ILLINOIS POLLUTION CONTROL BOARD
    July 8, 1998
    IN THE MATTER OF:
    PETITION OF CITY OF SALEM FOR AN
    ADJUSTED STANDARD FROM 35 ILL.
    ADM. CODE PART 814, SUBPART D.
    )
    )
    )
    )
    )
    AS 98-2
    (Adjusted Standard - Land)
    OPINION AND ORDER OF THE BOARD (by M. McFawn):
    Before the Board is a petition for an adjusted standard filed by the city of Salem,
    Illinois (Salem). Salem operates its “Existing Landfill #2” in Marion County, Illinois.
    Pursuant to Board regulations at 35 Ill. Adm. Code 814.Subpart D and permits issued by the
    Illinois Environmental Protection Agency (Agency), Salem’s landfill was required to close by
    September 18, 1997. Salem petitioned for this adjusted standard so it may continue to operate
    the southern unit of its landfill until either September 18, 1998, or the date when a new
    (northern) unit of the landfill under construction is completed, whichever is sooner.
    The Board finds that Salem has not satisfied the statutory requirements necessary for
    the Board to grant Salem the adjusted standard it seeks. Accordingly, for reasons more fully
    set forth below, the Board denies the petition.
    PROCEDURAL HISTORY
    Salem filed its original petition for an adjusted standard with the Board on September
    12, 1997. The Agency filed its response to the original petition on May 18, 1998,
    1
    recommending that the adjusted standard be granted with certain conditions. On June 3, 1998,
    Salem filed an amended petition, in which it adopted most of the conditions suggested by the
    Agency. Also on June 3, Salem filed a “Revised Groundwater Non-Degradation
    Demonstration” (Demonstration) which it had filed previously with the Agency. The Agency
    and Salem had agreed that this document should be filed with the Board and made part of the
    record in this proceeding. Amended Petition at 4. On July 6, 1998, the Agency filed its
    response to the amended petition, recommending that the adjusted standard be granted but with
    all the previously recommended conditions, including two not adopted by Salem in its
    amended petition.
    Salem waived a hearing in its amended petition. Amended Petition at 9. On
    September 17, 1997, notice of Salem’s original petition was published in the
    Salem Times-
    Commoner
    , a newspaper of general circulation in the area around the landfill. The notice
    informed interested persons that any person could request a hearing within 21 days after
    1
    Under 35 Ill. Adm. Code 106.714(a), the Agency’s recommendation was due within 30 days
    of the filing of the petition; however, the hearing officer extended this date several times to
    facilitate negotiations between Salem and the Agency.

    2
    publication. No hearing was requested. On June 5, notice of Salem’s amended petition was
    published in the
    Salem Times-Commoner
    , again informing interested persons that a hearing
    could be requested within 21 days. Again, no hearing was requested. Consequently, no
    hearing was held.
    STATUTORY AND REGULATORY FRAMEWORK
    Section 28.1(a) of the Act (415 ILCS 5/28.1(a) (1996)) provides that the Board may
    grant adjusted standards from rules of general applicability. To obtain an adjusted standard, a
    petitioner must show that four criteria are met. The criteria are listed in Section 28.1(c) of the
    Act (415 ILCS 5/28.1(c) (1996)), which provides:
    c.
    If a regulation of general applicability does not specify a
    level of justification required of a petitioner to qualify for
    an adjusted standard, the Board may grant individual
    adjusted standards whenever the Board determines, upon
    adequate proof by petitioner, that:
    1.
    factors relating to that petitioner are substantially
    and significantly different from the factors relied
    upon by the Board in adopting the general
    regulation applicable to that petitioner;
    2.
    the existence of those factors justifies an adjusted
    standard;
    3.
    the requested adjusted standard will not result in
    environmental or health effects substantially and
    significantly more adverse than the effects
    considered by the Board in adopting the rule of
    general applicability; and
    4.
    the adjusted standard is consistent with any
    applicable federal law.
    The regulations relevant to Salem’s adjusted standard petition are those applicable to non-
    hazardous waste landfills. They do not specify a level of justification required to qualify for
    an adjusted standard. Therefore, the foregoing statutory criteria are applicable in this case.
    In 1990 the Board promulgated modified design and operating standards applicable to
    new and existing non-hazardous waste landfills. In the Matter of: Development, Operation
    and Reporting Requirements for Non-Hazardous Waste Landfills (August 17, 1990), R88-7.
    The regulation pertinent in this matter is the requirement that certain landfills in existence as of
    the effective date of the regulations (September 18, 1990) either close or comply with
    progressively more stringent operating and closure requirements. If the landfill chose to not

