ILLINOIS POLLUTION
    CONTROL BOARD
    August
    15,
    1996
    IN MATTER
    OF:
    )
    )
    PETITION OF COMMONWEALTH
    )
    AS
    96-9
    EDISON COMPANY
    FOR AN
    ADJUSTED
    )
    (Adjusted
    Standard
    -
    Land)
    STANDARD
    FROM
    35
    ILL. ADM. CODE
    )
    PARTS811and814
    )
    OPINION
    AND ORDER OF THE BOARD (by R.C.
    Flemal):
    This matter comes before the Board upon
    a
    “Petition for Adjusted
    Standards
    from
    Certain Regulations
    Governing
    Existing
    Landfills” filed by
    Commonwealth Edison Company
    (Edison)
    on April
    1,
    1996.
    The petition applies to
    Edison’s
    Joliet/Lincoln Quarry Site
    (Lincoln Quarry or the
    Site).
    The requested modifications
    apply
    to
    the following standards governing non-hazardous
    solid waste
    landfill operations:
    (1) the standard prescribing
    a
    leachate
    collection and
    management system;
    (2)
    the groundwater monitoring
    requirements for
    certain
    inorgailic and
    organic constituents;
    (3) the standards for location of monitoring
    wells;
    (4) the zone of
    attenuation standards
    applicable
    to
    the Site;
    (5)
    the standard prescribing finatcover for-the
    Main Quarry;
    and
    (6) miscellaneous additional
    standards
    that Edison assertsi&ctualiydo
    not
    apply
    to the
    mode of operation conducted at the
    Site.
    The Board’s responsibility
    in this
    matter arises from the Environmental Protection
    Act
    (Act)
    (415 ILCS
    5/1
    et seq.).
    The Board
    is charged therein to
    “determine,
    define and
    implement the environmental
    control standards applicable
    in the
    State of Illinois”
    (Act at
    Section 5(b)) and
    to
    “grant
    .
    .
    .
    an adjusted standard for persons who can justify such an
    adjustment”
    (Act at Section 28.1(a)).
    More generally,
    the Board’s responsibility
    in this
    matter
    is based
    on the system of checks
    and balances
    integral
    to
    Illinois
    environmental governance:
    the Board
    is charged with
    the rulemaking and
    principal adjudicatory
    functions, and the Illinois
    Environmental Protection Agency
    (Agency)
    is responsible for carrying out the principal
    administrative duties.
    The Act
    also
    provides
    that
    “the Agency
    shall participate
    in
    adjusted
    standard
    proceedings”.
    (415 ILCS
    28. 1(d)(3).)
    On May 3,
    1996 the Agency
    filed a response and
    recommended that the instant requested adjusted standard be granted’.
    Edison’s
    April
    1,
    1996 petition for adjusted standard will be cited as (Pet.
    at
    _)
    and the
    Agency’s May 3,
    1996
    response will
    be cited as (Res. at
    _).

    2
    Edison waived hearing in
    this matter pursuant to 35
    Ill. Adm.
    Code
    106.705(j).
    No
    other person requested
    a hearing, and
    accordingly
    no hearing was held.
    Based
    upon the record before it and
    upon review of the factors involved
    in the
    consideration of adjusted standards,
    the Board
    finds
    that Edison has demonstrated that grant of
    an adjusted standard
    in the instant
    matter
    is warranted for 35
    Ill.
    Adm.
    Code
    814.302(b)(1),
    811.319(a)(2),
    811.319(a)(3),
    811.318(b)(5),
    811.320(c),
    and
    811.314.
    NATURE OF THE FACILITY AND DISCHARGE
    The Lincoln Quarry, or Site,
    is
    located
    1/4 mile south of the Des Plaines River in
    incorporated
    Will
    County,
    southwest of the City of Joliet
    and
    adjacent to
    two
    of Edison’s
    coal-
    fired generating stations, Joliet Stations 9
    and
    29.
    (Pet.
    at 2.)
    The Site is comprised of former
    dolomite quarries that are now divided
    into three units:
    the Main Quarry,
    the North Quarry,
    and
    the West
    Filled
    Area.
    (Id.)
    Although the Joliet Stations generate
    fly ash,
    bottom ash,
    and
    slag as byproducts of the coal burning process, this
    petition only
    concerns the handling of
    bottom
    ash and
    slag.
    Fly ash
    is
    shipped off-site for disposal.
    Edison deposited bottom ash and
    slag
    into the West Filled Area prior to
    1975.
    The
    West Filled Area has since been leveled
    and vegetated.
    Since
    1975
    Edison has deposited the
    bottom ash and
    slag
    into the Main Quarry,
    which was permitted as a landfill for coal
    combustion wastes
    in
    1976.
    The bottom ash and
    slag
    are mixed
    with water from the Des
    Plaines River (River)
    and
    then sluiced
    into the Main
    Quarry.
    Edison maintains the water level
    in the Main Quarry between 549
    feet and
    555
    feet above
    sea
    level,
    approximately
    20
    to
    30 feet
    below
    the adjacent groundwater table.
    The difference
    in water
    level
    generates
    a
    hydraulic
    gradient
    that
    is directed into the Main Quarry.
    That is,
    the groundwater flows
    into the Main
    Quarry from the surrounding aquifer.
    From the Main Quarry the water drains by
    gravity
    into
    the North Quarry settling
    pond
    and
    finally
    the sluicing water
    is pumped back into the River
    (under NPDES
    permit #1L0002216).
    (Pet.
    at 3.)
    BACKGROUND
    As
    required under
    35
    Ill.
    Adm.
    Code
    814.103,
    Edison notified the Agency that
    it
    would be
    closing the Lincoln Quarry by September
    18,
    1997.
    (Pet.
    at 3-4.)
    However, due to
    the unanticipated capacity, Edison now believes
    that it can receive ash wastes from the Joliet
    Stations well beyond the expected useful
    life of those Stations.
    (Id.)
    As a result, Edison
    amended
    its
    notification to extend the closure date of the coal combustion waste monofill at the
    Lincoln
    Quarry beyond
    September
    18,
    1997.
    As
    a
    result of Edison’s
    closure extension,
    it was required
    to
    show that the Lincoln
    Quarry would
    satisfy the standards applicable
    to existing
    landfills under
    35
    Ill.
    Adm.
    Code
    814,
    Subpart C.
    (Pet.
    at 4.)
    However, Edison
    states
    that as its mandatory
    application for

    3
    significant modification indicated, Lincoln
    Quarry caimot satist~some of these standards.
    (Id.
    )2
    In the instant adjusted standard, Edison
    argues that the generally applicable
    standards
    at
    issue caimot rationally apply
    to
    the operations
    in the Main Quarry.
    In addition,
    it claims
    that
    such compliance
    would
    require structural modifications
    to
    the Main Quarry which are
    technically and economically
    impracticable for what amounts to
    a
    questionable environmental
    benefit.
    (Pet.
    at
    5.)
    ADJUSTED
    STANDARD PROCEDURE
    The Illinois Environmental Protection Act at Section 28.1(415 ILCS
    5/28.1(1994))
    provides
    that
    a petitioner may request, and
    the Board may impose,
    an environmental
    standard
    that
    is
    different from the standard that would
    otherwise apply
    to
    the petitioner as the
    consequence
    of the operation of a rule of general
    applicability.
    Such
    a
    standard
    is called an
    adjusted
    standard.
    The general procedures
    that
    govern an
    adjusted standard proceeding are
    found at Section
    28.1
    of the
    Act
    and within the Board’s procedural
    rules at
    35
    Ill.
    Adm.
    Code
    Part
    106.
    The standards
    from which Edison seeks modification do
    not
    specify
    a
    level of
    justification or other requirement for an
    adjusted standard for this matter.
    Therefore,
    Sections
    28. 1(c)(1)
    through
    (c)(4) of the Act are relevant in this
    proceeding.
    Petitioner has the burden
    of proving the following for an adjusted standard from
    a
    rule of general
    applicability:
    1.
    factors relating
    to that petitioner are substantially
    and
    significantly
    different from the factors relied upon by the Board
    in
    adopting
    the
    general regulation applicable to the petitioner;
    2.
    the existence of those
    factors justifies
    an adjusted standard;
    3.
    the requested standard will
    not
    result
    in environmental
    or health
    effects substantially
    and
    significantly
    more adverse than the effects
    considered by
    the Board
    in adopting
    the rule of general
    applicability;
    and
    4.
    the adjusted standard is consistent with
    any applicable
    federal
    law.
    2
    Edison originally filed a site-specific rulemaking with
    the Board,
    R94-30,
    which was
    subsequently withdrawn after negotiations with the Agency
    determined that Edison no longer
    needed relief from the groundwater quality
    standards.
    (Pet.
    at
    5.)

