1. i.Lnlts Is desI~nedto emit no more than 100,000 microcuries per

ILLINOIS POLLUTION CONTROL BOARD
November
15,
1971
In the matter of
JOINT APPLICATION OF
)
#
71-20
COMMONWEALTH EDISON CO. AND
IOWA—ILLINOIS GAS
& ELECTRIC CO.
(QUAD CITIES PERMIT)
O~inionof
the Board
(by Mr.
Currie):
Like in 70-21, Application of Commomwealth
Edison Co.
(Dresden
~3), decided March
3 and April
28,
1971, this is
an application under
Title \‘I-A of
the Environmental Protection Act for
a permit to
onerate
a new nuclear generating
station,
this one consisting
of two 809-mw boiling—water reactors at the Quad—Cities plant
near Cordova on the Mississippi River
in northwestern
Illinois.
We grant the permit on terms similar to those imposed in the
Dresden case, with differences
indicated below.
We note
that
there
are environmental considerations on both
sides in this case.
Petitioner Iowa-Illinois operates
an
old, smoky coal—fired power plant
in Moline that cannot be retired until Quad-Cities
is
in operation.
Every day’s delay
in bringing Quad-Cities
on line means another day
of dirty air
in Moline.
Sec Iowa-Illinois Gas
& Electric Co.
v,
EPA,
6
71-65
(Sept.
16,
1971).
The
statutory
framework,
the
operation
of
a
reactor,
the
environmental problems
and
their
means
of
control,
the
federal
radiation standards,
their derivation,
and their relation to
state law,
are all explained
in detail in our March
3 Dresden
opinion
and will not be repeated here.
The utilities raise once
again
the argument that federal
law deprives
us
of authority
to set standards for radioactive reactor discharges; we adhere
to
the
contrary
position
for
reasons
given
in
the
first
Dresden
opinion,
and
to the other lurisdicational and statutory interoretatio~
conclusions
there
reached.
As
held
in
Dresden,
our authority
in
this proceeding extends
to
all
environmental aspects of
the Quad—Cities
station,
the most
critical
of which
are gaseous
and liquid radioactive wastes,
protection
against
radiation
resulting
from
accident,
and
thermal
discharges
to
the
river.
We
also
must
examine
provisions
for
disposal
of~ .~olid radioactive
wastes,
for
ordinary
chemical
waste
and
sewage,
and
for
control
of
any
conventional
air
pollutants
that may be generated
by such sources
as boilers.
If construction
had not yet begun, we should be concerned with plant siting as
well.
But construction
is
all but complete.
Pursuant
bo permission
granted July
22
(see transcript of Board meeting of that date)
fuel loading
has
been completed
in
Unit
#1,
testing
at
significant
cower loads
is ready to begin, and full commercial service
is expecte~
in the
near future.
Unit
~2
is
to
be
loaded
in
November,
with
a
similar
testing schedule contemplating
full operation not long after
the
first
of
the
year
We shall discuss the several points of
environmental concern separately.
3—95

~.
Jaseous Radioactive Emissionr. Each of the two generating
i.Lnlts Is desI~nedto emit no more than 100,000 microcuries per
second ~.uCI/sec)
of gross activity,
and
with fair fuel performance
.s exzected to emit no more than 25,000 uCi/sec as a long—term
ave’ase
R. ~45l,5811,
593;
Environmental Feasibility Report,
r.
21), with monthly averages possibly ranging as much as
1~
1/2 times as high. (R. 454).
Emissions from other
sources are
far
smaller; the principal one is the turbine
~iandseals, which
are
expected to emit only 625 uCi/sec
(R.
1177).
Original
AEC
emission limits were designed in individual cases
so as to assure that the annual radiation dose to a hypothetical
person spending all his time in the open air at the plant boundary
(“fencepost”) wouldnot exceed 500 millirem (mr).
In the case
of Quad—Cities this standard could be
met
if emissions (except
for the
small
ventilation stack emissions) were limited to
350,000 uCi/sec when both units
are
operating at full power
and 250,000 when one is
(R.
11714).
Anticipating much better
performance than this, Edison
and
Iowa—Illinois have proposed
annual
emission limits of 110,000 uCi/sec and of 80,000, for
both units or for one, respectively, which would produce a
fencepost dose of 157 mr per year CR.
26, 474).
As the companies
point out, the actual dose to persons living or passing through
the vicinity will be significantly lower, since most people
live inside houses that provide some shielding, most do not
live at the property line, and most spend part of the time
away from the site.
Natural background radiation in the area
is said to yield an annual dose of 100 to 140 millirems
CR.
146; Environmental Feasibility Report,
p. 22).
Moreover,
at instantaneous emission levels Just under half the annual
average limits proposed (52,500 and 37,500 uCi/sec for both
units and for one), the companies pledge to
make
operational
changes if possible to reduce emissions at once and to look
toward early fuel replacement if necessary, since several
months may be required to rectify the sItuation without
unduly interfering with power production
(H.
26, 50—52).
Beyond this, however, as at Dresden, the utilities have
begun the design and are committed to the construction of
additional control facilities, consisting of a devibe for
reconbinin hydrogen with oxygen and e4ght charcoal beds to
afford a substantially longer delay before discharge ~sothat
short—lived isotopes
may
decay to insignificance.
These facilities
will cost $3,500,000
for
each of the two generating units
CR.
365—72); they will be completed within thirty months
after design was started, or about December 1973 CR.
28, 54);
they will reduce design level off—gas emissions fi’om each
unit
from 100,000 uCi/sec to less than 2500 (a factor of 40)
CR.
469,
473),
and
the annual fencepost off—gas dose from both
units operating at full power to 2.’I millirems, with an
3—Is

