ILLINOIS POLLUTION CONTROL BOARD
    September 30,
    1971
    ILLINOIS POWER
    CO.
    v.
    )
    #*
    71-193,
    71-195,
    71-196
    71—197,
    71—198
    ENVIRONMENTAL PROTECTION AGENCY
    Mr.
    Sheldon
    A.
    Zabel of Schiff, Hardin, Waite,
    Dorschel
    & Britton,
    for Illinois Power
    Co.
    Mr.
    Delbert
    D.
    Haschemeycr of Springfield,
    for Environmental Protection
    Agency.
    Opinion of the Board
    (by Mr.
    Currie)
    Illinois
    Power
    furnishes
    electricity
    to
    a
    substantial
    part
    of
    Illinois,
    from
    Danville
    in
    the
    east
    to
    Wood
    River
    in
    the
    west.
    Its
    program
    for
    bringing
    particulate
    emissions
    into
    compliance
    with
    regulations
    (Acerp)
    was
    approved
    by
    the
    Air
    Pollution
    Control
    Board
    in
    1968.
    After
    our
    decision
    that
    such
    programs
    were
    in
    effect
    variances
    and
    therefore
    required
    annual
    reanproval
    (En-
    vironmental
    Protection
    Agency
    v.
    Commonwealth
    Edison
    Co.
    ,
    #
    70-4,
    Feb,
    17,
    1971)
    ,
    Illinois
    Power
    filed
    the
    present
    petitions.
    The
    comeany
    does
    not
    concede
    that
    its
    Acerps require reapproval, hut
    in
    the
    event
    such
    approval
    is
    necessary
    asks
    that
    we
    grant variances
    to
    permit
    continued
    operation
    during
    completion
    of
    its
    program.
    We
    reaffirm
    our
    earlier
    holding
    that
    an
    Acerp
    is
    a
    variance
    whose duration
    is explicitly limited
    to
    one year
    by
    statute.
    The Acerp authorizes emissions
    in excess of regulation limits,
    and on the ground that immediate compliance would cause unreasonable
    hardship;
    this
    is
    the
    very
    essence
    of
    a variance.
    Moreover,
    any
    doubt
    on
    the
    issue
    is
    resolved
    by
    the
    specific
    statutory
    provision
    that
    all variance requirements apply
    to
    Acerps.
    This
    does
    not
    mean
    all
    crograms
    must
    be
    completed
    in
    one
    year.
    Renewals
    are
    authorized
    on
    adequate
    proof.
    But
    a
    prudent
    re—examination
    of
    such
    spensations
    is
    rightly
    recuired
    by
    statute.
    Cases
    ##
    71—195
    and
    71-196
    concern
    the
    Wood
    River
    generating
    station,
    which
    consists
    of
    five
    units
    located
    quite
    near
    the
    City
    of
    Alton
    in
    Madison
    Count~,
    tn
    the
    St.
    Louis
    metropolitan
    region.
    Unit
    ~5,
    which
    is
    enuieped
    with
    a
    99
    precipitator
    and
    allegedly
    meets
    the
    standard,
    is
    not
    subject
    to
    the
    variance
    request.
    Unit
    ~4
    (Case
    ~
    71—196)
    has
    a
    rated
    output
    of
    103
    megawatts,
    is
    presently
    equipped
    with
    a
    90
    meehanical
    collector,
    and
    emits
    0~87
    pounds
    of
    particulate
    per
    million
    btu,
    as
    contrasted
    with
    the
    applicable
    2
    547

    standard
    of
    0.6
    (R.
    19-21),
    The
    1968 Acerp called for compliance
    by
    1974
    (R.
    22)
    but
    the company has begun construction of
    a
    Monsanto catalytic oxidation
    (Cat—Ox)
    system, including
    a
    99
    precipitator,
    that will reduce the particulates well below standard
    (and reduce sulfur dioxide by 85)
    by June of 1972
    (R.
    25-26).
    Taking today as
    a vantage point,
    this is an exemplary program.
    We
    see no way the schedule can now be accelerated; emissions
    in
    the meantime are not so extreme
    as to suggest the possibility
    of a shutdown;
    the end result will be control not only of particulates
    but of sulfur as well.
