THE ILLINOIS POLLUTION CONTROLlLnJii'''n.,-"
    T-TOWN DRIVE THRU, INC.,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    PCB No. 07-085
    )
    (LUST Appeal)
    )
    )
    )
    Pursuant to 35
    ILL. ADM. CODE
    §§
    101.500(d) and 101.516(a), petitioner
    Town Drive Thru, Inc. ("Petitioner") submits this response to the cross-motion for
    summary judgment contained
    in the
    Response to Petitioner's Motion for Summary
    Judgment and Respondent's Cross-Motion for Summary Judgment
    ("Cross-
    Motion") filed by the Illinois Environmental Protection Agency ("Agency").
    The Cross-Motion relies on the same record as summarized in
    Petitioner's
    Motion for Summary Judgment
    filed September 12, 2007 ("Petitioner's Motion").
    However, the Cross-Motion makes several factual misstatements
    in characterizing
    that record. For example, at 2 it states that Petitioner's consultant, United Science
    Industries ("USI"), "sought reimbursement
    of $8,109.02 for analyses performed by
    Tek-Lab." That is not so. USI charged Petitioner $8,109.02 for a bundle of
    services,
    of which the analyses performed by Tek-Lab were only a part, and the
    remainder
    of which were performed by US!.
    See
    Petitioner's Motion at 12-16.
    Similarly, the Cross-Motion, again at
    2, claims "there was no invoice in the
    -1-
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    application ... documenting that these costs had been billed to T-Town". Again,
    this
    is incorrect. As shown in Petitioner's Motion at 2-3, Petitioner submitted
    two
    invoices which it had received from USI for this work.
    Next the Cross-Motion (at
    3) misrepresents the rulemaking record when it
    contends
    Mr. Clay warned that the Agency would still need subcontractor invoices.
    When one consults the transcript cited, one learns that the comments cited arose
    from a question raised
    by one Brad Schumacher regarding a proposal that all
    contractors prove they had paid subcontractors
    (Transcript
    of
    Proceedings Held
    August
    9,
    2004,
    R04-22A (Aug. 20, 2004) at 87 (Exhibit P attached hereto). Mr.
    Clay agreed to respond in the afternoon.
    Id.
    at 88. After lunch, he offered his
    answer, saying proof of the amount paid
    to the subcontractor was necessary for
    proof of the contractor's handling charge
    (id.
    at 104-05). After Mr. Schumacher
    asked a follow-up question
    (id.
    at 105-06), Mr. Clay went on to concede, on the
    page immediately prior to the excerpts the Agency offers, that "to be honest, one
    of the reasons this provision
    is in there is because we received complaints from
    subcontractors that said I'm not getting paid"
    (id.
    at 107). Although the Agency
    thus saw requiring subcontractor information to
    be a way of assuring that
    subcontractors were being paid,
    on First Notice the Board limited its approval of
    required subcontractor data to situations where the contractor was seeking a
    handling charge
    on the subcontractor charges
    (see
    Exhibit
    Q
    attached hereto, at
    72). And
    35 ILL. ADM. CODE
    §
    732.601 (b)(1 0), as enacted, provided that a
    complete application for payment required proof of subcontractor costs
    only
    when
    handling charges were requested.
    -2-
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    The Agency told the Board, in the very transcript at issue, that "[w]ith the
    new streamlining process" many documents "will no longer be submitted to the
    Agency", specifically citing subcontractor invoices. Exhibit N to Petitioner's Motion
    at 45. Moreover, it specifically cited "the difficulty of enumerating every cost that
    may be associated" with a task area
    in proposing broad, lump-sum amounts which
    would "streamline" the process. Exhibit G to Petitioner's Motion at
    30. Yet now it
    suggests that every such sub-cost must be itemized, proven and added up (Cross-
    Motion at 3-4). The quotation from
    Mr. Clay is ambiguous at best, unintelligible at
    worst, and the example
    he cited ($19 per foot for drilling done by a subcontractor)
    is one where all the services in the Subpart H price are performed by the
    subcontractor
    (see
    35 ILL. ADM. CODE
    §
    732.820(a)).
