ILLINOIS POLLUTION CONTROL BOARD
    November 23, 1971
    In the Matter of:
    Application of Commonwealth
    )
    PCB 70-21
    Edison Company for a Permit
    for Dresden
    Unit
    3, Dresden
    )
    Nuclear Power Station
    )
    Opinion of theBoard (by Mr. Kissel):
    On March 3, 1971, this Board issued a permit to Commonwealth
    Edison Company (“Edison”) to allow it to operate Dresden Unit 3
    a nuclear power generating station near Morris, Illinois. The
    Board~sprevious opinions detail the facts and reasons behind the
    issuance of the permit and the conditions contained therein, and
    those reasons and facts will not be repeated here, except as rele-
    vant to this ~articular part of the permit proceeding. The permit
    required that Edison submit certain reports concerning the installa-
    tion of control equipment for gaseous radioactive emissions, liquid
    radioactive discharges and heated water discharges as detailed in
    the following paragraphs of the permit:
    “3(b) The permittee shall within thirty (30) days after the
    issuance of this permit submit to
    the
    IPCB a written program with
    a time schedule for controlling the liquid radioactive discharges
    up
    to the amounts set forth in paragraph 3(a) of this permit from
    Dresden
    Unit III without the use of dilution water.
    “4(b) Within thirty (30) months from the date of issuance of
    this permit, permittee shall construct and install facilities on
    Dresden Unit
    3
    to
    reduce
    gaseous radioactive emissions permitted
    by paragraph 4(a) of this per~rtit by a factor of fifty (50). Within
    thirty (30)
    days
    after the date of the issuance
    of
    this permit,
    permaittee shall submit
    a
    written program to the IPCB for designing,
    constructing and installing
    the
    control facilities required by
    this
    paragraph~ Said written program shall include a detailed descrip-
    tion
    of the proposed facilities, the
    times when the design, purchase,
    installation
    and construction
    of the
    facilities shall
    be
    completed
    and any other information as would be needed
    by
    the IPCB to
    properly
    evaluate
    the
    amount of
    time needed by
    the permittee and its con—
    tractors1 if any,
    to complete
    said facilities.
    3
    125

    “5(b) Permittee in the operation
    of Dresden Unit
    3 shall
    comply with the thermal discharge
    requirements of SWB-8 as
    inter-
    preted in the opinion of~eBoard, In
    order to assure such
    com-
    pliance, permittee shall submit the following information to the
    Board within thirty (30) days from this date:
    1. Engineering information and costs on the kinds
    of additional facilities, if any, required to meet the standard
    covering heated discharges allowing for a mixing zone of 600 feet,
    2. The time required to construct the additional
    facilities referred to in paragraph l~.
    3, If additional time is required, the reasons why,
    in accordance with the variance provisions of the Environmental
    Protection Act and of the Board1s Procedural Rules, operation of
    Dresden Unit 3 should be permitted during said construction,”
    Edison filed the “thir~yday” report on April 13, 1971. It not
    only contained the many alternate programs called for by the con-
    ditions of the permit, but also contained a request by Edison to
    reform certain of the other conditions of the permit, that is,
    those dealing with the permitted gaseous emissions before control
    equipment is installed and the use of an emission reduction (in-
    stead of a dose reduction) factor as a measure of the effective-
    ness of the ‘radioactive gaseous emission control equipment. After
    receiving the detailed Edison report, the Board requested that the
    Institute for Environmental Quality (the “Institute”) employ the
    services of experts who could review the report and offer expert
    comments on the various alternatives proposed by Edison, The Insti-
    tute did hire three persons well qualified to review the report
    --
    Dr. Hermen Cember of Northwestern University, Dr. James Leonard of
    the University of Cincinnati and Dr. Henry Bremer, President of
    Datagraphics, Inc. The Institute’s experts did, in fact, file
    written reports which contained a detailed examination of the Edi-
    son alternatives, When Edison received the reports, it requested
    a hearing be held so that the various alternatives could be aired
    in a public forum. A hearing was held on October 19 and 20, in
    Chicago, Illinois,
    There are three basic areas in which the Board must make deci-
    sions as a result of the most recent hearings in this case: I) The
    gaseous emission control equipment which must be installed by Edison;
    2) the liquid radioactive control equipment to
    be
    installed by Edi-
    son; and 3) the futhet controls, if
    any,
    to be installed in order
    to reduce the thermal input into the Illinois River. Each of these
    areas will be considered separately, although there is a relation-
    ship between some of the issues.
    3— 126