additional
0.08
mr/yr
O.8~J from the gland
seals, which
cannot
be routed throughthe charcoal system
(R.
365~-72,
478).
Utilizing
the
expected
annual
average
emissions
rather
than
the design figures,
the additional facilities would reduce
single—unit
emissions
to 625 and emissions from both units
operating together to
1250, •which when added to the gland seal
emissions of 625
each
unit?
would yield an approximate
site
emission of only
2500 uC.i/sec
and
a total fencepost dose
clearly
less
than
5 millirems per year.
The utilities contend that exposure to 170 millirems
per year is quite
safe, as
the ABC standards themselves incorporate
substantial margins
of safety below dose levels at which adverse
sQnatic
or genetic effects have been found
(R.
324),
There
is
of course
a school of thought
that the effects of radiation
are
in linear proportion to
the dose and that there
is no
threshold
(see the March
3 Dresden opinion fbr discussion).
Because of this possibility,
and in order to be especially
safe in dealing with such
a dangerous phenomenon as radioactivity,
we adopted in the Dresden case, and reaffirm here, the policy
of requiring use of the best practicable technology
for controlling
radioactive
emissions,
even though
a lesser degree of control
might suffice to avoid doses
set
to give breathing space below
levels
at which harm has
so far been discovered.
Accordingly
in Dresden
w~
adopted
limits
whose
effect
was
to require
the addition óf
a
r~combiner
and
eight
charcoal
beds,
and
we
do the
~
here,
as
the
companies
have agreed to do~
They
have agreed that
a fencepost dose of
5 millirems, which will be achieved by
this system,
is
a desirable
and achievable
goal
(B.
324,
474),
The ABC has recently required,
as
a numerical translation of the requirement of best practicable
control,
that the
dose to persons living near the
site
(which
should be
less than that at
the fencepost)
be limited to
5
mr/yr
(ABC Release
#778,
June
7,
1971)..
The companies propose
an interim emission
limit of 110,000
uCi/sec for all sources when both units operate and
80,000 when
one operates.
The recombiner
and charcoal beds will reduce
total site emissions by
a factor of
30.
Therefore, in light of
the reasons given above,
we shall reduce the proposed limits by
a factor of
30,
allowing
a small leeway
in rounding
off, to
4000 and
3000 uCi/sec, respectively,
as annual averages.
These
standards, based on poorer than expected fuel performance, will
allow some room for less than optimal operation,
since the
resultant doses are quite small.
We do not, however,
agree
with the companies that we should give such leeway (10,000
uCi/sec)
as to ignore the problem of excessive
fuel leakage;
the policy of best practicable treatment requires both good fuel
and good
controls.
We do
agree that there
is
no need
for monthly
averages, since at these
low levels only long—term exposures
are relevant and
since monthly values fluctuate enough that meeting
a strict monthly standard might impose
a significant hardship
(B.
454).
3
97

