| - PETITIONER’S BRIEF
- I. INTRODUCTION
- II. STATEMENT OF FACTS
- III. REGULATORY BACKGROUND
- IV. ARGUMENT
- intended to be used by project managers in a case where a rate presented in a
- high priority CorrectiveAction Plan budget is above the maximum rate
- found on the rate sheet?
- or modified down to the maximum level.
- photographs which cannot conveniently be examined in court
- may be presented in the form of a chart, summary, or
- calculation. The originals, or duplicates, shall be made
- available for examination or copying, or both, by other parties
- at reasonable time and place. The court may order that they
- be produced in court.
- B. TECHNICAL REVIEW OF THE CORRECTIVE ACTION PLAN
- located to the south of Fourth Street. The remaining borings, B17 was
- located at that approximate distance based on preliminary ground water
- contaminant transport modeling conducted using TACO equation R26, as
- outlined in the application. The remaining three offsite borings were located
- so as to evaluate the lateral spread of the plume across the approximate
- center line as estimated, using equation R26.
- A.. According to their site classification report, yes, that is what theyfound.
- site, yes.
- However, that was not the case.
- A. Regional soil geology has been proven to be uniform at the site.
- It can be assumed that it is uniform off-site as well.
- A. If I remember correctly it did. I know it was an AX classification.
- Essentially what it was determined it was, it was homogenousthroughout the site.
- A. Yes.
- already confirmed, and it was homogenous?
- A. It was not going to give us any additional information that
- would be helpful.
-
- I think what are you four blocks from the river? It’s all sand.
- C. FINANCIAL REVIEW OF THE BUDGET
- Costs for the concrete coring machine and bentonite chips are unreasonable
- and have been modified accordingly.
- a. The Reduction to 10 direct-push borings is erroneous.
- Professional Engineer.
- pH/ORP/temperature meter (35 IAC 732.606(hh))
- Budget and Therefore Should Be Restored to the Extent the Budget is
- Restored.
- V. CONCLUSION.
|
RECE~VE~
CLERK’S OFFICE
BEFORE THE POLLUTION CONTROLBOARD
FEB
112004.
OF THE STATE OF IILLINOIS
STATE OF ILLINOIS
ILLINOIS AYERS OIL COMPANY,
)
Pollution
Control Board
)
Petitioner,
)
)
V.
)
PCBNo.03-214
)
ILLiNOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
)
NOTICE OF FILING AND PROOF OF SERVICE
TO:
Dorothy Gunn, Clerk, Illinois Pollution Control Board, James R. Thompson Center,
100
W.
Randolph, Suite 11-500, Chicago, IL 60601-3218
Carol Sudman, Hearing Officer, Illinois Pollution Control Board,
1021 North Grand
Avenue East, P.O.
Box 19274, Springfield,
IL 62794-9274
John Kim, Illinois
Environmental Protection Agency, Division ofLegal
Counsel, 1021
North Grand Avenue East, P.O.
Box 19276, Springfield,
IL 62794-9276
PLEASE TAKE NOTICE that on February 9, 2004,
I sent to
the Clerk of the Illinois
Pollution Control Board the original and nine (9) copies, via U.S. mail, ofPetitioner’s Brief for
filing in the above-entitled cause, a copy of which is attached hereto.
The undersigned hereby certifies that a true and correct copy of theNotice of Filing
together with a copy of
Petitioner’s Brief, was served upon the Hearing Officer via U.S. mail and
the Respondent via U.S.
mail and facsimile, on the
9th
day ofFebruary,
2004.
MOHAN, ALEWELT, PRILLAMAN & ADAMI
1 North Old Capitol Plaza, Suite
325
Springfield,
IL
62701-1323
Telephone: 217/528-2517
Facsimile:
217/528-2553
THIS FILING SUBMITTED ON RECYCLED PAPER
C:\Mapa\CSD Environmental\NoticeofFiling.wpd\crk\2/9/04
RECEIVED
CLERK’S OFFICE
BEFORE
THE ILLINOIS POLLUTION CONTROL
BOARD
FEB
112004
ILLINOIS AYERS OIL
COMPANY,
)
STATE OF ILLINOIS
Pollution
Control Board
Petitioner,
)
)
vs.