    Gaseous Radioactive Controls
    Before reaching the actual control equipment discussion, it
    is necessary to discuss the interim radioactive emission limits
    imposed as a condition in the original permit issued to Edison,
    The permit provided in paragraph 4(a) as follows:
    “The release rates of gross beta-gamma radio-
    activity of gaseous effluent released to the environs
    from DresdenUnit 3 shall not exceed a monthly average
    release rate of twenty-five thousand (25,000) micro-
    curies per second and on no occasion shall the emis-
    sions exceed one hundred thousand (100,000) microcuries
    per second.”
    This part of the permit was taken almost directly from the testimony
    of an Edison witness who testified, in essence, that an annual
    average emission rate at the Dresden 3 unit of 25,000 microcuries
    per second at the Dresden plant would be “average to good” fuel per-
    formance, An instantaneous emission of more than 100,000 micro—
    ounce per second would indicate “fair to poor” fuel performance.
    While the witness himself did not feel that an instantaneous emission
    rate should be adopted, the Board felt that this was a point at
    which emissions should be limited because we did not wish to encour-
    age Edison to continue to allow “poor” fuel performance. Since the
    original Dresden 3 hearings, there has been much testimony by
    General Electric and Edison personnel about paragraph 4(a) of the
    Dresden 3 Permit, In a hearing on the application for a permit to
    operate two identical boiling water reactor power generating units
    at Quad Cities, the same witness who had previously substantiated
    the emission levels in paragraph 4(a) of the Dresden 3 Permit, testi-
    fied that what he meant to say at the Dresden hearing was that the
    emission level Of 25,000 microcunies per second was an average to
    be sustained “over the years” and was not meant to be an annual aver-
    age, His testimony in the Dresden 3 hearing, however, was contrary.
    (See, Transcript of Original Hearing, December 9, 1970, page 480).
    Be that as it may, we are convinced, based upon new testimony in the
    Quad Cities hearing and the most recent hearings on the hardware to
    be installed at Dresden, that a new emission level should be set
    for the gaseous radioactive emissions prior to the installation of
    control equipment. The Quad Cities testimony demonstrated that a
    realistic emission level would be 80,000 microcunies per ~econd as
    an annual average for the operation of one unit essentially identical
    to Dresden 3, and this was adopted as the interim emission level in
    the recently issued permit for the Quad Cities plant. See Permit

    and Opinion of the Board, In the Matter of the Joint Application of
    Commonwealth Edison Company’and Iowa-illinois Gas & Electric company
    (Quad
    Cities Permit), PCB 71-20, deôided November 15, 1971, In the
    Quad Cities case the single unit emission level of 80,000 inicrocuries
    per second would produce a fencepost dose of about 157 millirem per
    year. The testimony in the Dresden 3 hearing demonstrated that
    the 80,000 inicrocurie emission from one unit would result in a fence-
    post dose of about 44 millirem per year. Of course, the fencepost
    dose is normally reduced by a factor of three because no one lives
    at the fencepost twenty-four hours a day, 365 days a year. With
    this
    factor reduction, the actual
    emission
    rate and dose to the public
    is still very low even at the emission level of 80,000 microcuries
    per year, considering the fact that background radiation provides a
    yearly dose to the public of about 100 millirem.
    The most recent hearing on the Dresden 3 hardware produced testi-
    mony that the expected annual average emission rate at Dresden 3,
    assuming the unit operated at full power for the entire year, is
    90,000 microcuries per year. The
    number
    was obtained by looking at
    the actual performance ‘~of the two large Dresden units, 2 and 3, at
    less than full power levels, and applying a computed factor increase
    of the emissions for operation at full power. According to Mr. Stiede,
    the 90,000 microcurie emission level could be sustained on a monthly
    basis, and as far as a yearly average is concerned, the unit can be
    expected to be operated about 75 of the time; therefore, an annual
    average of 67,500 microcuries per second could be maintained, We think
    that this level of emission is very close to the one proposed in the
    Quad Cities application hearing and in order to assure greater leeway,
    we adopt the Quad Cities standard for Dresden. We, therefore, be-
    lieve that based upon the new testimony of the actual performance of
    the units at Dresden, paragraph 4(a) of the permit should be amended
    as follows:
    “Gross beta—gamma radioactivity of gaseous emissions
    released to the atmosphere from Dresden Unit 3 shall not
    exceed an annual average of 80,000 microcuries per second,”
    The
    rates of emission at this level will not cause a significant in-
    crease of the dose to the population around the plant.
    With the establishment of a new interim emission rate for
    Dresden 3, we do believe that the action level suggested by Edison
    at the Quad Cities hearing should also be adopted for Dresden
    3
    for the same reasons as outlined in the Quad Cities opinion. We
    therefore will require that if the gaseous radioactive emissions
    from Dresden 3 exceed 37,500 microcuries per second at any time,
    Edison shall initiate operating procedures, to the extent permitted
    without interrupting electric service, to reduce such release.
    3— 128