Very
~
~h~rt —ter..
e’t.
r
‘1
on-’
‘?
enurue
‘iuat
be
~.
r’~vented;
we
thlntc
tn!s
‘trobet
cm
be
,..Je?aatnt;
handled
by
the
AEC’s
accIdent
prov..aiono
and
t::
ra’ut~n~
the
coni aries
as
ajreed,
to
take
action
ehen
high emission levels (57,500 or
37,500
uCi/sec)
are
exceeded
on
an
lnjtantaneous
basis.
‘Ac
are
ur~edb.
thn
.~ttorr~e;
~enera
to
require
still
:urther
control
c
:tenc
ror~
.‘i:eouz
e:.itatan3.
Ct.
is
atCd
that.
“eon
.3ystems,
for
esnr
c.,
can
-
roiide
even
creator
de~reea
of
cont~ol than
can
ch2c.jas,
at
low...r
cot,
and
can
in
adcCtion
r~.’~ovt“rot.
the
affluent.
:aa
lon.;—flved
vadlo1.’flojns
01’
XCflOfl
and
kr;pt.n,
t.ch
are
not
r.xauc1’d
by
trw
..
.te
rianne’I
for
~uad—C1t..es
(~.
6S0—3).
ae
ec’: ‘miss
rest ona
t.nat
~uc’i
syatetto
iave mt
crt
teen
,~i’~m
Cu.
ez’ci’aLl
rs.~’:o..
for
fwtfltles
as
lar-•e
a.~:‘iad—C.
t:ea
and
that
It.
a~ ,e
.
‘n.e
unoe..’
:
:‘t.
e
to
concentrate
ai,d
~tnre
tha
:rtalL
uantl I.
I e~
gy’
Ion.’—
I
.‘ed
inotopec
‘rouLced
tnan
t-’
‘ii:
srse
ther,
.
-‘al
dilutea,
to
the
2tiorphere
(‘.
402—c)’.).
W.~ ri”:ed
riot
deude
tr,e
trick;
~
is
oL~ corn-norcial
t~ia11ab11tty,
fl.~.
.e
~çj~rjic~
the rharrcni
..“,;tr.1 sUl reduce
etlsa,on.
to
a
zer:’
t.ucier.t
ic
gc~J
hidec’a
tn.’ofar
~.s .:~‘o.s~
tcti’flty
,:,
concerrvt’i.
The
ro~
a.
..
c..f
tn’s
lcn;—lLJeo
l.~tone,
• on’zer,
Is
one
at
to
:‘
~
~:e
..‘
‘:.
to
ex!re~’os-
e
addltcna
caution
.
t
L’utra
u
jflt~~)•
~..
rtofl
S.,,
cn’ch
t:.I.
r
e’ Ittod
:oz~’c z~ndt2KCJ
a
cent.tr’
.o
‘Jaca:
to
Lnaicrilticiiace
(t.
o~a’J—’,t).
O:~e ~
trttiictc’i
4.’.’C.,
unlus,~
3OntrOl
‘riea:t’1fl21’
i’.’
In.:t.tutod,
‘i
gorldcide
buI1Qu’
ci’
‘ndloactiqe
kr::~tonwIll
ocor’
Mnt
tap
annual
do’s
to
r...io
Lo
‘•
“st’:.;;ae~efro’.
th::
JOuP’!C
w)J1
nau;h
.7
~.i’Jire:..,
°:
the
.
.~‘.
OX
1n1
17—fl
:.!
LJ.”o:
a~
2’:
to
3J
•.e.•p.
t:aereactcr
(It.
.,f
—5i,
64—6a).
C.J?fs
t.
tb”.
i
ro.”ctt’d
1w
‘1;
are
rather
1045 ‘t
.n’
~tra’
cure-.
v
~n e. lei”i-
nr
p4ier’:i’
.a’~I’O1t
;oea,
aria
certi.n~
the.r~ L
no
c’tn’:e
Cr’
‘1r-2’J~n.e f”t•.
‘.
1.’.
not
toe
soon
t
.~t’rt, nc.wev ~r,
tL
—s
..
‘3?
~,ot
tnt ~n’i
t
c
a
I
I’r:
the
I
n :—1 I ‘r’d
raa’
tt
an
Pot
L’t
to
•‘c
‘.t.
anotac:.
ao’:
-
:t ~
.:
~,
~
...j!•j..
c”.la:lor.:
..t
~
iut~’
.
a.
I
a’
t.~,
to !ni!
nI”
•..p,4,
irs
t—5-
:~
n
t;
‘.
t
~
d
‘:1’.’
—c’
s’”:
~.
~.i
I
‘.ccu’
~tat..
to
(U
at’’
in
r’n
a
cti”.’r,t
it..on
•_•
A.
-*0
f’.
I’
~_O
rain
.-
~‘)
~,t.
P
.i..
-
‘-
1j~’
~~y•..at’e
t’
K’
r
~
‘.r
Jt.-!:
Inn
—‘:~
;_
-.--
-
‘•:.
Ua~—’’Y’-
:r,
‘.
‘s.,~I
.1...
..~‘.!,..-
‘‘_it’~’;
I
•~,
‘f~
‘IJ(n,
:z’.’.
..an•
~
.
:~--
~
-
Cs.
~
:
~
:
~-
,
~t
•).‘t’i
‘1
ti’.
‘I.
£
o~.ct’v..~t
~‘
.L4:~
c.’.•
_Uj)
.t~tI
~
—.•
-
.4
I
,
t’
t’LC
t
~
t”t?
t’.
.
-t”:.
.t.
•‘1’itnOt
t-,
._I
‘:
•:.“i,
~‘
T.’.
-
:•
ri
ic.’’’t
•_
t,3’...
‘‘0.
:0.:
chaerr,l
n’~
(
.
-
I.
~‘,
.
.
,
:-
lit
Lart’.~~
aL’~nL’t.
~•
a
‘-•
-
..
....n~to
tilt)
3:fll’c,t’
t’Iit”)
.5’.
.4
,
I
.‘.
;av
...
‘u..~
-‘.
‘1.’
to
4I~’
‘~)tit
‘at
,~“
‘‘~~~-
‘i
-
4~nc
.t
‘2
-
I’Y.’
3.’
4
•~
£
:rui’—
::
1.,,~.
sq
:.,c’
•1’
‘ii’
•,j
~
a.
.‘

