ILLINOIS POLLUTION CONTROL BOARD
January 31, 1972
NORTH
SHORE
SANITARY DISTRICT
V.
)
PCB 71—343
ENVIRONMENTAL PROTECTION AGENCY
Mr. Murray
R. Conzelman and Mr. John R. Sloan appeared for the
North Shore Sanitary District
Mr. Richard Cosby and Mr. Thomas W. Scheuneman appeared for the
Environmental Protection Agency
Mr. Richard H. Kates appeared for the League of Women Voters
OPINION OF THE BOARD ~by Mr. Richard J. Kissel):
On November 2, 1971, the North Shore Sanitary District
(~‘District”) sought a variance from the Pollution Control Board
(“Board”) with regard to Paragraph 7 of the Board order in the
case of League of Women Voters, et al
v.
North Shore Sanitary
District, PCB 70-7, 12, 13 and 14. Paragraph 7 of that order
adopted by the Board March 31, 1971, provided as follows:
“The District shall not permit any additions
to present sewer connections, or new sewer connec-
tions, to its facilities until the District can
demonstrate to the Board that it can adequately
treat the wastes from those new sources so as not
to violate the Environmental Protection Act, or
the Rules and Regulations promulgated thereunder.”
The March 31 order also provided that the District was to use
all statutory powers available to raise funds.
The District’s variance petition alleged that its research
and investigation showed it could increase its capacity on an
interim basis at the Waukegan and Clavey Road plants. Through the
use of chemical additives at Waukegan, the District anticipates
that it can increase its capacity by 17,000 population equivalents
(P.E.). Relying on chemical additives and the new 18 mgd effluent
lagoon at Clavey, the District looks for a 10,000 P.E. effective
increase in capacity. The District then asks that the Board
3
561
allow connections to these two plants in an amount not to exceed
80 of the population equivalents made available. Upon receipt
of the variance, the District agreed to enact a connection fee
ordinance. The variance petition further alleged that the
existence of a sewer ban does and would continue to impose a
severe economic hardship within the limits of the District.
in its recommendation, the Agency asked that the District’s
petition be denied. The Agency questioned whether the District was
suffering the hardship required by the Act for the granting of a
variance. It pointed out that the hardship was actually upon those
prohibited from building due to the sewer ban. If the variance
were granted, the Agency indicated that it should not extend to
those areas served by sewers where overflows and surcharging are
presently occurring. The Agency agreed that if the District were
meeting the requirements of SWB-14 at Clavey Road and 3~B-7at
Waukegan by discharging an effluent of 20 mg/l of BOD5 and 25 mg/l
of suspended solids, it would have no objection to the grant of a
variance.
Upon the receipt of the petition, the Board entered a prelim-
inary order in this case. This order, dated November 23, 1971, direc-
ted that the League of Women Voters (the “League”) be joined as a
party to the variance proceedings, since the League was the party
that instituted the original enforcement proceedings, and directed
that the subject of screening at Water Street be made a matter for
the hearings in the instant case. The latter was added because
the Board’s implementation order in previous proceedings, dated
June 23, 1971, directed the District to undertake a study of the
economic and technical feasibility of the use of screening devices
at the Water Street sewer discharge. Further, the Board directed
that the hearings discuss the problem of bacterial and other con-
tamination from combined sewer overflows and plant bypasses. This
preliminary order of the Board thus expressly included within the
scope of the hearings the subject of bacterial discharges to Lake
Michigan, as well as the consideration of BOD5 and suspended
solids to which the District’s petition had addressed itself.
The League also responded to the variance petition and indi-
cated that it had no opposition provided several conditions were
met. Among such conditions, the League asked that financing be
assured before sewers were permitted to hook up, that no hookups
occur until the new additions which the District proposes to
install were in operation, that no additional b~.cterialharm be
created with the new hookups, that air pollution control at Clavey
continue, that the District show that it is in compliance with the
3
—
542
March 31 order of the Board, that building be restricted in those
areas of the District where sewers are shown to be inadequate,
that a manner of allotting hookups be indicated, and that there
be a limit on the number of hookups so that if the chemical
additives do not adequately perform further hookups be prohitibed.
BASIS OF PARAGRAPH SEVEN)
In order to understand the Paragraph from the March 31 order
from which the District seeks a variance, it is helpful to examine
the original Board opinion in the case of League of Women Voters,
et al v. North Shore Sanitary District, PCB 70-7, 12, 13 and 14.
The testimony received in that case established that each of the
District plants, with the exception of the Ravine Drive Plant,
had far exceeded its capacity, and therefore was incapable of
treating the sewage each received even to the degree for which the
plant was desiqned. (See page 4 of the opinion, March 31, 1971).