    In the original permit Edison was required to construct gas-
    eous emission control facilities within thirty (30) months from the
    date the permit was issued, which facilities would reduce the “gaseous
    radioactive emissions
    . . .
    by a factor of fifty (50).” Paragraph 4(b)
    of the Dresden 3 Permit. The intent of that paragraph was to require
    that Edison construct, install and operate the catalytic recombiner
    and eight charcoal beds to treat the air ejector effluent. This,
    according to Edison, would result in an emission reduction by a fac-
    tor of 40 and a dose reduction by a factor of 80. Edison has already
    begun its program to install this equipment, and, in fact, the comple-
    tion date will be earlier than originally anticipated
    —-
    the present
    completion date now hoped for by Edison is April 1, 1973, and we
    will hold them to that date. We will also modify the language of
    paragraph 4(b) to be consistent with the rate at which gaseous radio-
    activity will be emitted from the air ejector system and the gland
    seal system. Since Edison has testified that the recombiner and eight
    charcoal beds will result in an emission reduction factor of 40, and
    since the record shows that as an annual average Edison can achieve
    an airejector emission rate of80,000 microcuries per second, we will
    require that after the installation and operation of
    the
    control
    equipment
    --
    which will be no later than April 1, 1973
    --
    Edison shall
    not emit more than 2000 microcuries per second gross beta—gamma
    activity from the air ejector off gas system. In addition, the gland
    seal system will result in emissions of about 1000 microcuries per
    second on an annual average, so that paragraph 4(b) will be modified
    to read as follows:
    “By April 1, 1973, Edison shall have completed
    the installation of a catalytic recoinbiner and eight
    charcoal bed system, as outlined in the record of this
    proceeding, to treat the air ejector effluent, On and
    after that date, gaseous radioactive emissions from
    Dresden Unit 3 shall not exceed an annual average of
    3000 microcuries per second. The latter emission limit
    shall include emissions from the
    gland seal.”
    Liquid Radioactive Controls
    The Permit originally issued to Edison for the operation of
    Dresden 3 provided that the liquid radioactive emissions from the
    Dresden 3 facility should not exceed l0~ microcuries per liter,
    Further, paragraph 3(b) provided as follows:
    “The permittee shall within thirty (30) days after
    the issuance of this permit submit to the IPCB a written
    program with a time schedule for controlling the liquid
    radioactive discharges up to the amounts set forth in
    paragraph 3(a) of this permit from Dresden Unit III with-
    out the use of dilution water.”
    3
    129