Construction of the recombiner and charcoal beds at Quad—
Cities will not be complete until December 1973, and the :plant
is ready for operation this year.
It
is badly needed both to
provide more adequate reserve capacity to guard against interruptions
of electric service
that would impose significant hardships.
on innocent customers
(see the detailed discussion in the April
Dresden opinion)
and to relieve the load on older fossil-fuel
plants
that contribute significantly to air pollution.
Most
significantly,
the operation of Quad-Cities will make possible
the greatly reduced use of coal at an inadequately controlled
station in Moline
(see Iowa—Illinois Gas
& Electric Co.
v.
EPA,
#
71-165,
Sept.
16,
1971).
At the same time the emissions from
Quad-Cities during the interim before completion of the additional
control facilities will be low enough to afford
a substantial safety
margin below dose
levels at which adverse effects have been
detected.
While we have required that those levels be greatly
reduced for additional safety in the future because they reasonably
can be, we hold as
in the Dresden case that
the plant should be
allowed to operate in the meantime subject to interim limits,
namely, that not more than the proposed 110,000 uCi/sec be emitted
from both units,
or 80,000 from either alone.1
2.
Liquid Radioactive Wastes.
The planned discha9e
of
gross activity to the Mississippi River from various sources
of liquid waste at Quad-Cities is
26 curies per year plus
30
curies of tritium
(R.
384).
The utilities intend to dilute
these radioactive wastes with cooling water to a concentration
of
1 x 10-8 uCi/cc
(excluding tritium)
in the discharge canal.
In the river further dilution will reduce concentrations to
7 x 10-10 uCi/cc, affording
a safety factor of 2300 below the
drinking-water standard of
1 x
10-7 uCi/cc
(which is based
on
a 500 mr/yr dose to
a hypothetical person drinking river
water exclusively),
so that the dose to one drinking solely
from the river would be 0.2 millirems per year.
Dilution would
also leave
a large margin below the drinking-water tritium
standard of
3 x 10—3 uCi/cc
(R.
481-83).
On the basis
of these
facts the companies contend that the expected doses are
so
insignificant that no further treatment
is worthwhile.
Confronted with
a similar situation
in the Dresden case,
we pointed out that dilution is not
an adequate substitute for
treatment because it is better to keep harmful materials out
of the environment than
to dilute
them.
This is especially
true of materials,
such
as certain radioisotopes, that retain
their dangerous properties
for long
times after discharge and
that can be biologically concentrated by organisms
as they
move up the food chain.
A utility witness acknowledged that
cesium,
for example, concentrates
in fish by
a factor of 100 or
1000
CR.
333-34)~ A ~1~ais~f
Fcr
the Attorney General testified
1.
These tigures were substantially confirmed by additional testimony
in
the
Dresden
case,
#70-21
(Oct.
19,
1971), which predicted annuaL
emissions in the neighborhood
of 67,500 uCi/sec from one unit.
99

that strontium 90
is concentrated
20,000
to 30,000
times
(R.
2168),
It may therefore be
that the
most
limiting aspect of liquid waste
discharges
is not drinking water but aquatic life.
It is true
that the total quantity of activity to be discharged to
the
water
is quite small as compared with that to be discharged to the
air
(26 curies per year as compared
with
several thousand microcuries
per second, even after maximum control).
But
the discharge
is
tc
a much more limited receptacle,
the river,
not to the enormous
atmospheric reservoir;
and, in light of the policy of keeping
as
much radiation out of the environment as we reasonably
can, we
think it important
to consider possibilities
for reducing liquid
radioactive discharges still further.
In response to our concern over this
issue,
the utilities
have with accustomed thoroughness described for us two alternative
systems that would provide dramatic additional reductions in
radioactive discharges to the river.
Neither system will remove
tritium from water,
for the evidence
is
that
cannot
be
done.
But
the “maximum recycle”
plan,
by
the
addition
of extra
ion—
exchange
demineralizers
in
the
floor
drain
system, would reduce
non-tritium activity to
2
x
10-5
uCi/cc
before
mixing,
reduce
the
total
non-tritium
discharge
from
26
Cl/yr
to
1,2,
and
reduce
the
non—tritium
dose
to
a
hypothetical
river
drinker
from
0.
2
to 0.009 millirems per rear.
This system would
cost
$5,000,000
and require
24 months
to construct
(R.
372-77, 483)~
Or,
with the
“maximum treatment” plan, utilizing further concentration,
distillation,
and
ion exchange, the companies think
it
probable
they
could
meet
the effluent standards
without
any
dilttion
(except
for
tritium)
With
this
alternative,
non-tritium
re-
leases
would
be
only
0.0004
Cl/yr
and
the
dose
to
a
river
drinker
0~000003millirems per year.
The
estimated
cost
of
this
alternative would be $9~000~O00and the time
for construction
36 months
CR.
377—83, 483~
We
think the “maximum recycle”
system i~a desirable addition
to the Quad-Cities
slant,
in that
for
a
price
that
is only
2
1/2
of
total
plant
cost
it
will
reduce
radioactive
discharges
from
26
Cl/yr
to
1,2,
The
companies
have
agreed
to
the
installation
of
a
similar
system
at
Dresden
(#70—21,
hearings,
Oct.
19,
1971,
Ex.
1).
Although
the
need
for
such
a
system
is
greater
there
in
order
to
avoid
radiation
buildup
in
the
largely
closed
cooling
system
planned
to
meet
the
thermal
standards
for
the
Illinois
River,
we
agree
with
the
Attorney
General
s
witness
D~
Devolpi
that
this
additional
caution
is
worth
the
money
in
dealing
with
something
so
dangerous
as
radiation
(R.
630)
.
On
the
other
hand,
we
shall
not
be
dogmatic
in
insisting
on
a
complete
absence
of
dilation
irrespective
of
the
costs
and benefits
of
so
doing.
The important policy
is
that
dilution
not
be
emsloyed
in
lieu
of
reasonably practicable treatment; when all reasonable means
of
treatment
have
been asplied,
and
the
costs
of
further
treat-
ment are excessive, dilution should not he forbi~len.
In
the
Dresden
case
we
announced
the general policy against unnecessary
dilution.
In the light of additional evidence received since
that:
decision, we think the further reductions below the already small
discharges
from
the
proposed
“maximum
recycle”
system
that
would
he
afforded
by
the
“maximum
treatment”
system
would
not:
at
the
present
time
be
worth
the
$4,000,000
extra
cost.
3—
100

