ILLINOIS POLLUTION CONTROL BOARD
August 29, 1972
NEW JERSEY ZINC CO.
v.
)
#
71—362
ENVIRONMENTAL PROTECTION AGENCY
)
Mr. Richard W. Austin and Mr. Eugene W.
Beeler, (Winston & Strawn),
for New Jersey Zinc Co.;
Mr. Prescott B. Bloom
,
Special Assistant Attorney General, and Mr.
Timothy Elder,
Staff assistant to Assistant Attorney General, and
Mr. Delbert Haschemeyer,
for Environmental Protection Agency.
Opinion and Order of the Board
(by Mr. Currie):
New Jersey Zinc is
the owner of
a plant in DePue, Illinois,
in which sulfuric acid was manufactured and used for the
production of phosphate fertilizers.
The plant was closed
in
1971
(see attachment of Elan W. Hale to petition,
p.
7);
the
company petitioned us
in November 1971 for permission to reopen
it, indicating that the Environmental Protection Agency would
not allow reopening unless further provisions were made
to
control the emission of sulfur dioxide and alleging that
compliance with Agency requirements would impose an arbitrary
and unreasonable hardship.
No numerical standard for sulfur dioxide emissions was in
effect when the petition was filed, although the statutory
prohibition against air pollution applied to sulfur dioxide,
EPA
v.
City of Springfield,
#70—9
(May
26,
1971)
.
The
Agency had just proposed, however,
a new regulation
that
would limit emissions from new sulfuric acid plants to 6.5
pounds of sulfur dioxide per ton of 100
acid produced and
from other process
sources
(including existing acid plants)
to 1500 ppm
(see Board Newsletter
#35,
Nov.
10, 1971,
Proposed
Standards #R 71—23, Rule 204(d) (1)).
The attached explanation
recited that the standard for new plants could be met by pro-
viding “multistage systems of 99.5
conversion efficiencies,”
Newsletter #35 at
p.
30.
The company’s petition indicated
that
it
was
this proposed new-plant standard that the Agency
attempted
to
impose
as
a condition of reopening the DePue
plant•a~df
~which
relief was sought.
The Agency’s re-
co~m~endati~n
that the ~ariance be denied confirmed
this,
stating tha~99.5
conversion would be required.
The complexion of the New Jersey Zinc case changed con-
siderably as hearings on the varIance petition and the proposed
regulations simultaneously proceeded.
Among other things,
the
5
—
263
—2—
Agency revised its proposed sulfur dioxide standard, and the
company decided to seek a variance with regard to sulfuric acid
mist as well.
Briefs were filed.
The company amended its
petition to request sulfur dioxide emissions of 1800 ppm or
27 pounds per ton of acid produced; acid mist emissions of
0.5 pounds per ton of acid produced; and permission to exceed
the latter standard for 26 weeks until a new demister could be
installed.
The Agency argued that a better demister should be
obtained to meet the then proposed acid standard of 0.2 lb/ton
and that,
on the basis of mathematical prediction utilizing
relevant emission and meteorological data, excessive atmospheric
concentrations of sulfur dioxide would result under adverse
weather conditions if the requested emissions were allowed.
Representatives of both parties attended an open Board
meeting in which all issues were discussed.
Board members
informally indicated that the DePue plant would probably be
subject to the rules governing existing rather than new plants
and that the 1500 ppm standard should probably be revised to
1800, which would moot the request for variance from the
sulfur dioxide emission standard.
Concern was expressed that
the entire petition, except as it related to statutory air
pollution,
might be premature in that no regulations had yet
been adopted,
cf. Granite City Steel Co.
v.
EPA,
#72-34
(Feb.
7,
1972)
,
but that the statutory requirement that the Board decide
within 90 days after filing of the petition might make it im-
possible
to postpone decision until adoption of the regulations.