    In its “thirty-day” report Edison detailed for alternative systems
    which it indicated would meet the Board’s requirements under the
    above quoted condition of
    the permit.
    Alternate 1 is entitled, “Liquid Waste Dilution Station with
    Closed Cycle Lake”, This system involves a closed—cycle lake operation
    with sprays for Units 2 and 3 and the installation
    of a dilution sta-
    tion for Unit
    1
    condenser cooling water discharge. There would be no
    need for major modifications to the presently radwaste
    system. At a
    dilution station on the north side of the Dresden Unit
    2-3
    intake canal,
    250,000
    gallons per minute (gpm)
    would
    be piped to the Unit I dis-
    charge canal where it would mix with the existing 190,000 gpm of cool-
    ing water from Unit I. In addition, the 50,000 gpm of blowdown water
    from the lake would
    be piped to
    the Unit 1 discharge canal and mixed
    with the cooling
    water before discharge into the river, Units 2 and
    3
    discharge line would be rerouted to the Unit 1 canal and discharged
    into the canal to provide distribution of the waste across the canal,
    The waste would be mixed with the cooling water as it passed down the
    canal
    and
    would be released along with the Unit 1 liquid waste to the
    river at an activity level of 100 picocuries per liter, for the com-
    bined releases from all units, The 50,000 gpm blowdown will benefit
    management of the lake by limiting the buildup of impurities in the
    lake, The installed cost of the dilution station, and mlated costs,
    will be $2,898,000 and the operating costs will be $130,000, These
    costs would be in addition to the cost of $12,500,000 which is common
    to all alternates proposed by Edison, The time for completion of
    this alternate would be twenty-six months.
    Alternate 2 is entitled, “300,000 GPM Continuous Discharge of
    Cooling Lake Water for Dilution of Liquid Waste”. Under this system
    the liquid radwaste would not be changed from its present design.
    The water use system of the plant would be changed to require that
    only 300,000 gpm of water from the facility would be discharged to
    the river. This would require that the plant reuse either 700,000 gpm
    for six-pump operation and 420,000 gpm for four-pump operation. The
    discharge flow would travel through the existing Units 2 and 3 dis-
    charge canal to the river and would be discharged through a diffuser
    pipe. Under certain circumstances Dresden Unit 1 will have to be
    reduced in operation in order to meet the present SWBL8 standards.
    The cost to install this system would be $1,903,000 with operating
    costs of $40,000,
    Alternate 3 is entitled, “Maximum Recycle Liquid Waste System
    with Closed Cycle Lake”, This system would result in compliance of
    the radioactive standatd of 100 picocuries per liter with a minimum
    blowdown of 50,000 gpm which blowdown is only
    necessary
    to assure
    proper
    operation
    of
    the lake. The present waste collection system
    3
    130

    would not be changed, but additions would be made. The floor drain
    subsystem would be modified to permit recycling of most of the
    effluent, This would be accomplished by the addition of two deep
    bed demineralizers after the floor drain filter. These demineral-
    izers would provide ion exchange treatment. The water so treated
    could be returned to the condensate storage tank for recycling. A
    small amount of the recycled water, however, will not meet the con-
    densate purity standards and would have to be discharged to the
    canal, A floor drain surge tank would be added to serve as a con~
    tingency collector. Also as part of this proposed Alternate,
    the
    existing concentrators in the chemical waste subsystem would be
    utilized to remove dissolved impurities for solidification. The
    concentrator distillates would go to the collector subsystem for
    further
    treatrnent
    and recycling, and the waste salts will be drummed
    as
    solid wastes, This system would reduce the radioactivity from
    1.2 microcuries per second to approximately .009 microcuries
    per
    second, and this estimate is
    based upon fuel performance which would
    be approximately 0.1 microcuries per second. Thus, this alternate
    would allow for meeting the proposed effluent standard with the
    50,000 gpm blowdown, which is necessary for the proper operation of
    the
    cooling lake. According to Edison’s estimate, the total exposure
    from Dresden Units 2 and
    3
    to a person using river
    water as drinking
    water for his entire liquid intake is 0.0038 millirem per year. This
    alternate would also use the diffuser pipe for the Unit 1 discharge.
    The installation cost of this equipment will be $2,946,000 with
    operating cost of
    $165,000 per year. This system could be completed
    within 21 months.
    Alternate 4 is entitled, “Maximum Treatment Liquid Waste
    System with Closed Cycle Lake”,
    The
    waste collector system will re-
    main as is presently
    designed except
    that there will
    be a contingency
    collection system. There will be two
    parallel demineralizers in-
    stalled and a line from the floor drain sample tanks
    to
    the Contin-
    gency subsystem.
    All
    floor drain wastes complete recycling, but
    there will
    be a small
    amount not able to be recycled. This small
    amount will be routed to the contingency
    subsystem.
    In the chemical
    waste
    subsystem
    the chemical wastes will be concentrated, a~dnot
    discharged. In the decontamination subsystem, the wastes will be
    connected to the solid waste system, mixed with cement and drummed,
    The
    contingency subsystem
    is completely new and will allow
    the dis-
    charge of 100
    picocuries per liter without the use of dilution.
    This system will include a floor drain surge tank, two 2&-gpm con-
    centrators, two 500-gallon distillate tanks, two demineralizers with
    10
    ft.3
    of ion exchange resin each and two 30,000-gallon sample tanks.
    There will be a large contingency collector tank of approximately
    200,000 gallons. As has been previously stated, the discharge of
    radioactive liquid wastes would be met before mixing with the blow-
    down water.
    Unit
    1, in this alternate as well, would have its
    discharge routed through
    a diffuser pipe. The installation cost
    of this alEernate
    would be $4,498,000 and the operating cost would
    be $300,000,
    3— 131