)
PCB
No.
03-214
)
(UST Appeal)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
)
PETITIONER’S BRIEF
NOW COMES Petitioner, Illinois Ayers Oil
Company (hereinafter“Petitioner” or
“Illinois Ayers”), by its undersigned attorneys, and for its brief states as follows:
I.
INTRODUCTION
Petitioner seeks Board review ofthe Agency’s decision to
modifythe proposed corrective
action plan by reducing the number ofsoil borings and drastically slashing the budget from
$52,367.96
to
$22,074.77.
These
$52,367.96
is actually a reduction from
an earlier budget
proposal which is
currently before the Board in Illinois Ayers v.
JEPA, PCB No. 03-70.
By
reducing the scope ofwork and
certain costs to
$52,367.96,
Petitioner had hoped to avoid
litigation of this matter.
Unfortunately, those concessions did not sate the Agency’s appetite and
the Board is now asked to
decide whether the
$52,367.96
is reasonable and appropriate.
Most ofthe problems with the Agency’s decision stem from three major mistakes.
First,
the Agency Reviewer cut rates for persoimel and equipment solelybased upon a secret rate sheet
which is illegal and incompetent evidence in this proceeding.
Petitioner asks that the rate sheet
and all testimony premised on the rate sheetbe stricken.
Second, the Agency Reviewer
1
eliminated ten direct-push soil borings on her mistaken assumption that soil conditions at the site
were homogenous.
The subject corrective action plan and the referenced Berg Circular clearly
state the contrary.
Finally, the Agency Reviewer concluded that each of the direct-push borings
could be accomplished in an hour based upon a number ofarbitrary assumptions and little
attention to
the technology ofpush-driven technology.
Since a number ofcosts
in the budget
depend on the number of soil borings and the time requirements for a direct-push investigation,
these last two mistakes resulted in corresponding reductions in a number ofrelated costs which
should not have been reduced, either.
Petitioner asks that the Board approve the entire corrective
action plan and budget, as submitted.
II.
STATEMENT OF FACTS
Illinois Ayers operates a gasoline service station at 310 State Street, Beardstown, Cass
County, Illinois.
(Agency Rec., at p. 4) In 2000, a release was reported from three underground
storage tanks on the property, eachofwhich is eligible for reimbursement from the LUST Fund.
(Agency Rec., at p.
82) The site was subsequently classified
as a “high priority” site because one
or more groundwater quality standards were exceeded at the property boundary line.
(Agency
Rec.,atpp.4&84)
Illinois Ayers hired
CSD Environmental Services, Inc. (hereinafter “CSD
Environmental”) to perform remediation services related to
the incident.
CSD Environmental is
an experienced civil and environmental consulting firm specializing in land development and
environmental restoration projects.
(Pet.’s Ex.
18(a)) On behalf ofits client, CSD
Environmental
submitted corrective action plans and budgets to
the Agency.
The plan that
is the subject of this
2
Board Appeal is entitled “Revised’ Phase
1
—
Corrective Action Plan & Budget” and was
submitted to the Agency fOr review and
approval on December 4, 2002.
(Agency Rec., at p.
1 ~
~q~) Before discussing the subject application, the events leading up to the revised plan and
budget are pertinent.
The initial High PriorityCorrective ActionPlan was submitted to
the Agency on June 20,
2002.
(Pet. Ex.
6(A)) On October 11, 2002, the Agency rejected the planbecause,
inter alia,
“the
plan proposed
direct push groundwater sampling.
The Illinois EPA wishes
to clarify that
monitoring wells must be installed to obtain groundwater samples.”
(Pet. Ex. 6(A)) The Agency
also rejected as excessive some ofthe hours and the numberof soil samples to be taken.
(~)
In an attempt
to resolve these issues without an appeal, Illinois Ayers and the Agency
obtained a ninety-day extension ofthe appeal deadline.
~
Illinois Ayers Oil Co.
v. JEPA, PCB
03-70 (Nov. 21, 2002).
Thereafter, representatives ofCSD Environmental and the Agency met
twice.
(Hrg. Trans. at pp.
26 & 29)
In the first meeting, the parties discussed both the Illinois Ayers site and another CSD
Environmental project in Gibson City, Illinois, called the Royal Oil
site.
