ILLINOIS POLLUTION CONTROL BOARD
    October
    14,
    1971
    COMMONWEALTH
    EDISON COMPANY
    )
    v.
    )
    PCB 71—129
    ENVIRONMENTAL PROTECTION AGENCY
    Mr.
    Richard E.
    Powell
    and Mr.
    Charles
    E. Whalen of
    Isham,
    Lincoln
    & Beale, Attorneys
    for Commonwealth Edison Company
    Mr. Thomas
    M. McMahon and Mr.
    Delbert Haschemeyer, Assistant
    Attorneys. General, Attorneys
    for Environmental Protection
    Agency
    Opinion of the Board
    (by Mr. Kissel):
    On May
    28, 1971, Commonwealth Edison
    (“Edison”)
    filed a
    variance petition with the Pollution Control Board
    (“Board”)
    seeking permission to continue violating Rule 2-2.11 of the
    Rules
    and Regulations Governing the Control of Air Pollution,
    regarding particulate emissions
    of various units
    at three of
    its coal-fired stations.
    Edison sought the variance for
    its
    Fordam Station in Rockford
    (which consists of six units), for
    units
    1,
    2,
    3 and 4 of Powerton Station in Pekin, and
    for
    units
    1,
    2 and
    3 of the Will County Station near Romeoville.
    Edison’s Air Contaminant Emission Reduction Program
    (“ACERP”)
    for bringing the above facilities into compliance was approved
    by the Air Pollution Control Board
    in 1968,
    and
    it provided
    for
    a long-term schedule
    for bringing the various coal-fired units
    into co~npliancewith the applicable particulate regulations.
    (Ex.
    7).
    However,
    this Board decided that such an ACERP pro-
    gram for Edison’s Joliet facility was,in effect,
    a variance
    and hence demanded annual reapproval
    (Environmental Protection
    Agency
    v.
    Commonwealth Edison Company, PCB 70-4, February 17,
    I~71).
    Therefore, Edison filed
    this petition concerning these~
    three facilities.
    Edison contends that its ACERP was not
    a
    variance under the Air Pollution Control Act and is,therefore,
    still in effect, thereby nullifying the need
    for reapproval
    by this
    Board.
    But,
    in the event such approval is necessary
    due
    to changes
    in the original program,
    the company asks that
    the Board grant the affected facilities variances
    in order to
    permit their continued operation during the completion of the
    abatement. program.
    2
    627

    The
    Fordam Station
    The Fordam Station near downtown Rockford is scheduled to
    be retired by October 31,
    1971
    in accordance with the approved
    ACERP.
    From the time of
    the application for the variance until
    the unit’s retirement, Edison has a firm contract
    for off-peak
    natural gas; except for those days when the average daily tempera-
    ture
    is 32°or less, Fordam will be operated at its maximum gas
    burning capability.
    All but one of the Fordam boilers
    is
    capable of operating with
    gas, but the remaining~five
    do not
    have sufficient capability to Operate with maximum power solely
    on natural
    gas.
    Only two
    of the boilers are equipped with
    mechanical dust collectors which will bring them into compliance
    with the Illinois standard.
    When using only coal the uncon-
    trolled units do not meet the standard.
    The Fordam Station
    presently has
    a capacity of 60 megawatts.
    Edison contends that
    this station’s availability
    is essential in order to provide
    zone protection to the downtown area of the City of Rockford.
    This downtown area has
    an aggregate peak demand of about
    50
    megawatts.
    With Fordan~unavailable,
    load reductions during
    periods of peak demand might be necessary if there were outages
    in the connection system.
    The problems
    in the connection
    system are being alleviated,
    so that retirement can be accom-
    plished by October
    31,
    1971,
    We
    are satisfied that to deny the
    variance
    and thereby force
    a premature shutdown at Fordam
    would impose an unreasonable hardship upon Edison and upon the
    downtown area of Rockford dependent upon this plant.
    In grant-
    ing the variance we will continue to insist that Edis.on main-
    tain its plans to use natural gas whenever available.
    On
    appropriate conditions, the variance as
    to the Fordam plant is
    granted.
    The Agency also asks that the Board impose
    a penalty for
    Edison’s failure to transfer
    the multiclone presently installed
    on boiler 10 to boiler
    9.
    The multiclone was installed on
    boiler 10
    in 1940; boiler
    10
    has
    not been operated since
    1961.
    Boiler
    9
    is still in operation with 100
    coal.
    The precipi-
    tator on boiler 10
    is designed for
    a negative operating pressure.
    The only possible location on boiler
    9 for
    the precipitator would
    be after the induced draft
    fan,
    a positive pressure
    area.
    The
    Fordam plant superintendent stated that in this location the
    precipitator would not perform its function competently.
    We
    believe that the different pressures on the units would signifi-
    cantly mar any compatibility, thereby making transfer unfeasible.
    A penalty is not in order on this account.
    2
    628

