THE ILLINOIS POLLUTION CONTROLlLnJii'''n.,-"
T-TOWN DRIVE THRU, INC.,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
PCB No. 07-085
)
(LUST Appeal)
)
)
)
Pursuant to 35
ILL. ADM. CODE
§§
101.500(d) and 101.516(a), petitioner
Town Drive Thru, Inc. ("Petitioner") submits this response to the cross-motion for
summary judgment contained
in the
Response to Petitioner's Motion for Summary
Judgment and Respondent's Cross-Motion for Summary Judgment
("Cross-
Motion") filed by the Illinois Environmental Protection Agency ("Agency").
The Cross-Motion relies on the same record as summarized in
Petitioner's
Motion for Summary Judgment
filed September 12, 2007 ("Petitioner's Motion").
However, the Cross-Motion makes several factual misstatements
in characterizing
that record. For example, at 2 it states that Petitioner's consultant, United Science
Industries ("USI"), "sought reimbursement
of $8,109.02 for analyses performed by
Tek-Lab." That is not so. USI charged Petitioner $8,109.02 for a bundle of
services,
of which the analyses performed by Tek-Lab were only a part, and the
remainder
of which were performed by US!.
See
Petitioner's Motion at 12-16.
Similarly, the Cross-Motion, again at
2, claims "there was no invoice in the
-1-
Electronic Filing, Received, Clerk's Office, October 12, 2007
application ... documenting that these costs had been billed to T-Town". Again,
this
is incorrect. As shown in Petitioner's Motion at 2-3, Petitioner submitted
two
invoices which it had received from USI for this work.
Next the Cross-Motion (at
3) misrepresents the rulemaking record when it
contends
Mr. Clay warned that the Agency would still need subcontractor invoices.
When one consults the transcript cited, one learns that the comments cited arose
from a question raised
by one Brad Schumacher regarding a proposal that all
contractors prove they had paid subcontractors
(Transcript
of
Proceedings Held
August
9,
2004,
R04-22A (Aug. 20, 2004) at 87 (Exhibit P attached hereto). Mr.
Clay agreed to respond in the afternoon.
Id.
at 88. After lunch, he offered his
answer, saying proof of the amount paid
to the subcontractor was necessary for
proof of the contractor's handling charge
(id.
at 104-05). After Mr. Schumacher
asked a follow-up question
(id.
at 105-06), Mr. Clay went on to concede, on the
page immediately prior to the excerpts the Agency offers, that "to be honest, one
of the reasons this provision
is in there is because we received complaints from
subcontractors that said I'm not getting paid"
(id.
at 107). Although the Agency
thus saw requiring subcontractor information to
be a way of assuring that
subcontractors were being paid,
on First Notice the Board limited its approval of
required subcontractor data to situations where the contractor was seeking a
handling charge
on the subcontractor charges
(see
Exhibit
Q
attached hereto, at
72). And
35 ILL. ADM. CODE
§
732.601 (b)(1 0), as enacted, provided that a
complete application for payment required proof of subcontractor costs
only
when
handling charges were requested.
-2-
Electronic Filing, Received, Clerk's Office, October 12, 2007
The Agency told the Board, in the very transcript at issue, that "[w]ith the
new streamlining process" many documents "will no longer be submitted to the
Agency", specifically citing subcontractor invoices. Exhibit N to Petitioner's Motion
at 45. Moreover, it specifically cited "the difficulty of enumerating every cost that
may be associated" with a task area
in proposing broad, lump-sum amounts which
would "streamline" the process. Exhibit G to Petitioner's Motion at
30. Yet now it
suggests that every such sub-cost must be itemized, proven and added up (Cross-
Motion at 3-4). The quotation from
Mr. Clay is ambiguous at best, unintelligible at
worst, and the example
he cited ($19 per foot for drilling done by a subcontractor)
is one where all the services in the Subpart H price are performed by the
subcontractor
(see
35 ILL. ADM. CODE
§
732.820(a)).