    3
    comply with the more stringent requirements, closure must have begun within two years,
    i.e
    .,
    by September 18, 1992. However, if the landfill chose to comply with the more stringent
    operating and closure requirements, there were two options. Landfills that intended to remain
    open after September 18, 1997 were required to meet the most stringent design and operating
    requirements. These requirements are found at 35 Ill. Adm. Code 814.Subpart C, and hence
    landfills subject to these requirements are commonly known as Subpart C landfills.
    2
    The
    second option was to remain open after September 1992 and close no later than September 18,
    1997. In that case, the landfills were required to meet less stringent design and operating
    requirements and are commonly known as Subpart D landfills, in recognition the applicable
    closure requirements found at 35 Ill. Adm. Code 814.Subpart D.
    3
    NATURE OF THE FACILITY
    4
    Salem’s “Existing Landfill #2” is a municipal solid waste and non-hazardous special
    waste landfill located in Salem, Illinois. The city’s Public Works Director serves as the
    landfill’s certified operator. The landfill consists of a southern unit of approximately 11 acres
    (subject to Subpart D, as explained below) and a northern (undeveloped) unit of approximately
    10-11 acres (subject to Subpart C, as explained below.) Salem owns and operates the landfill
    as part of the ongoing municipal services provided to its residents and the community. Salem
    also provides residential waste collection as part of the city’s municipal services. The landfill
    is run by the city’s Sanitation Department. Operations are funded through a combination of
    property taxes, payments or assessments from residents, and tipping fees.
    Salem collects or generates approximately 8,000 cubic yards of waste annually from its
    residential waste collection program. Residential waste collected from the city has historically
    made up approximately 15% of the total waste disposed at the landfill. Until 1995, the landfill
    also accepted business and industrial waste which provided major financial support for the
    landfill’s operations. In 1995, Salem imposed air space conservation measures to insure that
    landfill capacity would be available for the residential collection program pending issuance of a
    significant modification permit (SMP). This appears to have involved suspending waste
    receipts from industries and businesses. Salem states that it resumed receiving waste from
    these customers in mid-July, 1997 after receiving its SMP on June 2, 1997. Consequently,
    2
    Subpart C is titled “Standards for Existing Units Accepting Chemical or Putrescible Wastes
    That May Remain Open For More Than Seven Years.” Subpart C consists of just two
    sections, Sections 814.301 and 814.302. Section 814.301 sets out the scope and applicability
    of Subpart C, and Section 814.302 prescribes the operation and closure standards that apply to
    Subpart C landfills.
    3
    Subpart D is titled “Standards for Existing Units Accepting Chemical or Putrescible Wastes
    That Must Initiate Closure Within Seven Years.” Subpart D consists of just two sections,
    Sections 814.401 and 814.402. Section 814.401 sets out the scope and applicability of Subpart
    D, and Section 814.402 prescribes the operation and closure standards that apply to Subpart D
    landfills.
    4
    Facts set forth in this section are drawn from Salem’s petition, pp. 4-10 and Exh. A.