Pursuant to discussion among Board members and staff engineer
Richard Wadden, Board members suggested that the petition should
be denied due to prematurity and due to the failure of the
company to convince the Board on the following three contentions:
First, that contemplated emissions in excess of the proposed
limits during startup of the plant were justifiable;
second,
that installation of a demister that would meet the acid standard
was economically unreasonable; and third, that dangerous at-
mospheric concentrations of sulfur dioxide would be avoided dur-
ing adverse meteorological conditions.
The company thereupon moved that the Board defer final
action pending adoption of the regulations and authorize
another hearing in which evidence could be presented on the
points raised by the Board.
In light of the prematurity of
the case as it stood, the incomplete state of the record, and
the company’s agreement to waive its right to
a decision within
90
days,
the Board granted the motion for further hearing.
New Jersey Zinc Co.
v.
EPA,
#71—362
(Feb.
17,
1972).
Since that time the company has reexamined the issues we
raised and has presented
a thoroughly revised and improved
petition that the Agency recommends we grant.
The company moves
that we dispense with the requirement of a further hearing,
and the Agency does not object to that course.
We find that
the revised petition and the Agency’s position
5
—
264
—3—
render the variance request moot and make
a further hearing
unnecessary.
We shall recite the relevant facts and con-
siderations at some length both to demonstrate why we be-
lieve the case
is moot and because what has been achieved
in this case should serve
as a precedent for what can be
done at similar installations in other cases.
1.
Normal sulfur dioxide emissions.
When
the plant is
in
operation,
sulfur is burned to form sulfur dioxide in a con-
centration of
8 or 9,
which
is then oxidized to sulfur trioxide
with the aid of
a catalyst and absorbed
in sulfuric acid to
create more and stronger acid.
The plant’s capacity is 50 tons
of new acid per hour,
or 1200
tons per day.
The efficiency of
the
catalytic converter
is 98;
the remaining
2
of the sulfur
dioxide escapes
to the air.
The company expects sulfur
dioxide emissions during normal operation to approximate 1,820
ppm or about 1200 lb/hour or
26 lb/ton of acid
(R.
259-60,
271,
361—78,
428—34).
The originally proposed standard of 1500 ppm (roughly 23
pounds per ton)
,
it will be seen,
thus would have required a
rather marginal reduction in sulfur dioxide emissions
from
standard existing plants of 98
conversion efficiency.
The
technology required to achieve such a reduction,
the evidence
indicates, would in fact achieve far greater reduction.
New
Jersey Zinc testified that by adding
a second absorber in
series it would reduce emissions from the contemplated 26
pounds per ton of acid not to the
23 required by
the 1500 standard
but to the range of
10, and that certain scrubbers could achieve
emissions of
7
to
14 pounds per ton
(B.
280-84)
.
The only
other means of reaching the 1500
level, according to
the testimony
here, would be to curtail production by 15,
which would be
as costly as the installation of the above controls
(B.
303-04)
Thus the 1500 standard made little sense;
if existing plants
were to be required to install expensive controls,
the standard
could without extra cost be made considerably tighter.
The
basic policy question was whether or not such controls ought
to be required.
By proposing the 1500 ppm standard for existing plants
and a much stricter standard
fox- new,
the Agency appeared to
be attempting to resolve that policy question in favor of
not requiring expensive backfitting;
but,
as the testimony
showed,
1500 ppm was not the right place to draw the line
to
express that decision.
Evidence in the rule—making proceeding
established that new plants are being built and operated on
a dual—absorption basis, apparently able to survive economically,
to emit no more than
4 pounds of sulfur dioxide per ton of
acid produced.
That is the federal standard for new acid plants,
and that is the standard we adopted for new plants on the
ground that what is being efficiently dOne elsewhere represents
a standard of good practice for all to follow in designing
new facilities to avoid unnecessary degradation of the air.
PCB Regs., Ch.
2, Rule 204(f) (1) (B).