    The
    Powerton Station
    The Powerton Station is located southwest of Pekin.
    The
    ACERP program approved in 1968 provided that the
    four units at
    Powerton would
    all be eventually shut down;
    the phaseout sched-
    ule for
    the units was
    as follows:
    Units
    1 and
    2, October,
    1974;
    unit
    3,
    October,
    1976;
    and unit
    4, October,
    1977.
    Edison has
    revised its phaseout schedule
    so as to retire units
    3 and
    4
    each one year earlier than originally scheduled,
    The Powerton
    facility consists of twelve pulverized coal—fired boilers,
    with no control equipment,
    served by three stacks all over
    300 feet tall.
    Powerton has available
    364 megawatts generating
    capability.
    Edison, claims that it needs
    the full generating capability
    of the Powerton Station
    in order
    to provide power during necessary
    maintenance
    outages.
    Even more critical
    for the Powerton Station
    is Edison’s need for
    160 megawatts of generating capability to
    provide first contingency protection
    for the Crawford substation
    serving downtown and mid-north Chicago on the
    69 kv line,
    Edison
    defines first contingency protection
    as that generating capability
    necessary to tolerate the
    loss of
    (a)
    two major generating units,
    (b) one generating unit and one transmission line,
    or
    (c)
    one
    major transmission
    line.
    Edison has established
    a long—range
    program intended to eliminate
    its dependence upon the Powerton
    facility
    for first contingency protection.
    That program contem-
    plates
    converting the outdated 69 kv transmission system to 138 kv.
    The first step in this changeover
    is to convert the Humboldt Park
    transmission substation to 138 kv;
    then it will be possible to
    add support to
    the Crawford Station by changing it over to
    Edison’s
    345 kv grid system.
    The Humboldt Park conversion
    will
    not be completed until mid-1974, with September,
    1974
    as the
    so-called
    “date of reliability”.
    As of that date then, Edison
    intends to retire Powerton
    1 and
    2,
    the oldest units.
    Powerton
    3 and
    4,
    it estimates, will be necessary into 1975
    in order to
    maintain system reserve at the then-projected 13.3,
    The
    Agency
    recommended
    that
    the
    petition
    as
    to
    Powerton
    be
    granted
    until
    June
    1,
    1972,
    subject
    to
    several
    conditions.
    It asked that Powerton not be allowed
    to operate above
    160 mega-
    watts
    and that no such power generated leave Illinois.
    The
    Agency also asked that Edison begin
    a program of design and con-
    struction
    for sulfur dioxide removal at the Powerton unit
    5 which
    is now under construction.
    The Agency also. sought the imposition
    of
    a penalty.
    2
    629