That opinion also detailed the deleterious effect which the over-
loading of the lakefront plants had upon the Lake, (See opinion,
pages 4-7). In order to avoid adding additional sewage to already
overloaded plants where it would receive little or no treatment,
the Board ordered the imposition of a sewer ban. This ban affected
not only extensions to existing sewer lines, but also individual
hookups to existing sewer lines. The Board found such an order
“imperative” in order to avoid the continuing threat of increased
water pollution and serve the purposes of the Envirqnmental Pro-
tection Act. (See opinion, page 16). The March 31 opinion also
pointed out sevgral alternatives were available to aid in alleviat—
ing
effects of the ban and cited that method which the District
proposes herein, the addition of chemical coagulants to
increase
the effective capacity of existing secondary plants. (Opinion, p.l7).
THE CLAVEY ROAD PLANT)
The Clavey Road plant provides primary and secondary treat-
ment
of all wastes through the use of an activated sludge process.
(R. 61) Since the imposition of the March 31 order, the District
has attempted to abate air pollution from the Clavey site by the
addition of sodium hypochiorite into the sewer about 3 miles upstream
from the Clavey plant and at the influent chamber to the plant itself.
In the District’s judgment, such a program has been very successful
in inhibiting the decomposition of the sewage and thereby aidii~ig in
alleviating the air pollution problem. (R.
62)
Two other facili-
ties have also been added to Clavey in 1971. The District com-
pleted its chlorination facilities and can now provide for pre-
chlorination ahead of the plant. (R. 63) In conjunction with this
3
—~543
variance application, the District also conducted a study to
determine the effect on the plant effluent of adding chemicals
and polymers and of using the new l8-mgd effluent lagoon at
Clavey. (R. 66) A plant scale test indicated that a dosage of
alum at 20 mg/i ahead of the final settling tanks would result
in obtaining an effluent with approximately 14 mg/i of both
BOD5 and suspended solids, (R. 66-67, 106) The District’s
studies determined that the addition of chemicals and polymers
would have about the same effect
on
the effluent as the use of
the new effluent lagoon. The chemicals, however, when used in
conjunction with the effluent lagoon would assure that the pro-
jected results are attained and would mean an additional improve-
ment of about 10 or 15 over what would be achieved by the efflu-
ent lagoon alone. (R. 67) The cost of installing the polymers
and chemical feed system at Clavey would approximate $75,000;
to operate that system throughout the year would cost about
$140,000, including an amount for additional sludge removal.
(R. 68) The District does not believe that it would be necessary,
however, to operate using the chemicals and polymers throughout
the year. (R. 223) It would be possible to obtain the same
degree of assurance at Clavey by using the facilities only inter-
mittently. Such use could lower the operating costs to about
$lO-20,000 annually. (R. 257, 259) In any case, however, after
July 1, 1972, the District will not be meeting the SWB-l4 effluent
criteria of 4 mg/i BOD5 and 5 mg/i suspended solids effective
after July 1, 1972.
THE WAUKEGAN PLANT
The flow from the Waukegan plant discharges to Lake Michigan.
The Waukegan plant is capable of giving secondary treatment to
approximately 8-12 mgd, the remainder receiving primary treatment
and chlorination. (R. 145) Over the past year, the Waukegan
plant has operated on an average of just under 14 mgd. (R. 111)
At present, the District is adding ferric chloride at Waukegan
ahead of the primary tanks. (R. 219) The District has polymer
feed equipment on order and it should be installed within three
months. The District then contemplates adding chemicals and poly-
mers ahead of
the final tankds in addition to the present ferric
chloride
being added ahead of the primary tanks. (R. 220) The
District believes that such additions before the final tanks will
permit improved removal efficiency fo~that portion of the flow
which receives secondary treatment. It also means that a
larger proportion of the flow can pass through the secondary
~ The League questioned whether the District should employ
cationic rather than anionic polymers in order to obtain a higher
degree of treatment. The District shall study whether such in-
creased efficiency is attained and report to the Board and the
Agency on the type of polymers it has instalie~.and why.
3
— 544
treatment facilities. (R. 220) The capital cost of such chemi-
cal and polymer feed equipment is about $5-iO,000 and could be
installed by District personnel in approximately three months.
(R. 221) The annual operating cost would approximate $50,000.
(R. 221) The District has not conducted any plant scale tests
at Waukegan, as was done at Clavey. With the present use of
ferric chloride, the Waukegan plant is obtaining approximately
30 mg/i of BOD5 and suspended solids on a total effluent average.
(H. 114) After adding the chemical feed and polymer system and
taking on new loadings, the District’s chief engineer indicated
that the final concentration in the effluent would remain in
basically the same 30—35 mg/l range. (R. 146-7) The present
SWB-7 standard for the Waukegan plant provides for an effluent
of 20 mg/i BOD5 and 25 mg/i of suspended solids.
EFFECT OF CHEMICAL TREATMENT
The quality of treatment afforded by the effluent lagoons
and the increased chitrination at Clavey have had the effect of
removing from the effluent the organic raw equivalent of a popu-
lation equivalent of about 10,500 people. CR. 107) The District
projects that an addition of 80 of the increased loading capa-
bility, or approximately 8000 P.E., will still result in the
Clavey Road plant meeting the applicable state standards. With
the use of the ferric chloride chemical feed system at Waukegan,
the District has been able to obtain a BOD5 and suspended solids
reduction of approximately 24,000 P.E. The District’s variance
petition, however, only seeks to add on 13,600 P.E. The District’s
figures are based upon the use of 100 gallons per person per day,
having an average BOD5 loading of .167 pounds per person per day.