    On appropriate conditions the variance for
    Unit
    #4
    is granted.
    Units
    ##
    1-3 present considerably more difficulty.
    They
    discharge
    through
    a
    common
    stack
    and
    have
    been
    treated as
    a unit
    by the parties.
    Together their capacity
    is 155 mw
    (R.
    19).
    Their
    control equipment, although they were constructed as late as
    1949—50,
    is practically nonexistent.
    The company estimates
    its
    efficiency at 15
    and the consequent emission at 7.38 lb/mbtu,
    about
    13 times the applicable regulation limit of 0.55
    (R.
    20—21).
    The emission is extremein terms
    not only of concentration but of
    volume as well; units 1-3
    are estimated to emit 24,000 tons
    of
    particulates per year
    (R,
    160)
    ,
    which
    is more than
    a third
    as much as all sources
    in the nearby area of the Interstate Study
    (St.
    Louis area)
    in 1963—64
    (F.
    176—78).
    A local pollution official
    testified flatly that this plant
    is “the major source of pollution
    in Madison County”
    CR.
    202)
    ,
    which emission inventories
    show has
    considerable particulate sources
    (F.
    163).
    An Agency witness
    testified without contradiction
    that ambient air concentrations due
    to emissions from units
    1—3 alone could be expected to reach
    325 micrograms per cubic meter for the worst 24-hour period
    (F.
    181)
    and federal criteria based on epidemiological studies indicate
    that adverse health effects can occur when the 24—hour level
    is in the range of 200-300
    (Air Quality Criteria for Particulate
    Air Pollutants,
    p.
    188).
    Consequently,
    to leave none too large
    a safety margin, both~ourpredecessor board and the federal govern-
    ment have set air-quality standards
    of 260.
    Ours
    is to be met~by
    January,
    1972,
    The proof
    is clear that emissions from units
    1-B will
    in themselves cause
    a violation of the
    air quality standard
    as well as
    of
    the emission regulations.
    It
    is abundantly
    clear that
    we here deal with
    one of the most significant contaminant sources
    in all Illinois.
    It is particularly important that abatement occur
    with all practicable expedition because
    this plant
    is ~1ocated in
    a densely populated region that suffers badly from numerous other
    contaminant sources.
    It
    is therefore with surprise
    and displeasure that we learn
    from this record that the former Air Pollution Control Board
    in
    1968 allowed Illinois Power an additional six years--a td~al
    of
    seven years after adoption of the regulations—-in which
    to bring
    -these truly extreme emissions under control
    (F.
    22)
    .
    Pursuant
    to that extensive
    free pass,
    the company has not yet commenced
    2
    54~

    construction of facilities to give relief to its
    unfortunate
    -
    neighbors,
    although the regulations are already four and one
    half years old.
    For
    a part
    of that
    time Illinois Power was assured
    that it would be able, when compliance time came,
    to purchase gas
    for full—time operation of these boilers
    (R.
    61).
    The recent
    gas shortage has put holes
    in that plan
    (R.
    62),
    and now the company
    expects-- although
    the final decision has
    not been made
    (R.
    34)--
    to convert Units
    1-3
    to oil burning and to utilize low-sulfur
    residual oil that would substantially reduce sulfur emissions as
    well
    as bring particulates down to 0,1 lb/mbtu
    (R.
    27).
    This program,
    too,
    is exemplary,
    apart from the question
    of time.
    It is
    a tragedy that
    over four years have
    gone by
    without getting the work even
    started.
    No penalties
    can, however,
    be imposed,
    since the delay had the inexplicable blessing of the
    Air Pollution Control Board.
    See EPA v.
    Commonwealth Edison Co.,
    #
    70—4
    (Feb.
    17,
    1971)
    ;
    EPA v.
    M.S.
    Kaplan Co.,
    #
    71—50
    (June
    8,
    1971).
    Today’s questions therefore are how quickly the work can
    now be
    done,
    and whether or not the plant should be
    allowed to
    operate in the meantime.
    The company in its petition asked that we reconfirm the
    1974
    date
    of
    the
    original
    acerp,
    but
    at
    the hearing
    reported,
    commendably,
    that
    its present schedule contemplated completion of
    the conversion,
    and therefore compliance,
    by June
    1973
    (F.