In such a case, the
contractor
is entitled to handling charges, not to compensation for its own
additional services which are a part of the bundled price. The attempt to apply
Mr.
Clay's unclear and self-contradictory statements
1
to the current situation makes no
sense in light of the Agency's many clear statements to the contrary, set forth in
Petitioner's Motion at 10-11, 17-19. Proof of a subcontractor's charges is relevant
only
in situations where the contractor is seeking a handling charge on those
charges - which
is not the situation here. And merely citing language about
"mandatory documents" (Cross-Motion at
3) does not turn what clearly were not
regarded
as "mandatory documents" into mandatory documents.
Because the services provided by Teklab are only a part of those covered
1
E.g.,
"that's what we would expect
from the subcontractor.
It would be
from the consuftanf'
(emphasis added).
-3-
Electronic Filing, Received, Clerk's Office, October 12, 2007
by the Subpart H lump sum, the Agency's demand for documentation of Teklab's
charges and its attempt to limit reimbursement to those amounts are improper.
The Agency told the Board
in the rulemaking that a reimbursement application
properly could include merely "an invoice with a minimum amount of information to
document the costs requested for reimbursement (e.g., the task performed, the
amount charged for the task, and the date the task was conducted)."
Comments
of the Illinois Environmental Protection Agency,
R04-22A (Sep. 23, 2005) at 19
(Exhibit
J
to Petitioner's Motion). Petitioner clearly provided
more than
that here.
See Petitioner's Motion at 2-4.
In this regard, Rezmar Corp. v. IEPA, PCB 02-91 (Apr. 17, 2003), and
Malkey v. IEPA, PCB 92-104 (Mar. 11, 1993), cited
in
the Cross-Motion, are
inapposite because both arose before the Agency and Board adopted the bundle-
of-services, lump-sum approach. Case decisions cannot be divorced from the
regulations being applied; if the Agency wanted to maintain the approach applied
under those cases it ought not to have proposed the "streamlining" lump-sum
approach. Similarly, the invocation of "generally accepted accounting practices"
(Cross-Motion at 4) cannot be relied upon to require documentation of matters
which the regulations,
as a matter of law, have made irrelevant. If IRS regulations
and
an employer policy permit reimbursement for use of one's car at the rate of 30
cents a mile, "generally accepted accounting practices" do not call for the
accountant to demand that the employee produce evidence
he has been making
timely payments
on the car, changing the oil, and paying a garage for tune-ups.
Petitioner seeks only the amount that has been determined to be
-4-
Electronic Filing, Received, Clerk's Office, October 12, 2007
reasonable by both the Board and the Agency in passing Subpart H.
See
Petitioner's Motion at 7-8, 11, 18-19. The Agency repeatedly stated that if a
budget had been approved for such amounts, they would be paid upon submission
of a simple invoice for same.
Id.
at 9-11,18-19. The lump-sum bundling principle
was expressly applied to analysis costs where some of the services were
performed by the contractor and others by
an outside lab.
Id.
at 14-15. Petitioner
submits that the Agency is estopped to repeal in this underhanded fashion
2
the
regulations which it insisted upon so vigorously and so long
in 2004-06.
Conclusion
For the foregoing reasons and for those stated in Petitioner's Motion,
petitioner T-Town Drive Thru, Inc. prays that the Board deny the Agency's Cross-
Motion and grant the Petitioner's Motion for summary judgment.
October
2007
T-TOWN DRIVE THRU, INC.
John
1. Hund!ey
Mandy
L. Combs
THE SHARP LAW FIRM, P.C.
P.O. Box 906 - 1115 Harrison
Mt. Vernon, IL 62864
618-242-0246
Counsel for Petitioner T- Town Drive Thru, Inc.