    4
    REOUESTED ADJUSTED STANDARD
    Section 814.302(b)(1)
    Edison requests
    an adjusted standard from the rule-of-general applicability
    at 35
    Ill.
    Adm.
    Code
    814.302(b)(1), which states:
    b)
    Units
    regulated under this
    Subpart shall be
    subject to
    the following
    standards:
    1)
    The unit
    must be equipped with a system
    which will effectively
    drain and
    collect leachate
    and transport it to
    a leachate
    management system.
    Leachate
    is
    defined in
    the regulations
    as a
    “liquid which has been or
    is in
    direct contact
    with
    a
    solid waste”.
    (35
    Ill.
    Adm.
    Code
    810.103.)
    Under this
    definition, Edison handles
    approximately
    8.5
    million gallons of leachate per
    day
    through its current gravity flow system.
    According to
    Edison this
    is
    a high volume
    of leachate,
    as compared
    to an average
    landfill
    which
    handles approximately
    1000
    gallons per acre per day.
    (Pet.
    at 50.)
    It is
    this
    substantial
    daily water inflow
    at Edison’s
    inward-gradient landfill
    that justifies
    its current tailored leachate
    collection and management
    system.
    Under the present regulations
    Edison would
    be
    required to drain, collect and transport
    the approximately
    8.5
    million gallons per
    day of sluice water, groundwater,
    and precipitation,
    all
    which flow directly or indirectly to
    the Main Quarry.
    (Pet.
    at 49.)
    Under the proposed
    adjusted standard Edison would
    manage the water through
    its current gravity-flow drainage
    system.
    This
    system
    includes drainage pipes
    which draw water from the Main Quarry into the
    North Quarry and
    a pumping station which discharges that water from the North Quarry into
    the River.
    (Pet.
    at 62.)
    This
    system captures all
    but
    101,400 gallons per day, or 1.2
    of the
    water volume reaching the
    Site.
    (Id.)
    According
    to
    Edison,
    installing
    any alternative leachate
    collection and management
    system to
    capture only
    the incremental water would
    “result
    in
    little,
    if any,
    discernible environmental benefit”.
    (Pet.
    at 63.)
    The cost of using the gravity-
    flow system would be
    $150,000 per
    year at present value, including
    capital costs to
    replace
    slag lines
    and pumps,
    and
    operating
    costs
    for the pumps.
    (Id.)
    Any additional compliance
    system
    which Edison
    puts
    in place
    would
    address the
    incremental water which bypasses
    its
    present gravity-flow system.
    Furthermore, Edison
    claims
    that any
    alternative or additional
    leachate
    system
    would simply change the path of the
    leachate,
    but it would
    still
    flow to the
    same destination.
    Specifically, the leachate which
    would under the proposed adjusted standard flow from the bedrock directly into the River,
    would
    instead flow first to
    its
    leachate management system and then discharge into the River.

    5
    (Pet.
    at 63-64.)
    According
    to
    Edison there are no
    known wells or other known environmental
    receptors
    in the region of the Site.
    (Pet.
    at 63.)
    Edison examined various
    alternatives
    to
    its current gravity-flow system
    (Pet.
    at
    5 1-62)
    and
    found those
    leachate collection
    and
    management systems
    to
    be
    “prohibitively expensive
    and present significant technological challenges”. (Pet.
    at 51).
    Initially
    Edison evaluated the traditional leachate
    collection
    systems and
    found them to
    be
    incompatible
    with its
    current operating
    practices.
    Edison
    sluices
    its
    ash waste into the Main
    Quarry and
    operates the Quarry
    as a surface impoundment.
    (Pet.
    at 51.)
    A traditional leachate
    system requires restricting the amount of water
    that reaches
    the waste.
    Specifically,
    Edison
    examined and
    rejected two
    traditional landfill methods to
    collect leachate:
    (1) an
    underdrainage system located beneath the waste
    and
    above a low permeability bottom
    liner in
    newer
    landfills,
    and
    (2) leachate
    recovery wells
    drilled into the
    waste
    from the top of existing
    or older landfills.
    First,
    the underdrainage
    system
    could be
    installed either
    above the existing
    waste to
    collect and manage
    leachate
    for future
    waste placement, or below the existing
    waste.
    Installing
    it above the current waste
    would not effectively
    address the groundwater which
    would continue to
    enter the Main Quarry and migrate downgradient after flowing
    through the
    waste.
    (Pet.
    at
    52.)
    Edison could install
    the underdrainage
    system,
    which would
    involve
    removing the existing
    waste,
    lining
    the fractured dolomitic rock base
    and
    walls of the Main
    Quarry, and
    installing
    a low-permeability layer and leachate collection system.
    (Pet.
    at 52.)
    Edison detailed the specifics of removing the ash,
    and cited
    the problems associated with
    relocating the wet ash into not-yet constructed
    settling
    basins,
    including extensive
    dewatering
    at the Quarry throughout the installing
    period, dredging the settling basin,
    and
    the possibility
    of having
    to
    store
    the large volume of ash offsite.
    (Pet.
    at
    52-56.)
    Once
    all
    of the ash was
    finally
    removed, Edison would
    install
    a three-phase
    leachate control system consisting of a
    groundwater gradient control layer, a low-permeability liner system,
    and a leachate
    system on
    the sides
    and bottom of the Quarry bedrock.
    Any new ash deposited into the Quarry would
    have to be under dry,
    and not wet, ash handling
    practices.
    When considering an
    underdrainage
    system,
    Edison is
    unclear of the potential
    environmental harms.
    For example
    risks associated
    with handling
    dry ash at the Site such as increased worker exposure to ash
    waste,
    increased truck traffic between the
    settling
    basin and
    the
    Main
    Quarry, and dust
    generated by
    dumping the dry ash into the dry Quarry.
    (Pet.
    at 56.)
    Second,
    Edison examined the possibility
    of installing leachate
    recovery wells
    drilled
    into the waste
    from the
    top of the landfill, at or near the downgradient boundary of the
    disposal cell
    to pump
    leachate from the
    waste
    into a leachate management system.
    (Pet.
    at 57-
    59.)
    Edison found such pumping
    wells not technically viable for the
    Site
    due
    to the fact it uses
    a wet disposal
    method.
    Under the current wet
    disposal
    system,
    8.6 million gallons per
    day of
    sluice water, precipitation, and groundwater saturate the ash in
    the Main Quarry.
    It would be
    impossible
    for Edison to remove such a
    large amount of leachate
    daily through
    collection
    wells.
    (Pet.
    at 57.)
    Additionally, Edison believes
    such placement of the well would create a
    localized
    inward hydraulic
    gradient which,
    through pumping,
    would draw additional
    sluice