    128).
    Re—examination of the program,
    as required by
    the statute and our
    Edison
    decision,
    has
    eliminated
    a year~s pollution.
    Illinois Power testified that because of tight space limitations
    at
    the
    Wood
    River
    site
    work
    cannot begin on the conversion of
    Units
    1—3 until materials
    for the Cat—Ox system on Unit
    4 are
    out
    of the way,
    that
    is,
    until the Cat—Ox
    is completed
    in
    June
    1972
    (F,
    27,
    31—33).
    The Agency attempted without much success
    to attack this testimony
    (F.
    66-73,
    77-78)
    ,
    but we
    are not convinced
    that
    the start
    of construction could be much accelerated
    even if
    the space difficulty
    were
    overcome.
    The
    company
    testified
    without
    contradiction
    that
    the
    lead
    time
    for
    obtaining
    the
    necessary
    equipment was from six
    to eight months
    (F.
    74).
    Starting today,
    that period would
    run
    until April
    of 1972 at
    the earliest.
    The
    June date
    for starting construction seems the best
    that we can expect
    en the record.
    There was nothing to show,
    either,
    that the one-
    year estimated construction. time could be improved
    upon.
    To assure
    the company~sbest efforts, however, we shall order,
    as
    in prior
    cases
    (GA? Corp.
    v.
    EPA,
    # 71—ils,
    Sept.
    16,
    1971),
    that overtime
    be employed whenever to do so will advance the ultimate compliance
    date.
    There
    remains
    the
    alternative
    possibility
    of
    forbidding
    the use of Units
    1-3
    until
    they
    are
    brought
    under
    control.
    This
    is
    an
    attractive possibility because of the extreme emissions in
    question, and in
    a most inappropriate
    location.
    The company presented
    a good deal of evidence
    to the effect that these units constitute
    549

    about half of the 15
    reserve
    it says
    is necessary to enable
    it to meet peak demands that may outstrip predictions,
    to assure
    continued supply in the event
    of
    a failure
    ‘of other generating
    facilities,
    and to allow for the requisite maintenance of other
    units
    (R.
    39—55, 138).
    The Agency attempted to minimize the need
    for coal burning
    in Units
    1-3, pointing out that the largest
    demands come during summer months when gas is more likely to be
    available
    (R.
    57,
    99—120).
    All three units
    can burn gas
    (R.
    19),
    The company counters by observing that,
    precisely because summer
    loads are greatest, maintenance down time is grea.test at other
    times
    so that there is no guarantee coal burning may not be necessary.
    We think there
    is sufficient danger
    on this record that the
    complete refusal to allow coal burning on Units
    1-3 might result
    in an interruption
    of electric service that it would be improper
    for us to enter
    such an order.
    On the other hand,
    this does not
    mean we must allow unlimited use of
    coal.
    Our order makes
    it clear
    that coal may be burned in these units only as
    a
    last resort.
    All available gas must be used
    in units
    1-3 in preference to other
    units
    in the system
    CR.
    20)
    ,
    if
    those units
    are to be operated,
    since
    1-3 are
    the most ~‘erious polluters.
    All
    other
    sources of
    available power must be exhausted, including all other operable
    units
    of this company not down
    for legitimate maintenance and includ-
    ing
    all purchases that can be made from other producers.
    These
    provisions will
    limit
    coal burning on Units
    1— 3 to the minimum
    necessary to avoid the extreme hardship of
    a power shortage.
    If
    the Agency
    is right that these units
    are never needed when gas
    is
    unavailable,
    these provisions will mean these units will never
    burn coal.
    On these and other appropriate conditions
    ‘the variance
    will
    be granted in
    #71-195.
    Case
    # 71-197 concerns
    the
    Vermilion Station near the
    bewn
    of Oakwood in Vermilion County.
    This
    plant consists of two ex-
    clusively coal-burning units
    of
    77
    and
    109 mw and equipped with
    mechanical collectors
    of
    86
    and
    87
    respectively discharging
    through
    a single stack
    (P.
    7).
    Their emissions are calculated
    to
    be
    1.06 lb/mbtu as opposed to
    the
    permissible 0.59
    (F.
    7).