To build a second
5
—
265
—4—
absorption unit into a new design is one thing;
to backfit a
second unit onto an existing plant is somewhat different.
It
is conceded itcould be done here, with dramatic effect in re-
ducing emissions,
for something on the order of $1,150,000
(B.
280—85)
,
and that a scrubber could be installed instead,
with similar results, for one to two million dollars
(id.)
It is, however,
argued that to do so would
so increase the
cost of producing acid that the plant would be unable to com-
pete and would not be operated
(H.
288,
397).
Thus the suggestion
was clearly made that,
while new
plants could meet the strict standard and survive economically,
existing plants could not.
While we firmly believe that no
pollution program worth
its hire can afford to overlook existing
pollution sources, and while many of our regulations impose
strict limits requiring backfitting of existing facilities, we
found no proof that
the particularly burdensome requirement of
backfitting existing 98
-
efficiency sulfuric acid plants
for sulfur dioxide control was needed across the board to se-
cure satisfactory air quality.
The 2000 ppm limit was adopted
because
“a stricter concentration limit would require plant
derating or addition of auxiliary scrubbing systems and has not
been shown to be uniformly necessary to meet air quality
standards”.
Rule 204(f) (1) (A);
see opinion in In the Matter
of Emission Standards,
#R 71—23,
p.
37
(April 14, 1972).
The
use of the word “uniformly” was intentional and important; the
door was left open,
as more fully explained below,
for requiring
additional controls in individual cases where necessary
in
light of
facts such as adverse atmospheric conditions,
low
stacks,
or high concentration of sources
(id.,
p.
5).
Under Rule 101 a new source is one
“the construction or
modification of which is commenced on or after the effective
date
of this Chapter,” which was in April,
1972.
The DePue
plant was constructed long before 1972;
the argument that it
should be treated as
a new facility derives
from
the fact
that
it had been closed when the regulations were adopted and
is sought to be restored to operation thereafter.
For certain
purposes we have said there is a close analogy between a new
plant and one that is to reopen after having been shut down.
In EPA
V.
Lindgren Foundry Co., #70—1
(Sept.
25,
1970)
,
we held
that on
the facts there presented it was reasonable to require
a closed foundry to be brought into compliance ~cqithparticulate
emission regulations of long standard before reopening,
just
as
a new plant would have to be, although we might decline to
order an operating plant shut down under the same circumstances.
Lindgren thus holds that the interruption of
a going business
is an important factor in determining
whether or not to grant
a variance allowing operation while building controls
to meet
a currently enforceable standard.
But this
is not to equate
the reopened plant with the new for all purposes.
Not only
5
—
266
—5—
do we deal in the present case with
a squarely applicable
definition
in the regulations that draws the line in terms of
old and new construction rather than present operation,
but the
policy underlying the distinction between old and new plants
for purposes of sulfur dioxide emissions indicates that the
DePue plant is properly considered
an existing one.
For this
particular distinction is not a matter of timing for the
installation of given controls; our decision was that there was
no showing of a justification for requiring the expenditure of
the large sums required to backfit old facilities at all,
in
the
absence of special conditions bringing the statutory
nuisance rule or
the air-quality standard into play.
This policy
that old acid plants should not be generally required to backfit
is as applicable to
a plant that has been closed for a year as
it is to one that is currently in operation.
We conclude,
therefore,
that the DePue plant is an “existing” rather than
a
“new”
acid plant and therefore is subject to the 2000 ppm
sulfur-dioxide standard.
This means, according to the revised
petition,
that normal emissions will be in compliance
with the standard, and no variance on this account is there-
fore necessary.
2.
Normal acid mist emissions.
Some sulfuric acid mist
is also
emitted from the manufacturing process;
it has
been
partially controlled by a demister designed to reduce acid
mist emissions
to 0.5 pounds per ton produced
(R.
292-93)
The existing demister has been less than satisfactory:
A serious
incident in April,
1969 resulted in damage to neighboring
property because
of acid emissions
(See B.