Thus we shall order Edison and Iowa—Illinois
to reduce
gross
activity
discharges,
exclusive
of
tritium,
to
1.2
Ci/yr
and to
2 x i05
Ci/cc before mixing, by December
1,
1973, and in
the meantime to meet the gross activity limit of
1 x l0~7uCi/cc
after
dilution,
at the point of discharge to
the
river.
Asin
the
case
of
gaseous discharges,
there is
no
serious
risk
from
the
discharges
during
the
interim,
and
to
require
the
stricter
standard
to
be
met
at once
would
keep
the
plant
closed
for
two
years,
im-
posing an unjustified hardship.
3.
Heat.
Two thirds of the
heat
generated
in
a nuclear
power plant cannot be translated into electricity;
it
is
a waste
product that presents
its own disposal problems.
The companies’
original plan was simply to discharge
the heated cooling water
(which at low flow will comprise
1/4
to 1/5 of the river’s entire
flow and which will be 23°warmer than the river)
into the main
river channel
(R.
698—99,
715,
731,
768).
In the
sunimer of 1970,
however,
a study demonstrated that this scheme would violate the
then existing water quality standard
(SWB-12)
(R,
768), which
limited stream temperatures to~90°F.
and to 5°above natural
temperatures outside
a mixing zone extending 600
feet
in any direction
from the point
of discharge.
So the companies proposed to install
a diffuser,
a pipe extending most of the way across the river,
discharging heated water at various points in order to maximize
rapid mixing with the cooler river water
CR.
722)
.
It was their
contention that with
such an arrangement the standard could be
met
(R.
824).
But the old standard, we concluded
in
a recent rule-making
proceeding
(#R 70-16, Mississippi River Thermal Standards, adopted
Nov.
15,
1971), was inadequate to protect
the river against
a substantial
risk of ecological alteration,
since it would allow
the whole river to be raised by 5°nearly all the time.
For this
reason we adopted
a new standard that imposes monthly maximum
temperatures, based upon federal recommendations derived from
prevailing temperatures and
the requirements
of the biota at various
seasons, that must be met during all but
a
few days each year
at the edge
of the 600—foot mixing zone.
The companies’
evidence,
not substantially contradicted,
is that they can meet
the new
standard too with their diffuser alone, avoiding the expenditure of
$40,000,000 or more
for cooling towers or spray ponds.
We find
it: probable
on this record that
they can and therefore will not
require the installation
of alternative cooling devices at this
time.
We do require that the companies condubt
a detailed study
of the effects of discharges and that additional measures be taken
if significant harm
is shown to occur.
A more difficult issue is what
to prescribe while the diffuser
is being built,
As in the Dresden case,
we find it somewhat sur-
prising that the companies did not discover until
1970 that the
long—existing standards would require even so much as
a diffuser
pipe, with
the unhappy result
that even the diffuser will not be
3
101