    The
    Acerp approved
    in 1968 gave Illinois Power until
    1973 to install
    a 99
    precipitator on
    Unit
    #1 and until 1974
    to
    do
    the same on
    #2;
    it
    is expected that emissions will be reduced
    to
    0.08
    lb/mbtu
    (R.
    8).
    Consequently work has not yet begun;
    the company was given
    time not to do the work,
    as contemplated by
    the
    regulations, but
    to
    delay the start of construction.
    Bids have
    just
    been
    received
    for
    #1 and are soon to be received
    for #2
    (F.
    ii).
    The company has
    at the Agency’s suggestion
    upgraded
    the pro-
    jected precipitators
    to 99.5
    (R.
    30)
    but seeks
    to adhere to
    the
    original unhappy schedule.
    Unfortunately the only testimony
    :~n
    the record
    is
    that the schedule cannot be accelerated
    at all
    os
    to Unit
    #1 and may indeed not be met
    (H.
    28,
    3t).
    If it
    is
    not:,
    the
    company will have only itself to blame.
    W~.cannct on the presant
    record find that
    #1 can be completed more qu~:~lythan the
    compaey
    sees,
    but
    we
    do
    not
    find
    persuasive
    the
    evidence
    a~- to
    wny,
    as
    1 lii
    pci ~ Power
    2

    says, construction cannot even begin until December 1972
    (R.
    30),
    which
    is fifteen months away.
    Consequently, while we grant the
    variance to permit operation of Unit
    1 during the coming year,
    we condition the grant on the company’s prompt submission of an
    additional affidavit,
    subject to Agency response, detailing why
    this delay
    is necessary, especially
    in light of the company’s
    evidence that
    a similar installation at Hennepin
    (see below)
    will
    take
    only 18 months from order to completion.
    With regard to Unit
    2
    the
    company admits that the schedule can
    be
    accelerated
    by six months
    (R.
    32)
    and we think it should be.
    If
    this
    places
    Illinois Power in an unfavorable bargaining position
    with respect to its supplier,
    as contended,
    that is the company’s
    doing because it chose to put off the installation
    of
    controls
    on Unit
    2,
    The same condition will apply
    to
    Unit
    2 witfr respect
    to
    an
    affidaVit
    showing
    why
    construction cannot be further accelerated.
    With these qualifications,
    the variance
    for
    the Vermilion
    station must be granted.
    Illinois Power cannot do without
    this
    station.
    And it
    is certainly better that coal be burned at Vermilion,
    where emissions
    are only
    twice
    the
    limit,
    than
    at Wood River
    1-3 with
    its virtually uncontrolled short
    stacks
    in
    a
    highly
    populated and highly polluted
    area,
    In case
    #
    71-198
    the
    company seeks approval of
    a
    drastically
    revised
    and much improved program for its
    Havana station,
    Consisting of eight boilers driving five units totalling
    260 mw
    (F.
    31—32)
    ,
    Havana is admittedly
    a
    bad
    actor,
    “a real problem.
    The station puts out
    a great deal of contamination”
    (R.
    123).
    It burns only coal;
    its controls are
    a paltry
    15
    effective;
    its
    emissions are estimated by the company at 6.3
    and by EPA at 7.4
    lb/mbtu,
    with an allowable
    of 0.33
    (F.
    32,
    104).
    It
    is scarcely
    surprising that several citizens, brought forward by
    the City of
    Havana as well
    as by the Agency,
    found the plant
    a severe nuisance,
    depositing sticky soot on cars
    and window sills, requiring extra
    cleaning, and interfering with such outdoor activities
    as clothes
    drying and cookouts
    (F.
    5-28).
    There was testimony that two
    families had moved their mobile homes out of the area,
    and three
    others had threatened soon to do so, because of pollution from
    the
    plant
    (F,
    25-26).
    Petitions urging that something be done were
    presented to the City as early as 1965
    (F,
    21).
    The regulations that were
    to give relief came in l967~
    although action could have been taken under the statute itself
    long before.
    The Acerp, approved in 1968, incredibly provided
    for no controls
    at all, but merely for declining use of the
    old plant until
    1976, when
    it was
    to be placed on cold standby
    for possible emergency use--still without meaningful controls——
    until
    1985
    (F.