(Hrg. Trans.
at pp. 68-
69) Both projects involved direct-push groundwater sampling and were “essentiallyidentical.”
(Hrg. Trans.
at pp. 69)
Joseph Truesdale,
a professional engineer with CSD
Environmental,
brought to
the Agency’s attention an Agency fact sheet stating that push-driven technology is
acceptable for sampling both soil
and groundwater.
(Hrg. Trans.
at pp.
33-34, Pet.
Ex.
9) Doug
Clay of the Agency conceded this to be
true.
(Hrg. Trans.
at p. 34) The Agency agreed to
approve the investigation plan for the Royal Oil site, but requested a second meeting to
independently discuss the Illinois Ayers site.
(Hrg. Trans. at p.
70)
3
At the second meeting, Truesdale emphasized that the investigation plan for Illinois
Ayers was the same as that
approved for Royal Oil.
(Hrg. Trans.
at p.
69) He noted on his
copy
ofthe denial letter:
“NEED
TO CLARIFY
LIKE
ROYAL OIL.”
(Hrg. Trans. at p.
60; Pet.’s Ex.
6)
Truesdale justified to Agency representatives the number of hours for the work (Hrg. Trans.
at
pp.
36-38,
56)
and the number of soil samples.
(Hrg. Trans. at p. 67)
At the request ofthe
Agency, he described how the direct-push ground water samples would be
obtained, drew
diagrams depicting the equipment and strategy, explained average number oflineal feet of
borings that could be accomplished in a day and identified the proposed locations for the borings.
(Hrg. Trans.
at pp.
37-38) Truesdale testified that he felt that the Agency understood and agreed
with his rationale.
(Hrg.
Trans.
at p.
67)
The Agency asked for concessions on the numberofhours for certain personnel and the
number ofsoil borings.
(Hrg.
Trans. at pp.
56
& 67) These concessions were made in the hopes
ofavoiding litigation before the Board (Hrg. Trans.
at p.
119), but as will be discussed later, they
merely set the stage for the Agency to demand further reductions.
However, no understandings were reached with respect to the rates charged for personnel
and equipment.
Members ofthe Agency are not allowed to disclose an acceptable rate to
the
public, even at meetings intended to resolve budget disputes.
(Pet.’s Ex.2 at pp.
96-98)
The
Agency’s denial letter does not disclose which rates are excessive and what an
appropriate rate
may be.
(Admin. Rec. at p. 91) Thus, the only non-litigation resolution proposed by the Agency
was to make arbitrary cuts
as to rates.
4
After the last meeting, Illinois Ayers submitted a new application entitled “Revised’
Phase
1
—
Corrective Action Plan & Budget” (Agency Rec. at p. 2) The accompanying
correspondence indicated that the enclosed plan and budget contained revisions “in
accordance
with our October 24, 2002 meeting.”
(Agency Rec. at p.
1) The Petitioner did not make any
reductions in its standard rates, stating that its rates are actual billing rates and that the Agency’s
analysis ofrates is statistically invalid.
(~)
On March 27, 2003, Carol Hawbaker, the Agency Reviewer, reviewed the plan and
budget.
(Agency Rec. at p.
84) On March 28, 2003, the Agency issued a letter rejecting the plan
and budget as submitted and modifying the plan by (a) reducing the number ofdirect-push soil
borings from
13
to 3,
and (b) reducing the budget from
$52,367.96 to
$22,074.77.
(Admin. Rec.
atpp.
86-92) Among the items reduced were those which had alreadybeen reduced as a
concession to
the Agency.
For example, Petitioner reduced the number ofhours for licensed
professional engineering oversight from ten to five as a concession, but the Agency cut the hours
to two.
(Hrg.
Trans. at p.
56)
In addition, Petitioner eliminated laboratory analysis for ten soil
borings as a concession to
cost, only to have the Agency eliminate the ten soil borings as
irrelevant without the chemical
analysis.
(Hrg.
Trans. at p.
1 04)\
From the March 28, 2003
letter, Illinois Ayers brought this LUST appeal.
The previous
appeal concerning the initial corrective action plan is still pending before the Board and is
currently stayed until the subject appeal is decided.
5
III.