334; Hale attach-
ment to petition,
p.
5)
and at best the acid collected fails
to drain away properly, interfering with efficiency
(R.
293).
Repairs have somewhat improved the situation, but the company
initially pledged
to buy a new York demister guaranteed
to
restore emission to less than 0.5 pounds per ton
(B. 293-94)
The standard we adopted after considerable testimony,
however,
is
0.15 pounds per ton
(PCB Begs., Ch.
2, Rule 204(f) (2)),
on
the
basis
of
evidence
that
this
reduction
of
a
particularly
dangerous
pollutant
could
be
readily
achieved in both existing
and
new
plants
by
the
use
of
a
Brinks
demister
(see
Opinion
in
4tH 71-23,
supra,
at
p.
38).
At the variance hearing New Jersey Zinc argued that,
although such
a demister would do the trick and was available
at a cost
($200,000 to $300,000)
not in our view greatly in
excess of that the company was prepared to spend
($70,000
-
$80,000)
for the less efficient device
(H.
295,
390)
,
to in-
stall the Brinks
would diminish the effective production
capacity of the plant by 10,
resulting in considerable economic
losses that would make it impossible
to open the plant
(B.
295
-
98,
355-56,
397).
The company made ‘quite clear that it was this
feared loss of capacity, not the capital cost,
low in comparison
5
—
267
—6—
to that of a second absorber as discussed above,
that it found
an unreasonable burden
CR.
409)
The revised petition, submitted after
Dr. Wadden’s suggestion
that the feared capacity loss might be due to the inadequacy
of other plant equipment
to provide sufficient pressure,
commits the company to installing
“a Brinks HE demister,
or
its equivalent, capable of meeting the 0.15 lbs.
of acid mist
per ton standard,” by no later than the December 31,
1973
deadline of the regulation
(Rule 204(h) (3)).
Emissions in
the meantime will be controlled by the existing repaired
demister, and there is no need for a variance from the acid
mist standard because the company will meet it on or before
its date of application.
3.
Startups.
Testimony at the hearings brought out that,
although no request for a more lenient variance during start-
up had been made, the plant could not be expected to conform to
its normal sulfur dioxide emissions of less than 2000 ppm or
26 lb/ton while
starting operation
after
a shutdown of
24 hours or more.
(B.
263).
It was explained that the efficiency
of the converter
is dependent upon the temperature of the
catalyst, and that although efforts were made
to preheat the
catalyst before commencing operation,
“when you reheat,
If
you have been down too long,
the catalyst doesn’t reactivate
and start its proper function quite as good or as quickly
.
.
.
CR.
321).
During Board discussion, Dr. Wadden suggested that
the record failed to show the company had taken all practicable
steps, beyond preheating of the catalyst, to minimize excessive
emissions during startups.
He specifically called attention to
the question of heating the acid in the absorber and maintain-
ing its strength so as to achieve maximum reaction in the
shortest time.
The company’s amended petition addresses itself in con-
siderable detail to the startup problem and commits New Jersey
Zinc to a far—reaching program to reduce startup emissions.
As
in the past,
the company will preheat the sulfur burner and the
cnnverter catalyst before commencing operation,
will begin burn-
ing sulfur at 25
of the design rate,
and will take precautions to
maintain the strength of the acid entering the drying tower.
In addition,
the company with the aid of its consultant
has developed what it terms a unique program to improve the
operation of the absorber during startup.
This plan includes
by-passing acid around the acid coolers
in order to heat the
acid as quickly
as possible; maintaining a high acid strength in
the absorber; and gradually increasing the operating rate, with
normal operation to be achieved within four hours after sulfur
burning begins,
as contrasted with an estimate of twelve hours
given by another company in the rule-making proceeding
(#R 71-23
R.
1596).
Sulfur dioxide emissions
(at a reduced production
rate and therefore a reduced volume of emissions)
will not
exceed 8,000 ppm during the first hour of operation or 4,000
i~pmduring the next three hours.