2
The plethora of cases where the Agency has raised this issue (with an aggregate value of
$145,000 and rising) demonstrates that
in fact the Agency's error here is not an isolated
occurrence and that a repeal of the rule
is in fact being applied. See
Petitioner's Motion to
Consolidate
filed herein Sept. 12,2007.
-5-
Electronic Filing, Received, Clerk's Office, October 12, 2007
I, the undersigned attorney at law, hereby certify that
1
served the foregoing
document upon
all persons entitled to same by causing copies to be deposited in
the United States Post Officemailboxat14thandMainStreets.Mt.Vernon.IL.
before 6:00 p.m. this date, in envelopes with proper first-class postage affixed,
addressed
as follows:
Dorothy
M. Gunn, Clerk
Illinois Pollution Control Board
James
R.
Thompson Center
100 West Randolph Street
Suite 11-500
Chicago,
IL 60601
James
G. Richardson, Esq.
Illinois Environmental Protection Agency
1021 N. Grand Ave. East
Springfield,
IL 62702
Hon. Carol Webb
Illinois Pollution Control Board
1021 N. Grand Ave. East
P.O. Box 19274
Springfield,
IL 62794
October 1 2007
John
1.
Hundley
Mandy
L. Combs
THE SHARP LAW FIRM, P.C.
P.O. Box 906 - 1115 Harrison
Mt. Vernon, IL 62864
618-242-0246
Counsel for Petitioner T- Town Drive Thru, Inc.
MandyCombs\USI\T-Town/SummJ udg Resp.doc
-6-
Electronic Filing, Received, Clerk's Office, October 12, 2007
1
for my handling for my time to go get those bids for
2
the scope of work? Because I'm a person who is
3
using a subcontractor with the indirect financial
87
4
5
interest.
A
I mean, how do I get paid?
(By Mr. Clay) In that case, I think you
6
would be entitled to that lump sum as if the owner
7
and operator were paying for the subcontractor. And
8
then, you know, that's sort of a business decision.
9
That's a decision you're
lllC>hLll.Y, that you want, in
10
your case, your company to do the work as opposed to
11
the low bidder.
12
13
14
15
MS. DAVIS:
Okay.
HEARING OFFICER TIPSORD:
Go ahead.
MR. SCHUMACHER:
Brad Schumacher.
QUESTIONS BY MR. SCHUMACHER:
16
Q
I didn't get an answer.
If I sent in my
17
reimbursement claim, I am not going to have any
18
waivers, cancelled checks, affidavit, because I
19
haven't paid my contractor yet.
So are you going to
20
deny my claim? Or how does that work? Obviously,
21
we're going to pay our subcontractor, but what if my
22
terms are 90 days, I submit a claim, and you're
23
going to not process the claim because I don't have
24
the waivers? Or backups that I'm paying the
Keefe Reporting Company
(618) 244-0190
Electronic Filing, Received, Clerk's Office, October 12, 2007
1
subcontractor?
88
2
3
4
5
6
7
8
MR. CLAY:
Can I respond to that this
afternoon?
HEARING OFFICER TIPSORD:
Sure.
MR. CLAY: Let us discuss it.
MR. SCHUMACHER:
Thanks.
HEARING OFFICER TIPSORD:
Mr. Truesdale?
QUESTIONS BY MR. TRUESDALE:
9
Q
One more question. It's related to what
10
Mr. Goodwin talked about earlier and about the TACO.
11
You mentioned before, Doug, that you
12
don't expect that there will be deed restrictions or
13
other environmental land use controls required for
14
sites that use the Tier 2 objectives. And
15
Mr. Walton referred to the PNA background analysis
16
for metropolitan areas, for instance.
17
What if an owner/operator did soil
18
removal at a site after issuance of an SRN based on
19
background PNA data, and that soil was subsequently
20
moved to a site outside of the metropolitan area, or
21
in a case where a Tier 2 inhalation objective was
22
calculated based on site-specific moisture content
23
and that soil was subsequently excavated and spreads
24
to the soil where the physical characteristics
Keefe Reporting Company
(618) 244-0190
Electronic Filing, Received, Clerk's Office, October 12, 2007
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
much they're going to force sites within that
community to clean up relative to groundwater.