THE HARDSHIP
The hardship in this case is only incidentally imposed upon
the Sanitary District, but affects directly others within its
boundaries. Though the Agency in its Recommendation challenges
whether any hardship is imposed at all on the District and, there-
fore, whether such a subject is a proper matter for consideration
in this variance case, the Board believes otherwise. Numerous
variance cases decided by the Board have been based on hardship
to others rather than the petitioner. For example, when detail-
ing the hardship that would be imposed upon the GAF Corporation
were the Board to deny the variance, the Board described as “more
serious
. * -
the testimony that closing the plant would cause
the layoff of 700 employees.” (PCB 71-li) The hardship imposed
3
— 545
upon the residents and the proposed residents of the District
were the variance to he denied is both an economic and social
one. In the economic area, it results in the loss of income;
in the social realm, it imposes substantial inconvenience on the
owners of land within the District who wish to build and on the
owners of existing facilities who wish to expand. The testimony
of several witnesses established that construction of new houses,
as well as other buildings, within the District has virtually
come to a halt. Examples of this testimony follow.
The First Federal Savings and Loan Association of Waukegan
indicated that with the imposition of the sewer ban in the North
Shore Sanitary District it. has ceased the issuance of all normal
construction loan commitments, except where the Lake County
Health Department had approved installation of a septic system.
The volume of new construction loans handled by the Association
had decreased dramatically in the course of 1971. The first
quarter witnessed a volume of $1.8 million, the second quarter
$42,000, the third quarter $41,000, and the fourth quarter $58,000,
(H. 367) Though the ban has increased the values on existing
real estate within the District, it has had the opposite effect
on developed building sites. CR. 370) For example, a lot which
would sell for a certain amount when the District’s work was com-
pleted and which could then be used for its intended purpose,
would have a current value of between 77-81 of its future worth.
Robert MacGruder, Executive Secretary of the Waukegan—North
Chicago Chamber of Commerce testified that the only real effect
of the ban has been an increase in the selling and rental price
of existing real estate. (R. 395) He found that virtually no
new construction was underway within the District. (H. 391) If
the variance which the District seeks was granted, he indicated
that 1000 building permits could be issued in 1972, 2000 in 1973,
and 2000 in 1974. Thus, the additional load to the treatment
plants would be gradual over three years. (H. 397-98)
Allan Pickus, of Pickus Construction Company and a registered
architect working in Waukegan, testified that a majority of his
employees were laid off due to a lack of new work brought about
by the imposition of a sewer ban. (R. 317-18) At present, Pickus
Construction Company is almost non—existent; all work started as
of April 1, 1971 has now been completed and there is nothing to
take its place. CR. 314-5) Further, for the company to do busi-
ness outside of Waukegan is difficult since such business would
be outside the normal working area and would undoubtedly entail
higher costs and therefore mean less competitive bids. CR. 318)
Pickus estimated that if the sewer ban were lifted, within one
year from that date the total capacity of building within the
3
—
546
District would be approximately 700 units, In the following
year, for example, 1973, the production capacity would be
approximately 1300-2000 units for occupancy. That would simi-
larly be true for the year subsequent to that, e.g. 1974,
CR. 326-27) Approximately 80—85 of new construction would
occur in the areas served by the Clavey Road and Waukegan Sewage
Treatment plants. (H. 331) There is no question that there
has been an economic impact on those people who build new homes
in the District and those who benefit from the Oonstruction,
but the question is whether this hardship is great enough when
balanced against the harm caused by the pollution from the
District plants to compel the Board to grant the District a
variance.
THE DISTRICT’S (NON)COMPLIANCE
Before discussing whether a variance should be granted,
it is necessary to di~cusssome of the things the District has,
or rather, has not been doing, since the Board entered its June 23,
1971 order. This discussion is important because in setting the
terms for the
grant of any variance, this Board has consistently
insisted that the petitioner be proceeding according to the sched-
ule in implementing his compliance program. Under the Air Con-
taminant Emission Reduction Program (ACERP), petitioners were
obliged to set forth their implementation program; when the time
of the ACERP grant had expired, the parties were to peek a variance
from this Board in order to, in effect, renew the variance. When
such parties filed for a variance, they had to make a showing
that their implementation of the ACERP
was proceeding according
to schedule.
Failure to adhere to the schedule or to provide
adequate excuse for such failure has resulted in the imposition
of a monetary penalty.
(See Environmental Protection Agency v.
Marquette Cement, PCB 70-23; Greenlee Foundries v. Environmental
Protection Agency, PCB 70-33).