Startup emissions of acid
5
—
268
—7—
mist,
it is
said, will be substantially reduced in comparison
with past startups because of the absorber procedures proposed.
The Agency recommends approval of the startup plans along
with other elements of the company’s program.
Our regulations recognize,
as we said in the opinion
accompanying their adoption, that “startup conditions may result
in less than optimum emission control.”
In the Matter of Emission
Standards,
supra,
at p.
8.
Rule 105
(PCB Regs., Ch.
2) requires
that normal emission standards be met durthg startup in the
absence of
a showing that this
is impracticable;
the policy of
the Rule,
the opinion said,
is
that “insofar as is practicable,
efforts shall be made to reduce the incidence and duration of
startups and excessive emissions during startup periods.”
The
emission standard was set on the basis of what could reasonably
be achieved during normal operation,
and the Agency in its permit
program may authorize excessive startup emissions shown to be
unavoidable.
We think,
in the spirit of Rule 105, that New
Jersey Zinc has demonstrated that it will do
all that is practicable
to reduce startup emissions.
Because the Agency has power to
approve the emissions in question and has indicated it will do
so,
there is no need for a variance for this purpose.
4.
Neighborhood
Effects.
Perhaps the most serious re-
servation voiced by Board members and staff about the original
variance petition had to do with the danger that operation
under the conditions initially proposed might create substantial
harm to persons in the neighborhood.
Our concern was based in
part upon considerable citizen testimony as to offensive
conditions in the past
CR.
82 et seq.)
and in part upon Agency
predictions that renewed operation would cause high ambient
sulfur dioxide concentrations in downwind portions of DePue.
The company conceded that it had had an especially bad
incident in April of
1969
(B.
176,
186A,
334;
Hale attachment
pp.
5-6), in which significant property damage was done by ex-
cessive emissions of acid mist.
Improved surveillance has pre-
vented recurrence
(id.)
,
and even before the new demister
is
installed the situation will not be as it was during that inci-
dent.
Of greater concern are citizen statements that irritating,
bad-smelling fumes from the acid plant were common during plant
operation
(e.g.,
H.
93-94),
tending to suggest that the plant
during normal operations created nuisance conditions by its
emissions of sulfur dioxide and/or acid mist.
We did not wish
to grant any variance that would permit such conditions
to
continue,
even if the numerical standards were met.
New Jersey Zinc testified that,
although no new control
equipment for sulfur dioxide
is to be installed,
suLfur dioxide
emissions in the past had probably been higher than they
5
—
269
—8—.
should have been because of operating problems
caused by
utilizing zinc smelter gas as feedstock.
Not only,
the
company said,
did smelter gas provide an irregular concentration
of sulfur dioxide at best, but the plant experienced frequent shut-
downs and startups as
a result
of
operating problems.
These difficul~
ties,
we
are
assured,
will
no
longer
exist
if
the
plant
is
reopened,
for smelter gas is not to be used
(H.
260-66)
.
Moreover,
some
of the problem in the past may have been due to particulate or
other emissions from the zinc smelter itself, which will not
be reopened
CR.
30).
We find
this somewhat reassuring, but only experience
will reveal whether the switch from smelter gas will eliminate
nuisance conditions.
We do not interpret the petition as
seeking permission to create an active nuisance, and if i~
did we would not he readily disposed to grant it,
especially since equipment to reduce sulfur dioxide emissions
considerably is concededly available.
The Agency is required
to consider whether or not operation will cause statutory air
pollution before granting any permit.
See EPA v. Southern
Illinois Asphalt Co.,
# 71—31
(June
9,
1971).
In the present
case the Agency has voiced its approval of renewed operation.
Since there
is no request for a variance to allow a nuisance,
and since the Agency has indicated it has no present objec-
tion to allowing the plant to operate, there is no controversy
now before us as to whether operation will violate the air
pollution prohibition and no need to consider granting a
variance from that provision.