    6
    water,
    precipitation, and
    groundwater through
    the ash to
    the well, increasing
    the amount of
    leachate
    in
    the Main Quarry and
    suspended sediments
    which flow from the Main to
    the North
    Quarry.
    (Id.)
    Edison
    found that converting its
    system to dry ash collection,
    to
    take advantage of
    leachate
    recovery wells
    would
    create
    a
    series of other associated
    difficulties.
    Those
    difficulties
    include
    converting
    several other surrounding wells,
    adding additional
    wells,
    and maintaining
    the
    water
    level below the River level.
    (Pet.
    at
    58-59.)
    Both
    wet
    and dry systems
    face
    significant obstacles to any
    installation of collection wells,
    such as dewatering the ash and
    using
    barges
    to
    access the north wall of the Quarry
    for well installation.
    Edison also examined a
    variety
    of other more advanced
    leachate
    management
    technologies
    and likewise found them to
    be
    “technologically
    impracticable and cost
    prohibitive
    at the Lincoln Quarry Site”.
    (Pet.
    at
    59-62.)
    Those
    technologies included a
    leachate
    collection trench, which proved
    to be
    prohibitively expensive to
    install,
    and
    a downgradient
    drainage gallery
    tunnel,
    with drain holes
    to accumulate
    leachate
    seepage from
    fractures and
    joints
    in rock walls,
    which may
    not even
    be technically feasible.
    (Pet.
    at 60-62.)
    As
    an alternative to
    compliance
    with
    Section 814.302(b)(1) Edison proposes
    to
    operate
    a leachate
    collection system at the Lincoln Quarry Site which assures that the water
    level
    in the
    Main Quarry
    is maintained below the natural
    watertable level,
    assures
    that the leachate
    is
    discharged to the Des Plaines River through
    Edison’s
    NPDES-permitted outfall,
    and
    assures
    that Edison has properly complied
    with all
    effluent limitations
    in
    the NPDES permit.
    (Pet.
    at
    12.)
    The Board
    finds
    that,
    given the configuration of Edison’s Site,
    and
    the need
    to handle
    almost
    8.5
    million gallons of water per day,
    it is
    impracticable to
    require compliance with 35
    Ill.
    Adm.
    Code
    814.302(b)(1).
    The Quarry configuration, including
    the differences
    in
    the flow
    regime,
    mode of operations, and
    waste characteristics,
    are substantially
    different
    from the
    factors upon which the Board
    relied
    in adopting
    this general regulation.
    Moreover, the
    adjusted disposal
    system proposed by
    Edison does not appear to result
    in any
    environmental or
    health effects
    substantially more adverse then those
    considered by
    the Board
    in initially
    adopting
    Section 814. 302(b)(1).
    Section 811.3 19(aX2) and Section 811.3 19(a)(3)
    Edison requests an
    adjusted standard from the rule-of-general applicability
    at 35
    Ill.
    Adm.
    Code
    811.319(a)(2),
    which states:
    2)
    Criteria for Choosing
    Constituents
    to
    be Monitored
    A)
    The operator shall monitor each well for constituents that
    will provide
    a means for detecting groundwater

    7
    contamination.
    Constituents
    shall be
    chosen for
    monitoring
    if they meet
    the following requirements:
    i)
    The constituent appears
    in,
    or is expected
    to be in,
    the leachate; and
    ii)
    The Board
    has established
    for the
    constituent a public or food processing
    water supply
    standard, at 35
    Ill.
    Adm.
    Code 302,
    the Board has established
    a
    groundwater quality
    standard under
    the
    Illinois
    Groundwater Protection
    Act (Ill.
    Rev.
    Stat.
    1991,
    ch.
    111
    1/2,
    par.
    7451
    et
    seq.
    415
    ILCS
    55/1
    et.
    seq.),
    or the
    constituent may otherwise cause or
    contribute
    to groundwater contamination.
    B)
    One or more indicator constituents,
    representative of the
    transport processes of constituents
    in
    the leachate,
    may be
    chosen for monitoring
    in place of the constituents
    it
    represents.
    The use of such indicator constituents
    must be
    included
    in an Agency
    approved permit.
    Along with subsection (a)(2)
    above,
    Edison requests an adjusted standard
    from
    35
    Ill.
    Adm.
    Code
    811.319(a)(3),
    which states:
    3)
    Organic Chemicals Monitoring
    The operator shall monitor each existing
    well that
    is being used as a part of the
    monitoring
    well network
    at the facility within one year of the effective date of
    this Part,
    and
    monitor each new well within the three months of its
    establishment.
    The monitoring required by this
    subsection shall be for a broad
    range of organic chemical contaminants in accordance with the procedures
    described below:
    A)
    The analysis shall be at least as comprehensive and
    sensitive as the tests
    for:
    i)
    The
    51
    organic chemicals in
    drinking water described at
    40 CFR
    141.40
    (1988),
    incorporated by reference at 35
    Ill.
    Adm.
    Code
    810. 104;
    and
    ii)
    Any other organic chemical for which a
    groundwater quality
    standard or criterion has been
    adopted pursuant to
    Section
    14.4 of the Act or

    8
    Section
    8 of the Illinois
    Groundwater
    Protection
    Act.
    B)
    At least once every two years,
    the operator shall monitor
    each well
    in accordance
    with
    subsection (a)(1)(A).
    C)
    The operator of a MSWLF unit shall monitor each well
    in
    accordance with
    subsection (a)(l)(A) on an
    annual basis.
    Edison argues that the concerns which underlie
    the monitoring requirements
    in the
    Board’s landfill regulations do not
    apply to
    the Lincoln Quarry.
    Consequently,
    Edison
    requests that the Board
    limit the groundwater monitoring
    requirements applicable
    to
    the Site.
    Edison claims that the groundwater monitoring
    program
    was
    established to ensure that
    constituents
    from landfill wastes do not migrate
    into
    and degrade the groundwater.
    This
    migration is especially important when the wastes within the landfill vary
    significantly
    (i.e.
    municipal
    landfill), or where the
    waste
    constituent or the constituent migration pathways
    are
    poorly characterized.
    (Pet.
    at 65-66.)
    However, Edison asserts that
    an adjusted standard is
    warranted because it has operated
    the Lincoln Quarry as a coal combustion waste
    monofill for over 20
    years,
    and
    has
    fully
    characterized the ash waste and groundwater constituents derived from that waste
    (the
    composition of combustion wastes deposited at the site has remained generally consistent,
    although the specific percentages of each constituent in
    the ash varies somewhat).
    (Pet.
    at 65-
    66.)
    Accordingly this
    should eliminate the Board’s primary concerns regarding characterizing
    the groundwater composition or impact on the environment of leachate from the landfill.
    (Id.)
    Edison also claims
    the Board’s requirement of broad based
    organic and
    inorganic
    constituent monitoring
    is
    not necessary at the
    Site because studies
    show no
    organic parameters,
    or volatile
    or semi-volatile
    organic compounds
    in
    the groundwater sampling.
    (Pet.
    at 65-67.)
    The ash samples contained primarily silicon, iron,
    aluminum, calcium,
    potassium, magnesium,
    sulfur, sodium,
    barium, and
    boron.
    (Pet.
    at 66.)
    Edison argues that
    it is
    economically
    unreasonable to
    require it to
    monitor
    groundwater for organic and
    inorganic constituents
    that
    could have
    no environmental
    impact.
    As
    stated, there are
    no
    organic constituents
    in
    its
    coal
    combustion waste.
    (Pet.
    at 67.)
    The
    cost for organic groundwater sampling and
    testing
    for all
    the regulatorily tequired
    parameters would
    cost approximately $46,000 per year, as
    compared to the $1,000 per year
    ash sampling proposed
    in Edison’s
    petition for adjusted standard
    which would
    sufficiently
    examine the organic composition of its combustion waste
    to predict whether this
    waste
    could
    impact the groundwater.
    (Id.)
    According to
    Edison,
    the cost to
    analyze the groundwater for
    the regulatory
    parameters regarding inorganic constituents would
    cost approximately
    $28,600
    per year, versus
    the proposed testing
    at $16,640 per year cost to analyze only
    the potentially
    impacted parameters plus
    alkalinity.
    (Pet.
    at 68.)