available before February,
1972
(R.
9).
Indeed,
later dalays re—
~ulting
from permit proceedings before the federal government and
the Iowa water pollution agency have so
far prevented construction
of the diffuser and put
its operation off until
later in the
Spring.
However,
as noted above,
the plant
is badly needed,
and
right away,
if innocent consumers
(and the air-breathing public)
are not
to suffer.
The harm to the
river
in the meantime,
if we
impose certain conditions
to keep
it within bounds,
is
a risk
rather than
a certainty; while we would not allow it over
the
long term,
the great probability is that any harm that does occur
will be undone naturally by repopulation from unaffected areas
after adequate cooling is provided.
So we will allow Unit #1
to be operated, with the discharge
improvements promised by the companies,
as soon
as it
is ready.
With only one unit in operation,
the increase in temperature
through the plant will be only 13° (R.
30), and river dilution
will be adequate to 9sure
that
the whole stream not be raised by
5°even
at low water.
Moreover,
we shall require the companies to report on the
feasibility
of installing spray modules
in the discharge canal,
as at Dresden,
to reduce the heat discharged
to the
river.
Unit
#2
may be tested during this period,
as the utilities request,
in order to assure its availability
for the peak demands of
summer
1972
(R.
31)
,
but,
to avoid
a full heat load on the river
without even rapid mixing, which might do considerable damage,
the total station output shall not exceed 809 mw--that of either
unit alone——until
the diffuser pipe is
in operation
to assure that
large areas are not raised more than 5°.
4.
Nuclear Accident.
The Attorney General raised the
question of the adequacy of safeguards against the possible escape
of radioactive materials
in the event of an accident.
In light of
recent controversy over the adequacy
of certain systems
for cooling
reactor cores
in the event of
a coolant loss, we scheduled
an
additional two days of hearings, after
the record had been
closed,
to pursue the question.
On the basis
of the record we
cannot.
find such
a significant danger of failure of
the emergency cool Inc
system as to lead us to dalay further
the operation of this
needed
facility.
21
The companies say
the area raised by more than 5°will be on1~~
20 acres
(R.
791)
3—
102

A highly qualified witness from General Electric,
manufacturer of the reactors, testified in great detail as
to the integrity
of normal controls making the need for
emergency cooling highly improbable;
to the quadruple
emergency systems provided, each independently capable
of quelling any foreseeable problem;
and to the extensive
testing that had been
and would be performed to determine
and to maintain the adequacy of the systems.
He assured
the Board that the problems encountered
in recently
publicized tests were specific to an entirely different
type of emergency
system that had never been used or planned
for boiling water reactors
(R.
2336-2426).
Dr. Alexander
DeVolpi of Argonne National Laboratory suggested that
a
1970 incident at Dresden raised questions
as to the adequacy
of BWR emergency cooling systems, but he was unable to
demonstrate that
the incident was
one in which
an emergency
cooling system would be expected to operate.
Dr. Henry
Kendall of MIT emphasized the desirability of further
testing of these systems but agreed that the problems
recently encountered with cooling systems had no application
to the BWR’s
and had
no suggestions
for improving the Quad-
Cities system.
Neither he nor Dr.
DeVolpi asked that the
permit be delayed or withheld;
the latter expressly said
that “inherent safety features make water reactors ex-
tremely safe”
and that the “probability
of failure
necessitating emergency core cooling is very small”
(R.
2428—2542)
While
we shall maintain
a continuing concern for
this
and
all
other
matters
related
to
possible
radiation
hazards,
and while we
~hall provide that the permit may be modified
or revoked if this
is proved necessary by new information,
we
do
not
perceive
a
justification
today
for
withholding
the
permit.
5.
Other
Issues,
Because of the advanced stage of
construction,
siting
considerations
are
of
little
consequence
in this proceeding;
suffice it that we see no reason to require
that
this
plant
be
dismantled
and rebuilt somewhere else.
Solid
radioactive
wastes
will
be
contained
and
shipped
to
an
established
burial
site
(Environmental
Feasibility
Report,
p.
36),
and
we
have
no
evidence
to
indicate
any
undue
dangers
in
the
plans
for
this
operation,
either
at Quad-Cities,
in transit,
or
at the ultimate disposal site.
The appropriate disposal of
such dangerous
wastes,
however,
is
an
important subject with
which we expect to have more to do in the near
future.
The
Attorney General raises the question of nuclear accidents, but
we
think the evidence insufficient
to show
the need for
additional precautions on this score beyond those already
3
103

provided.
The gaseous radiation controls agreed
to by
the
utilities will add significantly
to accident protection
(R.
641—42),
The sewage treatment system and the gas-fired boilers
are designed to comply with all relevant regulations,
and
there is no indication that any nonradioactIve solid wastes
generated at the
site will be improperly dispos~dof.
No
chemical water contaminant problems
appear;
the use of sodium
hypochiorite
for condenser cleaning will add some chlorine
to the river, and chlorine
and its compounds can be toxic
to
fish; but the undisputed testimony
is that the small amount
of chlorine added will be rendered innocuous within two minutes
by
the chlorine demand in the river
CR.
285-87).
The Attorney General moved on November
11 that we
further delay decision in this case pending
study of the
transcript of
a recent
Iowa hearing with respect to the
effects of the proposed diffuser.
We denied this motion
4-1, Mr.
Dumelle dissenting,
on the ground that ample
opportunity had already been afforded for
the presentation of
evidence and that there was nO justification for
the extra-
ordinary course of reopening and further delay.
In conclusion, we should like to commend the applicants
for
a thorough and lucid presentation of the relevant facts,
and to thank
the Attorney General
for his participation,
which provided the adversary proceeding that
is
so necessary
to adequate resolution of the issues by the Board.
Mr.
Dumelle dissents
for reasons to be stated ih
a separate
opinion.
This opinion constitutes
the Board’s findings of fact
and conclusions of
law,
3—
104