Though the North Shore Sanitary District witnesses and
Brief state and argue that the District is in “substantial com-
pliance” with the Board implementation order of June 23, 1971,
we believe that the evidence shows otherwise. Only Paragraphs
2, 3 and 9 of that Order have been complied with, though by this
date all paragraphs except the first were to have been complied
with fully. For example, Paragraph 4 orders the District to
install and operate interim disinfection facilities at the North
Chicago plant by January 1, 1972; Paragraph 7 also applied to
the North Chicago plant and ordered the use of alum by January 1,
1972. Neither has been done. Instead the District decided to
3
— 547
build a lagoon and permanent chlorination facilities. In the
District’s opinion, such interim facilities were a waste of
time.
(R.
52) Completion of the permanent facilities
is
expected before the 1972 bathing season.
While we commend the
District’s thoughtfulness and desire to achieve certain economies,
that was not what the Board Order directed. If the District
sought to deviate from the Order it should have so informed the
Board and the Agency rather than just blithely changing its mind.
Further, the Board order, Paragraph 3, directed that screen-
ing facilities be installed at Gillette Avenue Sewer by January 1,
1972. At the hearing, the District indicated that such screening
should be completed “within a few weeks.” (H. 54) Paragraph 6
of that Order obliged the District to employ chemical precipita-
tion and polymers at Waukegan Treatment Plant by September 1,
1971.
Though the District added ferric chloride as of September 1, poly-
mers are not yet added, but are a subject of this hearing and
should be installed within three months. Paragraph 8 of the
June 23 Order directed that chemicals be employed at the other
Lakefront plants by January
1, 1972. As of December 9, 1971, the
District had finally submitted a permit request to the Agency for
such an addition.
Even more disappointing is the District’s failure to
adhere to its own construction
schedule according to Paragraph 1
of the June 23 Order. For example, the Lake Bluff Pumping
Station
(PS-6) was to be completed by November 30, 1971; today
it is delayed “some months beyond that.” CR.
232) The Lake
Front Intercepting
Sewer (Section
1)
(S-8A) was to start con-
struction on October 31,
1971; construction has not yet begun
due to problems of right-of-way.
The District
does not know
when that will go ahead. CR. 233) The same is true for the Lake
Front Intercepting
Sewer CSection 2) (S-8A) which was to have
started construction
on October 10, 1971.
Though the
Board realizes that certain problems as to
the Clavey Road plant were caused by the necessity of obtaining
a Federal Environmental Impact statement and approval thereof,
this still does not excuse the District from notifying the Board
that certain delays will be incurred due to that.
In addition,
the delays here are quite substantial.
Construction on the
Ciavey overflow treatment facilities
was to have begun on
February 1, 1972; because the Federal Environmental Protection
Agency required covering
of these retention basins, the facili-
ties had to be re-designed. This design will be complete by
mid-1972, with completion scheduled for April 1, 1974, instead
of August 1, 1973
—
an eight-month delay. Due to bidding~diffi-
culties work on the Clavey sludge loading facilities
(P liE) and
pumping station additions
(P hF) will each be involved in a
three-month delay.
3
— 548
Right-of—way problems also plague the Winthrop Harbor
Ravine Sewer (S-l) and the interceptor extension CS-2A) so that
construction scheduled for last summer has not yet begun. (R.237)
The Kellogg Ravine Sewer (S-3) has been subject to a five-month
delay due to right—of—way problems. No date is set for con-
struction of the Waukegan Interceptor Sewer, though work was to
have begun on December 1, 1971, again due to right—of-way problems.
(H. 239) There is a two-month delay on the Waukegan—Bull Creek
Sewer (Section 1) (S-5A) because of right-of—way difficulties,
The North Chicago Pumping Station is now scheduled for
completion three months late. CR. 238) The Upper Skokie Pumping
Station construction will be completed about 1-1/2 months late.
The additional treatment facilities at Waukegan were to have been
completed on June 1, 1973; due to problems with the Federal govern-
ment, completion is now predicted for December 1, 1973, a six-
month delay. The Waukegan overflow treatment facilities are now
scheduled for completion five months late. The Waukegan sludge
dewatering facilities, (P-3D) and sludge incineration facilities
(P-3E) were both scheduled for completion on February 1, 1973,
At present, the District is looking for alternative means of
sludge disposal; though the Board realizes that this may bring
a cost-saving to the District, this searching has already pre-
cipitated a six—month delay in the sludge disposal projects.
The implementation order of the Board in this case was
entered scarcely seven months ago and already the Di,strict is as
much as six or eight months behind on some of the major projects.
If it were not that the variance, which the Board shall approve
in this case, will substantially improve the quality of the
waters in Lake Michigan, the variance petition of such a lax peti-
tioner
should be summarily denied. Conduct of the kind demon-
strated by the District in its utter disregard for the June 23
Order of the Board cannot be tolerated. The District, and others
who are subject to orders of the Board, must learn to take them
seriously, to follow them and to get approval from the Board
before they unilaterally decide to institute new programs. Other
sanitary districts have been diligent in complying with Board
oders and keeping the Board informed. (See Environmental Pro-
tection Agency v. Danville Sanitary District, PCB 71-28).
