1
    BEFORE THE ILLINOIS POLLUTION CONTROL BOARD
    IN THE MATTER OF:
    PROPOSED AMENDMENTS TO:
    )
    REGULATION OF PETROLEUM LEAKING
    )
    R04-22
    UNDERGROUND STORAGE TANKS
    )
    (Rulemaking – UST)
    35 ILL. ADM. CODE 732
    )
    ________________________________________________________________________
    IN THE MATTER OF:
    PROPOSED AMENDMENTS TO:
    )
    REGULATION OF PETROLEUM LEAKING
    )
    R04-23
    UNDERGROUND STORAGE TANKS
    )
    (Rulemaking – UST)
    35 ILL. ADM. CODE 734
    )
    Consolidated
    Proposed Rule. First Notice
    PREFILED TESTIMONY FROM CINDY S. DAVIS, P.G. AND JOSEPH W.
    TRUESDALE, P.E., P.G. OF CSD ENVIRONMENTAL SERVICES, INC.
    REGARDING THE ILLINOIS POLLUTION CONTROL BOARD’S 1
    ST
    NOTICE OF
    AMENDMENTS TO 35 ILL. ADM. CODE 732 AND 734.
    1.)
    CSD Environmental owns Heartland Drilling (HDR) and has been denied
    handling charges due to a direct financial interest. The problem for CSD and HDR is that
    HDR does not own the landfill, backfill, trucking or supply companies used. HDR only
    provides the labor and equipment. When the HDR invoice includes the charges from
    these other companies, the Agency denies the handling charge. The definition of
    handling charge includes administrative, insurance, interest costs and a reasonable profit
    for procurement, oversight and payment of subcontracts and field purchases.
    Although it may be true that CSD, when hiring HDR, eliminates much of the cost of
    procurement for HDR provided labor and equipment since we have a direct financial
    interest, however, we do not eliminate the costs for administrative, insurance, interest
    costs and a reasonable profit for oversight and payment of subcontractors and field
    purchases.
    CSD’s professional liability insurance premium is based upon the total sales
    of the company which includes the costs of all subcontractors. Our professional liability
    insurance company informed CSD that they include the costs for subcontractors because
    they assume a risk for those subcontractors under the professional policy. They provided
    ELECTRONIC FILING, RECEIVED, CLERK'S OFFICE, JULY 8, 2005

    2
    the following example, if CSD hires a drilling company (any company even if CSD has a
    direct financial interest in them) CSD is in charge of instructing the company where to
    drill, if the drilling company strikes a product line, water line, etc, CSD’s professional
    liability insurance company is responsible to pay for any damages.
    Any prime contractor should be entitled to a handling charge for any subcontractor costs
    for which the prime contractor is responsible for administrative, insurance, interest costs
    and a reasonable profit for oversight and payment of subcontractors regardless of whether
    they have a direct or indirect financial interest in the subcontractor. CSD is responsible
    for paying all subcontractors hired for the job, and must borrow large sums of money in
    order to complete the job and pay the subcontractor, if we show proof of payment, as the
    Agency is requesting, we should be entitled to recoup the cost for administrative,
    insurance, interest costs and a reasonable profit for oversight and payment of
    subcontractors and field purchases through a handling charge.
    2.)
    In the matter of financing, CSD believes the Board should be aware that many
    consultants provide financing to our clients. The Agency stated in response to prefiled
    question 17, by Jay Koch, that “The Illinois EPA has no opinion on this issue.” The
    reality is that many of these sites would not be remediated or going through the
    remediation process without this service. Many of our clients are small businesses who
    do not have the capital to pay for our services without being reimbursed from the LUST
    Fund. In addition, many clients do not have the collateral to go to a lending institution
    and obtain a loan for their LUST compliance expenditures. Because of this need,
    financing was offered by many, but not all consultants. Most financing arrangements are
    simple, the consultant will wait for payment until the owner or operator is reimbursed
    form the LUST fund, and the consultant will not charge the owner/operator for costs
    which are not reimbursed by the State of Illinois LUST Fund. In some cases,
    arrangements are made with subcontactors such as landfills and trucking firms to wait for
    payment until the owner is reimbursed. In other cases, the consultant agrees to pay the
    subcontactors and wait for payment. Obviously, time is of the essence in receiving the
    payments to keep costs down. The longer a consultant has to borrow money to pay a
    subcontractor, or the longer a consultant has to wait for money, the more we have to
    borrow on our lines of credit to make payroll. All of this costs money and is paid out of
    the consultants profit on the job. The implementation of maximum lump sum payments
    as they are currently proposed will in our opinion cut the profit margin of many
    consultants to a point at which they will no longer reasonably be able to provide the
    upfront financing for LUST compliance. If we eliminate financing in turn we can expect
    non compliance to increase amongst the small businesses and those of limited financial
    means who truly cannot afford to proceed with LUST compliance without some
    mechanism of financing. This will just result in more properties subject to the
    Brownfield’s (USTfields) initiative and additional financial encumbrances on that
    program.
    4.)
    We understand the Agency’s need to control costs, we are not opposed to
    maximum lump sum payments when the payments are fair and equitable and we know
    exactly what is to submit to achieve compliance. The Board has acknowledged that the
    ELECTRONIC FILING, RECEIVED, CLERK'S OFFICE, JULY 8, 2005