    33—34)
    2—551
    ~

    The company’s own evidence
    is clear that the conditions
    of
    even
    this most accommodating variance were grossly violated.
    Loads around the time of APCB approval in 1968 averaged less than
    -
    26
    of capacity
    CR.
    36).
    In
    1970, due to increased requests to sell
    power to neighboring electric companies,
    the
    load was increased
    to an average of
    39.7
    (ibid).
    In
    the
    first
    six
    months
    of
    1971
    the
    load further increased
    to
    47
    (ibid),
    In defense the company
    asserts that the
    APCB
    in
    accepting the promise to reduce the
    use
    of Havana “was well aware of the contingencies that could arise
    in the power industry”
    (H. 130-31)--
    contingencies, that created
    an allegedly unexpected shortage of power elsewhere-— and that the
    promise
    was
    not
    a
    promise
    at
    all:
    “Those submissions were projections.
    They were not guarantees.”
    “We did
    not.,
    spate anywhere in
    those
    ACERP
    documents
    that
    we
    would
    not
    operate above
    ‘x’
    capacity”
    H.
    143—44,
    130).
    While
    the
    English
    language
    has
    its
    ambiguities,
    we
    see
    no
    possibility
    of
    reading
    the
    Acerp
    as
    Illinois
    Power suggests.
    The company’s
    own schedule,
    submitted as
    part of
    its
    Acerp and
    appended
    to the Agency’s recommendation here, provided
    that “from
    1968
    to 1976
    the station’will be operated
    for peaking purposes
    on
    a cycling basis
    at progressively
    lower load factors.”
    If the
    company did not promise to reduce its use of Havana it promised
    nothing at
    all.
    Its violation is plain.
    If conditions changed to
    make that promise no longer suitable,
    it was the company’s duty
    to request an amended variance;
    that would have enabled the Board
    to order
    a new compliance program.
    The company chose instead simply
    to violate its commitment, which thereupon ceased to be
    a shield
    against prosecution for exceeding the emission
    limits.
    We there-
    fore condition the grant of
    a further variance
    for Havana upon
    payment of
    a
    $5000 penalty for failure to adhere
    to its earlier
    program,
    Our authority to impose penalty conditions has been challenged
    here;
    it
    is
    supported by the statutory direction to impose conditions
    that will further statutory policy, for example to deter violations.
    We could
    of course deny the variance in order to leave the company
    open
    to
    a complaint on which
    the same penalty could be directly
    imposed;
    to do so would merely cause duplication of litigation with
    attendant
    loss of time and money.
    In making the variance contingent
    on payment of the penalty, we make it clear that the variance falls
    if the penalty
    is defaulted or set aside, ‘so that
    a complaint
    can be filed.
    See, e.g., Marquette Cement Co.
    v.
    EPA,
    #
    70-23
    (Jan.
    6,
    1971);
    City of Springfield
    v,
    EPA,
    #
    70—55
    (March
    31,
    1971).
    Nor
    is there,
    as the company says,
    any inconsistency
    in holding
    that
    the
    Acerp
    has
    expired
    and
    that
    it
    was
    not
    adhered
    to.
    As
    we have made clear before
    (EPA v.
    M,S,
    Kaplan
    # 71-50, July
    8,
    1971)
    ,
    while
    an Acerp must be renewed yearly we will not
    impose money
    penalties
    on one who has followed such
    a program in the good
    faith
    belief it
    is still valid.
    The reason
    is not that there has been
    no violation;
    it
    is
    that
    good faith reliance
    makes
    penalties
    2
    552

    inappropriate.
    However, that defense disappears when,
    as here,
    the
    program was itself not followed.
    The company’s present program is
    a decided improvement.
    Conversion or the boilers to oil has begun and
    is
    to be completed
    in either May of July 1972
    (H.
    37).
    The contractor says May
    (R.
    62-63);
    the company asks until July to leave room for
    unexpected possible delays
    (ibid).
    We will set the May date.
    If
    justifiable delays occur,
    a petition
    for extension may be
    submitted——
    in time that we can pass
    on it before
    the present
    grant expires.
    The new program is happily short,
    and we think the
    need for these units
    in the meantime greatly outweighs even the
    substantial harm
    they cause.