If the District were to follow the lead of the Danville Sanitary
District, perhaps the District would not have the problems it
does today.
— 549
In promulgating the June 23 implementation order, the
Board chose not to order the District to file interim reports
detailing its compliance with that order. Perhaps finding that
the District had been troubled enough in the recent past and
that it should rather get about its business of cleaning up
Lake Michigan, we simply ordered the District to adhere to its
own projected completion schedule. To our great dismay and
surprise and to the detriment of Lake Michigan, the District
has fallen markedly behind and, further, has even failed to
implement particular Board directives on time. Henceforth,
as will be specified in the order, the District shall file
monthly progress reports with the Board and the Agency.
The question remains as to what the Board should do as
a result of the District’s failure to follow the June 23 Order.
Of course, many alternatives are available to the Board, includ-
ing, as we have said, a summary denial of the variance or even
the imposition of a monetary penalty. No such penalty shall
be imposed, however, since it cannot be determined from the
record whether such delays as have been incurred were justifiable
ones. In addition, we think that the water quality of Lake
Michigan and the economy of Lake County are best served by not
being punitive against the District now. Rather, the District
will be required, when and if it seeks an additional variance
from the Board next year, to prove that it has complied with all
of the orders of the Board, or that it has exercised every effort
to comply in good faith, but could not. A new variance will
only be granted if the Board is satisfied that the District has
done everything it could to satisfy its obligation.
THE VARIANCE
Under Section 36(b) of the Environmental Protection Act,
the Board can only grant a variance for a period of one year,
and only if compliance with the laws will impose an arbitrary
or unreasonable hardship. Based upon the evidence in the record,
we feel that denial of the variance would impose such a hard-
ship. The economic hardship imposed by the “sewer connection
ban” has been, and would be great
if
the variance is not granted.
If the
variance were not granted, and therefore the conditions
of the variance not
met, Lake Michigan will be the worse for it.
In fact, by meeting the conditions of the variance, the people
in the District will probably be able to use some of the beaches
during the
latter part of the 1972 bathing season and for all
bathing seasons thereafter. Accordingly, the North Shore Sanitary
3—550
District shall be granted a variance as to Paragraph 7 of the
Board Order of March 31, 1971 for its Waukegan and Clavey Road
sewage treatment facilities. The District shall be permitted
to accept at either or both of these plants a total of 1000 new
living units or a total of 4000 P.E. The grant of 1000 living
units is based upon the testimony of Robert MacGruder of the
Waukegan-North Chicago Chamber of Commerce. Allan Pickus of
Pickus Co~structio~Companyeven indicated that the number of
additional iiving.units during the first year ~iould be less
than 1000 an~that only 80-85 of the number would be in areas
tributary~tothe~Waokega.nand Clavey Road treatment plants.
The District may ap~rtibn the allotment under this variance
between the two plants.4~s i~?shall determine. Should the Dis-
trict decide, it may grant~a~p~rtionof the allotment to
industrial users; such an allotment~‘of course, will consume a
part of the 4000 P.E. Variances granted by the Board since
March 31, 1971 shall not count against the District’s total
allotment. Any allotment shall be in accordance with the priori-
ties set forth under proposed Chapter IV, Part VI,
Rule 604 Ce)
in the regulatory case, In the Matter of Sewer Bans, R71-l9.
If any party ~,saggrieved by the denial of a permit from the
Agen~y~orthe District, his rights of permit appeal shall be
as set. ~forth under Section 40 of the Environmental Protection
Act. The procedures on appeal shall be as under Rule 502 of the
Board’s Procedural Rules.
With regard to connections to sewers in Waukegan, the
District shall adhere to the stipulation entered into in the
record in this case. The Agency’s and the League’s testimony
established that definite overloading and surchargii~igof sani-
tary sewers occurs at about ten locations on sewers tributary
to the Waukegan treatment plant. (R. 559-572) This’testimony
from the Lake County Health Department affords ample grounds
for the stipulation to which the parties have agreed. In
sum, that stipulation would provide: The North Shore Sanitary
District and the Environmental Protection Agency each state that
they presently have statutory power to require permits for
all sewer extensions and connections; any connection, extension
or increase in strength or volume of influent shall not be
allowed with a permit approved by the District and the Agency;
the District shall maintain a record of all new permits or
connections issued and Shall include those number~and identi-
fications in its monthly report to the Board; no connections
shall be allowed if any part of the downstream sewer ‘system
is incapable of adequately transporting the additioaal or new
waste to the District’s treatment works. This condition is
not meant to preclude connections to lateral or interceptor
3
—
551
sewers upstream of the Water Street and Gillette Avenue sewers
just on the basis that these two sewers may overflow. Rather,
it is intended to reach surcharging and overflow problems from
Waukegan sewers to ditches and ravines as described in the record.
