ILLINOIS POLLUTION CONTROL BOARD
    November 17, 2004
     
    VILLAGE OF FINDLEY,
     
    Petitioner,
     
    v.
     
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
     
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
     
     
     
     
     
    PCB 02-158
    (NPDES Permit Appeal)
          
     
    HEARING OFFICER ORDER
     
    On November 17, 2004, the parties participated in a telephone status conference with the
    hearing officer. Petitioner continues to report progress on the development of a new a regional
    water treatment facility in Shelbyville, Illinois. This regional treatment center would process
    sewage for petitioner, and would result in petitioner’s withdrawal of this permit appeal. The
    preliminary engineering report has been approved, and the project engineers plan to complete the
    final design details during the winter months. Hopefully, construction will begin next spring.
    Some delays have stemmed from the expansion of this project to now include Eagle Creek State
    Park, the Findley marina, and a new lift station.
     
    The parties are directed to participate in a telephone status conference with the hearing
    officer at 8:45 a.m. on May 26, 2005. The status conference shall be initiated by the petitioner.
    At the status conference, the parties must be prepared to discuss the status of the above-captioned
    matter.
     
    There is an open waiver of the decision deadline in this docket.
     
    IT IS SO ORDERED.
     
    _____________________
    Carol Webb
    Hearing Officer
    Illinois Pollution Control Board