REGULATORY BACKGROUND
The purpose of a corrective action plan is to formulate a remedy “to mitigate any threat to
human health, human safety, or the environment resulting from the underground
storage tank
release.”
(415 ILCS
5/57.7(b)(2))
Ifreimbursement from the LUST Fund will be
sought, the
plan must also be accompanied by a budget that includes an
accounting ofall costs associated
with the implementation and
completion ofthe corrective action plan.
(415 IILCS
5/57.7(b)(3))
The Agency is
directed to
review and approve corrective action plans pursuant to Section
57.7(c)
ofthe Illinois Environmental Protection Act.
(415 ILCS
5/57.7(c))
In making
its
determination, the Agency must utilize “a procedure promulgated by the Board under Section
57.14.”
(415 ILCS
5/57.7(c)(3))
These procedural rules begin at Section 732.500 ofthe Board’s
rules.
(35
Ill. Admin.
Code
§
732.500) Together, the Act and the Board’s procedural rules
govern the obligations of the respective parties and define the issues for review by the Board.
All plans submitted to
the Agency must be made on forms proscribedby the Agency.
(35
Ill. Admin.
Code
§
732.50 1) Within 45
days ofreceiving a plan, the Agency must conduct a
completeness review “to determine whether all information and documentation requiredby the
Agency form
for the particular plan are present.”
(35
Ill. Admin.
Code
§
732.502(a)) If any
information or documentation is missing, the Agency must notify the applicant ofthe specific
type of information needed.
(35
Ill.
Admin.
Code
§
732.502(b))
Ifthe Agency fails to notify the
owner or operator within 45
days that a plan is incomplete, the plan is deemed complete.
(35
Ill.
Admin.
Code
§
732.502(d))
6
Assuming that the plan is complete, the Agency initiates a full technical and financial
review of the corrective action plan and associated budget.
(35
Ill. Admin. Code
§
732.504(a)(1)) Such
a review is described in the Board’s procedural rules as follows:
A full technical review shall consist ofa detailed review of the steps proposed
or completed to accomplish the goals of the plan and to achieve compliance
with the Act and regulations.
Items to be reviewed, if applicable, shall
include, but not be limited to, number and placement of wells and borings,
number and
types of samples and analysis, results of sample analysis, and
protocols
to be followed in making determinations.
The overall goal of the
technical review for plans shall be to determine if the plan
is
sufficient to
satisfy the requirements ofthe Act and
regulations and has
been prepared in
accordance with generally accepted engineering practices....
A full financial review shall consist of a detailed review of the costs
associated with each element necessary to accomplish the goals of the plan as
required pursuant to the Act and regulations.
Items to be reviewed shall
include, but not be limited to, costs associated with any materials, activities
or services that are included in the budget plan.
The overall goal of the
financial review shall be to assure that costs associated with materials,
activities and
services shall be reasonable, shall be consistent with the
associated technical plan,
shall be incurred in the performance of corrective
action activities, and shall not be used for
corrective action activities in
excess
of those necessary to meet the minimum requirements of the Act and
regulations.
(35 Ill. Admin. Code
§
732.505(a),(c))
Ifthe Agency determines that the plan should be rejected ormodified, the Agency must
give the owner or operator written notice within 120
days ofreceipt ofthe plan, and said notice
shall be accompanied by a detailed explanation ofthe legal provisions which might be violated if
the plan is approved, ofthe “specific” type of information, if any, which the Agency deems the
applicant did not provide, and ofthe “specific” reasons why the law might not be met if the plan
is approved.
(415 ILCS
5/57.7(c)(4)(A)-(D))
7
Within 35
days ofreceipt ofthe Agency’s decision, the owner or operator may appeal the
Agency’s decision to the Board.
(415 ILCS
5/57.7(c)(4))
The
Agency’s denial letter frames the
issues before the Board.
Kathe’s Auto Service Center v.
IEPA, PCB 96-102 (Aug.
1,
1996).
The
Agency is precluded from raising additional reasons not specified in the denial letter.
IEPA v.
IPCB, 86 Ill.2d 390 (1981);
Clinton County Oil Co.
v. JEPA, PCB 91-163 (June 4,
1992).
The
burden ofproofis on the petitioner.