If a community does not want to have that
ordinance, and that is certainly our -- that is
certainly their option. Many communities have
seen that there was a benefit to having
projects move forward, be cleaned up, you know,
when they have that groundwater ordinance in
place.
HEARING OFFICER TIPSORD:
I don't think
we're going to get done with the Agency.
I
would hope we'd get done before lunch, but it's
now 12:15. We have been at it for about 2
hours and 15 minutes.
So I think we need to go
ahead and take a lunch break. We'll break one
hour. We'll come back promptly in one hour and
continue with the Agency at that time. Thanks.
(Lunch break.)
HEARING OFFICER TIPSORD:
Let's go ahead
and go back on the record.
Mr. Clay has indicated that they have a
response to, I think, Mr. Schumacher's
question.
Go ahead, Mr. Clay.
104
24
MR. CLAY:
Yeah.
As we stated, there's
Keefe Reporting Company
(618) 244-0190
Electronic Filing, Received, Clerk's Office, October 12, 2007
1
2
3
4
5
6
7
8
9
10
11
12
13
14
canceled checks, a waiver or affidavit would be
acceptable to payment, but I mean, it's part of
the handling charge. In reading the definition
of handling charge, it's for interest. And so
it's presumed or expected that the prime would
pay their subcontractors, and reimbursement and
then get reimbursed from the Agency.
So I mean, that's, you know, like I said,
part of the -- in the definition of handling
charges interest.
MR. SCHUMACHER:
Can I?
HEARING OFFICER TIPSORD:
Sure.
Do you
have a follow-up? Sure.
QUESTIONS BY MR. SCHUMACHER:
105
15
Q
Even, say, we paid our subcontractors
16
within 30 days.
When I do the cleanup, I want to
17
immediately submit the remediation and all the
18
reimbursement.
I don't want to wait 30 days to get
19
a waiver of lien, you know, if I'm paying on that.
20
Is there any way that I can go ahead and submit the
21
claim, and is there any way that I -- say the
22
comptroller is going to give us a check within, you
23
know, we get the letter in a month and a half or two
24
months, and then I have that time frame that before
Keefe Reporting Company
(618) 244-0190
Electronic Filing, Received, Clerk's Office, October 12, 2007
1
I get paid, before the comptroller actually issues a
2
check. Could I submit the waiver of liens?
3
Because, say, you know, if it takes a hundred days
4
to get paid, and I pay my subcontractor in 30 days
5
or 60 days, and I can get the waiver of liens, I
6
have that time frame to get that waiver of liens to
7
the EPA or to somebody before the check is actually
106
8
cut. That will at least show that, hey, I did pay
9
all my subcontractor. Here's a waiver of lien.
10
Because what I don't want to
30 days, I don't
11
want to wait 30 more days to get in the line for
12
reimbursement just for a waiver of lien.
13
Is there any way that we can submit
14
them prior to getting a check? Like, would you
15
normally do for a normal contract -- you submit your
16
waiver of lien before the company pays you?
17
A
Right. And I mean, basically you need to
18
wait until you get a waiver of lien before you
19
submit the bills. And I understand what you're
20
saying.
21
But you've got to remember from the
22
Agency's standpoint, we're dealing with thousands of
23
these things.
So you're talking another review now
24
or at least a portion of a review to now you
Keefe Reporting Company
(618) 244-0190
Electronic Filing, Received, Clerk's Office, October 12, 2007
1
submitted your waiver of liens, which you already
2
reviewed the package and said, you know, you haven't
3
paid your subcontractors, at least you haven't shown
4
us that you paid your subcontractors.
