ILLINOIS POLLUTION CONTROL BOARD
December
21,
1971
CENTRAL ILLINOIS PUBLIC
SERVICE COMPANY
)
PCB 71-261
PCB 71—262
v.
)
PCB 71—263
)
PCB 71—264
ENVIRONMENTAL PROTECTION AGENCY
THOMAS L. COCHRAN, ATTORNEY FOR THE CENTRAL ILLINOIS PUBLIC SERVICE
COMPANY
DELBERT
D. HASCHMEYER, ATTORNEY FOR THE ENVIRONMENTAL PROTECTION
AGENCY
OPINION OF THE BOARD
(by Mr.
Kissel):
On September
3,
1971,
the Central Illinois Public Service
Company
(CIPCo)
filed
a petition for variance with
the Board for
four of its generating stations
-
Coffeen
(PCB 71-261), Hutson-
yule
(PCB 71-262), Meredosia
(PCB 71-263),
and Grand Tower
(PCB
71-264)
-
from
the applicable particulate regulations.
Each
generating station was under
a program to install emission control
equipment as detailed later in this opinion.
CIPC0 had been granted
an ACERP by our predecessor Board,
the Air Pollution Control Board,
but sought this variance because of our previous decision in the
Commonwealth Edison case which held that ACERPs were indeed
variances and could only be granted for
a period of one year.
See
Commonwealth Edison Company
v.
EPA,
PCB 70-4, February 17,
1971.
The Environmental Protection Agency filed separate recommendations
for each of the stations generally advising that
the
variances
should be granted with exceptions noted later in this opinion.
Hearings were held
in October and November of 1971 before Arthur
Rosenblum, Hearing Officer.
Case 71-261 involves the CIPC0 Coffeen Power station which
is located three miles south of the city of Coffeen,
Illinois in
Montgomery County.
It is surrounded mostly by
farm lands.
Presently,
the Coffeen station has one coal fired unit in operation
(Coffeen Unit
#1) which has an operating capacity of 365 MWE.
This
Unit #1 presently emits its off gases through
a 350—foot chimney,
and
is presently equipped with
a mechanical dust collector with an
efficiency of
34.5.
3—27~
The key unit in CIPCo’s future plans is one presently under
construction at the Coffeen station
-
Coffeen Unit
#2.
The sched~-
uled completion date for this unit is March of
1972.
It will have
an operating capacity of
600 MWE,
and will be equipped with
an
electrostatic precipitator with
a collection efficiency of 99.
A new 500—foot stack is being built at the Coffeen station and the
off gases of both units will be emitted through the new,
larger
stack.
The 350-foot Unit
#1 stack, now being used, will,
then,
be dismantled.
Coffeen Unit #2 will from the inception of its operation comply
with
the existing regulations concerning particulate emissions,
according to CIPC0,
and therefore
no variance is being sought for
the operation of that unit.
Because of its size, however, bring-
ing it in line in March of
1972 will have an effect on the other
“dirtier” CIPC0 units,
as will be discussed later in this opinion.
CIPCo does
say, however,
that Coffeen Unit #2 will need about six
months time of operation before the other units
in the line can
be taken off.
Coffeen Unit
#1, on the other hand,
is presently violating
the particulate regulations.
The present stack emission of Coffeen
Unit
#1,
calculated by CIPCo is
4.0 pounds per hour per million BTU,
and the applicable regulations only permit 0.8 pounds
an
hrnr per
million BTU.
The Agency calculated Coffeen Unit #1 emits 12,000
tons of particulates per year into the atmosphere.
In addition,
the emissions from the Coffeen Unit #1 are causing
a problem with
the
local residents.
Several of Coffeen’s neighbors testified at
the hearing and described the dust from the unit which affects their
lives.
To the neighbors,the particulate emissions represented an
almost unbearable source of dust so that windows in homes can’t be
kept open,
air conditioners had to be bought, yards could not be
used
for
barbecuing,
furniture
gets
dirtier
faster
and
the
paint
on
cars
comes
off.
An
Agency
witness
who
did
some
ambient
air
sampling
testified
to
being
near
the
plant
and
feeling
the dust get
in
his
eyes.
There
is
no
question,
from the uncontradicted evidence
in
the
record,
that
the
particulate
emissions
are
interfering
with
the
life
and
property
of
the
people
near
the
plant.
CIPC0
did
present
a
program for controlling the particulate emissions from
Coffeen
Unit
#1
—
the
installation
of
an
electrostatic
precipitator
with
a collection efficiency of 99.
When installed,
the precipi-
tator will bring Coffeen Unit #1 into compliance with
the existing
particulate emission regulations.