The Agency shall indicate in writing to the District those
sewers or sewer lines which it finds incapable of adequately
transporting wastes; the District shall not approve any permits
which would add or increase any waste source to any sewer or
sewer line so designated. The District shall also have a
continuing responsibility to identify any additional inadequate
sewer on the basis of its own records or information submitted
to it. In that stipulation, the District also agreed that the
Agency would have the right, either through the present or
future proceedings, to recommend to the Board that all connec-
tions that would be tributary to specific sewers maintained by
the District would be prohibited. Though the Agency’s right
in this regard is amply guaranteed by statute, such a stipula-
tion re-inforces that right. The Board finds adequate cause in
the record to insist upon such a stipulation; it will be incor-
porated into the Board Order as agreed by the parties. We would
commend the parties for strong interest they exhibited in such
a stipulation and agree that such is necessary to prevent further
water and land pollution in the ravines and ditches upstream of
Lake Michigan.
The District may issue permits under this variance at any
time within that year. Connection to an existing line or con-
struction of a new sewer line under such a permit need not occur
within the one-year period. Any such additional connections
authorized under this variance and not assigned by the District
within the one—year period of the variance shall lapse upon the
termination of the variance.
Of course, any hookups or new sewer lines granted pursuant
to this variance and under an Agency and District permit do not
become revocable by the mere lapse
of this variance. In other
words, it is intended that such hookups and new sewer lines only
be subject to the customary rules of the District, the Agency
and the Board. The possible subsequent denial by the Board of
a District variance petition will in no way affect those who have
already been granted a hookup or completed installation of a new
sewer line through an allotment of the capacity available under
the grant of the variance in the instant case.
3
—
552
In addition to the above, there will be other conditions
imposed as part of the grant of a variance. The following para-
graphs outline each of those conditions:
The District shall install polymers and chemicals at the
Clavey Road plant. This installation shall be as described in
the testimony of M.D.R. Riddeil, the District’s consulting engineer.
Even though such an installation may need only intermittent use,
it is necessary to assure that Clavey will consistently achieve
the 20 mg/h BOD5 and 25 mg/l suspended solids standard presently
in effect under SWB-l4. Due to the hardship that would be imposed
wereand
5themg/lBoardsuspendedtoinsistsolidsthatstandardthe
Districtrequiredattainas
oftheJuly4
mg/h1,
19’72,BOD5
the District shall also be granted a variance from meeting that
new criterion. The polymer and chemical feed system shall be
installed within six months. These facilities need only be used
intermittently so as to hold down the cost to about $10,000 per
year. Because of the effluent lagoon and its operation, these
chemicals are not nee~Led~at all times.
The District shall continue to use sodium hypochiorite in
the sewers above the Clavey plant to aid in the abatement of
air pollution. This program has apparently been effective.
The District shall install polymers and continue to use
chemicals (ferric chloride) at the Waukegan plant. The District
presently has such polymer feed systems on order. With ferric
chloride the District can presently attain a total effluent dis-
charge of approximately 30-35 mg/h of both BOB5 and suspended
solids. To maintain such a characteristic effluent with the
additional loadings granted under this variance, the polymer in-
stallation is necessary and shall be completed within three months.
The District shall install bar screens on the Water Street
Sewer, which can be cleaned manually. The Greeiey and Hansen
Water Street study submitted to the Board and made a subject of
the hearing in the Board’s preliminary order described three
possible installations on the sewer. Each of the other two
suggested devices involved the expenditure of a larger amount of
money and also a longer installation period. The manually clean-
able bar screen would remove only coarse solids, but could be
installed within seven months. Its purpose would be mainly
esthetic, but, within the given time period, would be available
for a substantial portion of the 1972 bathing season. In order
that a reasonable time schedule can be maintained, within twenty
(20) days from the entry of this order the District shall submit
such a timetable to the Agency. The Agency shall then formulate
a written response to the Board within ten (10) days of receipt
of the District’s schedule. The Board shall issue an implementa-
tion schedule.
3
.--
553
The District shall install chlorination facilities at
Water Street and Gillette Avenue Sewers. 1 As previously
stated, the Board directed in its preliminary opinion that the
subject of bacteria removal be discussed in conjunction with
the variance case. The District’s engineering consultant,
M.D,R, Riddeil, described the two types of possible installations
at Water Street. Both would involve the construction of tem-
porary chlorinating facilities which would apply sodium hypo-
chlorite at a high rate to the sewage during overflow periods.
(H. 446) Such, as was mentioned above, occur sixteen to
eighteen times each year. The maximum flow in the Water Street
sewer is about 60 mgd; it would be approximately one part
sewage to eight to ten parts stormwater during overflow condi-
tions. (H. 445) One proposed chlorination facility would in-
volve the use of a contact basin developed by driving sheet
piling into the bottom of the Lake offshore from the present
overflow. This basin would provide about 15 minutes of contact
time, The other possible Water Street facility would be created
by building a diversion structure on the Water Street sewer
similar to that proposed in connection with the screening facili~.
ties and then to build a by--pass sewer generally paralleling the
Waukegari River. (H. 446) The cost of the first alternative
would be about $200,000; the second, about $240,000. For each
the operating cost would be about $15,000 annually.
