ILLINOIS POLLUTION CONTROL BOARD
    December
    21,
    1971
    CENTRAL ILLINOIS PUBLIC
    SERVICE COMPANY
    )
    PCB 71-261
    PCB 71—262
    v.
    )
    PCB 71—263
    )
    PCB 71—264
    ENVIRONMENTAL PROTECTION AGENCY
    THOMAS L. COCHRAN, ATTORNEY FOR THE CENTRAL ILLINOIS PUBLIC SERVICE
    COMPANY
    DELBERT
    D. HASCHMEYER, ATTORNEY FOR THE ENVIRONMENTAL PROTECTION
    AGENCY
    OPINION OF THE BOARD
    (by Mr.
    Kissel):
    On September
    3,
    1971,
    the Central Illinois Public Service
    Company
    (CIPCo)
    filed
    a petition for variance with
    the Board for
    four of its generating stations
    -
    Coffeen
    (PCB 71-261), Hutson-
    yule
    (PCB 71-262), Meredosia
    (PCB 71-263),
    and Grand Tower
    (PCB
    71-264)
    -
    from
    the applicable particulate regulations.
    Each
    generating station was under
    a program to install emission control
    equipment as detailed later in this opinion.
    CIPC0 had been granted
    an ACERP by our predecessor Board,
    the Air Pollution Control Board,
    but sought this variance because of our previous decision in the
    Commonwealth Edison case which held that ACERPs were indeed
    variances and could only be granted for
    a period of one year.
    See
    Commonwealth Edison Company
    v.
    EPA,
    PCB 70-4, February 17,
    1971.
    The Environmental Protection Agency filed separate recommendations
    for each of the stations generally advising that
    the
    variances
    should be granted with exceptions noted later in this opinion.
    Hearings were held
    in October and November of 1971 before Arthur
    Rosenblum, Hearing Officer.
    Case 71-261 involves the CIPC0 Coffeen Power station which
    is located three miles south of the city of Coffeen,
    Illinois in
    Montgomery County.
    It is surrounded mostly by
    farm lands.
    Presently,
    the Coffeen station has one coal fired unit in operation
    (Coffeen Unit
    #1) which has an operating capacity of 365 MWE.
    This
    Unit #1 presently emits its off gases through
    a 350—foot chimney,
    and
    is presently equipped with
    a mechanical dust collector with an
    efficiency of
    34.5.
    3—27~

    The key unit in CIPCo’s future plans is one presently under
    construction at the Coffeen station
    -
    Coffeen Unit
    #2.
    The sched~-
    uled completion date for this unit is March of
    1972.
    It will have
    an operating capacity of
    600 MWE,
    and will be equipped with
    an
    electrostatic precipitator with
    a collection efficiency of 99.
    A new 500—foot stack is being built at the Coffeen station and the
    off gases of both units will be emitted through the new,
    larger
    stack.
    The 350-foot Unit
    #1 stack, now being used, will,
    then,
    be dismantled.
    Coffeen Unit #2 will from the inception of its operation comply
    with
    the existing regulations concerning particulate emissions,
    according to CIPC0,
    and therefore
    no variance is being sought for
    the operation of that unit.
    Because of its size, however, bring-
    ing it in line in March of
    1972 will have an effect on the other
    “dirtier” CIPC0 units,
    as will be discussed later in this opinion.
    CIPCo does
    say, however,
    that Coffeen Unit #2 will need about six
    months time of operation before the other units
    in the line can
    be taken off.
    Coffeen Unit
    #1, on the other hand,
    is presently violating
    the particulate regulations.
    The present stack emission of Coffeen
    Unit
    #1,
    calculated by CIPCo is
    4.0 pounds per hour per million BTU,
    and the applicable regulations only permit 0.8 pounds
    an
    hrnr per
    million BTU.
    The Agency calculated Coffeen Unit #1 emits 12,000
    tons of particulates per year into the atmosphere.
    In addition,
    the emissions from the Coffeen Unit #1 are causing
    a problem with
    the
    local residents.
    Several of Coffeen’s neighbors testified at
    the hearing and described the dust from the unit which affects their
    lives.
    To the neighbors,the particulate emissions represented an
    almost unbearable source of dust so that windows in homes can’t be
    kept open,
    air conditioners had to be bought, yards could not be
    used
    for
    barbecuing,
    furniture
    gets
    dirtier
    faster
    and
    the
    paint
    on
    cars
    comes
    off.