The Agency did not disagree with
this,
but the Agency did suggest that the time schedule for instal-
lation of the precipitator could be accelerated.
CIPC0’s schedule
on Unit #1 calls
for receipt of the precipitator in July of
1972,
but not actually installing it until
1973.
(The actual date on
which Coffeen Unit #1 will have the precipitator installed and
operating is June
9,
1973,
and the unit will be shut down on March
4,
8— 27*
1973,
to begin the tie-in of the precipitator to Unit #1.
Unit
#1 will not be operated between March
4 and June
9,
1973.
See
CIPCo’s petition for variance, paragraph 5).
In the hearing
the Agency suggested that Unit #1 be shut down some time in the
fall of 1972
(after Coffeen Unit #2 is reliably operational)
and
complete the installation before the time suggested by CIPC0.
CIPCo’s witnesses agreed that from a technical standpoint the
Agency’s suggestion on timing of installation could be done, but
CIPCo argues that from a system reliability standpoint Coffeen
Unit #1 cannot be shut down until
1973.
CIPC0 argues that it
has a scheduled planned maintenance program which requires Coffeen
Unit
#1
to be in operation until March 1973 so that certain other
units
in their system can operate efficiently and give reliable
electric service to the CIPC0 customers when Coffeen Unit
#1
is taken down for installation of the precipitator.
In addition,
CIPC0 is
a member of the Illinois-Missouri Power Pool, which
also includes Illinois Power Company and Union Electric Company
(Missouri).
The membersof this Pool have scheduled staggered
shutdowns~ofmajor turbine generators of the respective companies
so that several
large units are not out of service for planned
maintenance at any one time.
CIPC0 says that if the shutdown of
Coffeen Unit #1 were required before March of 1973,
this “would
probably postpone the maintenance plans
for other units thus
affecting each of the three companies” and “would place all three
companies in the vulnerable position of not having performed
planned maintenance as scheduled resulting in decreased reliability”.
According to CIPC0, a hardship to CIPC0’s customers could result.
While we feel that control equipment should be put on as early
as possible, we agree with CIPCo’s position in this case.
The
need for reliable electric power is
an important consideration and
outweighs the few months
(five at most)
during which Coffeen
Unit #1 would not emit excessive amounts of particulate matter.
Five months is
a short time, particularly because they are late
fall and winter months when the neighbors would be less likely
to use the out-of-doors which has been taken from them by CIPCo
in the past.
CIPC0, then, will be granted a variance to operate
Coffeen Unit #1 for one year in violation of the applicable par-
ticulate standards with the understanding that its program is to
shut down Coffeen Unit #1 on March
9, l973,for the installation
of an electrostatic precipitator and connection of the new 500-foot
stack.
In its recommendation filed in this case,
the Agency recom-
mended granting of the variance, but only on the condition that
within ten months from the granting of the order of the Board,
CIPCo develop a sulfur dioxide
(SO2)
emission program for Coffeen
Units #1 and #2, which will”significantly reduce the sulfur dioxide
emissions
oh
or before June
1, 1974”.
See paragraph 10(b)
of the
3— 27*
Agency recommendation.
To substantiate the need for SO2 reduction,
the Agency introduced testimony of many neighbors who identified
a sulfur odor in the area, which, the Agency said, was indicative
of an SO2 problem.
In addition,
the Agency also mathematically
calculated the ground level concentrations of SO2 and found
tha:.
if the mixing height of the stack was 5000
feet,
the ground level
concentration of SO2 between 5.8 miles and 6.8 miles from the
stack would be approximately 641
mg/rn3
(about
.25 ppm).
If the
mixing height were lOCO feet,
rather than 5000 feet, the cancer-
tration of SO2 would vary between 400-3861 mmg/n3
(.17 ppm to
1.5 ppm)
in an area between 2.3 and 50 miles from the plant.
If
the model were
to be believed, concentrations near 1.5 ppm could
pose a serious health problem, but as pointed out by a CIPC0
witness, one of the assumptions made by the Agency in its calcu-
lations was wrong, namely,
the Agency assumed that the 350—foot
stack would still be used for the emission of off gases from Coffeen
Unit
#1.
In fact, CIPC0 plans
to discontinue use of that stack
and emit the off gases from both Coffeen Units
#1 and #2 through
a new 500-foot stack.
CIPCo’s witness testified that this would
make
effective stack height greater, first, because the stack
height itself will be higher and, second, because the greater
heat flow through the one stack
(rather
tha’i two stacks) would cause
the emissions to go higher in
the air.
