ILLINOIS POLLUTION CONTROL BOARD
    June 21, 2007
    DYNEGY MIDWEST GENERATION, INC.,
    (HENNEPIN POWER STATION),
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 07-123
    (Permit Appeal - Air)
    (90-Day Extension)
    ORDER OF THE BOARD (by G.T. Girard):
    On June 5, 2007, the parties timely filed a joint notice to extend the 35-day period within
    which Dynegy Midwest Generation, Inc. (Dynegy) may appeal a May 29, 2007 determination of
    the Illinois Environmental Protection Agency (Agency).
    See
    415 ILCS 5/40(a)(1) (2006); 35 Ill.
    Adm. Code 105.206(c), 105.208(a), (c). The Agency issued a permit for construction and
    operation of baghouses and sorbent injection systems for the Unit 1 and 2 boilers at the Hennepin
    Power Station, Hennepin, Putnam County. Dynegy received the permit on June 1, 2007.
    The Board extends the appeal period until October 4, 2007, as the parties’ request.
    See
    415 ILCS 5/40(a)(1) (2006); 35 Ill. Adm. Code 105.406. If Dynegy fails to file an appeal on or
    before that date, the Board will dismiss this case and close the docket.
    IT IS SO ORDERED.
    I, John T. Therriault, Assistant Clerk of the Illinois Pollution Control Board, certify that
    the Board adopted the above order on June 21, 2007, by a vote of 4-0.
    John T. Therriault, Assistant Clerk
    Illinois Pollution Control Board