    Neither
    the
    testimony
    at
    the
    several
    days
    of
    hearings
    nor
    the Agency’s brief ever established any basis
    for the imposition
    of
    a
    penalty.
    Edison
    has
    maintained
    a
    commitment
    to
    its
    1968
    ACERP and,
    in fact, has improved upon
    it.
    The Board has con-
    sistently held that
    if
    a company is following the schedule
    detailed
    in
    a proposed ACERP, there is
    a shield against
    the
    imposition of
    a penalty,
    and no penalty shall be imposed.
    The Board also sustains
    the Hearing Officer’s ruling that the
    subject
    of Powerton
    5 and possible
    502 removal was beyond the
    scope of
    this hearing.
    Powerton
    5
    is not presently on
    line
    and thus
    is
    in no need of
    a variation from the existing regula-
    tions.
    The testimony of the Pekin and Peoria residents, however,
    established
    the effect of the heavy uncontrolled emissions from
    Powerton.
    Billy Keen
    of’ Pekin complained that the smoke would
    sometimes
    blot
    the
    sun
    out
    and
    that
    ash
    often
    covers
    his
    yard
    and house.
    Ray Riek described the grayish brown smoke emanating
    from the plant.
    The
    Tazewell County Director of Environmental
    Health indicated
    that
    his
    department
    had
    received
    numerous
    com-
    plaints regarding emissions from Powerton.
    William L.
    Rutherford
    described the plume from Powerton as extending several miles
    from
    the
    plant.
    The
    hardship
    imposed
    upon
    the
    Pekin
    residents
    by
    such
    emissions
    is
    considerable.
    During
    the
    course
    of
    the
    hearing,
    Edison
    moved
    to
    significantly
    lessen
    the
    present
    and
    projected
    emissions
    from
    Powerton
    by
    amending
    its
    variance
    so
    a~ to
    provide
    for
    decreased
    use
    of
    the
    facility.
    With
    two
    exceptions,
    Edison
    indicated,
    Powerton
    will
    be
    the
    last
    facility
    on
    its
    system
    to
    be
    committed,
    and
    the
    first
    to
    be
    taken
    off
    after
    the
    daily
    peak
    period
    has
    passed.
    When
    it
    is
    committed,
    this
    will
    be
    done
    only
    with
    sufficient
    lead
    time
    to
    ensure
    availability
    for
    the
    peak
    daily
    period.
    The
    two
    exceptions
    are
    as
    follows:
    When
    the
    system
    load
    is
    expected
    to
    equal
    or
    exceed
    70
    or
    80
    of
    the
    estimated
    yearly
    peak
    load,
    Powerton
    must
    generate
    at
    least
    160
    megawatts
    as
    first
    contingency
    protection
    to
    Crawford;
    during
    ice
    formation
    conditions,
    Powerton
    must
    be
    operated
    at
    approximately
    240
    megawatts
    to
    prevent
    ice
    buildup
    on
    the
    transmission
    lines.
    It
    is
    expected
    that
    these
    operating
    con-
    ditions should reduce operating time at P.owerton by two-thirds,
    thus bringing emissions down to one-third of present levels.
    Under the operating conditions which Edison has applied
    to the Powerton facility, the hardship to the residents will be
    minimized.
    If the Board were
    to deny the variance,
    it would be
    2— 630

    placing
    a large
    area of downtown Chicago in imminent jeopardy of
    losing its power
    source.
    In essence,
    Powerton will
    not be
    operated except under emergency conditions.
    The variance
    shall be granted for all units until October
    15,
    1972,
    subject
    to extension until October
    31,
    1974.
    This variance
    is being granted on the basis
    of the hardship Edison alleges con-
    cerning the changeover on
    the
    69
    kv and 345 kv transmission
    lines,
    It is not clear on the record that the two changeovers will be
    completed by October
    31,
    1974, with the need for Powerton thereby
    ceasing as of that date,
    We hope that
    in its subsequent variance
    petition Edison can clarify this question for the Board,
    The
    Will County Station
    For the Will County Station, Edison seeks
    a variance
    for
    unit
    1 until December
    31,
    1971;
    for unit
    2 until March
    1,
    1973;
    and
    for unit
    3 until June
    1,
    1973.
    On those respective dates,
    unit
    1 will have particulate and sulfur dioxide controls,
    and
    units
    2 and
    3 particulate controls.
    These units have
    a capacity
    of 609 megawatts.
    All three units presently have precipitators
    which, prior to
    1968, did not achieve their design efficiency.
    Edison’s
    1968 ACERP
    for Will County committed it to
    a program
    of interim improvement schedules
    to be completed in 1969 and
    costing $500,000.
    The interim improvements were completed
    according
    to schedule.
    Edison also committed itself
    to
    a long-
    range improvement program intended to bring Will County into
    compliance
    as follows:
    Unit
    1,
    spring,
    1972; unit
    2,
    fall,
    1972;
    and unit
    3,
    spring,
    1973.
    The program
    for unit
    1 is presently
    ahead of schedule,
    that for unit
    2,
    four months behind.
    As regards unit
    1,
    Edison is presently completing the
    installation of
    a Babcock
    and Wilcox sulfur removal system with
    a Venturi scrubber designed for particulate collection effi-
    ciency of 98.
    The sulfur removal system is designed to limit
    SO2 emissions while burning 3,5
    sulfur coal
    to those emissions
    experienced while burning
    .75
    sulfur coal,
    Total installation
    cost for unit
    1
    is over
    $7 million.
    The precipitator
    to be
    installed on unit
    2 will be in series with
    the existing pre-
    cipitator and
    is designed to achieve
    a 99
    collection effi-
    ciency.
    Unit
    2 installation cost
    is about
    $4 million,
    On
    unit
    3,
    Edison will install an additional precipitator,
    again
    in series,
    to achieve
    a collection efficiency of 99.
    The
    estimated cost
    is
    $7.8 million,
    Both units
    2 and
    3 will burn
    low sulfur coal,
    The Agency recommended that
    the petition be granted until
    June
    1,
    1972.
    The Agency asked that any grant be subject to
    the condition that all units be operated at
    a capability factor
    2
    631