The Agency calculations
also assumed
(when the high SO2 concentrations occurred)
that the
emissions from the Coffeen Units would not break an emission layer
at 1000 feet.
According to CIPC0, if both units are vented through
the one 500-foot stack, any inversion at 1000 feet will be broken
by the stack of off gas.
CIPCo calculated that the ground concen-
trations on a one—hour
basis would be
.17 ppm SO2 which calcula-
tion is a factor of ten less than the Agency calculation.
The Board is faced with deciding between two mathematical
calculations, which differ by a factor of
ten.
The Agency calcula-
tions were not based on the proper assumptions,
and, therefore,
if
we were to accept one set of calculations
or the
other,
we
would
accept that of CIPC0.
However, we do not feel that it is appro-
priate for the Board to consider the question of SO2 reduction in
this case for basically two reasons.
First,
the Board
is presently
considering the adopti.on of statewide regulations on SO2 reduction,
and second,
the Agency only presented half a case here.
As
to the
second point, we have previously held that where an SO2 problem
was identified and control equipment was generally shown to be
available and adaptable, we would order a boiler operator to install
such equipment.
See EPA v. City of Springfield, PCB 70—9, May 12,
197
However,
that case was different from this case because that case
was an enforcement case brought by the Agency to get SO2 control
equipment installed and because
in that case the Agency demonstrated
3— 2*0
at least on
a prima
facie basis
that control equipment could be
installed.
The Agency here has demonstrated
a possible problem,
but has
not demonstrated even on
a prima
facie basis that control
equipment can be installed.
In this
case we
feel,
therefore, that
CIPC0 need not submit a plan
for controlling SO2 emissions.
It may
be, however,
that in other cases where
a variance is shown,that
we will require
the emitter or discharger to come forward with
plans
to control the source of pollution, even where the Agency
has offered us proof that such equipment is available.
There-
fore, we will not require
that CIPC0 study
the ways of reducing
SO2 emissions
from its Coffeen plant at this time.
This does
not preclude, however,
the Agency’s bringing an enforcement case
against CIPC0 and proving at
that time that control equipment is
available and that the SO2 problem is
a real
one.
Nor does our
decision prevent the Board from adopting regulations in the near
future which would require CIPC0 to install SO2 control equipment
on the Coffeen units.
Case #71-262 involves
the Hutsonville Power station, which
is located along the Wabash River
in Crawford County,
Illinois,
two miles north of the City of Hutsonville.
Hutsonville has
four
turbine
generating
units
served
by
six
coal-fired
boilers
(Boilers
1-4
serve
Units
#1
and
#2,
Boiler
5
serves
Unit
#3,
and
Boiler
#6
serves
Unit
#4).
CIPCo’s
petition
for
variance
on
the
Hutsonville
Power
station
only
involves
Units
#1
and
#2.
Unit
#3 already has an electrostatic precipitator installed with
a tested efficiency of 99
(CIPC0 has not yet operated this unit
on other
than
a test basis).
Unit
#4 was scheduled
to be shut
down on October
3,
1971 to have
an electrostatic precipitator
installed,
and the unit was to be placed back in service on
November
20,
1971.
CIPC0 does
not intend to install any control equipment on
Units
#1 and #3.
What CIPCo requests is that a variance from the
particulate regulations be granted to CIPC0
for Units
#1
and
#2,
so that those untis will be allowed
to operate on
a
“hot standby”
basis until September 30,
1972, and then operate on “cold standby”
until January
1,
1980.
“Hot standby” means
the boilers are main-
tained near normal operating pressure and can be fired up to be
able to produce steam in
a minimal time.
Generally,
the furnace
is fired 15-30 minutes every
4 to
6 hours
to keep
the pressure up.
“Cold standby” means
that no pressure
is maintained in the boiler
and
to operate it
a
fire would have
to be placed in the boiler.
However,
in order to assure that the unit can be operable,
a fire
must beplaced
in the boiler about every three months
for a 4-6
hour period.
The reasons~given by CIPC0
for needing Units
#1 and #2 on
a
hot standby basis
is to allow
for time for testing the new Coffeen
Unit
#2, which
is scheduled
to go on line in March,
1972.
CIPCo
says
that until there
is
an adequate shakedown of Coffeen Unit #2
(about six months),
it will
not be
a reliable enough unit and
3—281
—6—
therefore the Hutsonville Units #1 and
#2 will provide the backup.
While the Agency recommended that.Hutsonville Units
#1 and *2
be placed on
“cold standby” when Coffeen Unit #2 comes on line,
we
feel that CIPC0’s position has merit.