    3
    Agency did not use scientific or statistically valid methods to arrive at lump sum prices.
    CSD suggests that the Board adopt the proposed maximum lump sum payments as
    threshold values at or below which proposed budgets and requests for reimbursement can
    be approved without significant Agency review, but require the owner/operator to submit
    actual costs for Agency review and approval. The Agency will be able to use actual costs
    in their triennial review to determine if the threshold values need adjusted. The threshold
    values will provide an incentive to the owner/operator and the consultants in so much as
    if the task can be completed for at or below the threshold value, the costs are more
    expeditiously approved and reimbursed. If the owner/operator has to submit additional
    information to justify exceeding the threshold value, they will be subjected to a longer
    more detailed review.
    5.)
    We are asking the Board to require the Agency to revise the forms prescribed and
    provided by the Agency as required in proposed 732.110 (a) and 734.135 (a) and proved
    a comprehensive list on each form of the tasked to be completed including the expected
    minimum number of maps, cross sections, etc to be included in the report. CSD also
    requests at anytime the Agency modifies the forms they establish a procedure to adjust
    the Subpart H costs accordingly.
    6.)
    The board stated in the proposed rulemaking on page 78, item 19, “Furthermore,
    the proposal, as adopted for the first notice, will include a bidding process for projects
    that cannot be undertaken for the maximum rate in Subpart H.” However, the board
    needs to be aware that Professional Services are not normally bid. In addition, the
    owners and operators of many gasoline stations, except for the large petroleum
    companies, do not employ environmental professionals to assist them in complying with
    the regulations.
    The smaller owner/operators hire environmental consultants and
    engineers to assist them with the regulations and compliance issues. If the owners
    consultant cannot complete foe example, the Stage II Site Investigation for the specified
    amount in Subpart H, the owner has to try and establish a scope of work, set the scope out
    for bid, choose the lowest bid, and if the existing consultant cannot complete the work for
    the lowest bid, then the owner / operator will have to pay out of pocket for the chosen
    consultant to review the 20 & 45 Days reports and Stage 1 Site Investigation Reports to
    come up to speed on the project. In simplest terms, the bidding process for professional
    services does not seem feasible, and should be reserved for UST compliance costs
    associated with all items except professional services..
    7.)
    In the Agency’s response to Daniel Kings, pre-filed question 5, we believe the
    Agency should further evaluate and provide for the additional costs of abandonment
    slurry (flowable fill), as required by the Illinois State Fire Marshall’s regulations
    concerning UST abandonment, separate from the price of UST removal and
    abandonment. The labor to abandon a UST is similar to the labor necessary to remove a
    UST. For example, to abandon a UST the contractor must uncover the UST; purge the
    UST of vapors; cut a hole in the top of the UST for access; enter the UST; clean the UST;
    remove sludge and wastes from the UST; fill the UST with flowable fill and properly
    place backfill on top of the UST. To remove a UST the contractor conducts all the above,
    ELECTRONIC FILING, RECEIVED, CLERK'S OFFICE, JULY 8, 2005