If serious harm results, as
neither party expects, further proceedings may be instituted.
The Agency, utilizing standard dispersion equations, pre-
dicted emissions, measured wind information from Illinois stations,
and
an effective stack height determined
on a standard basis,
calculated that ambient concentrations of sulfur dioxide
attributable to the DePue acid plant would exceed 365 micrograms
per cubic meter
(ug/m3)
(0.14 ppm) atthe worst point 58.3
of the time
(see generally
B.
452—509, especially 497)
365 ug/rn3 is the federal air-quality standard for a 24-hour
period, which for health reasons
is not to be exceeded more
than one day per year
(H.
466)
.
The Agency’s calculations
cannot be directly compared with this standard,
since it is
not clear that the high concentrations predicted,
despite
their frequency, will persist in any one place long enough
to cause a 24-hour average of
365 ug/m3.
But it was this
sort of evidence, including estimates that under certain con-
ditions concentrations could reach as high as
5893 ug/m
CR.
499-500) and that the regulation level (1048
ug/m3 or
0.4 ppm) whose persistence for four hours can give rise
5
—
270
—9—
to an emergency alert could be expected 4.8
of the time at one
point
(R.
507-08), that led Board members to suggest the need
for proof by New Jersey Zinc, which as petitioner carries the
burden of proving that a variance would not unreasonably harm
the public,
that its operations would not in fact cause
serious violations of health-related air—quality standards.1
New Jersey Zinc respondedby disputing the Agency’s calcu-
lations,2 maintaining that normal operations would seldom cause
violations of air quality standards,
and agreeing
to an episode
control plan,
as suggested by the Agency, designed to assure that
plant operations will be curtailed whenever that is necessary to
prevent dangerous concentrations of sulfur dioxide
(see State-
ment of Further Evidence and Offer of Proof; First Amendment to
Petition)
.
The company agrees to monitor weather conditions
continuously;
to maintain two
instrunients
to monitor ambient
sulfur dioxide concentrations continuously; and to submit sampling
data to the Agency weekly.
The appropriate location of the
sensors is of course crucial,
and the company agrees that the Agency
must approve their siting.
Moreover,
this program in no way
disables the Agency from doing its own monitoring or from in-
specting
to be sure the company’s monitors are operating properly.
The Agency has an obligation to do so, because the important
business of ascertaining whether excessive levels are reached
cannot be left entirely to
the company.
If either instrument
yields
a reading of 0.14 ppm
(the level which if persisting
for
24 hours would violate the federal health standard),
the
company will prepare for a possible production cutback.
If
the 0.14 level persists as an arithmetic average for four
hours, production must be reduced in accord with
a stated for-
mula unless the Agency directs otherwise.
The basis for the formula is not spelled out, but by
plugging in illustrative ambient concentrations we can observe
the effects of its implementation.
There is a term permitting
1.
The Agency’s ‘~iitnesstestified that his calculations ignored
the possible effects
of fumigation or downwash and the
fact that winds
in the river valley at DePue were less
favorable than the Peoria values used in his calculations.
All these factors, he said, meant that actual conditions were
likely to be even worse than he had calculated
(R.
502—05)
2.
Although the company acknowledged that the long-term average
SO2 concentration at a nearby Agency monitor had been 0.05
ppm, which exceeds the federal annual primary standard of
0.03,
it contended that without the sinter plant of the zinc
smelter, which will not be operated,
levels would “approach”
the federal standard
(Hale attachment,
pp. 10—11).
No
mention is made of the secondary standard, which must also
be met.
5
—
271
—10—
smaller cutbacks to be made to the extent that other sources
are responsible for ambient levels,3 which is quite rea-
sonable so long as those sources are in a position to effect
reductions of their own.
Assuming that the acid plant is the
only significant source, however, the formula is as follows:
(Ambient air
-
.