    greater than 25
    only when necessary to maintain a daily pro-
    jected actual reserve of 10.
    They also asked that Edison
    begin
    a program of sulfur dioxide control for units
    2,
    3 and
    4
    at Will County.
    Several citizens did testify regarding emissions
    from Will County, but we do
    not find their testimony conclusive
    that air pollution results from sulfur dioxide emissions from
    this facility.
    In the absence of such proof,
    this Board
    is con-
    strained from holding that sulfur dioxide emission abatement
    equipment must be installed.
    (See Environmental Protection
    Agency v.
    City of Springfield,
    supra, and Illinois Power
    v,
    Environmental Protection Agency, supra).
    The Agency’s suggested limited operation of Will County
    would place
    the facility on an intermittent operation schedule.
    At present Will County represents about 10
    of Edison’s system
    capability.
    This Board realizes that Edison’s reserve capacity
    has been severely strained over the past several years as
    a
    result of extended
    lag times before Dresden III and
    the Quad-
    Cities facilities were able to come on—stream,
    On
    the evidence
    in the record,
    it
    is clear that this tight reserve condition
    will persist at least for
    the next yearS
    The Board realizes
    that heavy dose of emissions from the Will County facility has
    a strong adverse effect on the ‘area around
    the plant.
    None-
    theless,
    this hardship must be balanced by the great need
    for
    the Will County facility in the Edison system.
    Further,
    a posi-
    tive control program is proceeding at Will County which, within
    a short space of
    time, will bring the facility into compliance.
    With its
    new installations
    on units
    2 and
    3, Edison
    iiatends to
    burn
    low sulfur coal;
    by December 31,
    1971,
    it will control
    sulfur emissions from unit
    I.
    In addition,
    any intermittent
    operation of the facility may inflict serious metallurgical
    damage
    to the Will County units.
    In order that the Board may
    reexamine the variance in the light of changing reserve conditions,
    the variance, except
    for Will County
    1,
    shall be grantedfor
    a
    period of one year subject
    to the appropriate conditions.
    Though the Agency has not sought
    a penalty
    for the delay
    in the implementation of the ACERP for Will County,
    we
    feel
    that this Board should face that question.
    The original date
    given by Edison in the 1968 ACERP
    for compliance on unit
    2 was
    fall,
    1972.
    That compliance date has now been delayed until
    March
    1,
    1973;
    this was occasioned by Edison’s taking several
    months
    out of
    the implementation schedule in early
    1971
    to
    study whether
    a wet scrubber system could be used on unit
    2 as
    a means
    of controlling particulate emission instead of the
    precipitator.
    Due
    to cost, weight, water treatment,
    and waste
    2—632

    disposal problems with
    the wet scrubber, Edison elected to
    proceed with the precipitator
    as originally planned.
    Not
    until this hearing did Edison notify the Agency or the Board
    that it was undertaking a scrubber feasibility study which
    would delay the implementation of the ACERP,
    This
    is
    a
    four
    month delay in an implementation plan spread over several years.
    The precipitator which Edison intends to install obtains
    99
    particulate collection efficiency rather than the
    98
    under
    the original ACERP.
    The Board has previously stated its disin-
    clination to impose money penalties on anyone who in good
    faith adhered to an approved program.
    (Environmental Protection
    Agency
    v.
    Commonwealth Edison Company,
    PCB
    70-4, and Moody
    v.
    Flintkote
    Company,
    PCB 70-36,
    71-67).
    Edison’s overall program
    for these three units shows substantial compliance with the
    ACERP dates, with advancement of the date on
    some of the units,
    including Will County
    1.
    This case is not so serious
    as Illinois Power Company
    v.
    EPA, PCB 71-198
    (September 30,
    1971)
    ,
    where
    the company had
    ~~iarted
    from its ACERP by substantially increasing rather than
    decreasing
    its use of certain ill—controlled boilers,
    But
    here too there was an unapproved deviation from the promised
    schedule, which exposes the neighbors of the Will County plant
    to an additional
    four months of pollution.
    It may well be
    that
    if Edison had asked permission
    to risk
    a few months’
    delay
    in order to test an experimental
    scrubber, the delay would have
    been approved.
    But it is important that such permission be
    requested rather than that
    a company unilaterally decide whether
    or not
    the experiment
    is in the public interest.
    The decision
    whether or not the delay is justified
    is for the Board and not
    for the company to make,
    For the above reasons, we
    do not
    believe that
    a penalty should be imposed
    for the delay occa-
    sioned on the Will County units.
    The
    One-Year ACERP Issue
    In the instant case, Edison asks that the Board disaffirm
    its holding in EPA v.
    Commonwealth Edison,
    PCB
    70-4,
    that the Air
    Contaminant Emission Reduction Program was
    not
    a variance under
    the Air Pollution Control Act and
    is,
    therefore, not subject to
    automatic cancellation
    one year after
    it has been granted,
    Edison contends that
    the ACERP program was enacted under Section
    5
    of the prior Act and not under Section
    11.
    But,
    as this Board
    reaffirmed most recently:
    an ACERP is
    a variance whose duration
    is explicitly limited to one year by statute,
    The
    ACERP authorizes emissions in excess
    of regulation
    limits,
    and on the ground that immediate compliance
    2
    633