ORDER
After due notice and hearing,
and
for the reasons given in the
Board’s
opinion,
a
permit
is
hereby
issued
to
Commonwealth
Edison
Co.
and
Iowa-Illinois
Gas
& Electric
Co.
to operate Units
#*l
and
2 at the Qtiad-Cities Nuclear Power Station near Cordova,
Illinois,
subject to the following conditions:
General
Conditions
1.
This permit shall not release the permittees from any
liability or obligation
imposed by Illinois statutes or local ordinances
and shall remain in force subject to all conditions
and limitations
now or hereafter imposed by law.
The permit shall be permissive
only and shall not be construed
as estopping or limiting any
claims against the permittees for damage or injury to person or
property resulting
from any acts, operations,
or omissions of
the permittees, their
agents, bontractors or assigns,
nor
as estopping
or limiting any
legal claim of the state against the permittees,
their agents, contractors
or assigns,
for damage to state property,
or for ~ny violation of subsequent regulations or conditions of
this permit.
2.
This permit is subject to modification
or revocation,
and
may be suspended at any
time for failure
to comply with the terms
stated herein
or
wjth
the
provisions of any other applicable
present or future regulations or standards of the IPCB or its
predecessors
or successors,
and
is issued with
the understanding
that
it does not estop the Board from subsequent establishment
of further requirements
for treatment or control at any
time.
The Board upon notice and opportunity to be heard may reopen
this proceeding at any time
for the purpose of such revocation
or modification
in order to prevent or reduce possible pollution
of the environment,
3,
The permittees
or their assigns shall defend, indemnify and hold
harmless
the State of Illinois,
its officers, agents and employees,
officially or personally,
against any
and all actions, claims or
demands whatsoever which may arise from or on account of the
issuance of this permit,
or the construction or maintenance of
any facilities hereunder.
~al
Conditions Relatin
to Radioactive Dischar es
(I,
Policy of
the Board)
it is the policy of the IPCB that all radioactive pollution
of the environment
shall he held to the lowest level that
is
attainable within the limitations imposed by technological feasibility
and economic reasonableness.
In no case
shall members of the public
be exposed to radiation beyond the limits recommended by the
International Commission on Radiological Protection,
nor shall
radioactive emissions ever exceed the limits imposed by the TTnited
States Atomic Energy Commission.
In addition, the actual levels

of
radiation
exposure
of
members
of
the
public
shall
be
kept
as
far below those limits
as possible, consistent with technological
feasibility
and reasonableness
of cost.
2.
Radioactive Discharges Generally)
In
keeping
with
the
above
policy
of
the
IPCB,
all
practical
measures
for treatment, control and containment of
radioactive
wastes from Quad—Cities
Units
1
&
2 nuclear generating plant of the
Commonwealth Edison Company shall be employed for the purpose of pre-
venting the release of radioactivity to the environment,
Such
measures
shall
include
at
least,
but
not
be
limited
to;
all measures
for the treatment,
control and~containment of
liquid and gaseous
radioactive
effluents
that
are
indicated
in
the
Final
Safety
Analysis
Report
of
the Quad-Cities Units
1
&
2
nuclear
generating
plant.
3.
Liquid
Radioactive
Discharges
(a)
The
annual
average
gross
beta-gamma
radioactivity
of
liquid
effluents
released
to
the
Mississippi
River
shall
not
exceed l07
uCi/mI
(100 pCi/l).
(b)
Total activity discharged
to the Mississippi River
in any year, exclusive of tritium,
shall not exceed
26
curies.
(c)
Tritium discharged to the Mississippi River in any year
shall not exceed
30
curies.
(d)
On and after December
1,
1973, total activity discharged
to
the Mississippi River in any year, exclusive of tritium,
shall
not exceed 1.2
curies,
and qross activity exclusive of tritium
shall be reduced to
2
x l0~ Cl/cc before dilution.
4.
Gaseous Radioactive Discharges
(a)
Gross beta—gamma radioactivity of gaseous emissions
released to the
atmosphere
from
either
Unit
1
or
Unit
2
shall
not
exceed
an annual average of 80,000 microcuries
per
second,
and emissions from both units operating at the same
time shall
not exceed an annual average of 110,000,
(b)
If gaseous radioactive
emissions
at
any
time
exceed
37,500
uCi/sec
from
either
Unit
I
or
Unit
2,
or
exceed
57,500
uCi/sec
from
both
units
operating
at
the
same
time,
the permittees
shall initiate operating
procedures,
to
the
extent
permitted
by
power demand,
to reduce such release.
(c)
On
and
after
September
1, l973,gaseous radioactive emissions
from
either
Unit
1 or Unit
2 shall not exceed an annual average
of 3000 uCi/sec,
nor shall emissions from both units operating
at
the
same
time exceed an annual average of 4000 uCi/sec.
3
106