    An
    Agency
    witness
    who
    did
    some
    ambient
    air
    sampling
    testified
    to
    being
    near
    the
    plant
    and
    feeling
    the dust get
    in
    his
    eyes.
    There
    is
    no
    question,
    from the uncontradicted evidence
    in
    the
    record,
    that
    the
    particulate
    emissions
    are
    interfering
    with
    the
    life
    and
    property
    of
    the
    people
    near
    the
    plant.
    CIPC0
    did
    present
    a
    program for controlling the particulate emissions from
    Coffeen
    Unit
    #1
    the
    installation
    of
    an
    electrostatic
    precipitator
    with
    a collection efficiency of 99.
    When installed,
    the precipi-
    tator will bring Coffeen Unit #1 into compliance with
    the existing
    particulate emission regulations.
    The Agency did not disagree with
    this,
    but the Agency did suggest that the time schedule for instal-
    lation of the precipitator could be accelerated.
    CIPC0’s schedule
    on Unit #1 calls
    for receipt of the precipitator in July of
    1972,
    but not actually installing it until
    1973.
    (The actual date on
    which Coffeen Unit #1 will have the precipitator installed and
    operating is June
    9,
    1973,
    and the unit will be shut down on March
    4,
    8— 27*

    1973,
    to begin the tie-in of the precipitator to Unit #1.
    Unit
    #1 will not be operated between March
    4 and June
    9,
    1973.
    See
    CIPCo’s petition for variance, paragraph 5).
    In the hearing
    the Agency suggested that Unit #1 be shut down some time in the
    fall of 1972
    (after Coffeen Unit #2 is reliably operational)
    and
    complete the installation before the time suggested by CIPC0.
    CIPCo’s witnesses agreed that from a technical standpoint the
    Agency’s suggestion on timing of installation could be done, but
    CIPCo argues that from a system reliability standpoint Coffeen
    Unit #1 cannot be shut down until
    1973.
    CIPC0 argues that it
    has a scheduled planned maintenance program which requires Coffeen
    Unit
    #1
    to be in operation until March 1973 so that certain other
    units
    in their system can operate efficiently and give reliable
    electric service to the CIPC0 customers when Coffeen Unit
    #1
    is taken down for installation of the precipitator.
    In addition,
    CIPC0 is
    a member of the Illinois-Missouri Power Pool, which
    also includes Illinois Power Company and Union Electric Company
    (Missouri).
    The membersof this Pool have scheduled staggered
    shutdowns~ofmajor turbine generators of the respective companies
    so that several
    large units are not out of service for planned
    maintenance at any one time.
    CIPC0 says that if the shutdown of
    Coffeen Unit #1 were required before March of 1973,
    this “would
    probably postpone the maintenance plans
    for other units thus
    affecting each of the three companies” and “would place all three
    companies in the vulnerable position of not having performed
    planned maintenance as scheduled resulting in decreased reliability”.
    According to CIPC0, a hardship to CIPC0’s customers could result.
    While we feel that control equipment should be put on as early
    as possible, we agree with CIPCo’s position in this case.
    The
    need for reliable electric power is
    an important consideration and
    outweighs the few months
    (five at most)
    during which Coffeen
    Unit #1 would not emit excessive amounts of particulate matter.
    Five months is
    a short time, particularly because they are late
    fall and winter months when the neighbors would be less likely
    to use the out-of-doors which has been taken from them by CIPCo
    in the past.
    CIPC0, then, will be granted a variance to operate
    Coffeen Unit #1 for one year in violation of the applicable par-
    ticulate standards with the understanding that its program is to
    shut down Coffeen Unit #1 on March
    9, l973,for the installation
    of an electrostatic precipitator and connection of the new 500-foot
    stack.
    In its recommendation filed in this case,
    the Agency recom-
    mended granting of the variance, but only on the condition that
    within ten months from the granting of the order of the Board,
    CIPCo develop a sulfur dioxide
    (SO2)
    emission program for Coffeen
    Units #1 and #2, which will”significantly reduce the sulfur dioxide
    emissions
    oh
    or before June
    1, 1974”.
    See paragraph 10(b)
    of the
    3— 27*

    Agency recommendation.
    To substantiate the need for SO2 reduction,
    the Agency introduced testimony of many neighbors who identified
    a sulfur odor in the area, which, the Agency said, was indicative
    of an SO2 problem.
