ILLINOIS POLLUTION CONTROL BOARD
    November 1, 2007
    DYNEGY MIDWEST GENERATION, INC.
    (HENNEPIN POWER STATION),
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 07-123
    (Permit Appeal - Air)
    ORDER OF THE BOARD (by N.J. Melas):
    By order of October 18, 2007, the Board accepted for hearing the October
    4, 2007 petition for review (Pet.) of a May 29, 2007 construction permit issued to
    Dynegy Midwest Generation, Inc. (Dynegy) by the Illinois Environmental
    Protection Agency (Agency). The Agency granted Dynegy a permit for
    construction and operation of two baghouses, sorbent injection control systems
    and induced draft fans for units at the Hennepin Power Station located at 13498
    East 800 Street, Hennepin, Bureau County.
    Dynegy challenges numerous permit conditions. Dynegy characterizes the issues
    on appeal as falling into several categories:
    One category addresses the manner in which the Agency has addressed the
    requirements of the Consent Decree applicable to Dynegy. A second category
    of issues concerns the Agency's treatment of the mercury rule adopted by the
    Board at 35 Ill. Adm. Code Part 225. Additionally, the Agency has included
    unnecessary conditions and "notes" in the permit that should be deleted.
    Dynegy also appeals provisions that were appealed in the CAAPP [Clean Air
    Act Permit Program] appeal, PCB 06-072, or are otherwise CAAPP-related.
    Dynegy objects to certain testing, recordkeeping, and reporting provisions in
    the permit and has other general objections. Pet. at 6.
    Included in the body of its petition was Dynegy’s request for partial stay of the
    contested conditions. Pet. at 4-6, and Ex. 2. In its September 6, 2007 order accepting the
    petition for hearing, the Board reserved ruling on the requested stay pending any Agency
    response. To date, the Board has received no response from the Agency regarding
    Dynegy’s request for a stay. Section 101.500(d) of the Board’s procedural rules provides
    that, “[w]ithin 14 days after service of a motion, a party may file a response to the
    motion. If no response is filed, the party will be deemed to have waived objection to the

    2
    granting of the motion, but the waiver of objection does not bind the Board or the hearing
    officer in its disposition of the motion.” 35 Ill. Adm. Code 101.500(d).
    In its request for a partial stay, Dynegy notes that, “[h]istorically, the Board has
    granted partial stays in permit appeals where a petitioner has so requested.” Pet. at 4-5
    (citations omitted). Stressing the risk that it will suffer irreparable harm and that the
    environment will not benefit from improved pollution control, Dynegy asks the Board to
    “exercise its inherent discretionary authority to grant a partial stay of the construction
    permit.
    Id
    . at 5. Specifically, Dynegy asks the Board
    to grant a partial stay of the construction permit, staying only those conditions
    or portions of conditions indicated in Exhibit 2,
    i.e.,
    Conditions 1.1(a), 1.2(b),
    1.3, 1.4(a) Notes, 1.5, 1.6(a)(i), 1.6(a)(i) Note, 1.6(a)(ii), 1.6(a)(ii) Note,
    1.6(a)(iv), 1.7(a)(i), 1.7(b)(ii)(B), 1.7(c) 1.7(e)(v), 1.7(e)(viii), 1.7(e) Note,
    1.8(a), 1.8(c), 1.8 Note, 1.9-1, 1.9-2, 1.9-3, 1.9-4, 1.10-1, and 1.10-2. In the
    alternative, if the Board believes that it must stay the entirety of an appealed
    condition rather than only the portions of the condition where so indicated in
    Exhibit 2, Dynegy requests that the Board stay the entirety of each of the
    conditions identified in Exhibit 2 except for Conditions 1, 1(a) and 1.7(a)(i).
    Id.
    at 5-6
    The Board clearly has the authority to grant discretionary stays of the type
    requested here. In Community Landfill Co. and City of Morris v. IEPA, PCB 01-48, 01-
    49, slip op. at 4 (Oct. 19, 2000), the Board found "that it has the authority to grant
    discretionary stays from permit conditions." The Board noted it "has previously granted
    or denied discretionary stays in permit appeals, both when the Agency did and did not
    consent to such stays."
    Id
    . (citations omitted). The Board elaborated that "[t]he permit
    appeal system would be rendered meaningless in many cases, if the Board did not have
    the authority to stay permit conditions."
    Id
    .
    The Board has reviewed the allegations in Dynegy’s stay request, as well as the
    specific language requested to be stayed and detailed in Exhibit 2 to Dynegy’s petition.
    On the basis of that review, and in the absence of any response to the request from the
    Agency, the Board grants Dynegy's request for partial stay of the contested conditions in
    the construction permit for the Hennepin Power plant. The Board stays those contested
    conditions and portions of conditions as reflected in the edited permit filed as Exhibit 2 to
    Dynegy’s October 4, 2007 petition for review and request for stay. Exhibit 2 is
    incorporated herein by reference as if fully set forth. The partial stay remains in effect
    until the Board takes final action on the construction permit appeal, or until the Board
    orders otherwise.

    3
    IT IS SO ORDERED.
    I, John T. Therriault, Assistant Clerk of the Illinois Pollution Control Board,
    certify that the Board adopted the above order on November 1, 2007, by a vote of 4-0.
    ___________________________________
    John T. Therriault, Assistant Clerk
    Illinois Pollution Control Board