    9
    Edison’s
    proposed adjusted standard would waive the organic constituent requirement
    of 35
    Ill.
    Adm.
    Code 811.319,
    and would
    only
    require Edison to
    annually sample for semi-
    volatile
    organic compounds
    which
    could remain in
    the bottom of ash and
    slag,
    and report these
    results to the Agency,
    and to institute sample of the semi-volatile organic constituents if
    necessary.
    (Pet. at
    14 and 68.)
    Edison feels
    it is unnecessary
    to
    sample for volatile
    organic
    compound because they are destroyed
    in the combustion process.
    Edison’s
    proposed adjusted standard also
    limits
    the frequency of the groundwater
    sampling
    for inorganic
    constituents.
    Edison proposes to quarterly
    monitor the inorganic
    constituents of which
    it has detected statistically significant increases
    over background
    concentrations in
    downgradient wells.
    (Pet.
    at 68-69.)
    The other inorganic
    constituents
    regulated within 35
    Ill.
    Adm.
    Code
    811.3 19(a)(2),
    those
    whose parameters
    were
    not detected
    in the groundwater or were
    found not to have a
    statistically significant increase
    in parameter
    concentrations over
    background levels, would
    be
    sampled annually
    simply
    to
    verify that
    the
    groundwater composition
    remains constant.
    (Pet.
    at 68-71.)
    Specifically,
    Edison proposes to
    sample, on an annual basis, all constituents for which the Board has established Class II
    groundwater standards; if a statistically-significant increase in
    any ofthe concentrations is
    shown, then Edison proposes to add
    those parameters in
    the sampling
    mode prescribed at Section
    811.39l(a)(l).
    (Pet. at
    13.)
    Edison argues that its proposed monitoring
    plan, eliminating organic chemical
    monitoring of groundwater and focusing primarily on
    inorganic
    monitoring of those
    potentially
    impacted parameters at the
    Site, provides
    environmental protection comparable to
    the Board’s
    generally applicable
    standards.
    (Pet.
    at 69-71.)
    It reasons that
    “if
    those organici
    constituents
    are absent, eliminating the monitoring
    requirement for those constituents
    would
    have no environmental
    impact”.
    (Pet.
    at 70.)
    Edison also observes that,
    because of the
    consistency and
    predictability of the groundwater concentrations of parameters attributable
    to
    the
    Site,
    “if previous
    monitoring
    results did
    not detect a particular inorganic
    constituent
    in
    Site
    groundwater,
    it is
    improbable that that constituent would
    appear
    in future
    sampling
    events”.
    (Pet.
    at 70.)
    As
    for those
    inorganic parameters
    which have been detected at the
    Site,
    Edison
    claims
    that the “groundwater concentrations should remain constant or decrease over time as
    the leachable
    concentrations of those parameters in
    the ash decreases”.
    (Pet.
    at 70.)
    Edison’s proposed monitoring
    plan, given the frequency and type of groundwater
    monitoring,
    appears
    to be
    adequate to justify the grant of an
    adjusted standard.
    The Site
    presents
    factors substantially
    and
    significantly different from the factors the Board considered
    in adopting
    the landfill groundwater monitoring
    requirements with regard to choosing
    the
    constituents
    to be
    monitored and organic chemical
    monitoring.
    Given the absence of organic
    chemicals and consistency of constituents for almost 20 years
    in this
    monofill,
    the concerns
    which underlie
    the monitoring requirements
    in
    the Board’s landfill regulations
    are
    not present
    at the Lincoln Quarry.
    The Board
    accordingly believes Edison has demonstrated that the
    instant
    groundwater monitoring
    requirements, Section
    811.3 19(a)(2) and
    Section
    811.3 19(a)(3), warrant an adjustment suitable to the Site.
    The Board
    also
    finds
    that Edison’s

    10
    proposed alternative
    standards provide environmental protection comparable to that
    contemplated under
    the rule of general applicability.
    Section 811.3 18(b)(3) and
    Section 811.3 18(b)(5)
    Edison requests
    an adjusted standard from the rule-of-general applicability
    at
    35
    Ill.
    Adm.
    Code
    811.318(b)(3),
    which states:
    b)
    Standards
    for the Location of Monitoring Points
    3)
    Monitoring wells
    shall be established as close
    to
    the potential
    source of discharge
    as possible without interfering with the
    waste
    disposal
    operations, and within half the distance from the edge of
    the potential
    source of discharge
    to
    the
    edge of the zone of
    attenuation downgradient,
    with respect to
    groundwater flow,
    from the source.
    Edison also
    requests an
    adjusted standard from
    35
    Ill.
    Adm.
    Code
    811
    .318(b)(5),
    which states:
    5)
    A minimum of at least one
    monitoring
    well shall be established at the
    edge of the
    zone of attenuation and shall be
    located downgradient with
    respect to groundwater flow and
    not excluding the downward direction,
    from
    the unit.
    Such well or wells
    shall be used to
    monitor any
    statistically significant increase
    in the concentration of any constituent,
    in accordance with
    Section
    811.320(e) and
    shall be used for determining
    compliance with an applicable groundwater quality
    standard of Section
    811.320.
    An observed statistically
    significant increase above the
    applicable groundwater quality
    standards of Section 811.320
    in a well
    located at or beyond the compliance boundary
    shall constitute
    a
    violation.
    Edison claims
    that
    due to physical constraints at the Lincoln Quarry, it
    is unable to
    install the large number of groundwater monitoring
    wells
    required
    in the above regulations.
    Specifically,
    if the Board
    grants
    Edison its
    request to adjust the zone of attenuation for the
    Site, Edison will be unable to
    install a well at the edge of the adjusted zone.
    (Pet.
    at 72.)
    Edison argues that the landfill conditions relied upon the Board in
    adopting these
    regulations
    are not
    the conditions
    which
    exist at Edison’s
    Site.
    First,
    the landfill regulations
    assume
    a
    lined landfill located in
    a porous media,
    where groundwater flow rates
    and physico-
    chemical processes
    of soil attenuation
    are consistent and
    the entire
    site can be easily modeled
    with limited
    flow volumes.
    (Pet.
    at 73-75.)
    In contrast, the
    Site
    is
    located
    in
    fractured
    dolomitic
    rock.
    The type of limited groundwater monitoring
    required
    in the regulations
    would

    11
    not present an accurate picture of the constituent transport.
    On the whole,
    the groundwater
    flow rates through the rock
    at the
    Site are
    very
    slow;
    however,
    flow rates within individual
    fractures and bedding planes can be
    very
    rapid.
    (Id.)
    As
    a result of this widely divergent
    ground formation,
    Edison believes an
    accurate representation of the
    Site’s
    water bearing
    material can only be achieved through a
    large-scale modeling process, unlike
    that required
    in
    Section 811.318.
    Secondly, Edison argues
    that due to the terrain surrounding the Site, it would be
    technically impracticable
    and economically unreasonable
    to
    install
    a
    groundwater monitoring
    system which would comply
    with the Board’s landfill
    regulations.
    (Pet.
    at 76-78.)
    For
    instance, there are physical obstacles
    (screening berms
    and
    security fencing) and
    natural
    environmental barriers (sheer vertical dolomite faces
    and
    deep ponds) within
    100
    feet
    downgradient of the Main Quarry boundary.
    Most significantly
    Edison explains that there
    exists
    a narrow strip of land between the Main and
    North Quarries
    which provides
    insufficient
    access
    for well drilling
    equipment and personnel
    safety to
    install a
    network--of wells.
    Regardless of the physical constraints preventing
    well installation, Edison claims that any
    constituent migration or groundwater flow data would not likely
    be accurate.
    (Pet.
    at 76-77.)
    Due
    to
    the quarrying
    and
    other land use activities
    which
    have altered the natural groundwater
    flow patterns,
    and differences
    in the hydraulic
    gradients between the Main and
    North Quarries,
    any
    wells
    installed
    in this
    area would
    give atypical information regarding the entire
    Site.
    (Id.)
    Given the unlikelihood the required wells
    will provide meaningful monitoring data,
    Edison
    argues that it should
    not be
    required to expend capital to
    install
    such wells.
    Lastly,
    Edison states that
    if the adjusted zone of attenuation is granted,
    it would be
    technically impracticable to
    install
    wells
    at the edge of the zone.
    The adjusted zone of
    attenuation boundary
    is contiguous with the northern-most property boundary
    and
    is
    located at,
    or sometimes
    beyond,
    the banks of the Des Plaines
    River.
    Because of its proximity
    to
    the
    River and subsequent mixing
    of groundwater and River water,
    installing monitoring
    wells
    in
    this
    area would not provide reliable data regarding the pertinent constituents, nor allow access
    for drill equipment or personnel.
    (Pet.
    at 77.)
    According
    to
    Edison,
    it would
    be
    required to
    install
    30 new groundwater monitoring
    wells
    to
    comply with the Board’s regulations,
    at an estimated total
    cost of $300,000.
    (Pet.
    at
    77.)
    Edison proposes
    to
    install
    a groundwater monitoring
    network,
    which
    instead of placing
    wells
    at or near the locations prescribed by the Board’s regulations,
    will place the wells
    beyond the regulatory
    100-foot standard and within the North Quarry.
    Specifically,
    Edison
    will continue to use ten existing
    wells3
    at the
    Site.
    ~
    The pre-existing
    wells
    are:
    upgradient wells
    92-2S
    and 92-2D in the South Quarry,
    and
    downgradient wells:
    nested wells RO8S
    and
    RO8D northwest of the Quarry, nested
    wells
    92-
    5S and 92-SD
    north of the Main Quarry, nested wells
    G205
    and R16D northeast of the
    Quarry, well 93-9 north of the Quarry, and
    well
    93-11 northwest of the Quarry.