    Havana shall in the interim be used
    as little as possible, making it
    a last resort save only
    Wood River Units
    1—3, which
    are equally uncontrolled and in a more
    densely populated area.
    When conversion of one or more boilers
    is
    completed,
    the company will be required to use
    the converted boiler
    or boilers
    in preference
    to those yet unconverted
    (H.
    76-77).
    Overtime shall be employed whenever it will accelerate completion.
    The Hennepin station
    (#
    71—193)
    consists of Units
    1 and
    2
    of
    76 and
    235 mw respectively
    (H.
    5).
    Equipped with mechanical
    collectors of alleged 83.8
    and
    85
    efficiency,
    the units discharge
    through
    a common stack at an estimated rate of 1.49
    lb/mbtu,
    contrasted with
    an allowable 0.42
    (R.
    5-6).
    The company’s acerp,
    approved
    in 1968,
    called for installation of
    a 99
    precipitator
    on Unit
    2 by sometime
    in 1972, relying on mixing with the
    precipitator effluent to bring Unit l’s emissions within the standard
    (R.
    6-7).
    The petition
    left doubts
    as to the availability of the
    low—ash coal needed
    for this stratagy,
    but
    the record shows
    the
    supply has been contracted for
    (H.
    9).
    The precipitator
    is under
    construction,’ and completion
    is scheduled for June 1972
    (H.
    9).
    The company asks that we confirm the program.
    We do
    so.
    Again
    the need
    for reliable power, and to minimize
    use of Wood River 1-3,
    dictate against an interim shutdown.
    Again——given today’s vantage point—-we see no way to accelerate
    the construction schedule.
    That the company can meet the standard
    by controlling only one
    of its two units once more demonstrates
    the laxity
    of the existing standard, which we may well tighten in
    the near
    future.
    But under the present regulation our concern is
    with the quality of the emission, not with how it
    is achieved.
    While dilution with outside air to reduce contaminant concentration
    without reducing the quantities discharges would violate the anti-
    circumvention provision of the regulations,
    that
    is
    not what
    is
    occuring here.
    For the quantities
    of fly ash removed and those
    emitted,
    as well
    as the concentrations, will be the same as
    if both
    units were equipped with precipitators
    of somewhat lower efficiency.
    2
    553

    Moreover,
    the company’s plan leaves
    it in a
    better
    position
    to
    conform to more stringent regulations
    that
    may be
    adopted
    in
    the
    future.
    In all
    these cases
    the Agency asked not only that security
    be
    posted
    to
    assure performance——as the statute requires—-but also
    that we condition any variance on the submission
    of
    a program for
    controlling
    sulfur dioxide and
    for developing technology
    to
    control
    various other pollutants.
    On adequate proof we have found air
    pollution by virtue of contaminants
    for which there are no emission
    standards;
    that
    is
    one
    of
    the
    chief
    purposes
    of
    the
    statutory
    prohibition.
    B.
    g., EPA v.
    City of Springfield,
    #
    70-9
    (May
    12,
    1971).
    Here, however,
    there was’ no proof
    of such pollution, except
    possibly for the Havana station, whose sulfur problems will be
    greatly reduced by
    the program we approve today.
    We cannot order
    correction of pollution without proof that a problem exists.
    This opinion constitutes the Board’s findings
    of fact and
    conclusions of law.
    ORDER
    Upon examination of
    the record,
    Illinois Power Co.
    is hereby
    granted variances
    to emit particulate matter
    in excess of regulation
    limits
    as
    follows:
    1.
    (#71-196)
    From Unit #4 at
    the
    Wood
    River
    Station
    until
    June
    30,
    1972;
    2.
    (#71-195)
    From
    Units
    ##
    1-3 at Wood River until
    September
    30,
    1972,
    subject to extension to June
    30,
    1973,
    provided that:
    a.
    Overtiine
    shall
    be employed
    on these units
    and on
    Unit
    #4 whenever
    to do so will advance the date
    of
    compliance;
    b.