    would cause unreasonable hardship; this
    is the
    very essence of
    a variance.
    .
    .
    .
    any doubt on
    this issue
    is resolved by the specific statutory
    provision that all variance requirements apply to
    ACERPS.
    This
    does
    not mean all programs must be
    completed in one year.
    Renewals
    are authorized
    on adequate proof.
    But
    a prudent reexamination
    of such dispensations
    is rightly required by
    statute.”
    (Illinois Power Co.
    v.
    EPA,
    PCB 71—193,
    195—8)
    One-Year
    Limitation on Variances
    Also, Edison contends that under
    the present Act
    the Board
    can grant variances
    for more
    than
    one year.
    Section
    36(b)
    of the Environmental Protection Act states:
    “Any variance granted pursuant to the provisions
    of this section shall be granted
    for such period
    of time,
    not exceeding one
    year,
    as shall be
    specified by the Board
    ,
    .
    .
    (Emphasis supplied)
    But Edison contends that the word
    “section” in
    36(b)
    limits
    the Board to that type of case
    set forth under Section 36(a).
    Thus,
    a Section
    36 variance would
    be one where the
    “hardship complained
    of consists solely of the need
    for
    a reasonable delay’in which
    to correct
    a violation”;
    a Section
    35 variance would be one neces-
    sary to avoid an “arbitrary
    or unreasonable hardship”.
    It is clear
    that
    the Act did not intend
    to establish two different variances,
    each requiring different proof.
    It is also clear that the word
    “section” refers to the entire variance section,
    or Title
    IX of
    the Act,
    and we
    so hold.
    In addition, Section
    38 provides
    in part:
    “All the provisions of
    this Title shall apply
    to petitions
    for extensions of existing variances
    and to proposed contaminant reduction programs de-
    signed to secure delayed compliance with
    the Act or
    with Board regulations.”
    This reference to
    “all provisions of
    this Title
    .
    .
    .
    refers
    to
    Title
    IX variances, which Title contains Section
    36(b)
    within its
    one—year limitation.
    The instant case indeed concerns
    an extension
    of
    a proposed contaminant reduction proqram and thus, h~
    r~F~r~nr~
    2
    634

    comes under the one-year limitation,
    Finally,
    Section
    36(a)
    of
    the Act directs that
    the Board in granting
    a variance
    “may impose
    such conditions as the policies of
    the Act may require”.
    In this
    case, we
    find that the policies of the Act require an annual review
    of the variance
    and the progress toward compliance.
    As Edison
    has often reminded the Board,
    the power industry is one that is
    subject to daily,even hourly,
    changes.
    Faced with such
    a volatile
    situation, we have no choice but to conduct an annual review.
    In
    the hypothetical
    futute,
    it
    is entirely possible that Powerton
    3
    and
    4 can yet be retired earlier than Edison now projects,
    or that
    a further extension may be necessary at Will County
    3 in order to
    provide
    for the additional installation of
    a sulfur dioxide removal
    unit.
    Thus,
    the grant of the variance shall be for one year, with
    appropriate extensions,
    We would also remind Edison,
    in their
    expressed concern over the rñultiplicity of hearings which may be
    called for,
    that in
    a variance case hearings need not be scheduled
    if either the Board in its discretion does not conclude that one
    is advisable
    or if the Agency or other person does not object to
    the grant of the variance.
    (Section
    37).
    Of course,
    once com-
    pliance
    is attained, no further hearings will be necessary.
    The above constitutes
    the Board’s findings of fact and
    conclusions of
    law.
    ORDER
    Upon examination of the record, Commonwealth Edison is here-
    by granted
    a variance
    to emit particulate matter
    in excess of regu-
    lation limits
    as follows:
    1.
    For the Fordam Station until October
    31,
    1971,
    provided
    that:
    (a)
    Edison shall operate this facility
    so
    as
    to make maximum use of gas.
    Edison may use
    coal
    to avoid
    a voltage reduction in the Rockford
    area when power
    is unavailable
    for purchase from
    another facility.
    Edison may use
    coal
    if neces-
    sary to keep these units fired up
    so that they
    can be used as ready reserves.
    (b)
    Edison shall submit a report by November
    15,
    1971,
    to the Agency stating for the month of
    October
    the amounts of electricity produced and coal
    burnt at Fordam.
    2
    635

