    ORDER OF THE BOARD (by J.P. Novak):
     
    On November 8, 2004, the parties timely filed a joint notice to extend the 35-day period
    within which Gateway FS, Inc. (Gateway FS) may appeal an October 1, 2004 determination of
    the Illinois Environmental Protection Agency (Agency).
    See
    415 ILCS 5/40(a)(1) (2002); 35 Ill.
    Adm. Code 105.402, 105.406. The Agency rejected petitioner’s amendment to the high priority
    corrective action plan budget for Gateway FS’s leaking underground petroleum storage tank
    facility located at C Avenue, Prairie Du Rocher, Randolph County.
     
    The Board extends the appeal period until February 7, 2005, as the parties request.
    See
     
    415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code 105.406. If Gateway FS fails to file an appeal on
    or before that date, the Board will dismiss this case and close the docket.
     
    IT IS SO ORDERED.
     
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
    adopted the above order on November 18, 2004, by a vote of 5-0.
     
    Dorothy M. Gunn, Clerk