14)
Production Cutback from
.30
full capacity.
If
the ambient concentrations Is
.24 ppm,
the percentage of
cutback will be
.10/.30,
or one third;
if we assume a straight-
line relationship between continuing emissions and ambient
concentrations,
the
.24
concentration
would
be
reduced
to
.16
if weather conditions remained the same.
Similarly,
if
the
ambient
concentration
is
.34,
the cutback is
.20/.30 or
two thirds, reducing atmospheric s02 on the above assumption
to
.11.
If
ambient
is
.44,
the
cutback
is
.30/.30,
is
complete
shutdown.
The
assumed
relationship
between
emissions
and
ambient
levels
is
no
doubt
an
oversimplification,
but
it tends tosuggest
that
the
formula
seeks
to
prevent ambient evels
from
ever
significantly
exceeding
the
level
of
0.14
ppm,
which
is
the
federal
24—hour
standard.
The
formula
does
not
require
any
reduction
in
emissions
so
long
as
the
ambient
level
is
at
0.14
ppm.
This
means
the
formula
does
not
force
the
company
ever
to
take
action
even
if
the federal standard is actually violated
by
the
persistence of this level for two full days or longer.
But
acceptance
of
the
present formula to deal with what may be
the
bulk
of
the problem situations does not deprive the Agency
of
tools
with
which
to
compel
abatement of health dangers in
other
cases.
Should
the
.14
level
be
barely
exceeded
for
periods
exceeding
24
hours,
so
that
no
action
is
required
under
the
formula,
or
should
the
maintenance
of
the
annual
air-
quality standards be threatened,
the
Agency
could
proceed
under
the regulation forbidding emissions that cause violations of
the air quality standards or under the statutory prohibition
of air pollution,
invoking summary remedies if necessary to pro-
tect the public health.
PCB Regs., Ch.
2 Rule 102; Environ-
mental Protection Act, sections 9(a),
34.
The art of
episode control is not yet a science; we find the formula to
which New Jersey Zinc has agreed a significant
positive step
toward assuring that the company can and will operate without
causing
a danger to the public health.
We need not in evaluating this episode plan find that the
Agency’s predictions as to the frequency or severity of high
sulfur dioxide levels are right or wrong.
What governs is that
3.
The complete formula
is
(Ambient Air
-
.14)
C
Ambient Air
Production
.30
X Attributable to
=
Cutback from
Petitioner)
Full Capacity
5
—
272
—11—
the company has committed itself to cut back production when-
ever necessary
to keep dangerous concentrations from persisting
long enough to cause trouble.
If the ~irnpanyis right that
high concentrations and consequent cutbacks will be infrequent,
so much the better for everyone;
if high concentrations are more
frequent,
the
company
will
take
action
to
prevent
serious
harm.
Either
way
the
public
should
be
given
reasonable
protection.
We believe the pre~éntprogram goes
a long way toward assuring such
protection
at
at
the
same
time
permits
the
resumption
of
operations, with all the attendant benefits for the entire
community in terms of jobs and business, which were emphasized
by
witnesses
representing
the
Village,
the
School
District,
and the
Steelworkers’ Union
CR. 46—59,
143-50)
The Agency is required to approve episode control plans
in
passing
upon
permit
applications.
The
Agency
states
that
it
is
prepared
to
permit
operation
on
the
basis
of
the
present
episode program; we do not read the petition as asking permission
to
deviate
from
other
requirements
of
the
episode
regulations
or to bring about violations
of the air-quality standards;
there is
thus no controversy before us requiring us
to grant or
deny any variance with respect to the program.
We add a word of caution.
That the plant will comply with
our numerical emission limits by the date they become effective
we think has been
amply shown.
The most serious aspect of
the matter,
however,
is whether under the peculiar circumstances
of this case a bare compliance with emission standards of general
applicability will suffice to prevent significant harm to other
persons.