    4
    there is capacity remaining in the landfill to accommodate municipal waste from the city until
    the northern unit is completed.
    Salem filed its first SMP application with the Agency on September 16, 1994.
    According to the Agency, Salem notified it that the existing landfill (one unit at the time)
    would be complying with the Subpart C regulations. This application was deemed incomplete
    by the Agency and a subsequent application filed on May 15, 1995, was kept pending per
    Salem’s request. After a series of additional filings, Salem changed its option, filing an
    addendum to the pending permit application on December 20, 1995, wherein it proposed
    closing part of the landfill as a separate Subpart D unit and making the undeveloped and
    expanded portion of the landfill a Subpart C unit.
    5
    This change meant that the existing portion
    of the landfill (known as the southern unit) would be required to close no later than September
    18, 1997.
    After many more rounds of information requests and submissions, the Agency issued
    the SMP to Salem on June 2, 1997. Salem is now in the process of developing the northern
    (Subpart C) unit of the landfill. When operational, the northern unit of the landfill will serve
    the city’s waste disposal needs currently served by the southern unit. According to Salem,
    developing the northern unit of the landfill is projected to take approximately one year, which
    would mean the landfill would be operational sometime in the latter part of 1998.
    ANALYSIS
    Are Petitioner’s Factors Substantially and Significantly Different Factors?
    Salem identifies two factors which it contends are significantly different and were not
    considered when the regulations of general applicability (Subpart D) were adopted: (1) the
    length of time required to obtain its SMP to develop the northern unit of the landfill, and (2)
    the adverse effects of landfill closure in southern Illinois (an area with few landfills). Pet. at
    9, 20. Based upon the following analysis, the Board finds neither of these two factors
    presented by Salem to be “substantially and significantly different” than those factors
    considered when the rules in Subpart D were adopted.
    Concerning the first factor, the Agency responded to Salem’s claim that the length of
    the permitting differentiates it significantly from what the Board considered in adopting the
    rules of general applicability. The Agency “rejects any implication that the State is
    responsible for the 33-month period during which Salem’s sig-mod permit application was
    under review[.]” The Agency points out that it has ninety days to act upon permit applications
    or the permit is deemed issued by operation of law. (See Section 39(a) of the Act (415 ILCS
    5/39(a) (1996)). Response at 2. Salem responded that no such inference was intended.
    Amended Pet. at 3. The Agency did not respond the other factor cited by Salem.
    5
    This information is found in the recommendation filed by the Agency in connection with the
    variance petition filed by Salem on July 2, 1998, and decided concurrently, Salem v. IEPA,
    PCB 98-1 (July 8, 1998).

    5
    We agree with the Agency that the length of time it took for Salem to obtain its sig-
    mod permit does not distinguish it from the factors considered by the Board when it adopted
    the seven year timeframe for closing or upgrading those landfills that do not satisfy the Subpart
    C requirements. By adopting that phased in approach, the Board factored in that alternative
    disposal methods and/or locations would be needed to replace the landfills which closed. This
    seven year scheme was included in the initial rulemaking proposal developed to revise the rules
    for non-hazardous landfills, In the Matter of: Permit Requirement for Owners and Operators
    of Class I and Class II Landfills and for Generators and Haulers of Special Waste, R84-17.
    That rulemaking was the predecessor to the R88-7 rulemaking within which the seven year
    transition period was ultimately adopted. Throughout the course of those two rulemakings, no
    one contested that timeframe as applied to municipal landfills.
    To further ensure that the transition would be accomplished within this timeframe, the
    Board adopted a rule which required the existing landfills to decide and notify the Agency
    within the first six months of the transition period,
    i.e
    ., by March 18, 1991, whether they
    would close by 1992, close as a Subpart D landfill no later than September 18, 1997, or
    upgrade to Subpart C standards and remain open indefinitely. The Board also anticipated that
    the SMP permitting process might in many instances be lengthy. Therefore, the Board
    allowed SMP applications to be filed anytime, but required that they be filed no later than
    September 18, 1994, which is three years before closure must be initiated. Once Salem
    decided to close the southern unit as a Subpart D landfill, it knew it was subject to these time
    constraints and that closure at the southern unit must be initiated no later than September 18,
    1997.
    Salem has not identified any factor that makes it significantly or substantially different
    from what the Board considered in the R88-7 rulemaking. Salem has only demonstrated that
    obtaining the SMP necessary for the southern unit to remain open until September 18, 1997
    took longer than it anticipated According to the list set forth in the SMP ultimately issued,
    Salem submitted the SMP application on September 16, 1994, just two days prior to the last
    possible date for it to be filed. That application was deemed incomplete in October, 1994. A
    second application was filed in May, 1995, with additional information submitted seven times,
    up to and including the addendum filed December 20, 1995 (discussed above) wherein Salem
    clarified that the southern unit would be closed as a Subpart D unit.
    6
    Thereafter, Salem
    submitted five more documents containing additional information, the last submitted on
    January 27, 1997. Pet. Ex. A at 1-2. This list well documents a lengthy permitting process.
    Salem did not provide any explanation about why this permitting process was so
    lengthy. Salem only explained that the SMP was issued too late for it to develop the northern
    unit before September 18, 1997. Yet, the portion of the SMP relevant to this petition is that
    involving the southern unit. The availability and cost of replacing the closed Subpart D
    landfills was a factor considered by the Board in the R88-7 rulemaking. Whether the northern
    unit was available to replace the southern unit on September 18, 1997, is not relevant. The
    6
      
    Id
    .

