ILLINOIS POLLUTION CONTROL BOARD
December 17, 1998
KIEHL ENGINEERING COMPANY,
INC.,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
)
PCB 99-78
(Variance - Air)
ORDER OF THE BOARD (by C.A. Manning):
On December 11, 1998, Kiehl Engineering Company, Inc., filed a petition for variance
regarding its facility located in Bensenville, DuPage County, Illinois. This matter is accepted
for hearing.
Hearings shall be scheduled and completed in a timely manner pursuant to the
applicable statutory decision deadline or as extended by waiver. The assigned hearing officer
shall inform the Clerk of the Board of the time and location of hearing at least 40 days in
advance of hearing so that a 30-day public notice of hearing may be published. Unless
otherwise ordered by the hearing officer, the Agency shall file its recommendation for
disposition of the petition within 30 days of filing of this petition. See 35 Ill. Adm. Code
104.180.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
the above order was adopted on the 17th day of December 1998 by a vote of 6-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board