    In addition,
    the Agency also mathematically
    calculated the ground level concentrations of SO2 and found
    tha:.
    if the mixing height of the stack was 5000
    feet,
    the ground level
    concentration of SO2 between 5.8 miles and 6.8 miles from the
    stack would be approximately 641
    mg/rn3
    (about
    .25 ppm).
    If the
    mixing height were lOCO feet,
    rather than 5000 feet, the cancer-
    tration of SO2 would vary between 400-3861 mmg/n3
    (.17 ppm to
    1.5 ppm)
    in an area between 2.3 and 50 miles from the plant.
    If
    the model were
    to be believed, concentrations near 1.5 ppm could
    pose a serious health problem, but as pointed out by a CIPC0
    witness, one of the assumptions made by the Agency in its calcu-
    lations was wrong, namely,
    the Agency assumed that the 350—foot
    stack would still be used for the emission of off gases from Coffeen
    Unit
    #1.
    In fact, CIPC0 plans
    to discontinue use of that stack
    and emit the off gases from both Coffeen Units
    #1 and #2 through
    a new 500-foot stack.
    CIPCo’s witness testified that this would
    make
    effective stack height greater, first, because the stack
    height itself will be higher and, second, because the greater
    heat flow through the one stack
    (rather
    tha’i two stacks) would cause
    the emissions to go higher in
    the air.
    The Agency calculations
    also assumed
    (when the high SO2 concentrations occurred)
    that the
    emissions from the Coffeen Units would not break an emission layer
    at 1000 feet.
    According to CIPC0, if both units are vented through
    the one 500-foot stack, any inversion at 1000 feet will be broken
    by the stack of off gas.
    CIPCo calculated that the ground concen-
    trations on a one—hour
    basis would be
    .17 ppm SO2 which calcula-
    tion is a factor of ten less than the Agency calculation.
    The Board is faced with deciding between two mathematical
    calculations, which differ by a factor of
    ten.
    The Agency calcula-
    tions were not based on the proper assumptions,
    and, therefore,
    if
    we were to accept one set of calculations
    or the
    other,
    we
    would
    accept that of CIPC0.
    However, we do not feel that it is appro-
    priate for the Board to consider the question of SO2 reduction in
    this case for basically two reasons.
    First,
    the Board
    is presently
    considering the adopti.on of statewide regulations on SO2 reduction,
    and second,
    the Agency only presented half a case here.
    As
    to the
    second point, we have previously held that where an SO2 problem
    was identified and control equipment was generally shown to be
    available and adaptable, we would order a boiler operator to install
    such equipment.
    See EPA v. City of Springfield, PCB 70—9, May 12,
    197
    However,
    that case was different from this case because that case
    was an enforcement case brought by the Agency to get SO2 control
    equipment installed and because
    in that case the Agency demonstrated
    3— 2*0

    at least on
    a prima
    facie basis
    that control equipment could be
    installed.
    The Agency here has demonstrated
    a possible problem,
    but has
    not demonstrated even on
    a prima
    facie basis that control
    equipment can be installed.
    In this
    case we
    feel,
    therefore, that
    CIPC0 need not submit a plan
    for controlling SO2 emissions.
    It may
    be, however,
    that in other cases where
    a variance is shown,that
    we will require
    the emitter or discharger to come forward with
    plans
    to control the source of pollution, even where the Agency
    has offered us proof that such equipment is available.
    There-
    fore, we will not require
    that CIPC0 study
    the ways of reducing
    SO2 emissions
    from its Coffeen plant at this time.
    This does
    not preclude, however,
    the Agency’s bringing an enforcement case
    against CIPC0 and proving at
    that time that control equipment is
    available and that the SO2 problem is
    a real
    one.
    Nor does our
    decision prevent the Board from adopting regulations in the near
    future which would require CIPC0 to install SO2 control equipment
    on the Coffeen units.
    Case #71-262 involves
    the Hutsonville Power station, which
    is located along the Wabash River
    in Crawford County,
    Illinois,
    two miles north of the City of Hutsonville.
    Hutsonville has
    four
    turbine
    generating
    units
    served
    by
    six
    coal-fired
    boilers
    (Boilers
    1-4
    serve
    Units
    #1
    and
    #2,
    Boiler
    5
    serves
    Unit
    #3,
    and
    Boiler
    #6
    serves
    Unit
    #4).