For the Gillette Avenue sewer, Riddell indicated that it
would he possible to take advantage of the contact time in the
sewer itself and augment that with a small contact basin. It
would he possible to add chlorine to the sewer at Sand Street
in order to provide additional disinfection. Projected cost
of this installation would be approximately $150,000, with an
annual operating cost of about $15,000. In his opinion, an
adequate chlorine dosage, coupled with a fifteen—minute contact
time, should provide reasonably effective disinfection of the
overflows on the order of 95 reduction in bacteria. (H. 451,500)
i-
Though chlorination is the traditional method used,
the District still is held to the commitment it made at the
hearing to study ozonation as a means of disinfection CR. 642).
3
— 554
Even though there are potential problems as to placement
of the disinfection facilities at Water Street and Gillette
Avenue, the Board believes that such facilities are an absolute
necessity if additional connections are to be allowed. History
has indicated that the most serious problem involving the Lake
is the discharge of untreated bacteria to a prime recreational
area. Lake County Health Department 1971 Lake Michigan beach
sampling data indicate that the bacterial problem persists.
A significantly large percentage of the sample~ collected did.
not attain the SWB-7 criteria (LW Exs. 18-22). Though counsel
for the District stressed that such disinfection facilities
would only be available for one bathing season, the evidence
shows otherwise. Riddeli indicated that the facilities could
be on line within seven months. CR. 502) If so, that would
then mean that the beaches within the District could be used
in August and September, 1972, both months in which bathing
occurs. In addition, the chlorination facilities will be in
use during the 1973 bathing season, since the improvements to
the Waukegan plant will not be completed to allow the Water
Street overflows to be treated at the plant until August, 1973,
CR. 240) Finally, the dilatoriness which the District has dis-
played throughout the past seven months will probably be with
us throughout its current project. Though we do not like to
admit the possibility, even further delays will probably result
and we can only hope that the District approaches each one in
a good faith effort. For that reason, it is entirely likely
that the chlorination facilities which we order as a. condition
of this variance will still be installed and operating in the
summer of 1974.
It must be remembered that when we speak of a bathing
season we are not speaking of one “object” but of many days of
recreational
enjoyment for the residents of the District
and
Northeastern Illinois. The capital cost which the District
presents,
$350,000 for the chlorination
facilities,
is worth
the price.
It has not been BOD5 and suspended solids
which have
prevented bathing on the Northshore beaches for the past several
summers, but a high bacterial count. By the entry of this
order, we anticipate that this problem will be alleviated.
The projected capital costs of the program which the Board
hereby orders is approximately $450,000 ($350,000 for chlorina-
tion at Water Street and Gillette Avenue sewers, $75,000 for the
chemical feed at Ciavey and $10,000 for Waukegan); the annual
operating cost will be approximately $100,000 ($15,000 each at
Clavey, Water Street, and Gillette, and $50,000 at Waukegan).
3
—
555
In his testimony, the acting General Manager for the District
indicated that the proposed. connection fee to be adopted by the
District to pay for such a program would be “between a hundred
to two hundred dollars11 per single family home or equivalent.”
CR. 170) If the District were to adopt this higher figure,
then receipts for the first year under this variance grant
could equal approximately $200,000. With increased building
during subsequent years, perhaps in the neighborhood of 2000
units, as suggested by Robert MacGruder and Allan Pickus, their
receipts could total as high as $400,000. Over a projected
three-year period before the District can then complete its
improvements, over $1,000,000 may return to the District in
the form of connection fees. Such an amount would be in
excess of the projected total capital and operating costs for
the three-year period of $750,000. For this reason and those
noted above, the Board finds that not only are such improvements
technically feasible, but economically reasonable.
The District shall maintain treatment levels at the
Clavey Road plant of 20 mg/l BOD5, 25 mg/i suspended solids.
At Waukegan, the District’s total effluent shall be in the
range of 30-35 mg/i BOD5 and suspended solids.
The District shall file monthly written reports with the
Board and the Agency detailing its compliance with the conditions
of the variance. Such reports shall include, inter alia, the
number of connections granted by the District
in the period governed
by the report.
This opinion constitutes the findings of fact and
conclu-
sions
of law of the Board.
11 In its brief, the League suggested a connection fee
of $400. We do not suggest any particular figure; rather, that
should be within the purview of the District. In any case, the
fee should be sufficient to cover the cost of improvements.
3 556
ORDER
Upon examination of
the
record, the North Shore Sanitary
District is hereby granted a variance from Paragraph Seven of
the Order of the Pollution Control Board in the case of the
League of Women Voters, et al
V.
North Shore Sanitary District,
PCB 70-7, 12, 13 and 14 subject to the following conditions:
1. The variance shall only be granted with respect to
additional connections to Clavey Road and Waukegari Treatment
plants.
2. The District shall be permitted to add a total of
1000 living units or 4000 P.E. to the sewers tributary to the
Clavey and. Waukegari plants.
