a wholesale rate and capacity charge
structure. The wholesale rate
was developed by evaluating the costs of
operating the city's wastewater
utility using a financial model. The
capacity charge was based on the net value of the city's fixed assets and
available wastewater treatment capacity and
was designed to recognize
the value
of the city's additional system capacity, which will be sold to the
county.
City of Reno: Wastewater Cost of Service Evaluation and Rate Study
I
Reno, NV. Developed a financial plan and wastewater utility pricing
schedules
for the City of Reno. Project helped to ensure the funding and
financing
of the City's wastewater utility capital investment needs.
Developed
an interactive financial model that was used to evaluate future
rate revenue requirements, determine the cost
of providing wastewater
service. and determine equitable connection fees based on the estimated
value of fixed assets and the cost of wastewater system expansion.
Advised the City
in the design a rate structure that was aligned with the
City's needs and financial objectives. Presented study results
to City staff.
city council and other stakeholders using interactive financial modeling
tools that were developed
for the client.
• Saratoga County Water Authority: Water Bond Feasibility Report
I
Saratoga, NY. Prepared an engineering and financial feasibility report for
the issuance of $40 million in water system revenue bonds to finance the
construction
of water treatment plant, raw water pipeline. pump station,
and distribution mains.
• Summit County: Comprehensive Rate and Charge Study
I
Akron OH.
Completed a cost of service evaluation and rate. fee. and charge
assessment
to assist the County to generate sufficient revenues to pay
for upcoming sewer capital improvement and operation and maintenance
programs. The project included completing a cost
of service evaluation to
determine the cost responsibility of the County customers, wastewater
asset valuation estimates
to support capacity fee development, and a
rate structure evaluation
to identify sewer rate structures that were
closely aligned with the cost
of providing service. and developing rate
formulas
for the County's future use.
• U.S. Air Force Material Command: Hill AFB EUL
I
Ogden UT. Senior
Analyst
for the valuation and financial analysis of a proposed Enhanced
::
A282007
I
WHI
Pathways to Lasting Solutions
:.;;: REIIDAK
'. • ••. CONSULTING
• ••
" DIVISION
or
MALCOLM PIRtllE
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
Use Lease (EUL) at Hill Air Force Base. The analysis included evaluating
real estate market conditions and land sales data, completing a life cycle
cost analysis
of Air Force office space procurement options and
developing valuation models for potential site development scenarios.
Other activities included developing the financial portion of the Business
Case analysis, supporting presentations to leadership, responding to
technical questions and developing potential site development scenarios.
• Utilities Inc: strategic Financial Consulting
I
Northbrook, IL.
Managed
the completion of financial assessments,
and projections of performance
and value for more than
90 operating companies of an investor-owned
utility located in Arizona, Florida, Georgia, Illinois, Indiana, Kentucky,
Louisiana, Maryland, North Carolina, New Jersey, Nevada, Pennsylvania,
South Carolina, Tennessee, and Virginia. Provided analysis results
to the
senior leadership team
of Utilities, Inc.
• City of Virginia Beach: Financial Services
I
Virginia Beach VA.
Served
as project manager for a multi-year financial services contract for the
City
of Virginia Beach that included true-up evaluation, developing an
interactive financial planning model, and completing a cost of service
evaluation. The true-up evaluation consisted of reviewing the City of
Norfolk's cost allocation model
for allocating operation and maintenance
expenses, reviewing the rate model
for allocation of fixed assets, and the
rate of return
on rate base for reasonableness. The cost of service
evaluation consisted of assessing future capital funding needs
for the
water and sewer utilities due
to aging infrastructure, system expansion,
and new regulations, determining revenue requirements over a five
to ten
year period, and developing rates, fees and charges
to meet revenue
requirements and other City rate-setting goals and objectives.
Virgin Islands Public Services Commission: Expert Testimony
I
st
Thomas, VI.
Served as financial and rate expert for the U.S Virgin Islands
Public Services Commission regarding Waste Management Authority's
solid waste and wastewater
utility rate cases. Reviewed financial and rate
aspects
of the Authority's filings, prepared written testimony, and
presented oral testimony before the Public Services Commission.
Application involved establishment of new Authority Environmental User
Fees and Wastewater User Fees. Technical issues reviewed involved
reasonableness
of the rate revenue requirements, fairness and
equitability
of the rate structure, and affordability issues.
• Westchester Joint Water Works: Water Rate Study
I
Westchester,
NY.
Completed a comprehensive rate study for Westchester Joint Water
Works and its member municipalities. Evaluated revenue requirements
and the cost
to serve wholesale and retail customers, developed rate
models, and worked with Client and member municipalities
to evaluate
water rate structure alternatives.
• Wayne County, Department
of Environment: Comprehensive
Assessment
and Master Plan
I
Detroit MI.
Completed a financial
evaluation
in support of a comprehensive utility assessment and master
A282007
I
WHI
Pathways to Lastlnlj Solutions
:.:;:
REI])AK
•••• 0.
CONSULTING
• ••
A DIVISION
or
MALCOLM PIRNIE:
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
plan. Assessed the client's level of competitiveness, vulnerability
to
privatization, and degree of organizational alignment from a financial
perspective. Developed a cost allocation model that
was used throughout
the project. Evaluated many aspects of the client's financial operations
including a detailed evaluation
of DOE's rate and fee structure, as well as
a critical review of administration, finance, accounting, and general
management policies and procedures. Based
on the evaluation,
recommended revising and consolidating
DOE's fee structure.
EXPERT TESTIMONY
Valuation Expert in the Matter of the Joint Petition of the City Trenton, New
Jersey and New Jersey American Water Company,
Inc. for Authorization of
the Purchase and
Sale of the Assets of the Outside Water utility System of
the City of Trenton, New Jersey,BPU Docket
No. WM08010063.
Municipal
utility Rate Expert in the Application for Approval of
Environmental User Fee and Wastewater User Fee in the United States Virgin
Islands by the Virgin Island Waste Management Authority, Docket Number
554, before the Governement
of the Virgin Islands Public Services
Commission.
Rate Expert
In the Matter of the Application of Arizona-American Water
Company,
Inc. for Approvals Associated with a Proposed Transaction with
Maricopa Water Conservation District Number
One To Allow the Construction
of a Surface Water Treatment Facility Known as the White Tanks Project.
Docket
No. W-01303A-05-0718, before the Arizona Corporation Commission.
PUBLICATIONS AND PRESENTATIONS
Mastracchio, J.M..
Capital Project Funding, Improving Your Success Rate,
presented at the Greater Buffalo Environmental Conference, Buffalo, NY, March 18, 2008.
Mastracchio, J.M., et. al.
Water Capital Financing, Manual of Practice M29,
contributing author and workshop presenter at the American Water Works Association
Annual Conference and Exposition, Toronto, Canada. June
23, 2007.
Mastracchio, J.M.,
"Economic and Financial Elements of Water Utility
Facilities Master Planning,"
presented at the Spring Meeting of the American Water
Works Association,
New York Section, Saratoga Springs NY, April 24-27, 2007.
Mastracchio, J.M.,
"Budget Forecasting in the New Construction Cost Era -
It's Not
as Simple as the ENR Anymore,"
presented at the Conference of the
United States Society of
Dams, Pittsburgh PA, March 7, 2007.
Gangemi,
A.N, Mastracchio, J.M.,
"Dynamic Utility Financial Modeling - A Utility
Manager's Crystal Ball,"
presented at the Annual Conference of the New England
Water Works Association, Danvers
MA, September 17-20, 2006.
Mastracchio, J.M.,
"The Next Challenge in Eliminating Sewer Overflows: Who
Pays?,"
Clearwaters,
Vol. 35, p. 26-27, Winter 2005. New York Water Environment
Association, Inc.
Lockridge,
R.L., Mastracchio, J.M.,
"Dynamic Financial Modeling for Local
Governments,"
Proceedings,
91st Annual Conference of the International City/County
Management Association (ICMA), Minneapolis
MN, September 25-28, 2005.
A282007
I
WHI
Pathways to Lasting Solutions
:o;~:
REI])AK
'.0
0
°. CONSULTING
• ••
A DIVISION
or
MALCOLM PIRN1[
Electronic Filing - Received, Clerk's Office, August 4, 2008