(415 ILCS 5/40(a)(1)) Once the petitioner has established a
primafacie
case, it becomes incumbent,upon the Agency to refute the
primafacie
case.
Sexton Contractors Co.
v.
PCB, 201
Ill. App. 3d 415, 425
(1St Dist.
1990).
While the procedures in this appeal
are based upon those in permit appeals, the roles of
the parties are reversed.
In a permit appeal, the Agency’s role is to advocate those controls or
restrictions which best protect the environment from pollution and its threats, while the permit
applicant complains about the cost ofthose controls or restrictions.
In UST appeals, the Agency
seeks to protect the LUST Fund, while the petitioner seeks more environmental protection.
The
Board is the arbiter of those disputes, but in the final analysis it is environmental protection
which is the reason for the existence ofthe Act, the Agency and the Board.
IV.
ARGUMENT
A.
THE RATE SHEET
AND ALL
TESTIMONY BASED UPON THE RATE
SHEET
SHOULD BE STRICKEN.
For a number ofthe contested issues, the Agency’s decision was based solely upon a rate
sheet,
(Pet. Exhibit 2, at pp.
56, 68, 69, 70,
95)
A redacted version ofthe rate sheet can be found
as an attachment to
Petitioner’s Exhibit 3.
(Pet. Ex.
3(Att.
3)) Petitioner
sought, and was refused
access to, the entire rate sheet and the data which forms its basis.
Petitionerwas also refused
8
access to portions ofthe rate sheet which were relied upon in this case.
For example, the Agency
Reviewer testified that rates for drilling labor, utility trucks, and job trailers were not reasonable
based upon the rate sheet.
(Hrg. Trans. at pp.179-80) The same was true for rates for the
concrete coring machine and Bentonite chips, (id. at
182), the phlORP/temperature meter (j~at
184), the camera (jd.), the number ofUSP
sample shipments (id.), and the rate ofthe peristaltic
pump.
(Id.)
None ofthese items
is included in the redacted rate sheet given to Petitioners.
The
Agency’s continuing assertion that it has provided “relevant” portions ofthe rate sheet is
simply
untrue.
See Response to Motion for Interlocutory Appeal,
¶
1.
With the caveat that therehas not been anything close to
complete disclosure ofrelevant
portions of the rate sheet, Petitioner renews its legal
objectionto the rate sheet that the Agency
stated was prematurelyraised by pre-hearing motion.
~
at
¶5.
Specifically, the rate sheet is an
invalid rule which should be stricken and given no legal effect in this proceeding.
Alternatively,
the rate sheet is summary evidence which should be stricken and given no
legal effect in this
proceeding since the Agency refused discovery ofthe basis of said evidence.
1.
The Rate Sheet is an Invalid
De Facto
Rule.
The Agency’s rate sheet is
an unpromulgated rule that violates the Illinois Administrative
Procedure Act (hereinafter “the APA”).
5
ILCS
100/1
et seq.
Under the APA, a rule means
“each agency statement ofgeneral applicability that implements, applies, interprets, orprescribes
law or policy.
.
..“
(5
ILCS
100/1-70)
The Agency’s rate sheet implements an Agency policy
proscribing the “maximum allowable cost” for a wide variety ofitems.
(Pet. Ex.
2 (Att. 3)) The
Agency Reviewer testified that she and other members ofthe LUST
Section “are required to use
9
the rate sheets” as a matter ofAgency “practice.”
(Pet. Exhibit 2,
at p
70)
In reviewing the
reasonableness ofany rate, the Agency Reviewer did not deviate
one iota from the rate sheet or
look at
any information upon which the rate sheet was based.
(Hrg. Trans.
at 205)
Brian Bauer,
the LUST Project Manager most closely involved with the administration ofthe rate sheet,
testified that the rate sheet was intended to promote consistency and speed of review.
(Hrg.
Trans. at p. 221) While these objectives are laudable, the rate sheet accomplishes the goal of
consistencyby creating “standards ofgeneral
applicability” that implement the Act’s requirement
that only reasonable costs are reimbursed. The Illinois Supreme Court has ruled that there is “no
doubt” that an
agencypolicy for calculating reimbursable costs under Medicare is a rule of
general applicability subject to
strict adherence to the notice and comment provisions ofthe
APA.