    12
    Edison
    claims that
    although
    it cannot install
    all
    of the regulatorily required wells,
    it can
    “establish a network of groundwater monitoring
    wells
    that protects the environment”
    (Pet.
    at
    72), and
    which comprehensively and
    accurately
    depicts constituent migration at the Site.
    Edison states that the River is
    the only
    significant environmental receptor for groundwater at
    the
    Site.
    To
    accurately
    determine the groundwater flow to the River;
    Edison believes it
    is
    necessary to
    install
    monitoring
    wells under the North Quarry (as proposed
    in its
    adjusted
    standard request),
    as opposed to
    100 feet from the Main
    Quarry (as
    required in the
    regulations) or as opposed to the northern boundary
    line
    of the proposed adjusted standard.
    (Pet.
    at 78-80.)
    Only by
    installing wells
    under
    the North Quarry can Edison measure the
    water that bypasses
    its
    pumping system and flows directly into the River.
    If the wells
    were
    placed
    under or near the
    Main Quarry,
    it would primarily measure the groundwater which
    is
    flowing
    to the North Quarry due
    to pumping.
    Edison argues that
    its
    proposed network of
    monitoring wells
    satisfies
    the Board’s environmental
    objectives of monitoring
    environmentally
    relevant constituent flow at the Site.
    (Pet.
    at 80.)
    The Board
    finds that Edison has presented sufficient justification for an adjusted
    standard from
    Sections
    811 .318(b)(3) and
    Section
    811
    .318(b)(5).
    The conduits present in
    such fractures provide for groundwater flow quite
    distinct from the flow in homogenous
    porous
    media.
    Such a significantly
    different groundwater flow regime
    was
    not the type
    considered by the Board
    in
    adopting the rule of general
    applicability.
    The Board
    acknowledges that a altered groundwater monitoring network
    may be
    required.
    Indeed the
    physical
    location of the
    Site
    with
    relation to
    the River
    in addition to
    the unique widely
    divergent
    ground formation at the Quarries,
    justify an
    adjusted standard.
    Section 811.320(c)
    Edison requests an adjusted standard from the rule-of-general applicability
    at
    35
    Ill.
    Adm.
    Code
    811.320(c), which states:
    c)
    Determination of the Zone of Attenuation
    1)
    The zone of attenuation,
    within which concentrations of
    constituents
    in
    leachate
    discharged from
    the unit may
    exceed
    the applicable groundwater quality
    standard of this
    Section,
    is a volume bounded by
    a vertical plane at the
    property boundary
    or 100 feet from the edge of the unit,
    whichever
    is
    less,
    extending from
    the ground surface
    to
    the bottom of the uppermost aquifer and excluding
    the
    volume
    occupied by
    the waste.
    2)
    Zones of attenuation
    shall not
    extend to the annual high
    water mark of navigable surface
    waters.

    13
    3)
    Overlapping zones of attenuation
    from units
    within a
    single facility may be
    combined
    into a
    single zone for the
    purposes of establishing
    a monitoring
    network.
    As
    alternative to
    compliance
    with Section 811.320(c),
    Edison proposes
    a
    zone of
    attenuation that
    is
    100 feet from the edge of the Lincoln
    Quarry on
    the upgradient
    side and at
    the property boundary
    on the downgradient side.
    (Pet.
    at 14.)Edison believes
    this proposed
    zone of attenuation,
    coupled with the proposed monitoring well location
    standards
    discussed
    above,
    and an agreement with the Agency to
    establish
    a
    groundwater management zone (GMZ)
    at the Site,
    will be
    consistent with
    the Board’s current definitions and
    regulations.
    (Id.)
    The proposed zone
    is supported
    twofold:
    first,
    it places
    “all relevant site features that
    potentially contribute
    to
    elevated constituent concentrations
    in groundwater within a
    single
    zone of attenuation for the Site”;
    and the zone
    will be contiguous
    with
    the GMZ.
    (Pet.
    at
    86.)
    The Agency has agreed to designate
    the Lincoln Quarry Site from the waste
    boundary-to
    the site boundary as
    a
    GMZ (apparently to address exceedences of background
    concentrations).
    Edison states
    two
    reasons to justify
    a modification
    from the landfill
    standards relating
    to
    the zone of attenuation.
    First,
    Edison
    argues that the Board
    did not consider water flow
    conditions
    like those present at the
    Site
    in
    defining the generally applicable
    zone of
    attenuation.
    (Pet.
    at 81-83.)
    Specifically,
    Edison
    claims the
    Site
    consists
    of fractured
    rock,
    where,
    unlike
    in
    the Board’s models, groundwater flow rates
    vary
    considerably.
    Accordingly
    the “degree
    to which
    attenuation and
    hydrodynamic dispersion can occur under these
    conditions depends upon the existence, number, properties, and
    relationship between
    discontinuities
    in the rock mass”.
    (Pet.
    at 82.)
    Edison
    argues that
    the “geochemical processes
    of attenuation
    are of little
    or no
    significance at Lincoln Quarry because there
    is little
    interaction between the chemical
    constituents and
    the rock
    mass”.
    (Id.)
    Second,
    Edison argues that retaining the zone of attenuation
    at the
    100
    foot boundary
    would
    cause it to
    incur tremendous expense for minimal environmental
    benefit.
    (Pet.
    at 83-
    85.)
    Groundwater degradation over
    background concentrations already
    exists
    beyond the
    Main Quarry4 due
    to disposal of flyash in
    the West Quarry and
    lack of attenuation.
    Therefore
    groundwater downgradient of the
    Site beyond the 100-foot zone of attenuatiuwwilltontinue
    to
    exceed
    the Board’s non-degradation standard (particularly for boron and
    sulfate) iregardiesrof
    whether Edison takes additional precautions.
    (Pet.
    at 83-84.)
    As
    a result,
    Edison believes
    it
    is
    “technically impracticable to
    establish the zone of attenuation as required by-the generally
    applicable
    standards”.
    (Pet. at 83.)
    Edison examined several different options
    to bring
    the Quarry into partial or complete
    compliance with groundwater standards
    at the edge of the zone of attenuation-.
    The options
    Ammonia,
    arsenic, boron, cadmium, chloride,
    fluoride, manganese,
    molybdenum,
    PH,
    potassium, selenium,
    sodium,
    sulfate, total dissolves
    solids,
    total
    organic carbon and
    zinc.