The overriding requirements,
as we made clear in our
opinion adopting the emission standards, are that no unreason-
able interference with others be caused and that the air quality
standards
not
be
violated.
Emission
standards
represent
what
we think everyone in the State should do as a matter of good
practice
to
reduce
emissions.
In
many,
perhaps
in
most
cases
that
will
be
enough
to
achieve
satisfactory
air
quality;
but
“under
special
circumstances
of
geography,
meteorology,
or configuration, emissions meeting the standards may cause
a
nuisance,
and
that
the
statute
flatly
forbids.
.
Compliance
with
the
emission
standards
is
a
minimum;
it
is
essential
that
whatever
measures
are
necessary,
subject
to proof regarding economic reasonableness in the particular
case, be taken to assure that the air quality standards
are met.
.
.
.
Enforcement action may be undertaken against
an emission source even if it is in compliance with numerical
emission standards,
if such compliance is insufficient to
assure that the air is of satisfactory quality.”
5—
7
That
is the meaning of the statutory provision
that
compliance
with
Board
reculations is
only
a “prima facie” defense.
ifl
the
Matter of Emission Standards,
4tH 71-23,
pp. 4-5
(April 13,
1972), and cases cited.
The significance of these principles
in the present case
is as follows.
There has been significant pollution in the
past,
and the basic
source of
sulfur dioxide emissions will not
be further controlled,
The acid plant
is located in
a river
valley, where dispersion of contaminants
is often less effective
than
elsewhere
(H.
502)
.
Residential areas not
far
away are
at
higher
elevations, reducing
the
effective stack height
(B.
461)
.
The Agencyt s expert witness summarized
the matter
by
observing
that
Actually,
each
thing
that
I
have
looked
at
as
far
as
the location related
to
meteorology,
it almost
appears
that the DePue plant was picked to be in the worst possible
spot.
(r~.
506~
.
This is not meant to suggest any bad faith;
nobody
is oresumed to pollute out of sheer malice.
What it does suggest
is
that measures that are adequate for similar plants elsewhere
may be insufficient to prevent pollution under
the
specific
facts oi
this case.
It is for that reason thatthe episode plan
was developed,
and it
is our hope that this plan will permit
operation of the plant with the improvements proposed with-
out serious air pollution.
We urge both the Agency and the
company
to watch the situation closely to make sure this is what
actually occurs.
If frequent pollution results, there will have
to be frequent cutbacks of production;
at some point it may be
necessary once again to face the question of adding a second
absorption unit to reduce sulfur dioxide emissions or of abandon-
ing the operation.
We view our action today as permitting
a
final opportunity for the company to demonstrate that it can
operate enough hours without pollution to justify not making the
additional expenditures.
For the technology to reduce emissions
further
is
concededly available;
we will not hesitate to re-
quire it if it becomes clear that is is necessary to prevent
serious pollution.
In summary, we view this case as a success story in pre-
venting pollution before it begins, and a confirmation of the
value of a permit system.
As a result of Agency scrutiny
prior
to
opening
the
plant,
of careful Agency evidence as to
the predictable adverse effects of proceeding according to
the
company’s original plan, and of imaginative and thorough
evaluation of the record as to abatement practicability by
our
staff
engineer,
the
company
has
found
it
reasonable
to
install an improved demister making it unnecessary to exceed
5
—
274
—13—
the sulfuric acid standard;
it has developed an improved
plan
to
control
emissions
during
startup;
and
it
has
committed
itself to an episode plan that it believes will enable it
to operate without causing
air
pollution.
These
improve-
ments have made it unnecessary for us to grant a variance,
as there is no request before us for permission to violate
any law or standard.
The petition for variance is there-
fore moot,
and it is hereby dismissed.
I, Christan Moffett, Clerk of the Pollution Control Board4,
certify that the Board adopted the
bove Opinion this~9
“
day of August,
1972, by a vote of
-
5
—
275