    6
    rulemaking anticipated that all waste going to landfills subject to that closure date would have
    to be redirected. Again, for that very reason the transition period provided was seven years
    long.
    The Board notes that it has considered other petitions for adjusted standards requesting
    an extension of the September 18, 1997, closure date. In addition to Salem’s petition, the
    Board has considered petitions from Carus Chemical Company, AS 98-1 (September 18, 1997)
    and Waste Professionals, Inc., d/b/a Pekin Landifill, AS 97-10 (February 19, 1998). Among
    other reasons, the Board granted those petitions because each petitioner demonstrated that the
    Subpart D units in question were in substantial compliance with the Subpart C requirements.
    Unlike Salem, their respective needs for an extension were not premised on the length of the
    SMP process.
    As its second justification, Salem argued that the Board did not consider the amount of
    landfill space available in southern Illinois when it adopted the relevant regulations. The R88-
    7 rulemaking was a statewide regulation. The Board considered the effect of the regulations
    and specifically the permit application dates and closure dates for Subpart D landfills when it
    adopted the same. The purpose of phasing out existing landfills on a two year and seven year
    basis was to provide time for retrofitting existing landfills and providing new landfill space.
    However, at the time the landfill rules were adopted, the Board had no knowledge whether all
    landfills would close in two years, all would upgrade to Subpart C requirements, or some
    middle course would be taken. Thus, remaining landfill capacity in some part of the state at
    some time in the future cannot be considered a significant factor in development of the landfill
    regulations.
    Do Petitioner’s Factors Justify the Adjusted Standard?
    Even if the factors cited by Salem are different than those considered when the rules
    under Subpart D were adopted, they do not justify an adjusted standard for Salem. In a
    companion case, PCB 98-1 (a variance petition seeking essentially the same relief as this
    adjusted standard petition), the Board has found that the delay in issuance of Salem’s SMP was
    due more to Salem’s failure to timely submit the necessary applications and information to the
    Agency, than time necessary for review of that information. Thus, the problem facing Salem
    now is of its own making. Furthermore, landfill capacity (or lack thereof) in southern Illinois
    will not be significantly affected by the disposition of this adjusted standard petition, because
    (as the petition states on page 8) Salem’s landfill has the least remaining capacity of any
    municipal solid waste landfill in the region, and any impact from closure of the southern unit
    of Salem’s landfill will be offset in the long run by development of the northern unit.
    Are the Environmental or Health Effects Substantial or Significant?
    The Agency is “satisfied that the adjusted standard requested in the Petition should not
    adversely impact the environment,” based on the relatively small volume of waste to be
    accepted and the Demonstration submitted by Salem. Res. at 4, 5. The Demonstration
    includes a contingency plan to minimize the potential impact on groundwater. The Agency

    7
    qualifies its position by requesting a number of conditions on the adjusted standard to facilitate
    implementation of the contingency plan.
    Is the Adjusted Standard Consistent with Federal Law?
    There are no issues of federal law raised by this adjusted standard petition.
    CONCLUSION
    The Board finds that Salem has not established that factors relating to it are
    substantially and significantly different from those factors considered by the Board in R88-7.
    Furthermore, if such factors exist they do not justify the grant of an adjusted standard.
    Consequently Salem has not met its burden under Section 28.1(c)(1) or (2) of the Act. The
    petition is therefore denied.
    This opinion constitutes the Board’s findings of fact and conclusions of law in this
    matter.
    ORDER
    Salem’s petition for an adjusted standard from 35 Ill. Adm. Code Subpart D, most
    specifically Section 814.401(a), for the southern unit of its Existing Landfill #2 is denied.
    IT IS SO ORDERED.
    Section 41 of the Environmental Protection Act (415 ILCS 5/41 (1996)) provides for
    the appeal of final Board orders to the Illinois Appellate Court within 35 days of service of this
    order. Illinois Supreme Court Rule 335 establishes such filing requirements. See 145 Ill. 2d
    R. 335; see also 35 Ill. Adm. Code 101.246, Motions for Reconsideration.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above opinion and order was adopted on the 8th day of July 1998, by a vote of 5-0.
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board

    Back to top