    14
    considered include:
    converting
    the facility from sluiced to dry disposal andconstructing
    a
    new
    landfill
    on the existing
    ash designed in
    compliance with the standards
    in Sectium8it
    closing
    the landfill and contracting for off-site ash disposal at
    existing facilities; closing theiandflll
    and
    the generating stations; or closing the landfill
    and constructing
    a new off-site
    landfill for
    ash disposal.
    (Pet.
    at 84.)
    According to
    Edison each of the these compliance
    alternatives
    present severe adverse economic and/or social impacts
    for limited,
    if any,
    environmental
    benefit.
    (Id,
    see
    also Exhibit
    12)
    Edison notes
    that none of the compliance
    alternatives
    studied
    would
    address the
    groundwater impacts from prior waste
    operations which account for exceedences at the edge of
    the zone of attenuation.
    Edison believes those
    constituent concentrations would either
    remain
    constant or decrease
    over time,
    but would
    not decrease significantly
    immediately.
    (Pet.
    at 85.)
    Therefore,
    Edison would
    still
    need to
    request an adjusted zone of attenuation.
    If it desired to
    reduce the existing concentrations it could excavate the waste
    currently
    in
    the Main Quarry
    and West Filled Area
    (at a cost estimate
    $65-187 million) or install a leachate/groundwater
    collection system.
    Edison believes
    neither option
    is economically reasonable.
    Edison claims that the proposed zone of attenuation extension will adequately protect
    the environment.
    (Pet.
    at 86-88.)
    It claims
    that
    the only
    environmental
    receptor affected
    by
    the increase
    in the zone of attenuation
    is
    the River.
    The current constituent concentrations in
    groundwater have “no discernible impact on water quality
    in the Des Plaines
    River”.
    (Pet.
    at
    86.)
    Additionally, the contribution of constituents
    attributable
    to
    groundwater discharges
    which enter the River are indistinguishable from natural
    incremental deviations which are
    normally expected.
    Edison claims
    that
    “current discharges from the
    Site have
    no
    impact on
    River concentrations of constituents”.
    (Pet.
    at 87.)
    Edison also proclaims
    that the “proposed zone of attenuation does not
    impact any
    known or potential
    environmental
    receptors”.
    (Pet.
    at 88.)
    It states there will
    be
    no
    environmental
    impact on the area between the original and
    proposed zone, primarily because
    there are
    no current uses for impacted groundwater downgradient of the
    Site.
    (Pet.
    at 87-88.)
    In addition to current uses, the future use of this groundwater is
    also unlikely
    because Edison
    owns or controls
    most of the pertinent land,
    the impacted surrounding land is
    industrialized
    and unsuitable for residential development,
    and there exists
    an unimpacted, deeper acquirer
    to
    be used in the future.
    The Board’s rule of general
    applicability at Section
    811.320(c)
    is premised on the
    presence of an attenuating
    porous media,
    which differs
    from the fractured
    and jointed bedrock
    that occurs
    at the Lincoln
    Quarry Site.
    In this
    circumstance,
    and
    in
    light of the chemistry of
    the Lincoln Quarry waters
    and the
    local nature of the groundwater flow system,
    the Board
    believes that adjusting
    the downgradient zone of attenuation to
    the northern property
    is
    justified.
    Moreover,
    because Edison commits to controlling future use of the groundwater, it
    appears granting the requested adjusted standard will not result
    in environmental or health
    effects substantially
    more adverse than the effects considered by the Board inadoptingthetufe
    of general
    applicability.

    15
    Section 811.314
    Edison requests
    an adjusted standard from
    the rule-of-general applicability at35 IlL
    Adm.
    Code
    811.314,
    which
    states:
    a)
    The unit shall be covered by
    a final cover consisting of a low
    permeability layer overlain by
    a
    final protective layer constructed
    in
    accordance with the requirements of this
    Section.
    b)
    Standards for the Low Permeability
    Layer
    1)
    Not later than 60 days after placement of the final lift of solid
    waste,
    a low permeability layer shall
    be
    constructed.
    2)
    The
    low permeability layer shall cover the entire unit and
    connect
    with
    the liner system.
    3)
    The
    low permeability layer shall consist of any
    one of the
    following:
    A)
    A compacted earth layer constructed
    in
    accordance with
    the following standards:
    i)
    The minimum allowable thickness shall be 0.91
    meter
    (3 feet);
    ii)
    The layer shall
    be compacted to achieve a
    permeability of lxi
    o7
    centimeters per second and
    minimize
    void spaces.
    iii)
    Alternative specifications
    may be utilized
    provided
    that the performance of the low permeability layer
    is
    equal to
    or superior to
    the performance of a
    layer meeting the requirements of subsections
    (b)(3)(A)(i) and
    (b)(3)(A)(ii).
    B)
    A geomembrane constructed in
    accordance with the
    following standards:
    i)
    The geomembrane shall provide performance
    equal or superior to the compacted earth layer
    described
    in
    subsection (b)(3)(A).

    16
    ii)
    The geomembrane shall have strength to
    withstand the normal stresses imposed
    by
    the
    waste
    stabilization process.
    iii)
    The geomembrane shall
    be
    placed over a
    prepared base free from sharp objects and other
    materials which may
    cause
    damage.
    C)
    Any other low permeability layer construction techniques
    or materials, provided
    that
    they provide equivalent or
    superior performance to the requirements of this
    subsection.
    4)
    For a MSWLF unit, subsection (b)(3) notwithstanding,
    if the
    bottom liner system permeability
    is lower
    than
    1
    x
    1ff7 cmlsec.
    the permeability of the lower permeability layer of the
    final cover
    system shall be
    less than or equal to
    the permeability of the
    bottom liner system.
    c)
    Standards for the Final Protective Layer
    1)
    The final protective layer shall cover the entire
    low permeability
    layer.
    2)
    The thickness of the final protective layer
    shall be
    sufficient to
    protect the
    low permeability layer from freezing
    and
    minimize
    root penetration of the
    low permeability layer, but shall
    not
    be
    less
    than 0.91
    meter
    (3 feet).
    3)
    The final protective layer shall consist of soil
    material capable of
    supporting vegetation.
    4)
    The final protective layer shall
    be
    placed as
    soon as possible after
    placement of the
    low permeability layer to prevent desiccation,
    cracking,
    freezing or other damage to
    the
    low permeability
    layer.
    Edison claims
    that the Board’s generally applicable cover requirements
    do
    not apply
    to
    conditions
    at the Lincoln Quarry due
    to the
    mode of operation at the site.
    (Pet.
    at 88-94.)
    Edison examined the following environmental
    objectives in
    coming to that conclusion:
    minimization of water percolation and
    infiltration into the waste,
    control of water run-off from
    the cover,
    maximization of evapotranspiration,
    control of landfill gas and prevention of cover
    erosion,
    and
    minimization of maintenance.
    For instance,
    minimizing water percolation and
    infiltration into the waste would
    not
    be
    accomplished with
    a Section 811.314 cover because the water reaching the Quarry comes
    from

    17
    natural groundwater flows,
    not
    infiltration or percolation.
    (Pet.
    at 90.)
    The objectives of the
    impermeable
    layer and the
    final cover include minimization of water percolation and
    infiltration
    into the
    waste as well
    as controlling landfill
    gas and
    control of the runoff water.
    At
    the Site the water infiltration through
    percolation is
    relatively
    small compared
    to
    the
    groundwater infiltration into the waste area.
    Given the fractured
    rock
    and dolomite at the Site,
    along
    with
    the difference
    in
    water level
    in the Quarry and
    the adjacent groundwater table, the
    natural groundwater flows from the south
    through the Quarry to the River.
    A landfill cover
    system would
    reduce, but not
    eliminate the amount of water which reaches the bottom
    ash and
    slag
    due to precipitation.
    (Pet.
    at 91.)
    Maximizing evapotranspiration
    is
    not
    a
    factor at the
    Site because the majority of the water reaches
    the waste
    through groundwaterinflowandnot
    precipitation.
    (Pet.
    at 92.)
    The effect of the
    very
    small
    additional
    amount leachate
    through
    precipitation on downgradient groundwater quality
    would be
    undetectable.
    Because the wastes
    in the Quarry contain no
    organic constituents
    that might
    produce
    gases through decomposition,
    the type of cover system required
    in Section
    811.314
    is
    not
    necessary to
    control the
    gas.
    The
    waste
    at the Quarry contains only
    non-putrescible industrial
    wastes consisting of inorganic constituents,
    primarily oxides of silicon,
    aluminum, iron and
    calcium.
    (Pet.
    at 93.)
    Therefore,
    there
    is no
    need to control landfill gas because the coal
    combustion byproducts do
    not produce methane through
    decomposition as organic
    constituents.
    Another
    environmental objective
    examined, the prevention of cover erosionnd
    minimization
    of maintenance,
    would require significant upkeep and
    maintenance
    at the
    Site
    because of the hydraulic
    conditions,
    particularly the fact that pressures caused by
    groundwater
    flow into the landfill could degrade the required cap.
    (Pet.
    at 93-94.)
    Edison argues that
    it would be
    technically impracticable
    and economically unreasonable
    to
    install
    a final cover system
    satisfying the generally applicable
    requirements for the Main
    Quarry.
    (Pet.
    at 94-98.)
    Edison examined the two alternatives
    which
    satisfy
    the Board’s final
    cover requirements.
    First,
    the installation of a compacted earth low-permeability layer
    covered by
    three feet of soil.
    And second,
    the installation of a
    geomembrane liner covered by
    three feet of soil.
    Edison thoroughly examined the scenario of installing a cap using
    a wet
    closure and
    a dry closure
    with
    a total closure cost of $20-28 and
    $8
    million respectively.
    Lastly,
    Edison describes the proposed
    “Closure
    and Post-Closure Care Plan”.
    (Pet.
    at
    98-101.)
    Edison presents two
    possible options
    during closure, where the ash level
    in theMain
    Quarry is
    below
    and
    above the water level.
    If the ash level
    is below
    the water level
    for the
    groundwater table,
    Edison would close the landfill
    in
    its present “wet”
    condition.
    It would
    place
    a
    fence around the
    Site to prevent access and maintain the water at
    a
    level
    in
    the Quarry
    which supports
    the current inward hydraulic gradient.
    This
    would be
    the least costly
    alternative providing comparable environmental
    benefits.
    If the level of ash in the Main
    Quarry is
    above the natural
    groundwater table,
    Edison
    would install
    a
    two-stage cover system
    consisting of a
    “compacted
    clay layer that performs equivalently
    to two
    feet of compacted soil
    having a hydraulic
    conductivity
    of
    1
    x
    10
    -7
    cm/sec,
    overlain by
    at least four inches of topsoil.