    In such a case, the
    contractor
    is entitled to handling charges, not to compensation for its own
    additional services which are a part of the bundled price. The attempt to apply
    Mr.
    Clay's unclear and self-contradictory statements
    1
    to the current situation makes no
    sense in light of the Agency's many clear statements to the contrary, set forth in
    Petitioner's Motion at 10-11, 17-19. Proof of a subcontractor's charges is relevant
    only
    in situations where the contractor is seeking a handling charge on those
    charges - which
    is not the situation here. And merely citing language about
    "mandatory documents" (Cross-Motion at
    3) does not turn what clearly were not
    regarded
    as "mandatory documents" into mandatory documents.
    Because the services provided by Teklab are only a part of those covered
    1
    E.g.,
    "that's what we would expect
    from the subcontractor.
    It would be
    from the consuftanf'
    (emphasis added).
    -3-
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    by the Subpart H lump sum, the Agency's demand for documentation of Teklab's
    charges and its attempt to limit reimbursement to those amounts are improper.
    The Agency told the Board
    in the rulemaking that a reimbursement application
    properly could include merely "an invoice with a minimum amount of information to
    document the costs requested for reimbursement (e.g., the task performed, the
    amount charged for the task, and the date the task was conducted)."
    Comments
    of the Illinois Environmental Protection Agency,
    R04-22A (Sep. 23, 2005) at 19
    (Exhibit
    J
    to Petitioner's Motion). Petitioner clearly provided
    more than
    that here.
    See Petitioner's Motion at 2-4.
    In this regard, Rezmar Corp. v. IEPA, PCB 02-91 (Apr. 17, 2003), and
    Malkey v. IEPA, PCB 92-104 (Mar. 11, 1993), cited
    in
    the Cross-Motion, are
    inapposite because both arose before the Agency and Board adopted the bundle-
    of-services, lump-sum approach. Case decisions cannot be divorced from the
    regulations being applied; if the Agency wanted to maintain the approach applied
    under those cases it ought not to have proposed the "streamlining" lump-sum
    approach. Similarly, the invocation of "generally accepted accounting practices"
    (Cross-Motion at 4) cannot be relied upon to require documentation of matters
    which the regulations,
    as a matter of law, have made irrelevant. If IRS regulations
    and
    an employer policy permit reimbursement for use of one's car at the rate of 30
    cents a mile, "generally accepted accounting practices" do not call for the
    accountant to demand that the employee produce evidence
    he has been making
    timely payments
    on the car, changing the oil, and paying a garage for tune-ups.
    Petitioner seeks only the amount that has been determined to be
    -4-
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    reasonable by both the Board and the Agency in passing Subpart H.
    See
    Petitioner's Motion at 7-8, 11, 18-19. The Agency repeatedly stated that if a
    budget had been approved for such amounts, they would be paid upon submission
    of a simple invoice for same.
    Id.
    at 9-11,18-19. The lump-sum bundling principle
    was expressly applied to analysis costs where some of the services were
    performed by the contractor and others by
    an outside lab.
    Id.
    at 14-15. Petitioner
    submits that the Agency is estopped to repeal in this underhanded fashion
    2
    the
    regulations which it insisted upon so vigorously and so long
    in 2004-06.
    Conclusion
    For the foregoing reasons and for those stated in Petitioner's Motion,
    petitioner T-Town Drive Thru, Inc. prays that the Board deny the Agency's Cross-
    Motion and grant the Petitioner's Motion for summary judgment.
    October
    2007
    T-TOWN DRIVE THRU, INC.
    John
    1. Hund!ey
    Mandy
    L. Combs
    THE SHARP LAW FIRM, P.C.
    P.O. Box 906 - 1115 Harrison
    Mt. Vernon, IL 62864
    618-242-0246
    Counsel for Petitioner T- Town Drive Thru, Inc.
    2
    The plethora of cases where the Agency has raised this issue (with an aggregate value of
    $145,000 and rising) demonstrates that
    in fact the Agency's error here is not an isolated
    occurrence and that a repeal of the rule
    is in fact being applied. See
    Petitioner's Motion to
    Consolidate
    filed herein Sept. 12,2007.