Senn Park Nursing Center v. Miller,
104 fll.2d 169,
178 (1984).
Guidance or policy
statements that determine the amount ofmoney the State will compensate for services affect the
rights and procedures available to people and entities outside the agency.
jçj~
While there are certain statutory exceptions to the notice and comment requirements,
these are exceptions of“a limited nature which
should be appropriately applied.”
~
at
179.
The exceptions the Agency believes apply are obvious from the cover page ofthe rate sheet:
Effective immediately the attached rate sheet should be used in the review of
all budgets
and reimbursement claims.
The rate sheet is meant to be
a
guidance document therefore, any requests for reimbursement for costs
above the amounts listed on the rate sheet if justifiable, should be discussed
with your unit manager.
Please note that the rate sheet is for internal use
only.
(Pet. Ex. 2
(Att. 2))
This bit ofboilerplate reveals the Agency’s legal strategy in defending its
use ofthe rate
sheet, but it tells us little
about how the rate sheet is actually used.
First, while the rate sheet
10
states that it is
“for internal use only,” the sole purpose ofthe rate sheet is to decide how much
money people outside ofthe Agency will be paid.
In order for the rate sheet to be exempt from
notice and comment requirements, it must relate to the “internal management of an agency and
not affect
private rights or procedures available to persons or entities outside the agency.”
(5
ILCS
100/1-70(i)) Any question on this point is resolved by the Illinois Supreme Court’s
comparable ruling that the amount ofmoney the state reimburses nursing homes does not relate
“solely” to internal agency management.
Semi Park Nursing Center,
104 Iii. 2d at
181.
Nor is it true that the rate sheet is merely guidance.
According to
the Agency Reviewer of
this particular planthe Agency’s practice is that “we are required to use the rate sheets.”
(Pet.
Ex.
2, at p.
70) Similar testimony was provided by the Agency employee in charge ofthe rate
sheets:
Q.
.
.
.
What is your understanding of how the rate sheet is
intended to be used by project managers in
a case where a rate presented in
a
high priority CorrectiveAction Plan budget is above the maximum rate
found on the rate sheet?
A.
It would either be
—
that particular item would be either denied
or modified down to the maximum level.
(Hrg. Trans. at p. 217
(Bauer Testimony))
Now, Bauer admittedly refined his answer later under leading questions by the Agency’s
attorney (id.), but Bauer’s answer is not only clear and unequivocal, but corresponds precisely
with how the Agency Reviewerviewed her duty to the rate sheet.
For each cost or expense
to
which the rate sheet applied, no other evidence was relied upon by the Agency.
In other words,
the public face on the LUST program minimizes the significance of the rate sheets, while in
11
reality, the rate sheet is the only thing that matters and project managers have no idea under what
circumstances a larger rate would or could be justified.
Nonetheless, whether or not project manager’s have the discretion to exceed the
maximum costs allowed in the rate sheet, this
does not make the rate sheet any less an “agency
statement of general applicability that implements, applies, interprets,
or prescribes law or
policy.”
(5
ILCS
100/1-70) The rate sheet is not issued on a case-by-case basis; it is not a
statement made specifically about Illinois Ayers.
It is a statement of Agency policy applicable to
“all budget and reimbursement claims.”
(Pet. Ex. 2 (Att. 2)) Even the Agency’s explanation of
the program indicates that there is a general statement ofpolicy which discriminates between
costs which exceed the “maximum allowable cost” and those which do not.
By testifying that the purpose of the rate sheet is to promote consistency and speed of
review, the Agency has admitted that it has moved away from any pretense ofadjudicatory
decisionmaking in UST reimbursement decisions.
In Platolene 500
v. JEPA, PCB No.
92-9 (May
7, 1992), the Agency told the Board that it had electednot to promulgate rules, but instead make
case-by-case adjudications.
~
at pp.
13-14.
The Board commented on the practical problems
with such an
approach, namely the utter lack ofguidance to
applicants and the ultimate necessity
of a Board appeal to
determine what costs are reimbursable.
~
at 14.
To these problems must
be added that case-by-case determinations do not lend themselves to consistency or speed,
since
each budget request must be evaluated on its specific facts without reliance upon general
standards.