    CIPCo’s
    petition
    for
    variance
    on
    the
    Hutsonville
    Power
    station
    only
    involves
    Units
    #1
    and
    #2.
    Unit
    #3 already has an electrostatic precipitator installed with
    a tested efficiency of 99
    (CIPC0 has not yet operated this unit
    on other
    than
    a test basis).
    Unit
    #4 was scheduled
    to be shut
    down on October
    3,
    1971 to have
    an electrostatic precipitator
    installed,
    and the unit was to be placed back in service on
    November
    20,
    1971.
    CIPC0 does
    not intend to install any control equipment on
    Units
    #1 and #3.
    What CIPCo requests is that a variance from the
    particulate regulations be granted to CIPC0
    for Units
    #1
    and
    #2,
    so that those untis will be allowed
    to operate on
    a
    “hot standby”
    basis until September 30,
    1972, and then operate on “cold standby”
    until January
    1,
    1980.
    “Hot standby” means
    the boilers are main-
    tained near normal operating pressure and can be fired up to be
    able to produce steam in
    a minimal time.
    Generally,
    the furnace
    is fired 15-30 minutes every
    4 to
    6 hours
    to keep
    the pressure up.
    “Cold standby” means
    that no pressure
    is maintained in the boiler
    and
    to operate it
    a
    fire would have
    to be placed in the boiler.
    However,
    in order to assure that the unit can be operable,
    a fire
    must beplaced
    in the boiler about every three months
    for a 4-6
    hour period.
    The reasons~given by CIPC0
    for needing Units
    #1 and #2 on
    a
    hot standby basis
    is to allow
    for time for testing the new Coffeen
    Unit
    #2, which
    is scheduled
    to go on line in March,
    1972.
    CIPCo
    says
    that until there
    is
    an adequate shakedown of Coffeen Unit #2
    (about six months),
    it will
    not be
    a reliable enough unit and
    3—281

    —6—
    therefore the Hutsonville Units #1 and
    #2 will provide the backup.
    While the Agency recommended that.Hutsonville Units
    #1 and *2
    be placed on
    “cold standby” when Coffeen Unit #2 comes on line,
    we
    feel that CIPC0’s position has merit.
    The need for reliable
    electrical service during the summer demands of 1972 are impor-
    tant and there was no testimony that the present operation of
    Hutsonville Units
    #1 and
    #2
    (presently on
    “hot standby”)
    is
    causing any problem with
    the neighbors.
    In
    fact, the emissions
    should be much lessened from the whole plant because the two
    larger units at Hutsonville now are supposed to have operating
    electrostatic precipitators
    to reduce the
    off gas emissions.
    We
    will,
    therefore, allow the Hutsônville Units #1 and #2 to operate
    on
    a “hot standby” basis until September
    30,
    1972.
    The second part of the petition
    for variance regarding the
    Hutsonville units
    is a more difficult question.
    CIPCo asks
    that
    Hutsonville Units
    #1 and #2 be allowed to operate on
    “cold standby”
    until January
    1,
    1980.
    During this time,
    (from September
    30,
    1970
    to January
    1,
    1980)
    it may very well be
    that Units
    #1 and
    #2 will
    never be operated excepf at the three—month intervals, but the
    likelihood is that the units will be operated at some time.
    In
    either case, however, this Board has not favored programs which
    stretch
    far into
    the future and which do not contain pollution
    control programs.
    See Mt.
    Carmel Public Utility
    v.
    EPA,
    PCB
    71-15,
    PCB 7l-l5R, decided April
    14, l97land November
    11,
    1971.
    If Units
    #1 and #2 are valuable
    to CIPC0 and if they are to be opez~at~4at
    any time during the next eight years,
    it
    is worth the price now
    to install the necessary control equipment.
    We can understand
    that CIPC0 needs the units on
    “cold standby”
    for
    a short time,
    until January
    1,
    1974, but after
    that,
    if CIPC0 wants to use the
    units,
    it can only do so if it complies with the Act and the
    applicable regulations.
    We will, therefore, approve the use of
    Units #1 and #2 on a “cold Standby” basis after September
    30,
    1972,
    as long as it is on
    a long term program to use those units after
    January
    1,
    1974 only
    if their emissions comply with
    the Act and
    the applicable regulations.
