ILLINOIS POLLUTION CONTROL BOARD
July 6, 2006
OMNI BIOENERGY, LLC,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 06-187
(Air Permit Appeal)
(90-Day Extension)
ORDER OF THE BOARD (by G.T. Girard):
On June 22, 2006, the parties timely filed a joint notice to extend the 35-day period
within which Omni Bioenergy, LLC (Omni Bioenergy) may appeal a May 16, 2006
determination of the Illinois Environmental Protection Agency (Agency).
See
415 ILCS
5/40(a)(1) (2004); 35 Ill. Adm. Code 105.206(c), 105.208(a), (c). The Agency granted an air
construction permit, with added conditions, for Omni Bioenergy’s biodiesel plant at 2901 Rock
Road, Granite City, Madison County.
The Board extends the appeal period until September 25, 2006.
1
See
415 ILCS 5/40(a)(1)
(2004); 35 Ill. Adm. Code 105.406. If Omni Bioenergy fails to file an appeal on or before that
date, the Board will dismiss this case and close the docket.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
adopted the above order on July 6, 2006, by a vote of 4-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board
1
The request was for “90 days, to and including September 20, 2006.” Joint Notice and Request
for Extension of Time for Permit Appeal at 1. The 90th day is Sunday, September 24, 2006.
The Board used the next business day, September 25, 2006, for the deadline.