5
And I mean, to be honest, one of the
6
reasons this provision is in there is because we
7
received complaints from subcontractors that said
8
I'm not getting paid. And we said, well, let me
9
look that up. And we looked it up and said, well,
10
we paid the owner/operators three months ago. They
11
are not paying the subcontractor.
107
12
Q
That's not really the Agency's
13
responsibility? It should be the contractors, it
14
should be the consultant, it should be a contractor
15
thing. You know, the subcontractor is not getting
16
paid, the general, and you know, take legal action
17
against that person.
It's not --
18
A
No, I disagree.
I mean, we are to
19
reimburse corrective action costs.
If you haven't
20
paid your sub, then you haven't incurred that cost.
21
I mean, that's the way I look at it.
22
23
HEARING OFFICER TIPSORD:
Okay.
24
QUESTIONS BY MR. COOK:
Keefe Reporting Company
(618) 244-0190
Electronic Filing, Received, Clerk's Office, October 12, 2007
72
14. Should the Proposed Rule Require Proof of Payment to a Sub-Contractor Before
Allowing
Reimbursement for Handling Charges (Section 732.601(b)(10)1734.605(b)(10»?
Section 732.601 (b)(1
0)1734.605(b)(1
0) as proposed requires that the application for
reimbursement include proof
of payment to a subcontractor when handling charges are being
sought. The participants question the Agency's proposal. CW
3
M noted that requiring proof of
payment results in higher handling costs for the contractor and the higher costs will not be
reimbursable. Tr.4 at 36-37. PIPE asserted that by definition handling charges are due to the
contractor whether or not the subcontractor is paid by the contractor. Exh. 91 at 17.
Furthermore, PIPE noted that even
if the subcontractor has agreed to await payment until the
Agency reimburses the owner or operator, the prime contractor has incurred the costs
of
insurance and administration of the subcontract.
Id.
Because "of an alarming number of phone calls" to the Agency from subcontractors
claiming they have not been paid, the Agency added Section 732.601 (b)(1 0), according to Mr.
Oakley. Exh. 7 at
2. Mr. Clay pointed out that cancelled checks are not the only mechanism for
providing proof
of payment to a subcontractor, lien waivers or affidavits from the subcontractor
would be acceptable. Exh.
88 at 18. Mr. Clay testified that such proof is necessary to show that
the subcontractor was actually paid and the owner or operator
is therefore entitled to
reimbursement for handling charges.
!d.
The existing language in Section 732.606(11) includes as an ineligible cost "Handling
charges for subcontractor's costs when the contractor has not paid the subcontractor." The
language proposed by the Agency
is asking for proof that the contractor has paid the
subcontractor before allowing reimbursement. The existing language provides that handling
charges are only eligible reimbursement costs
if the contractor
paid
the subcontractor. To the
Board, it would appear that the Agency
is merely requiring proof of a prerequisite which already
exists. However,
to allay the concerns of the participants, the Board will propose language in
Sections 732.601 (b)(1 0) and 734.605(b)(1 0) which reflects the Agency's position that cancelled
checks are not the only mechanism for providing proof
of payment to a subcontractor; lien
waivers or affidavits from the subcontractor would
be acceptable. Sections 732.601 (b)(1 0) and
734.605(b)(10) will read:
Proof
of payment of subcontractor costs for which handling charges are requested.
Proof
of payment may include cancelled checks, lien waivers, or affidavits from
the subcontractor.
The Board invites additional comment on this language.
15. Should the Proposed Rule Delineate "Atypical" Situations in Section
732.8551734.855?
The Agency's original proposal at Section 732.855/734.855 included a provision that
allowed an owner or operator to seek payment for costs which exceeded the maximum rates in
Subpart H. The proposal allows for reimbursement costs which exceed the maximum if unusual
or extraordinary circumstances occur. The language as originally proposed in Section
732.855/734.855 has been moved to Section 732.860/734.860.
Electronic Filing, Received, Clerk's Office, October 12, 2007