    Case 71-263 involves the Meredosia Power Generating Station
    which
    is located along the Illinois River about one mile south
    of Meredosia, Illinois
    in Morgan County.
    Meredosia plant has three
    turbine power generating units served by
    five boilers
    (Boiler 1-4
    serve Units
    #1
    and
    #2 and are connected
    in such
    a way so
    as to
    permit any boiler to supply steam to etther of the
    two units, and
    Boiler
    5 serves Unit #3).
    CIPCo’s petition for variance regarding
    the Meredosia Station only involves Boilers #3 and
    4 which serve
    Units #1 and
    #2.
    ~An electrostatic precipitator has already been
    installed on Unit
    #3 and by now already is operating.
    Boilers
    #3
    3— 282

    and
    #4
    are Dresently having an electrostatic precipitator installed
    beginning on October
    24,
    1971, and completion of the precipitator
    was scheduled for November
    20,
    1971.
    Boilers
    #1
    and
    #2
    are the subject of the variance petition
    here.
    CIPCo’s
    plan calls
    for shutting down
    the boilers beginning
    on March
    26,
    1972, with
    the boilers scheduled to have construction
    of
    the precipitators completed on April
    22,
    1972.
    Presently
    Boilers
    #1 and
    #2 each
    vent through
    a separate stack
    and emit approxi-
    mately
    6.66 pounds per million BTU, which
    is
    in excess of the present
    state standard of
    0.8 pounds per million BTU.
    The Agency recom-
    mended granting of
    the variance
    for the time specified by CIPC0.
    We
    -ac~ree.
    There
    is
    no evidence
    that CIPCo can shut down Boilers
    #1 and
    #2 now to complete
    the installation
    sooner.
    While
    the
    Agency did receive some complaints
    about
    the emissions,
    no one
    appeared to testify that the schedule on Boilers
    #1 and
    #2 should
    be moved up.
    We think that
    the schedule
    for completion of instal-
    lation
    is
    a reasonable one,
    and hereby grant the variance as re-
    quested by CI?Co for
    the Meredosia Power Station.
    Case 71-264 involves the Grand Tower Power Station which is
    located on
    the Mississippi River approximately three miles north
    of the City of Grand Tower in Jackson County,
    Illinois.
    The
    Grand Tower Station has four turbine generator units which are
    served by nine coal-fired boilers
    (Boilers
    1-6 provide steam for
    Units
    #1 and
    #2, and each boiler can produce steam
    for either unit,
    Boilers
    7 and
    8 provide steam
    for Unit
    #3,
    and Boiler
    #9 provides
    steam for Unit #4).
    Units
    #3 and
    #4
    are presently operating with
    installed electrostatic precipitators with collection efficiencies
    in the range of 95.6
    to 98.7.
    Only Units
    #1 and #2,
    each with
    a generating capacity of
    25 MWE,
    are the subject of the petition
    for variance.
    The Units
    #1
    and
    #2 are presently on “cold standby”
    and CIPCo’s request for variance
    asks that we allow these units
    to
    remain on cold standby until September 1972, when Coffeen Unit
    #2 will be able
    to provide reliable electric service.
    After that
    date CIPC0 intends to retire the units.
    The Agency recommends
    granting of the variance,
    but suggests that the Board require the
    units to be physically dismantled at that time.
    While we aqree with
    the Agency
    that
    the variance should be
    granted,
    we do not
    agree that we should require as
    a condition of
    the variance that the units be physically dismantled.
    Without a
    variance, CIPCo cannot operate the units
    on any basis,
    “cold
    standby” or otherwise, without control equipment.
    Since these
    units would be the only
    “non-controlled” emission sources on the
    site,
    it would be relatively easy
    to know
    if and when the units
    3- 283

    are operated.
    We think that CIPCo has demonstrated
    a need
    for the
    “standby” of
    these units until September
    30,
    1972.
    The “standby”
    status will allow CIPC0
    some flexibility
    if Coffeen
    #2 doesn’t
    operate
    to specifications and,therefore, will allow CIPCo
    to pro-
    vide reliable electric service
    to its customers.
    Here,
    as
    in two
    of the three other cases,
    no one testified as
    to any effect of
    the particulate emissions;
    rather the people interviewed by the
    Agency had no objection
    to .the granting of
    the variance.
    We will, however,
    require that CIPC0 report to
    thEa Bottd~
    and the Agency within ten d~s after any operation of
    the two
    units.