    -5-
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    I, the undersigned attorney at law, hereby certify that
    1
    served the foregoing
    document upon
    all persons entitled to same by causing copies to be deposited in
    the United States Post Officemailboxat14thandMainStreets.Mt.Vernon.IL.
    before 6:00 p.m. this date, in envelopes with proper first-class postage affixed,
    addressed
    as follows:
    Dorothy
    M. Gunn, Clerk
    Illinois Pollution Control Board
    James
    R.
    Thompson Center
    100 West Randolph Street
    Suite 11-500
    Chicago,
    IL 60601
    James
    G. Richardson, Esq.
    Illinois Environmental Protection Agency
    1021 N. Grand Ave. East
    Springfield,
    IL 62702
    Hon. Carol Webb
    Illinois Pollution Control Board
    1021 N. Grand Ave. East
    P.O. Box 19274
    Springfield,
    IL 62794
    October 1 2007
    John
    1.
    Hundley
    Mandy
    L. Combs
    THE SHARP LAW FIRM, P.C.
    P.O. Box 906 - 1115 Harrison
    Mt. Vernon, IL 62864
    618-242-0246
    Counsel for Petitioner T- Town Drive Thru, Inc.
    MandyCombs\USI\T-Town/SummJ udg Resp.doc
    -6-
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    1
    for my handling for my time to go get those bids for
    2
    the scope of work? Because I'm a person who is
    3
    using a subcontractor with the indirect financial
    87
    4
    5
    interest.
    A
    I mean, how do I get paid?
    (By Mr. Clay) In that case, I think you
    6
    would be entitled to that lump sum as if the owner
    7
    and operator were paying for the subcontractor. And
    8
    then, you know, that's sort of a business decision.
    9
    That's a decision you're
    lllC>hLll.Y, that you want, in
    10
    your case, your company to do the work as opposed to
    11
    the low bidder.
    12
    13
    14
    15
    MS. DAVIS:
    Okay.
    HEARING OFFICER TIPSORD:
    Go ahead.
    MR. SCHUMACHER:
    Brad Schumacher.
    QUESTIONS BY MR. SCHUMACHER:
    16
    Q
    I didn't get an answer.
    If I sent in my
    17
    reimbursement claim, I am not going to have any
    18
    waivers, cancelled checks, affidavit, because I
    19
    haven't paid my contractor yet.
    So are you going to
    20
    deny my claim? Or how does that work? Obviously,
    21
    we're going to pay our subcontractor, but what if my
    22
    terms are 90 days, I submit a claim, and you're
    23
    going to not process the claim because I don't have
    24
    the waivers? Or backups that I'm paying the
    Keefe Reporting Company
    (618) 244-0190
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    1
    subcontractor?
    88
    2
    3
    4
    5
    6
    7
    8
    MR. CLAY:
    Can I respond to that this
    afternoon?
    HEARING OFFICER TIPSORD:
    Sure.
    MR. CLAY: Let us discuss it.
    MR. SCHUMACHER:
    Thanks.
    HEARING OFFICER TIPSORD:
    Mr. Truesdale?
    QUESTIONS BY MR. TRUESDALE:
    9
    Q
    One more question. It's related to what
    10
    Mr. Goodwin talked about earlier and about the TACO.
    11
    You mentioned before, Doug, that you
    12
    don't expect that there will be deed restrictions or
    13
    other environmental land use controls required for
    14
    sites that use the Tier 2 objectives. And
    15
    Mr. Walton referred to the PNA background analysis
    16
    for metropolitan areas, for instance.
    17
    What if an owner/operator did soil
    18
    removal at a site after issuance of an SRN based on
    19
    background PNA data, and that soil was subsequently
    20
    moved to a site outside of the metropolitan area, or
    21
    in a case where a Tier 2 inhalation objective was
    22
    calculated based on site-specific moisture content
    23
    and that soil was subsequently excavated and spreads
    24
    to the soil where the physical characteristics
    Keefe Reporting Company
    (618) 244-0190
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    12
    13
    14
    15
    16
    17
    18
    19
    20
    21
    22
    23
    much they're going to force sites within that
    community to clean up relative to groundwater.