    In providing to the Board the four Alternates for treatment
    of liquid radioactive wastes and heated water discharges, Edison.
    has complied fully with the condition of the permit requiring these
    submissions. The first opinion of the Board in the Dresden
    3
    case
    did make the point that dilution should not be used as an alterna-
    tive to the treatment of liquid radioactive wastes. We feel that
    although dilution water is still used, Alternate 3, the “Maximum
    Recycle” alternative, is the perfect blend of applying present
    technology with economic reasonableness for keeping the level of
    liquid radioactive discharges at a “safe” one,
    Alternate
    4 does
    comply with the “no dilution” concept, but we believ~that
    the addi-
    tional capital costs for
    Alternate 4 (over $2 millio~) is simply
    not worth the minimal reduction gained by using
    Alternate 4
    over
    Alternate 3. We will,therefore, order the installation of Alternate
    3, as described in the record, and in addition will
    require that the
    decontamination solutions be sent to
    solid waste disposal by putting
    the wastes into cement and drumming it for disposal. This recommen-
    dation was made by one of the Institute’s consultants and seems a
    reasonable one,
    Edison also raises the point that tritium should be handled
    differently in the permit and we agree. We, therefore, modify the
    permit and substitute the following paragraphs for paragraphs 3(a)
    and 3(b):
    “(a) Radioactivity in liquid effluents shall be
    controlled so that the annual average gross
    beta-gamma
    radioactivity, excluding tritiuiu,discharged to ~the
    Illinois River shall not exceed 1x107 microcuries per
    cubic centimeter (100 picocuries per liter) and annual
    average tritium activity discharged to the Illinois
    River shall not exceed 3xl04 microcuries per cubic
    centimeter,
    “(b) Edison shall immediately begin to install
    the system described in the April 13 report as the
    maximum recycle system (Alternate 3), a system which
    would require that the decontamination solutions be
    drummed
    and disposed of as a solid waste,
    Installa-
    tion of the system as required herein shall be com-
    pleted by September 1, 1973, and thereafter the emis-
    sion limits of paragraph 4(a), herein, shall apply to
    the blowdown of the cooling lake,”
    3
    132