The need for reliable
electrical service during the summer demands of 1972 are impor-
tant and there was no testimony that the present operation of
Hutsonville Units
#1 and
#2
(presently on
“hot standby”)
is
causing any problem with
the neighbors.
In
fact, the emissions
should be much lessened from the whole plant because the two
larger units at Hutsonville now are supposed to have operating
electrostatic precipitators
to reduce the
off gas emissions.
We
will,
therefore, allow the Hutsônville Units #1 and #2 to operate
on
a “hot standby” basis until September
30,
1972.
The second part of the petition
for variance regarding the
Hutsonville units
is a more difficult question.
CIPCo asks
that
Hutsonville Units
#1 and #2 be allowed to operate on
“cold standby”
until January
1,
1980.
During this time,
(from September
30,
1970
to January
1,
1980)
it may very well be
that Units
#1 and
#2 will
never be operated excepf at the three—month intervals, but the
likelihood is that the units will be operated at some time.
In
either case, however, this Board has not favored programs which
stretch
far into
the future and which do not contain pollution
control programs.
See Mt.
Carmel Public Utility
v.
EPA,
PCB
71-15,
PCB 7l-l5R, decided April
14, l97land November
11,
1971.
If Units
#1 and #2 are valuable
to CIPC0 and if they are to be opez~at~4at
any time during the next eight years,
it
is worth the price now
to install the necessary control equipment.
We can understand
that CIPC0 needs the units on
“cold standby”
for
a short time,
until January
1,
1974, but after
that,
if CIPC0 wants to use the
units,
it can only do so if it complies with the Act and the
applicable regulations.
We will, therefore, approve the use of
Units #1 and #2 on a “cold Standby” basis after September
30,
1972,
as long as it is on
a long term program to use those units after
January
1,
1974 only
if their emissions comply with
the Act and
the applicable regulations.
Case 71-263 involves the Meredosia Power Generating Station
which
is located along the Illinois River about one mile south
of Meredosia, Illinois
in Morgan County.
Meredosia plant has three
turbine power generating units served by
five boilers
(Boiler 1-4
serve Units
#1
and
#2 and are connected
in such
a way so
as to
permit any boiler to supply steam to etther of the
two units, and
Boiler
5 serves Unit #3).
CIPCo’s petition for variance regarding
the Meredosia Station only involves Boilers #3 and
4 which serve
Units #1 and
#2.
~An electrostatic precipitator has already been
installed on Unit
#3 and by now already is operating.
Boilers
#3
3— 282
and
#4
are Dresently having an electrostatic precipitator installed
beginning on October
24,
1971, and completion of the precipitator
was scheduled for November
20,
1971.
Boilers
#1
and
#2
are the subject of the variance petition
here.
CIPCo’s
plan calls
for shutting down
the boilers beginning
on March
26,
1972, with
the boilers scheduled to have construction
of
the precipitators completed on April
22,
1972.
Presently
Boilers
#1 and
#2 each
vent through
a separate stack
and emit approxi-
mately
6.66 pounds per million BTU, which
is
in excess of the present
state standard of
0.8 pounds per million BTU.
The Agency recom-
mended granting of
the variance
for the time specified by CIPC0.
We
-ac~ree.
There
is
no evidence
that CIPCo can shut down Boilers
#1 and
#2 now to complete
the installation
sooner.
While
the
Agency did receive some complaints
about
the emissions,
no one
appeared to testify that the schedule on Boilers
#1 and
#2 should
be moved up.
We think that
the schedule
for completion of instal-
lation
is
a reasonable one,
and hereby grant the variance as re-
quested by CI?Co for
the Meredosia Power Station.
Case 71-264 involves the Grand Tower Power Station which is
located on
the Mississippi River approximately three miles north
of the City of Grand Tower in Jackson County,
Illinois.
The
Grand Tower Station has four turbine generator units which are
served by nine coal-fired boilers
(Boilers
1-6 provide steam for
Units
#1 and
#2, and each boiler can produce steam
for either unit,
Boilers
7 and
8 provide steam
for Unit
#3,
and Boiler
#9 provides
steam for Unit #4).
Units
#3 and
#4
are presently operating with
installed electrostatic precipitators with collection efficiencies
in the range of 95.6
to 98.7.
Only Units
#1 and #2,
each with
a generating capacity of
25 MWE,
are the subject of the petition
for variance.
The Units
#1
and
#2 are presently on “cold standby”
and CIPCo’s request for variance
asks that we allow these units
to
remain on cold standby until September 1972, when Coffeen Unit
#2 will be able
to provide reliable electric service.
After that
date CIPC0 intends to retire the units.
The Agency recommends
granting of the variance,
but suggests that the Board require the
units to be physically dismantled at that time.