5.
Heated Water Discharges
(a)
With the discharge improvements described in the
Supplement
to Appendix
C of the Application
as Amended, Units
1
and/or
2 may be operated until April
1,
1972,
at
a total output
not to exceed 809 mw~without regard
to the heat limitations of
regulations SWB-l2 as amended by #R 70-16 or of successor
regulations, provided that:
Ci)
until operation of the diffuser
is achieved,
effluents shall not exceed ambient river
temperatures by more
than 12°F; and
(ii)
within thirty days after receipt of this
permit,
the permittees shall submit
a state-
ment regarding the feasibility and cost of
installing spray modules to reduce the heat
discharged
in the interim before completion
of
the diffuser.
The Board upon receipt of
such statement will take such further action
as appears appropriate.
(b)
On and after April
1,
1972,
Units
1 and
2 shall be
operated only
in full compliance with all provisions
of SWB—l2
as amended by
#R 70-16
or of successor regulations, with regard
to heated discharges.
6.
Reporting and Monitoring
(a)
Liquid discharges.
Prior
to any release of radio-
activity
in liquid effluents, each batch will be counted
for
gross beta activity,
excluding
tritium.
Records
of the radio-
active concentration and volume of each batch of effluent shall
be maintained as well as records of the amount of circulating
water available for mixing.
At least once per month
a gamma
scan of typical batches
of effluent shall be performed
to deter-
mine the gamma energy peaks of these batches.
Isotopic analyses
of representative batches
of effluent,
including determination
of
tritium,
shall
be performed and recorded at least once per
quarter.
If
the monthly gamma scan reveals energy peaks other
than
those
determined
by
the
previous
isotopic
analyses
and if
the difference
is significant,
a new set of isotopic analyses
will
be
performed
and
recorded.
(b)
Airborne activity.
Radioactive gases released from
the reactor building stack and plant chimneys shall be continuously
monitored.
To accomplish
this,
at least one reactor building
stack monitoring
system and plant chimney monitoring system shall
be operable
at all times.
Daily samples
of the air ejector
effluent will be
taken,
Within one month after initial
3
107

commercial operation
of the unit,
an
isotopic
analysis
will
be
made.
From this analysis
a ratio of long lived to short lived
activity will be computed.
If
a ratio based
on any daily sample
indicates
a change greater than
20 per
cent from the previous
isotopic analysis,
a new isotopic analysis will be performed
and
recorded,
In
any
event,
a
new
isotopic
analysis
will
be
performed at
least quarterly.
Gaseous releases of tritium shall
be calculated monthly from measured data,
Records from the
continuous monitors,
the daily samples
and the isotopic examinations
shall be maintained,
(c).
All effluent and environmental monitoring erogram
results shall be reported monthly by the Permittees
to the
Environmental Protection Agency
(EPA).
All monitoring program
results shall
also be available for inspection by the
Environmental Protection Agency
at the slant site at any time,
7.’
Emergency
Situations
The Permrttees shall cooperate
to
the
full extent necessary
with
the EPA and w.ith
the Ill~nozsDe~artment of Public Health
for par oses
of develojpment by those agencies
of an adequate
and effective esergency protection plan designed
to immediately
control and minimize the effects
of any accidental release
of
unexectedl
large quantities of radioactivity
from the Quad--
Cities nuclear generating plant.
In carticular,
the’ permittees
shall immediately notify both
the
EPA and the Illinois Department
of Publac Heaath or any uncontrolled release of unexpectedly
large quantities of radioactivity
to the offsite air and/or
water environment due to operational failure of any
of
the sower
plant systems,
and shall report monthly to the Board and EPA any
aCt1Va~
tion of the emergency core cooling system, whether
spurious or real,
exclusive
of today.
,
18.
Time
of Permltl
This permit shall expire
on November
15,
1973.
If the
permittees wish
to continua operation
of Quad--C.ities Units
1
and
2 beyond that date
they shall file with the
IPCB
an aoplication
for
a renewal permit on or before August
15.
1973.
Said
application shall contain comolote
information and data:
(a)
concerning the radioactive emissions,
osseous and
liquid,
ap to that date,
(b)
concerning the status of the construothan and installat:
of the radioactive control facilities
resurred
by
this oermrt,
and
Cc)
concerning thermal discharges
and their effects
on
t.he
Mississip~haRiver.
Said application shall
also include such
other information and data
as required by the Board
to oval~~~ate
the impact on the environment of
Quad-Cities. Units
1
and
2.
108

9.
Compliance with Existing Laws
The permittees
shall conform to all existing and future
laws and regulations in other aspects of the operation
of Quad-
Cities Units
1 and
2,
including among other things the operation
of boilers,
the operation
of sewage treatment facilities,
and the
disposal of solid waste, and
shall procure from the Environmental
Protection Agency such permits as may be required
for various
aspects of that operation.
I,
Christan
Moffett,
Acting
Clerk
of
the
Pollution
Control
Board,
certify
that
the
Board
issued
the
above
Permit
this
/~Y
~day
____
1971.
3— 109

Back to top