    18
    The cap would be
    sloped at no
    less than a two percent
    grade
    and
    would be
    seeded
    to
    prevent
    erosion.”
    (Pet.
    at
    100.)
    Edison alleges
    that its
    proposed final
    cover standards
    in
    the request for adjusted
    standard will provide environmental
    benefits that are comparable to those
    obtained under the
    generally applicable
    final cover standards
    at a lower cost.
    (Pet.
    at
    101-105.)
    The Board
    agrees that
    Edison’s
    operation at the
    Site does not
    lend itself to compliance
    with the Section
    811.314
    final cover requirements.
    The required impermeable layer and
    final
    cover operate to minimize
    water percolation and
    infiltration into the waste,
    and
    to
    control
    landfill gas and
    runoff water.
    At
    the Edison Site water infiltration through percolation is
    relatively
    small compared to
    the groundwater infiltration into the waste area.
    It therefore
    appears
    that there would
    be no environmental benefit to
    installing cover pursuant
    to
    this
    section.
    With regards
    to controlling landfill gas,
    Edison’s current discharges are only coal
    combustion byproducts
    with no organic constituents
    that might produce methane through
    decomposition.
    Therefore,
    there
    is no
    need to require control of landfill gas at the Quarry.
    “Attachnent A”
    Standards
    (Sections 811.105.
    811.106,
    811.107(a),
    811.107(b),
    811.107(i),
    811.310.
    811.311.
    811.312,
    811.313,
    811.321,
    and 811.322)
    Edison includes as part of its
    overall petition request that the Board find certain parts of
    the Board’s landfill regulations be
    found to not
    apply to the
    Site.
    For the purposes of
    discussion, these will be referred to the at the “Attachment A”
    standards,
    based on their
    presentation in Attachment A of Edison’s petition.
    (Pet.
    at
    110,
    Attachment A.)
    The
    regulations
    at issue
    are 35
    Ill.
    Adm.
    Code
    Section
    811.105
    (compaction of waste),
    811.106
    (daily cover), 811.107(a)
    (phasing of operations),
    811.107(b) (working face), 811.107(i)
    (vector control), 811.310,
    811 .311,
    811.312
    (landfill gas monitoring and management
    system),
    811.313
    (intermediate cover),
    811.321
    (waste
    placement),
    and
    811.322
    (final slopes
    and
    stabilization).
    The Board
    notes
    that Edison’s
    request regarding the Attachment A standards differs
    from
    its request regarding the main portion of the instant
    adjusted standardin thatEdisx,ndoes
    not
    seek to
    replace the Attachment A standards
    with alternate,
    site-specific standards.
    Rather,
    Edison requests
    that the Board
    “confirm that
    these standards do not apply to
    Lincoln
    Quarry”
    and
    to
    find
    that
    “Edison’s
    current management practices adequately
    satisfy The purposes behind
    these requirements”.
    (Pet.
    at 110.)
    In addition,
    Edison’s
    request regarding the Attachment A standards differs
    from
    its
    request regarding the
    main portion of the instant adjusted standard
    in that
    Edisoirdoesmot
    attempt to make the demonstrations required at Section 28.1(c) of the
    Act for any
    of the
    Attachment A requests.

    19
    AGENCY RESPONSE
    The Agency
    believes that the factors relating to
    Edison with regards to
    the applicable
    standards
    are substantially
    and
    significantly different from the factors upon which
    the Board
    relied upon
    in adopting
    the regulations of general applicability.
    (Res. at 4.)
    The Agency
    agrees that compliance
    with the applicable
    standards
    would be
    economically
    unreasonable and,
    with respect to
    some of the standards,
    technically infeasible
    for Edison to
    accomplish.
    (Res. at 3.)
    Moreover, the Agency
    states that it has “no
    basis
    for
    challenging Edison’s
    cost analyses”.
    (Id.)
    The Agency
    agrees with
    Edison that
    granting the adjusted standard will not have an
    adverse impact on the environment and
    specifically
    will not result in environmental or health
    effects substantially
    and
    significantly more adverse than the effects considered by
    the Board
    when adopting the rule of general
    applicability.
    (Res.
    at
    1-5.)
    The Agency
    agrees with
    Edison that the Board
    may grant the adjusted standard
    consistent
    with applicable federal law.
    (Res.
    at 4-5.)
    CONCLUSION
    The Board
    finds
    that Edison
    has demonstrated that grant of the adjusted standard
    requested by
    Edison is
    warranted.
    Regarding the request for adjusted standard from 35
    Ill.
    Adm.
    Code
    814.302(b)(1),
    811.319(a)(2),
    811.319(a)(3),
    811.318(b)(5), 811.320(c),
    and
    811.314,
    the Board
    finds
    that
    Edison has made the demonstrations required under
    Section 28.1(c) of the Act.
    In reaching
    this
    decision, the Board
    finds
    it noteworthy that
    Edison proposes
    and
    agrees
    to
    abide with
    a
    series of replacement standards.
    The Board believes these replacement standards
    will provide
    environmental protection at least equivalent to that
    which flows from the current regulations.
    The Board will accordingly condition
    grant of the adjusted standard upon Edison’s
    compliance
    with the replacement standards.
    As
    regards
    the Attachment A parameters, the Board will grant Edison’s
    request that
    we
    determine
    “that these standards
    do
    not apply
    to
    Lincoln Quarry”.
    (cf. In the Matter of Wood
    Energy,
    AS
    94-1
    (October 6,
    1994), esp. footnote 3).
    We will
    not grant an
    “adjusted
    standard”
    as
    such, since as we have noted above,
    Edison does not attempt
    to
    make the
    demonstrations
    required by
    Section 28.1(c) of the Act,
    and we do
    not
    wish to establish
    a
    precedent of acceptance of inadequate pleading in these cases.
    However, the Board believes
    that none of these standards
    are reasonably applicable
    to the circumstances encountered
    in
    the
    Lincoln Quarry disposal
    system.
    We will instead include
    in
    the order of adjusted standard
    a
    statement that the attachment A standards do
    not apply.

    20
    This
    opinion constitutes
    the Board’s findings of fact and conclusions of law
    in this
    matter.
    ORDER
    Commonwealth Edison Company
    is hereby granted
    an adjusted standard for the
    Joliet/Lincoln Quarry Site with respect to the following regulations:
    35
    Ill.
    Adm.
    Code
    814.302(b)(1),
    811 .319(a)(2),
    811 .319(a)(3),
    811 .318(b)(5), 811.320(c),
    and 811il4.
    In addition,
    the following Board regulations
    do
    not apply to the Joliet/Lincoln Quarry
    Site:
    35
    Ill.
    Adm.
    Code
    811.105,
    811.106,
    811.107(a), 811.107(b), 811.107(i),
    811.310,
    811.311,
    811.312,
    811.313,
    811.321,
    and
    811.322.
    In lieu of the standards
    above the following shall
    apply.
    1)
    Edison shall
    dispose
    only
    bottom ash and
    slag from the combustion of coalinthcMain
    Quarry.
    2)
    Edison shall operate a leachate collection and management
    system
    at the Joliet/Lincoln
    Quarry Site that assures compliance with effluent
    limitations contained
    in
    an NPDES
    permit duly
    issued by
    the Illinois
    Environmental Protection Agency.
    The leachate
    collection and management
    system
    shall consist of:
    a)
    A gravity flow drainage
    system that:
    i)
    Channels supernatant liquid
    from the Main Quarry into the North
    Quarry;
    and
    ii)
    Assures that the water
    level
    in the Main Quarry
    is maintained below
    the
    natural
    water table
    level.
    b)
    A permitted point source discharge from the North Quarry to
    the Des Plaines
    River.
    3)
    Groundwater
    Sampling.
    a)
    Edison shall analyze groundwater from
    the monitoring
    well system
    at the
    Joliet/Lincoln Quarry Site,
    in
    accordance with the requirements of 35
    Ill.
    Adm.
    Code
    811.3 19(a)(1), for the following constituents:
    Ammonia
    Fluoride
    Selenium
    Total Organic
    Arsenic
    Manganese
    Sodium
    Carbon
    Boron
    Molybdenum
    Sulfate
    Zinc
    Cadmium
    pH
    Total
    Dissolved
    Chloride
    Potassium
    Solids