    If a community does not want to have that
    ordinance, and that is certainly our -- that is
    certainly their option. Many communities have
    seen that there was a benefit to having
    projects move forward, be cleaned up, you know,
    when they have that groundwater ordinance in
    place.
    HEARING OFFICER TIPSORD:
    I don't think
    we're going to get done with the Agency.
    I
    would hope we'd get done before lunch, but it's
    now 12:15. We have been at it for about 2
    hours and 15 minutes.
    So I think we need to go
    ahead and take a lunch break. We'll break one
    hour. We'll come back promptly in one hour and
    continue with the Agency at that time. Thanks.
    (Lunch break.)
    HEARING OFFICER TIPSORD:
    Let's go ahead
    and go back on the record.
    Mr. Clay has indicated that they have a
    response to, I think, Mr. Schumacher's
    question.
    Go ahead, Mr. Clay.
    104
    24
    MR. CLAY:
    Yeah.
    As we stated, there's
    Keefe Reporting Company
    (618) 244-0190
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    12
    13
    14
    canceled checks, a waiver or affidavit would be
    acceptable to payment, but I mean, it's part of
    the handling charge. In reading the definition
    of handling charge, it's for interest. And so
    it's presumed or expected that the prime would
    pay their subcontractors, and reimbursement and
    then get reimbursed from the Agency.
    So I mean, that's, you know, like I said,
    part of the -- in the definition of handling
    charges interest.
    MR. SCHUMACHER:
    Can I?
    HEARING OFFICER TIPSORD:
    Sure.
    Do you
    have a follow-up? Sure.
    QUESTIONS BY MR. SCHUMACHER:
    105
    15
    Q
    Even, say, we paid our subcontractors
    16
    within 30 days.
    When I do the cleanup, I want to
    17
    immediately submit the remediation and all the
    18
    reimbursement.
    I don't want to wait 30 days to get
    19
    a waiver of lien, you know, if I'm paying on that.
    20
    Is there any way that I can go ahead and submit the
    21
    claim, and is there any way that I -- say the
    22
    comptroller is going to give us a check within, you
    23
    know, we get the letter in a month and a half or two
    24
    months, and then I have that time frame that before
    Keefe Reporting Company
    (618) 244-0190
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    1
    I get paid, before the comptroller actually issues a
    2
    check. Could I submit the waiver of liens?
    3
    Because, say, you know, if it takes a hundred days
    4
    to get paid, and I pay my subcontractor in 30 days
    5
    or 60 days, and I can get the waiver of liens, I
    6
    have that time frame to get that waiver of liens to
    7
    the EPA or to somebody before the check is actually
    106
    8
    cut. That will at least show that, hey, I did pay
    9
    all my subcontractor. Here's a waiver of lien.
    10
    Because what I don't want to
    30 days, I don't
    11
    want to wait 30 more days to get in the line for
    12
    reimbursement just for a waiver of lien.
    13
    Is there any way that we can submit
    14
    them prior to getting a check? Like, would you
    15
    normally do for a normal contract -- you submit your
    16
    waiver of lien before the company pays you?
    17
    A
    Right. And I mean, basically you need to
    18
    wait until you get a waiver of lien before you
    19
    submit the bills. And I understand what you're
    20
    saying.
    21
    But you've got to remember from the
    22
    Agency's standpoint, we're dealing with thousands of
    23
    these things.
    So you're talking another review now
    24
    or at least a portion of a review to now you
    Keefe Reporting Company
    (618) 244-0190
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    1
    submitted your waiver of liens, which you already
    2
    reviewed the package and said, you know, you haven't
    3
    paid your subcontractors, at least you haven't shown
    4
    us that you paid your subcontractors.