In Platolene
500, the Board held that Agency guidance (if that
is what this is) can
have no legal or regulatory effect in these proceedings. j~
12
Finally, the APA forbids the Agency from engaging in ratemaking unless expressly
authorized to do so by statute
and without promulgating rules which define the practice and
procedure to be followed in setting rates.
(5
ILCS
100/5-25;
see also
5
ILCS
100/1-65
(definition of“ratemaking”) Assuming in
arguendo
that the Agency’s statutory authority to
reimburse “reasonable” costs gives the Agency authority to’ set rates, then the Agency was
obligated to promulgate rules which would determine how such rates would be set.
The Agency
is further restricted in its exercise ofdiscretion by section 5-20 ofthe APA,
“whichrequires that
an agency define as clearly and precisely as possible the standards by which it will exercise its
discretionary power in order to fully inform those affected.”
Guzzo v. Snyder, 326 Iii. App.
3d
1058,
1062
(31(~
Dist. 2002) (citing
5
ILCS
100/5-20)).
Together, these provisions ofthe APA
indicate that the Agency should promulgate rules or propose rules to the Board.
The problems with the Agency’s secret rate setting
are numerous.
The practice spurs
litigation.
The only way Petitioner learned what rates were acceptable and which were not
acceptable to
the Agency was by bringing this appeal.
Second, errors in calculations cannot be
corrected through the scrutiny ofothers.
Testimony in this hearing indicated that the Agency
uses a statistical methodology for sampling which introduces bias.
(Hrg.
Trans. at pp.
237-38)
The Agency’s “expert” on the rate sheet heard this testimony and then left the room without
response.
(Hrg. Trans.
at p.
239)1
The Agency does not at all feel compelled to respond to
criticism about its closely-guarded secrets.
The final problem with secret rules is that it violates
the spirit ofopen government, encouraging cynicism and loss of confidence in the government.
1
Brian Bauer took
a single
class in basic statistics fifteen years ago.
(Pet.’s Ex. pp. 27-
28)
13
In summary, the rate sheet is
a
defacto
rule which should be given no legal effect in this
proceeding.
Since the Agency relied exclusively on the rate sheet in rejecting rates as
unreasonable, the corresponding costs should be restored to the budget.
2.
In the Alternative, the Agency’s Refusal to Disclose the Basis of the
Rate Sheet Prohibits its Use as Evidence.
Assuming that the rate sheet is
found not to be an illegal rule, the question remains as
to
whether the rate sheet has any legitimate evidentiary value in an adjudicatory proceeding.
Where
an Agency is reluctant to
disclose information it wants protected from the public, its
choices are
not without consequences:
Although one cannot force a government agency to disclose
information is deems confidential, the government has the option of holding
back such information and taking the risk of not being able to prove its case,
or ofproducing the material and allowing it to be subject to cross
examination.
(2
Am. Jur.
2d, Administrative Law
§
330 (citing Wirtz
v.
Baldor Electric
Co., 337 F.2d 518
(D.C. Cir.
1964).
In Wirtz, the government was calculating the prevailing minimum wage in the electrical
industry based upon employer surveys obtained under
a pledge ofconfidence.
Wirtz,
337 F.2d at
522.
Employers that did not pay the prevailing minimum wage were to be denied certain
government contracts.
Id. at 520 n. 1.
In an administrative hearing to set aside the wage
determination, the government refused to disclose the underlying data on which the wage
conclusions had beenreached, but instead offered into evidence tables summarizing the data.
While the Court ofAppeals refused to
compel the government to disclose the underlying data
under those circumstances, it held that the government could not support its decision based upon
14
summaries of evidence that it refused to disclose the opposing party.
~
at
526-27.
In support of
this conclusion, the Court ofAppeals stated that the rules of evidence permit the introduction of
summary evidence only if “the documents supporting the tables and on which they are based
are
introduced or at least made available to the opposing party.”
Id. at 526.
Furthermore, the
federal Administrative Procedure Act give parties the right to rebut evidence and conduct such
cross-examination as may be required for a full
and true disclosure of the facts.
~ft
at
525.