    This includes the testing of the units as well.
    If the
    units are fired other than
    for testing,
    CIPCo will have
    to state
    in the written report to
    the Board and Agency
    the reasons
    for
    the use of the units.
    As
    a general condition
    to the granting
    of. th~variances,
    the
    Board will require that CIPCo post
    a bOnd
    to insure performance
    of the acts detailed
    in~the granted program.
    The Agency recom-
    mended that
    a bond be required,
    and we believe that under
    the Act
    a bond is rnar~datorybecause the hardship complained of consists
    “solely of the need for
    a reasonable delay in which to correct
    a
    violation of the Act or of
    the Board regulations’.
    Section
    36(a)
    of the Act.
    In addition to the bond,
    the Board will also require,
    as
    it
    has in other cases of this
    type, quarterly reports from CIPCo
    which must detail how CIPC0 is progressing on each of
    the control
    facilities.
    See Illinois Power v.
    EPA, PCB 71-193,
    and
    PCB 71-195-8,
    decided September
    30,
    1971.
    This opinion constitutes the Board’s findings
    of fact and
    conclusions
    of law.
    ORDER
    Upon examination of
    the record,
    CIPCo
    is hereby. granted
    a
    variance for
    a period of one year from this date
    to emit particu-
    late matter in excess
    of regulation limits as follows and so long
    as
    the program outlined below is complied with:
    1.
    (PCB 71-261)
    From Unit #1 at the Coffeen
    Station until March
    9,
    1973.
    3— 284

    2.
    (PCB 71—262)
    From Units #1 and #2,
    at the Hutson—
    ville
    Station,
    until
    January
    1,
    1974,
    provided
    that:
    a.
    Units *1 and *2 shall be
    on
    “hot
    standby”
    as defined in the Board’s opinion only
    until
    September
    30,
    1972;
    and
    b.
    After
    September
    30,
    1972,
    Units
    #1
    and
    #2
    shall be placed
    on
    “cold
    standby”
    as
    de-
    fined in the opinion,
    only until January
    1,
    1974.
    3.
    (PCB 71-263)
    From Boilers
    #1 and #2,
    at the
    Meredosia
    Station,
    until
    March
    26,
    1972.
    4.
    (PCB 71-264)
    From Units
    #1
    and #2, at the
    Grand
    Tower
    Station,
    until
    September
    30,
    1972,
    provided
    that
    during
    this
    period
    the
    Units
    shall
    only
    be
    operated
    on
    a
    “cold
    standby”
    basis
    as
    defined.
    All
    on
    condition
    that
    the following are met:
    5.
    All existing emission control equipment shall
    be maintained
    and fully utilized.
    6.
    CIPCo
    shall
    within
    thirty-five
    (35)
    days
    after
    receipt of this order post with the Agency
    a
    bond
    or
    other
    security
    in
    the
    amount
    of
    $500,000
    in
    a
    form
    satisfactory
    to
    the
    Agency,
    which
    sum
    shall
    be
    forfeited
    to
    the
    State
    of
    Illinois
    in
    the
    event
    that
    conditions
    of
    this
    order
    are
    not
    complied
    with
    or
    the
    facilities
    in question are operated after expiration
    of these variances in violation
    of regulation
    limits.
    7.
    CIPCo
    shall
    file
    quarterly
    written
    reports,
    commencing
    on
    March
    31,
    1972,
    with
    the
    Agency
    and
    with
    the
    Board,
    detailing
    its
    progress
    toward
    completion
    of
    the
    program.
    8.
    CIPCo
    shall,
    within
    ten
    (10)
    days
    after
    use,
    file a written report with
    the Board and with
    the Agency, detailing when,
    for how long, and
    why any units or boilers on
    a
    “cold standby”
    basis were used.
    3— 28~

    .9.
    Failure to adhere to the programs as pre-
    sented or to the conditions of this order
    shall
    be grounds for revocation of these
    variances.
    10.
    CIPCo
    shall
    apply for any desired extensions
    of any of these variances
    to complete the
    programs approved today not later than ninety
    (90) days before expiration of that particular
    variance.
    I,
    Christan Moffett, Acting Clerk of the Pollution Control
    Board
    certify that the Board adopted the above Opinion and Order
    this
    1st
    day of December, 1971 by
    a vote of 4—0.
    Christan Moffe
    /
    Acting Clerk
    3—2*0

    Back to top