3. This variance shall extend only for a period of
one year from the date of the entry of this Order. The District
may issue permits under this variance at any time within that
year. Connection to an existing line or construction of a new
sewer line under such a
permit need. not occur within the one-year
period. Any such additional connections authorized under this
variance and not assigned by the District within the one-year
period of the variance shall lapse upon the termination of the
variance.
4.
The District may apportion the allotmenj. under the
variance between the subject plants as it in its own discretion
so determines, except it shall follow the guidelines set forth
in paragraph 5 below.
5. In assigning its allotment under this variance, the
District shall subscribe to the following preference order:
a. Those whose owners have paid for the im-
provements;
b. housing under government—aided progtams
for the disadvantaged;
c.
those for which substantial
expenditures,
beyond mere purchase of land, were made in good faith
prior to March 31, 1971;
c. hospitals, schools, and other buildings
providing essential public services.
3
—
551
6. In determining whether connections or the construc-
tion of new sewer lines shall be allowed the District shall
adhere to the following policies:
a. No connection, extension, or increase in
strength or volume of influent shall be allowed with-
out a permit approved by the District and the Agency;
b. the District shall maintain a record of
all new permits or connections issued and shall
include those numbers and identification in its
monthly report to the Board;
c.~ no connections shall be allowed if any
part of the down-stream sewer system is incapable
of adequately transporting the additional or new
waste to the District’s treatment works;
d. within 30 days of the entry of this order,
the Agency shall indicate to the District those sewers
or sewer lines which it finds incapable of adequately
transporting wastes; the District shall not approve any
permits which would add or increase any waste source
to any sewer line or sewer so designated;
e. The District shall have a continuing responsi-
bility to identify any additional inadequate sewer or
sewer line on the basis of its own records or informa-
tion submitted to it.
7.
The Agency shall have the right, either through the
present or future proceedings,to
recommend to the Board that all
connections that would be tributary to specific sewers-maintained
by the District would be prohitibed.
8. Any party aggrieved by the denial of a permit from
the Agency or the District shall have a right to appeal such
denial under Section 40 of the Environmental Protection Act.
9. The District shall install polymers and chemicals at
the Clavey Road plant. The District .aeed only use such an instal-
lation intermittently in order to maintain an effluent of
acceptable quality.
10. The District shall continue the use of sodium hypo-
chlorite in the sewer above the Clavey Road plant as necessary to
abate air pollution.
3
— 558
11. The District shall
install polymers and continue the
use of chemicals at the Waukegan plant.
12. The District shall maintain a monthly average effluent
of 20 mg/i BOD5 and
25 mg/i suspended solids at the Clavey Road
plant. The District shall maintain a monthly
average effluent in
the range of 30-35 mg/i BOD5 and suspended solids at the Waukegan
plant.
13.
The
District shall install bar screens which are
manually cleanable on the Water Street Sewer.
This installation
shall be as described in the bistrict’s report to the Board as
admitted into evidence as Agency Exhibit 5. Within 20 days of
the
entry of this order, the District shall
submit a timetable
for installation of the bar screen to the Agency. The Agency
shall formulate a written response to the Board within 10 days
of receipt of the District schedule. The Board shall then issue
an implementation schedule.
14. The Distr~ctshall install disinfection facilities
at the Water Street and Gillette Avenue Sewers.
Within 45 days
of the entry of the order, the District
shall present a timetable
for the installation
of such facilities
to
the Agency and the
Board. The Agency shall formulate a written response to the
Board within 15 days of receipt of the District timetable. The
Board shall then issue an implementation schedule.
15. In all other ways, the District shall cottinue to
maintain compliance with the Board orders of March 31, 1971 and
June 23, 1971.
16, The District shall make monthly progress reports to
the Agency and the Board,
Such progress reports shall detail the
District’s compliance with the Board orders of January 31, 1972,
March 31, 1971, and June 23, 1971, and with the District’s imple-
mentation schedule as entered into the record of the June 23
order. The monthly progress reports shall also detail the number
of permits issued, to whom issued, and the population equivalents
thereby added to the subject plant.
17. The District shall study the use of ozone as a method
of disinfection and submit such study to the Board and the Agency.
Such study shall be submitted within 90 days of the entry of this
order.
3
—
559
18. The District shall study the use of cationic as opposed
to anionic polymers and shall indicate to the Board and the Agency
the choice it has made and the reasons therefor.
19. Failure by the District to comply with any of the
conditions of this variance shall be grounds for revocation of
this variance.
20. The District shall apply for any desired extensions
of this variance no later than
90 days before the expiration of
this variance. Such a variance petition by the District and any
hearing authorized pursuant to such a petition shall indicate the
District’s good faith compliance with this Board order.
I, Christan L. Moffett, Clerk of the Pollution Control Board,
certify that the Board adopted the above Opinion and Order his
___________day of
,
1972 by a vote of
—
Mr. Dumelie dissent’ g.
~
Christan L. Moffe
Clerk of the Boar
3
—
560