John M. Mastracchio, P.E., CF A
Mastracchio, J.M.,
"Interactive Financial Modeling: An Effective Tool for
Utility Management and Planning,"
Proceedings,
68th Annual Conference of the
Indiana Water Environment Association, Indianapolis
IN, November 15-17, 2004.
Mastracchio, J.M.,
"The Use of Financial Modeling to Support Utility
Management and Planning,"
presented at the 78th Annual Conference of the Ohio
Water Environment Association, Columbus
OH, June 21-24, 2004.
Mastracchio, J.M.,
"Using Financial Models to Establish and Update Water
and Sewer Rates,"
presented at the Winter Conference of the County Commissioners
Association of Ohio, Columbus
OH, December 1, 2003.
A282007
I
WHI
Pathw8ys to Lasting Solutions
:.:;:
REIJDAK
•• • 0.,
CONSULTING
• ••
A DIVISION
or
h4ALCOlltA PIRtJI(
Electronic Filing - Received, Clerk's Office, August 4, 2008

Attachment 8
Rudimentary, Order-of-Magnitude Cost Estimates for Nutrient Removal
at District Water
Reclamation Plants
Rudimentary, Order-at-Magnitude Cost
Estimates tor Nutrient
Removal at District
Water Reclamation Plants
PLANT
CAPITAL COST
ANNUAL M&O
Stickney
$1,666,000,000
$100,000,000
Calumet
$605,000,000
$29,000,000
North Side
$408,000,000
$4,700,000
Kirie
$83,000,000
$1,000,000
Egan
$38,000,000
$2,500,000
Hanover Park
$17,000,000
$1,000,000
Total
$2,817,000,000
$138,200,000
NOTES:
1. Cost Estimate prepared by engineering department of MWRDGC.
2. Under the Master Plans for. the Calumet and North Side WRPs, conceptual level cost estimates
were performed for various nutrient removal processes. The purpose of the cost estimates was to
compare various nutrient removal processes relative to each other. These estimates were used to
generate a rudimentary, order-of-magnitude cost estimate for all seven WRPs.
In short, North
Side and Calumet estimates were used to arrive at capital and annual operating costs
on a flow
basis (Le. dollars per million gallons of sewage treated). These ratios were used to extrapolate
costs for the other four WRPs. The cost estimates that were derived assumed hypothetical
effluent limits of 0.5 mg/L for total phosphorus and between 6 to 8 mg/L for total nitrogen.
3. All costs are given in 2008 dollars.
4. Lemont Water Reclamation Plant is not included as it is planned to be converted to a sewage
pumping station.
13
Electronic Filing - Received, Clerk's Office, August 4, 2008

Back to top