    2,
    For unit
    1 at
    the Will County Station until December
    31,
    1971.
    3.
    For
    unit
    2 at the Will County Station until October
    15,
    1972,
    subject to extension
    to March
    1,
    1973.
    4.
    For unit
    3 at the Will County Station until October
    15,
    1972,
    subject to extension
    to June
    1,
    1973.
    5,
    At the Powerton Station,
    for units
    1,
    2,
    3 and
    4
    to
    October
    15,
    1972, subject
    to extension until October
    31,
    1974,
    provided that:
    (a)
    Powerton shall be
    the
    last units on the
    Edison system committed to service and the first
    taken off after the daily peak period has passed.
    Powerton shall be committed only with sufficient
    lead time
    to ensure the unit’s availability
    for the
    daily peak period.
    When Powerton capacity is re-
    quired to meet tth predicted daily peak load plus
    the operating reserve,
    the station will be initially
    loaded to approximately 50
    capacity.
    Before the
    remaining capability
    of the Powerton units will
    be
    utilized, all other units on the Edison system
    --
    including the fast-start peaking units
    --
    will be
    brought to full operating
    load,
    exclusive of emer-
    gency capability.
    (b)
    The restrictions set forth :~nparagraph
    5(a)
    above shall not
    apply
    if
    weather
    conditions which
    may cause icing on the transmission lines exist or
    if
    Edison’s
    acted daily peak load equals or exceeds
    70
    of the projected annual peak
    load,
    (c)
    In the absence of such conditions
    as
    described in paragraph 5(b)
    of
    this order,
    Powerton
    shall not be operated above
    160 megawatt capacity.
    6.
    Commonwealth Edison shall make maximum use of avail-
    able gas
    to minimize the necessity
    for burning coal in units not
    meeting standards when coal is used,
    7.
    All existing emission control equipment shall be
    maintained and fully utilized,
    2
    636

    The company shall within
    35 days after receipt of this
    order post with the Agency a personal bond or other security
    in
    the amount of
    $500,000 in
    a form satisfactory to the Agency,
    which sum shall be forfeited
    to the
    State of Illinois in the event
    that
    the conditions
    of this order
    are not complied with
    or the
    facilities in question are operated after expiration of these
    variances
    in violation of regulation limits.
    The Agency shall
    remit
    such portions
    of the bond as
    it deems suitable upon the
    comoletion of
    the installation of
    the control unit
    on
    Will County
    2.
    9.
    The company shall
    file quarterly reports, commencing
    December
    31,
    1971, with the Agency,detailing its progress toward
    completion of
    its program.
    Such reports shall also detail Edison’s
    orojected annual peak
    load, ~ts daily projected peak
    load, and
    the Powerton Station generation for each day
    in each month com-
    pared to the power generation for the
    same
    day in
    the
    same month
    in the previous
    two years, prepared much
    in the manner as Common-
    wealth Edison
    Ex,
    No.
    53.
    10.
    Failure to adhere
    to the program as presented or to
    the conditions
    of this order shall be grounds for revocation of
    this
    variance.
    11.
    The company shall apply
    for any desired extensions
    of these variances
    to complete programs approved
    in this variance
    not later than
    90
    days before
    the expiration of these variances,
    I,
    Regina
    E.
    Ryan, Clerk of the Illinois Pollution Control
    Board, certify that the Board adopted the
    above Opinion and Order
    on the
    14
    day of October,
    1971.
    2
    637

    Back to top