ILLINOIS POLLUTION CONTROL BOARD
March 18, 2004
HORTENSE SINGER,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 04-149
(UST Appeal)
(90-Day Extension)
ORDER OF THE BOARD (by J.P. Novak):
On March 5, 2004, the parties timely filed a joint notice to extend the 35-day period
within which Hortense Singer may appeal a January 27, 2004 determination of the Illinois
Environmental Protection Agency (Agency).
See
415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code
105.402, 105.406. Because the postmark date of the joint request is within the time for filing, the
joint request was timely filed. 35 Ill. Adm. Code 101.300(b)(2), 105.404. The Agency approved
portions of petitioner’s request for reimbursement from the UST Fund, but denied
reimbursement because the approved portions did not exceed the applied deductible, for
Hortense Singer’s leaking underground petroleum storage tank facility located at 3 South 338
Route 59, Warrenville, DuPage County. The Board extends the appeal period until June 1, 2004,
as the parties request.
See
415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code 105.406. If Hortense
Singer fails to file an appeal on or before that date, the Board will dismiss this case and close the
docket.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
adopted the above order on March 18, 2004, by a vote of 5-0.
Dorothy M. Gunn, Clerk