    4
    except he does not fill the UST with flowable fill, he removes the UST and disposes of it
    then fills the void left by the UST with standard fill material. CSD currently has a
    project which will require abandonment of three tanks, 4,000, 7,000 and 8,000 gallons in
    size, the costs for abandonment per Subpart H will be $9,450.00. The price we obtained
    from the concrete plant closest to the site is $5,035 for the flowable fill alone. In
    addition, CSD believes that the Board should revise 732.810 and 734.810 as specified in
    Attachment A to this testimony.
    8.)
    In the Agency’s response to Daniel Kings prefiled question 18, section 734.845(b)
    and 732.845(d) allows for field oversight not exceeding $390.00 per half day, plus travel
    costs, for advancing soil borings and installing monitoring wells. CSD would like to
    make both the Agency and the board aware that after soil logging, sampling and
    installation of the monitoring wells themselves, the wells must be developed and the
    casing elevations surveyed, the wells must also be purged, gauged, and have groundwater
    samples collected. These activities are typically not all performed on the same day, so
    there would be more than one applicable travel cost to the site associated with each
    monitoring well. Provisions for more than one travel charge associated with monitoring
    well installation should be allowed and provided for in the proposed Subpart H
    regulations. In addition, the previous activities are typical of all monitoring wells
    installed, however, hydraulic conductivity testing is only performed on one or more wells
    and the field costs associated with conducting the hydraulic conductivity tests should
    only apply to the monitoring well or wells in which hydraulic conductivity tests are
    performed.
    Although the proposed Subpart H rate of $390.00 per half day for each monitoring well
    installed may be adequate for the standard activities conducted for each monitoring well
    (soil logging and sampling, monitoring well installation, developing and surveying casing
    elevations, and purging gauging and sampling groundwater), it does not appear that the
    costs associated with field work and field oversight for hydraulic conductivity testing
    were provided for in the per half day rates for field work and field oversight for
    monitoring wells proposed in Subpart H, nor is it understood how costs associated with
    activities conducted on one monitoring well can reasonably be prorated through an
    unknown number of multiple monitoring wells. We suggest the addition of the following
    to 734.845(b)(2), 734.845(b)(6) and 732.845(d)(2), based on the RS Means published
    cost for “slug test, per well” of $540.39 adjusted by the average RS Means published
    localization factor for Illinois of 0.98
    C) $530.00 for conducting each hydraulic conductivity test.
    9.)
    In response to CSD’s prefiled question A-4, the Agency did not indicate whether
    or not the procedures to be used for the triennial review will be made available to the
    public. CSD request that the Board require the Agency to develop written procedures for
    conducting the triennial review and make those written procedures public information.
    10.)
    In the Agency’s response to CSD’s prefiled testimony, question I-5, it was stated
    that the question was unclear, and that the Illinois EPA will be happy to answer this
    ELECTRONIC FILING, RECEIVED, CLERK'S OFFICE, JULY 8, 2005

    5
    question at hearing if additional clarification of the question is provided. In an effort to
    clarify, we have restated the question as follows:
    Has the Agency considered requiring alternative technology corrective action
    plans to be submitted in phases? The first phase could consist of a review of two
    or more alternative technologies compared to conventional technology (including
    rough “feasibility” type total cost estimates for each) and a detailed budget
    proposal for the full scale design of the chosen technology, The second phase
    would then consist of completing design of the full scale alternative technology
    corrective action plan and a detailed budget proposal for implementation of the
    chosen alternative technology, as designed?
    CSD asks this question because we are concerned that significant amounts of designs
    costs would be incurred to prepare detailed cost comparisons of two or more alternative
    technologies to conventional technology, and subsequent preparation of the chosen
    alternative technology corrective action plan without having the Agency first review the
    cost comparison of the two or more alternative technologies to conventional technology
    and evaluated the design approach and the budget proposal for design of the chosen
    technology . If the alternative technology corrective action planning was divided into
    phases, it gives the Agency the opportunity early in the planning stage to evaluate the
    types of technologies being proposed as well as the design approach for the chosen
    technology and allows for Agency guidance as far as what they are looking for in the
    final design in order for it to be something the Agency feels comfortable approving.
    As Doug Clay mentioned in testimony “
    In alternative technology, the corrective action
    plan, fieldwork, all of that is time and materials, and I think you’re right, there is a lot of
    going back and forth as far as giving something that the Agency is comfortable
    approving, and part of that is I think we (the Agency) need to provide guidance [to]
    consultants as far as what we’re looking for. We’re working on that. But I think
    consultants also need to do a better job of explaining to us the design”
    (March 15, 2004
    transcript of proceedings page 50, lines 17-24 and page 51, lines 1 and 2) In turn, this
    provides consultants the opportunity to explain the design approach and receive guidance
    from the Agency prior to expending significant amounts of design costs. The Agency
    would then be able to limit the per project time and costs for the owner / operators
    consultant and the Agency by evaluating whether or not the design approach proposed
    and associated design budget proposal are reasonable, and will likely provide the
    information necessary for the Agency to feel comfortable approving the corrective action
    plan prior to expending actual costs for detailed design, and limit the amount of “back
    and forth” between the Agency and the consultant as much as possible.
    11.)
    In response to CSD’s prefiled question L-1, the Agency stated that they “did not
    include a particular number of applications for payment under any subsection of Section
    734.845”, however, in response to CSD’s prefiled question L-2, the Agency stated that
    “yes” they did allow for and include costs for completion of applications for partial or
    final payment every 90 days as provided for in the Environmental Protection Act Section
    57.8. These statements are in direct contradiction of one another, because in order for the
    ELECTRONIC FILING, RECEIVED, CLERK'S OFFICE, JULY 8, 2005