While we aqree with
the Agency
that
the variance should be
granted,
we do not
agree that we should require as
a condition of
the variance that the units be physically dismantled.
Without a
variance, CIPCo cannot operate the units
on any basis,
“cold
standby” or otherwise, without control equipment.
Since these
units would be the only
“non-controlled” emission sources on the
site,
it would be relatively easy
to know
if and when the units
3- 283
are operated.
We think that CIPCo has demonstrated
a need
for the
“standby” of
these units until September
30,
1972.
The “standby”
status will allow CIPC0
some flexibility
if Coffeen
#2 doesn’t
operate
to specifications and,therefore, will allow CIPCo
to pro-
vide reliable electric service
to its customers.
Here,
as
in two
of the three other cases,
no one testified as
to any effect of
the particulate emissions;
rather the people interviewed by the
Agency had no objection
to .the granting of
the variance.
We will, however,
require that CIPC0 report to
thEa Bottd~
and the Agency within ten d~s after any operation of
the two
units.
This includes the testing of the units as well.
If the
units are fired other than
for testing,
CIPCo will have
to state
in the written report to
the Board and Agency
the reasons
for
the use of the units.
As
a general condition
to the granting
of. th~variances,
the
Board will require that CIPCo post
a bOnd
to insure performance
of the acts detailed
in~the granted program.
The Agency recom-
mended that
a bond be required,
and we believe that under
the Act
a bond is rnar~datorybecause the hardship complained of consists
“solely of the need for
a reasonable delay in which to correct
a
violation of the Act or of
the Board regulations’.
Section
36(a)
of the Act.
In addition to the bond,
the Board will also require,
as
it
has in other cases of this
type, quarterly reports from CIPCo
which must detail how CIPC0 is progressing on each of
the control
facilities.
See Illinois Power v.
EPA, PCB 71-193,
and
PCB 71-195-8,
decided September
30,
1971.
This opinion constitutes the Board’s findings
of fact and
conclusions
of law.
ORDER
Upon examination of
the record,
CIPCo
is hereby. granted
a
variance for
a period of one year from this date
to emit particu-
late matter in excess
of regulation limits as follows and so long
as
the program outlined below is complied with:
1.
(PCB 71-261)
From Unit #1 at the Coffeen
Station until March
9,
1973.
3— 284
2.
(PCB 71—262)
From Units #1 and #2,
at the Hutson—
ville
Station,
until
January
1,
1974,
provided
that:
a.
Units *1 and *2 shall be
on
“hot
standby”
as defined in the Board’s opinion only
until
September
30,
1972;
and
b.
After
September
30,
1972,
Units
#1
and
#2
shall be placed
on
“cold
standby”
as
de-
fined in the opinion,
only until January
1,
1974.
3.
(PCB 71-263)
From Boilers
#1 and #2,
at the
Meredosia
Station,
until
March
26,
1972.
4.
(PCB 71-264)
From Units
#1
and #2, at the
Grand
Tower
Station,
until
September
30,
1972,
provided
that
during
this
period
the
Units
shall
only
be
operated
on
a
“cold
standby”
basis
as
defined.
All
on
condition
that
the following are met:
5.
All existing emission control equipment shall
be maintained
and fully utilized.
6.
CIPCo
shall
within
thirty-five
(35)
days
after
receipt of this order post with the Agency
a
bond
or
other
security
in
the
amount
of
$500,000
in
a
form
satisfactory
to
the
Agency,
which
sum
shall
be
forfeited
to
the
State
of
Illinois
in
the
event
that
conditions
of
this
order
are
not
complied
with
or
the
facilities
in question are operated after expiration
of these variances in violation
of regulation
limits.
7.
CIPCo
shall
file
quarterly
written
reports,
commencing
on
March
31,
1972,
with
the
Agency
and
with
the
Board,
detailing
its
progress
toward
completion
of
the
program.
8.
CIPCo
shall,
within
ten
(10)
days
after
use,
file a written report with
the Board and with
the Agency, detailing when,
for how long, and
why any units or boilers on
a
“cold standby”
basis were used.
3— 28~
.9.
Failure to adhere to the programs as pre-
sented or to the conditions of this order
shall
be grounds for revocation of these
variances.
10.
CIPCo
shall
apply for any desired extensions
of any of these variances
to complete the
programs approved today not later than ninety
(90) days before expiration of that particular
variance.
I,
Christan Moffett, Acting Clerk of the Pollution Control
Board
certify that the Board adopted the above Opinion and Order
this
1st
day of December, 1971 by
a vote of 4—0.
Christan Moffe
/
Acting Clerk
3—2*0