    Coal burning on Units ##l-3 shall be
    a last
    resort,
    only if the company has exhausted all other
    means
    of satisfying its demands including the following:
    i)
    Maximum use of all other ‘available units operated
    by
    the company;
    and
    ii)
    Maximum purchases of power from other producers;
    and
    iii)
    Preferential
    allocation
    of
    available
    gas
    supplies
    to
    Units
    ##1-3;
    Provided,
    that this paragraph
    shall
    not
    prevent
    the
    company
    from burning minimum
    quantities
    of
    coal
    if
    needed
    to
    maintain
    the
    readiness
    of
    the
    units in question;
    2
    554

    c.
    The company shall within 35 days after receipt of
    this order file with the Agency
    and with the Board
    a
    firm schedule for bringing Units
    ##
    1-3
    into
    compliance as follows:
    i)
    Equipment
    to be ordered by January
    1,
    1972;
    ii)
    Equipment to be delivered and construction
    to
    begin by July
    1,
    1972;
    iii) Compliance by June
    30,
    1973;
    3.
    (It
    71-197) From Units
    #
    1 at the Vermilion station until
    September
    30,
    1972
    subject to extension to June
    30,
    1973
    and from Unit
    #2
    at Vermilion until September
    30,
    1972,
    subject to extension
    to December
    31,
    1973,
    provided that:
    a.
    The company shall submit to the Agency and
    to the
    Board, within 35 days after receipt of this order,
    an affidavit,
    subject to Agency response, detailing
    why this schedule cannot be accelerated;
    b.
    After completion
    of the control equipment
    on Unit
    #1, that unit shall be used
    in preference
    to Unit
    #2;
    4.
    (#71-198)
    From Units
    H
    1—8
    at
    the Havana station until
    May
    31,
    1972,
    provided that:
    a,
    Overtime shall be employed whenever to do so will
    advance the date of compliance;
    b.
    Use of Units
    ##
    1-8 shall be resorted to only
    if the
    company has exhausted all other means
    of satisfying
    its demands,
    including the following:
    i)
    Maximum use of all other available units
    (except
    Wood River
    ##
    1-3)
    operated by
    the company;
    and
    ii)
    Maximum purchases
    of power from other producers;
    Provided, that this paragraph shall not prevent
    the company from burning minimum quantities of
    coal
    if needed
    to maintain
    the readiness
    of the
    units
    in question;
    c.
    After conversion
    of one or more of these units,
    preferential use shall be made of those units
    converted;
    d.
    A penalty shall be paid to the State of
    Illinois
    in the sum of $5000 within
    35 days
    after receipt of
    this order;
    2—555

    5.
    (#71-193) From Units ##
    1 and 2at
    the Hennepin station
    until June
    30,
    1972;
    all on condition that the following requirements are met:
    6.
    Illinois Power Co.
    shall make maximum use of available
    gas
    to minimize the necessity for burning coal in units
    not meeting standards when coal
    is
    used;
    7.
    All existing emission control equipment shall be maintained
    and fully utilized;
    8.
    The company shall within 35 days after receipt
    of this
    order post with the Agency a bond or other security
    in
    the amount of $500,000,
    in
    a form satisfactory
    to the
    Agency, which sum shall be forfeited
    to the State of
    Illinois
    in the event that
    the conditions
    of
    this
    order
    are not complied with or
    the
    facilities
    in question are
    operated after expiration of
    these
    variances
    in violation
    of regulation
    limits;
    9.
    The company shall file quarterly reports,
    commencing
    December
    31,
    1971, with the Agency and with
    the Board
    detailing its progress toward completion
    of
    its program;
    provided,
    that such reports in cases
    ## 71-195 and
    71—198 shall detail any occasions on which coal was burned at
    Wood River
    Units
    1-3
    or Havana Units
    1-8,
    together with
    reasons why
    such burning was necessary;
    10.
    These cases remain open for further proceedings on the basis
    of
    the submissions required by
    this order;
    11.
    Failure to adhere
    tO the programs
    as presented or to the
    conditions
    of this order shall be grounds for revocation
    of these variances;
    12.
    The company shall apply
    for any desired extensions
    of these
    variances to complete
    the programs approved today not later
    than 90 days before expiration of these variances.
    I, Regina
    B.
    Ryan, Clerk
    of the Pollution Control Board,
    certify
    that
    the
    Board
    adopted
    the
    above
    Opinion
    o~~&’.~~oardthis
    30
    day
    of
    September
    ,
    1971.
    2
    556

    Back to top