    Heated Water Controls
    Under the Dresden permit Edison was required to submit to
    the Board a plan for bringing the heated water discharges from the
    Dresden 3 plant into compliance with the standards of SWB-8. Since
    the issuance of the permit Edison has put the cooling lake into
    operation and has installed 98 spray modules in the canals at the
    Dresden facility. Even with those installations Edison has admitted
    that its heated water discharges will not meet the SWB-8 standards
    all the time. As stated by Mr. Ellis of Edison, the discharge from
    Dresden will meet the 93°F, temperature at all times, but will not
    meet the 5°F,after the 600’ mixing zone in the winter months under
    certain conditions. However, when Alternate 3 is completed by
    September 1, 1973, and the cooling lake is being operated closed
    cycle, and the discharge is passed through a diffuser, these condi-
    tions will be met.
    It is obvious that using Alternate 3, which is basically the
    closed cycle operation of
    the
    cooling lake, Edison has met the
    Board’s request that it find a method to meet the standards in SWB-8.
    From the uncontradicted evidence, all discharges, even that of
    Dresden 1, will meet
    the standards of SWB-8, when the closed
    cycle
    system is installed in September of 1973. This is indeed an example
    of compliance with the wishes of the Board.
    Edison askes that it be granted a variance to fully operate
    the Dresden units, even though during certain times
    in the winter
    it will not meet
    the 5°F.limitation at
    the end of the 600’
    mixing
    zone. To be granted a
    variance
    Edison must prove, as we have said,
    that compliance with the Rules, SWB-8 in this instance, would
    impose an arbitrary or unreasonable hardship, We believe that Edi-
    son has proved that such a hardship exists here. The harm to the
    River will be minimal because the violations of the temperature stand-
    ards will occur only in the wintertime, when the system is best able
    to take the additional heat. To require a cutback in the operation
    of the units could mean that electric power will not be available
    when the system demands it, For the little amount of damage., if any,
    that will occur as a result of the slight breach of the Rules, we
    do not feel that it is worth controlling that discharge by
    requir-
    ing
    that the production of power be cut back.
    The cost would be too
    high, and therefore, we grant the variance from the 5°limitation
    of
    SWB-8
    durinq the winter months until November 23, 1972. Edison can,
    if
    it desires, file a petition to extend that variance until September
    1, 1973, so
    long as the petition is filed not later than ninety (90)
    days before November 23, 1972. It is our intent at this time to
    allow the variance until the cooling lake is in operation, but the
    Act does not allow variances longer than one year.
    3
    133

    One other point concerning heated water discharges must be
    dealt with. On September 24, 1971, Edison directed a letter to the
    Board, in the nature of
    a petition for variance, asking for a var-
    iance
    covering heat discharges to the Illinois River because the
    cooling lake may not have operated by October 1, 1971, the date
    originally set by the Board, Since the testimony by Mr. Ellis
    is
    that the cooling lake is operating,the question of the variance
    requested in the letter of September 24, 1971
    is
    now moot and
    therefore will be denied as such.
    Emergency Core Cooling
    The
    subject of the emergency core cooling systems in Dresden
    Unit 3 were not
    really dealt with in any of the hearings specific-
    ally related to that Unit. However, the Board has had hearings
    related to that
    matter in the Quad
    Cities application. Since each
    Quad Cities unit
    is
    almost a “carbon copy” of the Dresden Unit 3,
    the testimony gained on the subject of core cooling in
    the Quad
    Cities case is certainly applicable here. In the Quad Cities
    opinion, we concluded the following after
    reviewing the testimony
    on the subject of core cooling:
    “While we shall maintain a continuing concern
    for this and all other matters related to possible
    radiation hazards, and while we shall provide that
    the permit may be modified or revoked if this is proved
    necessary by new information, we do not perceive’a
    justification today for withholding the permit.”
    In essence, then, we feel that the core cooling problem may be a
    real one and needs close supervision. It is for this reason that
    the Dresden Unit 3 permit is herein modified to require reporting
    of any activation, whether spurious or real, of the emergency core
    cooling system. This information, when provided and analyzed, will
    provide the basis, perhaps, for decisions in the area of emergency
    core
    cooling.
    While we
    do not feel the evidence warrants any more action
    than reporting of activation of
    the
    emergency core cooling systems,
    we do know from
    the evidence
    in
    the
    Quad Cities record that
    the
    Dresden Unit 3 should not be operated
    if
    ~ny of the emergency core
    cooling systems are unable to operate. This will be a condition of the
    permit, for to do otherwise would create a radiation risk which the
    public should not be forced to accept.
    This opinion constitutes the findings of fact and conclusions
    of law of the Board.
    3—134