    5
    And I mean, to be honest, one of the
    6
    reasons this provision is in there is because we
    7
    received complaints from subcontractors that said
    8
    I'm not getting paid. And we said, well, let me
    9
    look that up. And we looked it up and said, well,
    10
    we paid the owner/operators three months ago. They
    11
    are not paying the subcontractor.
    107
    12
    Q
    That's not really the Agency's
    13
    responsibility? It should be the contractors, it
    14
    should be the consultant, it should be a contractor
    15
    thing. You know, the subcontractor is not getting
    16
    paid, the general, and you know, take legal action
    17
    against that person.
    It's not --
    18
    A
    No, I disagree.
    I mean, we are to
    19
    reimburse corrective action costs.
    If you haven't
    20
    paid your sub, then you haven't incurred that cost.
    21
    I mean, that's the way I look at it.
    22
    23
    HEARING OFFICER TIPSORD:
    Okay.
    24
    QUESTIONS BY MR. COOK:
    Keefe Reporting Company
    (618) 244-0190
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    72
    14. Should the Proposed Rule Require Proof of Payment to a Sub-Contractor Before
    Allowing
    Reimbursement for Handling Charges (Section 732.601(b)(10)1734.605(b)(10»?
    Section 732.601 (b)(1
    0)1734.605(b)(1
    0) as proposed requires that the application for
    reimbursement include proof
    of payment to a subcontractor when handling charges are being
    sought. The participants question the Agency's proposal. CW
    3
    M noted that requiring proof of
    payment results in higher handling costs for the contractor and the higher costs will not be
    reimbursable. Tr.4 at 36-37. PIPE asserted that by definition handling charges are due to the
    contractor whether or not the subcontractor is paid by the contractor. Exh. 91 at 17.
    Furthermore, PIPE noted that even
    if the subcontractor has agreed to await payment until the
    Agency reimburses the owner or operator, the prime contractor has incurred the costs
    of
    insurance and administration of the subcontract.
    Id.
    Because "of an alarming number of phone calls" to the Agency from subcontractors
    claiming they have not been paid, the Agency added Section 732.601 (b)(1 0), according to Mr.
    Oakley. Exh. 7 at
    2. Mr. Clay pointed out that cancelled checks are not the only mechanism for
    providing proof
    of payment to a subcontractor, lien waivers or affidavits from the subcontractor
    would be acceptable. Exh.
    88 at 18. Mr. Clay testified that such proof is necessary to show that
    the subcontractor was actually paid and the owner or operator
    is therefore entitled to
    reimbursement for handling charges.
    !d.
    The existing language in Section 732.606(11) includes as an ineligible cost "Handling
    charges for subcontractor's costs when the contractor has not paid the subcontractor." The
    language proposed by the Agency
    is asking for proof that the contractor has paid the
    subcontractor before allowing reimbursement. The existing language provides that handling
    charges are only eligible reimbursement costs
    if the contractor
    paid
    the subcontractor. To the
    Board, it would appear that the Agency
    is merely requiring proof of a prerequisite which already
    exists. However,
    to allay the concerns of the participants, the Board will propose language in
    Sections 732.601 (b)(1 0) and 734.605(b)(1 0) which reflects the Agency's position that cancelled
    checks are not the only mechanism for providing proof
    of payment to a subcontractor; lien
    waivers or affidavits from the subcontractor would
    be acceptable. Sections 732.601 (b)(1 0) and
    734.605(b)(10) will read:
    Proof
    of payment of subcontractor costs for which handling charges are requested.
    Proof
    of payment may include cancelled checks, lien waivers, or affidavits from
    the subcontractor.
    The Board invites additional comment on this language.
    15. Should the Proposed Rule Delineate "Atypical" Situations in Section
    732.8551734.855?
    The Agency's original proposal at Section 732.855/734.855 included a provision that
    allowed an owner or operator to seek payment for costs which exceeded the maximum rates in
    Subpart H. The proposal allows for reimbursement costs which exceed the maximum if unusual
    or extraordinary circumstances occur. The language as originally proposed in Section
    732.855/734.855 has been moved to Section 732.860/734.860.
    Electronic Filing, Received, Clerk's Office, October 12, 2007

    Back to top