    6
    Agency to provide for costs for completion of applications for partial or final payment
    every 90 days in the maximum payment amounts under professional consulting services
    under Section 734.845, they would have had to estimate the time required to complete the
    each subsection of Section 734.845 and assign a particular number of applications for
    payment. Given that Agony’s contradictory responses to these questions, it would appear
    the Agency is intentionally withholding pertinent information fro the Board and the
    public with regards to this proposed rulemaking.
    The Agency throughout their responses for prefiled testimony states tasks were included
    in 734.845, but all of the tasks which the Agency continually states “have been included
    in the lump sum maximum payment amounts” have never been presented during this
    rulemaking process in their entirety. We believe one of the goals of this rulemaking
    should be to develop a fair system which is transparent and open to the public in an
    effort, as the Agency has stated time and time again, to “streamline the LUST program.”
    CSD suggests that the Board require the Agency to provide to the Board and the public
    any and all task lists, unit costs and quantity estimates which the Agency used to develop
    the maximum lump sum prices proposed in Subpart H.
    12.)
    In the Agency’s response to CSD’s prefiled question L-6, the Agency stated that
    they derived the lump sum price of $640 for “a plan that must be amended due to
    unforeseen
    circumstances” based upon eight hours of personnel time at the average rate
    of $80 an hour. If the amendment is truly required due to “unforeseen circumstances”,
    how could the Agency possibly
    foresee
    that these unforeseen circumstances will
    typically take 8 hours to address?
    CSD suggests the costs associated with any amended plan due to unforeseen
    circumstances should be reimbursed according to 734.850 and 732.850.
    13.)
    In response to CSD’s prefiled questions M-1 and M-2, the Agency declined to
    answer the questions since they didn’t know how the referenced statistics were generated.
    The statistics were generated from the LUST database by USI. USI will be explaining
    how the statistics were derived during their testimony. CSD may ask additional questions
    regarding the statistics at hearing.
    14.)
    In response to CSD’s prefiled question M-4, the Agency stated that “the Illinois
    EPA will continue to review information submitted to it to determine whether the
    information demonstrates compliance with the environmental protection Act and the
    Board’s regulations.” We would like to know if the Agency is going to establish a written
    standard for review for their project managers and if so, will that standard be made public
    information. CSD believes that a written standard of review, which is available to both
    Agency staff and the public, will aid tremendously in streamlining the program and
    insuring consistency of reviews amongst Agency project managers, and consistency of
    submittals amongst consultant thereby, reducing per project costs to the Fund..
    15.)
    CSD believes if this rulemaking is finalized in its current form, the following will
    occur in the State of Illinois:
    ELECTRONIC FILING, RECEIVED, CLERK'S OFFICE, JULY 8, 2005

    7
    Many environmental consulting firms will stop conducting work for
    LUST sites, or may even shut down entirely leaving fewer environmental
    consulting firms completing LUST work in the State of Illinois.
    Fewer engineers, geologists and scientists will be employed in the State
    of Illinois for the completion of LUST work.
    Financing of LUST projects will decrease substantially, and may cease
    entirely.
    Additional costs will be passed to the owners/operators of LUST sites
    being regulated, and
    Non compliance for LUST sites will likely increase.
    ELECTRONIC FILING, RECEIVED, CLERK'S OFFICE, JULY 8, 2005

    Back to top