    ORDER
    Based upon the testimony and exhibits in the record, the
    Board hereby orders the following:
    1. The Permit issued by
    the
    Board to Edison on March 3,
    1971 for the operation of Dresden Unit 3 is hereby amended as
    follows:
    (a) Paragraphs 4(a)
    and
    4(b) of the original permit
    are hereby replaced by the following paragraphs:
    “4(a)
    Gross beta-gamma radioactivity of
    gaseous emissions released to the atmosphere
    from Dresden Unit
    3 shall not exceed an
    annual
    average of 80,000 microcuries per second,
    “4(b) If gaseous radioactive emissions
    at any time exceed 37,500 microcuries per
    second from Dresden Unit 3, Edison shall ini-
    tiate operating procedures, to the extent
    permitted wit~outinterrupting electric ser-
    ‘~ice, to reduce such release,
    “4(c) By April 1, 1973, Edison shall
    have completed the installation of a catalytic
    recom.biner and eight (8) charcoal bed system,
    as outlined in the record of this proceeding,
    to treat the air ejector effluent, On and
    after that date gaseous radioactive emissions
    from Dresden Unit 3 shall not exceed an annual
    average of 3000 microcuries per second. The
    latter emission limit shall include emissions
    from the gland seal,”
    (b) Paragraphs 3(a) and 3(b) of the original permit
    are hereby replaced by the following paragraphs:
    “3(a) Radioactivity in liquid effluents
    shall be controlled so that the annual average
    gross beta-gamma radioactivity, excluding tn-
    tium, discharged to the Illinois-River shall
    not exceed lxlO7 microcuries per cubic centi-
    meter (100 picocuries per liter) and annual
    average tritium activity discharged to the
    Illinois River shall not exceed 3xl0’~4micro-
    cunies per cubic centimeter.
    3
    135

    “3(b)
    Edison shall immediately begin to
    install the
    system described in
    the
    April
    13
    report as the “maximum recycle” system (Alter-
    nate 3) plus a system which would require the
    decontamination solutions be drummed and
    dis-
    posed
    of as a solid waste. Installation of the
    system as required herein shall be completed by
    September 1, 1973, and thereafter the emission
    limits of paragraph 4(a), herein, shall apply
    to the blowdown of the cooling lake.”
    (c) Paragraph 7 of the Original permit is hereby
    replaced by the followinc; paragraphs:
    “7(a) Permittee shall cooperate to the
    full extent necessary with the Environmental
    Protection Agency and the Illinois Department
    of Public Health for purposes of development
    by those agencies of an adequate and effective
    emergency protection plan designed to imme-
    diately control and minimize the effects of
    any accidental release of unexpectedly large
    quantities of radioactivity from the Dresden
    Unit 3 nuclear generating plant. In particular,
    Edison shall immediately notify both the Environ-
    mental Protection Agency and the Illinois Depart-
    ment of Public Health of any uncontrolled
    release of unexpectedly large quantities of
    radioactivity to the offsite air and/or water
    environment due to operational failure of any
    of the power plant systems, and shall report
    monthly to the Board and the Environmental
    Protection Agency any activation of the emer-
    gency core cooling system, whether spurious
    or real, exclusive of testing.
    “7(b)
    Edison shall not operate Dresden
    Unit 3 if any of the emergency core cooling
    systems are unable to operate.”
    2. Edison is hereby granted a variance from the 5°F. limi-
    tation of SWB—8 during the winter months under the following condi-
    tions:
    (a) The variance shall end on November 23, 1972; and
    3— 136

    (b) If Edison seeks to extend the variance beyond
    that date to September of 1973 when it is contemplated
    that the cooling lake will be operated closed cycle, Edi-
    son shall file a petition for variance with the Board
    not later than ninety (90) days prior to November 23, 1972.
    I,
    Christan Moffett, Acting Clerk of the Pollution Control
    Board, certify that the Board adopted the above Opinion and Order
    this
    ..~
    day of November, 1971.
    Christan Moffet
    /29
    ~
    Acting Clerk
    3—1

    Back to top