    21
    b)
    Except for the constituents
    monitored
    in accordance with a),
    Edison shall
    sample its monitoring
    well system on an annual basis for all inorganic
    constituents for which the Board has established Class II groundwater standards
    under 35
    III. Adm.
    Code 620.420(a).
    i)
    If Edison detects,
    and
    confirms through
    replicate
    sampling,
    a
    statistically
    significant increase above applicable
    groundwater standards for any
    constituent monitored under this
    paragraph, Edison shall monitor that
    constituent
    in accordance with the requirements of paragraph a).
    ii)
    If, after monitoring for five years
    in accordance with this
    paragraph,
    Edison does not
    detect a
    statistically significant increase above applicable
    groundwater standards
    for a constituent monitored under this
    paragraph
    2),
    Edison may propose as a permit modification to
    discontinue
    monitoring for that constituent.
    4)
    Waste Sampling.
    a)
    At least once annually,
    Edison
    shall determine the semi-volatile
    organic
    constituent content of a representative
    sample of waste bottom
    ash and
    slag
    to
    be disposed at the Joliet/Lincoln Quarry Site.
    b)
    The results of such sampling
    shall be
    submitted to
    the Agency
    within 30 days
    after Edison receives the analytical report.
    c)
    If Edison detects
    one of the semi-volatile
    organic constituents
    listed under
    35
    Ill.
    Adm.
    Code
    811 .319(a)(3)
    in
    its ash samples, then Edison shall conduct
    confirmatory
    sampling and analysis.
    d)
    If the sampling
    and analysis conducted under
    c)
    above confirms the presence of
    one or more of the
    listed
    semi-volatile organic constituents,
    then Edison shall
    monitor
    its
    groundwater monitoring well
    system for those constituents
    in
    accordance with the
    sampling
    and
    analysis plan contained in
    Volume II of
    Edison’s
    Application for Significant pennit Modification at LincolnlJoliet
    Quarry Ash Landfill
    IL
    197809001
    (May
    1994).
    5)
    Standards for Monitoring Well Locations.
    a)
    In consultation with Edison,
    the
    Agency
    shall establish
    a monitoring
    well
    network for the Lincoln Quarry Site that
    achieves the monitoring
    objectives of
    part 811.
    The Agency shall
    not
    impose more stringent well location standards
    than the requirements
    in
    35 Ill.
    Adm.
    Code
    811.318(b).

    22
    b)
    If any of the
    wells
    in
    the monitoring
    network established
    by
    the Agency
    fails or
    is rendered unusable,
    Edison shall request permission from
    the Illinois
    Environmental Protection
    Agency
    to replace the well
    with
    another well, located
    as close as practicable to the non-functioning
    well and
    sampling
    the same
    aquifer.
    6)
    Zone of Attenuation.
    a)
    For purposes
    of this paragraph I),
    the zone of attenuation
    at the Joliet/Lincoln
    Quarry Site
    shall be defined
    as
    the volume bounded by
    a
    vertical plane
    extending from the ground surface to
    the bottom
    of the uppermost aquifer,
    excluding the waste,
    and
    located:
    i)
    100
    feet from the edge of Lincoln
    Quarry on the upgradient side
    with
    respect to groundwater flow;
    and,
    ii)
    At the property boundary
    on the downgradient side
    with respect to
    groundwater flow.
    If the property
    boundary extends beyond the annual
    high
    water mark of the
    Des
    Plaines River at any
    location, the zone of
    attenuation at that location will be
    reduced to
    satisfy
    the requirements
    of
    35
    Ill.
    Adm.
    Code
    811.320(c)(2).
    This
    zone of attenuation is depicted on Figure
    SAP-S, Volume II of
    Edison’s
    Application for Significant Permit Modification,
    attached to
    Edison’s petition for site specific
    relief.
    b)
    Groundwater
    quality
    at or beyond
    the zone of attenuation for the Joliet/Lincoln
    Quarry Site
    shall be maintained at each constituent’s background concentration.
    c)
    Nothing herein shall be construed to prohibit Edison from petitioning the Board
    for an adjustment of the groundwater quality
    standards
    applicable to the
    Site,
    in
    accordance with the procedures established
    in 35
    Ill.
    Adm.
    Code 811.320(b).
    d)
    Compliance Determination.
    Any statistically significant increase
    above an applicable groundwater quality
    standard that
    is
    attributable to
    the facility and
    which
    occurs at or beyond the
    zone of attenuation within
    100 years
    after closure of the last unit accepting
    waste
    within such a facility shall constitute
    a violation.
    7)
    Final Cover.
    a)
    For purposes of b) and
    c)
    below,
    “maximum adjusted seasonal water
    table
    level” means the maximum predicted water table
    level
    in
    the vicinity of the

    23
    Joliet/Lincoln Quarry Site, determined at the time of closure, plus sufficient
    elevation to ensure
    the integrity of a cap.
    b)
    Closure
    Below
    Water
    Table.
    i)
    If,
    at the time of closure, the level of settled
    ash in Lincoln
    Quarry
    is at
    or below
    the maximum adjusted seasonal water table level,
    no final
    cover
    is required for the Quarry and the Quarry shall be maintained as
    an impoundment.
    ii)
    Water
    levels in the Quarry shall be
    maintained at or below
    a maximum
    elevation of 570
    feet above
    sea
    level.
    iii)
    A chain link fence no
    less than eight
    (8)
    feet in
    height,
    topped by
    a no
    less than three (3) strands of barbed wire,
    shall be installed around the
    Joliet/Lincoln Quarry Site to prevent access
    and
    shall be maintained
    in
    good
    condition at all times.
    c)
    Closure
    Above Water
    Table.
    i)
    If, at
    the time ofclosure, the
    level of settled ash in Lincoln
    Quarry is
    above the maximum adjusted seasonal water table level,
    Edison shall
    install a two-stage cover system,
    which shall consist of a compacted clay
    layer that performs equivalently
    to a 2
    foot layer of compacted soil
    having a hydraulic
    conductivity
    of
    1
    x
    1ff7 cmlsec,
    overlain by
    at least
    four inches of topsoil.
    The cap
    shall be
    graded at no
    less
    than 2
    grade
    and
    shall drain to
    a collection area located on the cap.
    Stormwater
    collecting
    on the cap
    shall be
    pumped to the North Quarry for settling
    prior to discharge pursuant to the facility’s NPDES permit.
    The cap
    shall be
    seeded to prevent erosion.
    ii)
    Water
    levels in the Main Quarry shall be
    maintained at
    no more than 570
    feet above sea
    level
    through use of a gravel drainage
    blanket underlying
    the stormwater collection area.
    Water collecting
    in the drainage blanket
    shall drain by gravity to
    the North Quarry for settling prior to
    discharge
    pursuant to the facility’s NPDES permit.
    Section
    41
    of the Environmental
    Protection Act (415 ILCS
    5/41
    (1994)) provides
    for
    the appeal of final Board
    orders within 35
    days of the date of service of this order.
    The Rules
    of the Supreme Court of Illinois
    establish
    filing
    requirements.
    (See also
    35
    Ill.
    Adm.
    Code
    101.246
    “Motions for Reconsideration”.)

    24
    IT IS
    SO
    ORDERED.
    Board Member McFawn Concurred.
    I, Dorothy
    the above opinion
    of
    M.
    Gunn, Clerk of the Illinois
    Pollution Control Board,
    hereby certify
    that
    and
    order
    was adopted on the
    /5~
    day of
    ___________,
    1996,
    by
    a vote
    inn,
    Clerk
    Control Board
    Illinois

    Back to top