A
right to rebut and challenge the government’s case was impossible without an opportunity to
review the underlying data:
It
is
difficult to see how the accuracy, authenticity and
relevancy of
these tabulations could be tested in any way without the disclosure of the...
data upon which the tabulations
are based.
The tabulations were complied
from data which was kept secret, but which was in
the possession of the
government.
Errors in the computation could not be checked...
and the
real meaning of the figures could not be developed
unless the character of the
individual sales could be inquired into.
Id. at
526-27.
Similarly, if the rate sheet is seen as a compendium of data summarized by the Agency
and not
as a rule, then Petitioner should have been given access to the underlying data and not
merely summaries of the data or more specifically selectively-redacted summaries.
The rules of
evidence and
administrative law that were applicable in Wirtz are also
applicable in this
proceeding.
Illinois’ APA also gives parties to
administrative hearings a right to
respond to
evidence and
argument
(5
ILCS
100/10-25(b)), and to
conduct cross-examination (5 ILCS
100/10-40(b)).
Under the Act, parties to proceedings before the Board have a right to cross-
examination.
(415 ILCS
5/32)
Since the Agency’s decision on several matters is based solely
upon the rate sheet, the
only means a party has to
challenge the Agency’s decision is to examine
15
the facts surrounding the rate sheet.
The only opportunity to dispute evidence relied upon by the
Agency is in the Board’s hearing.
EPA v.
PCB,
138 Ill. App. 3d
550,
551
(3rd
Dist.
1985).
Similarly, Illinois
law follows federal
evidence law with respect to summaries.
~
People v. Wiesneske, 234 Ill. App. 3d 29,
41(1St
Dist.
1992) (applying Federal Rule ofEvidence
1006).2
It has also long been a rule ofevidence in Illinois that summaries may only be
considered if the documents summarized are made available in court or otherwise made available
to the opponent.
Heller Financial, Inc. v. Johns-Byrne Co., 264 Ill. App. 3d 681, 692 (Pt Dist.
1994); see
also In re Marriage ofDeLarco, 313 Ill.
App. 3d 107,
116 (2’~
Dist. 2000) (summaries
ofbilling records inadmissible).
A summary of evidence can only be
admissible if the
underlying materials upon which the summary is based are admissible.
Wiesneske, 234 Ill. App.
3d at 44 (holding that most ofthe underlying data would have been admissible, but the
summaries were also based in part upon discussions that were inadmissible hearsay).
In other
words, the admission ofsummary evidence is premised upon the notion that it is the underlying
data (the best evidence) which is actuallybeing admitted, albeit in a more convenient form.
Illinois law and the fundamental mechanics ofthe adversarial process require the underlying data
to
be subject to examination
and possible challenge.
2
The contents ofvoluminous
writings, recordings, or
photographs which cannot conveniently be examined in court
may be presented in the form of a chart, summary, or
calculation.
The originals, or duplicates,
shall be made
available for examination
or copying,
or both,
by other parties
at reasonable time and place.
The court may order that they
be produced in court.
(Fed. R.
Evid.
1006 (emphasis added))
16
Substantial
questions were raised about the rate sheet in this hearing. First,
a number of
the rates rejected were previously approved in earlier applications, raisingthe highly suspect
notion that the Agency’s statistical
analysis reveals falling prices.
(Hrg.
Trans. at pp.
135,
137)
Second,
since the Agency not only keeps its rates secret, but also the categories for which it
keeps rates, neither the private consultants nor the Agency project reviewers know for certain
what any ofthe titles mean (such as project engineer).
(Hrg. Trans.
at p.
138; Pet.’s Ex.
2, at p.
88) The only way to
know whether categorical rate correctly applies to
any job description would
be to
examine the underlying data.
Finally, the Agency’s description ofhow it obtains a
representative sample (subjectively eliminatingbudgets from the same consultant) for
establishing a “reasonable” statistical range indicates that it is
introducing bias into its
equations.
(Hrg. Trans. at pp. 237-38)~Without access to the underlying data, however, these problems
cannot be fully examined.
Petitioner was not even allowed to challenge the rate sheet with
Petitioner’s own list ofAgency decisions in which the rates were accepted.
(Hrg. Trans.
at p.
156;
Pet.’s Ex.
19)
The purpose ofthis proceeding is to allow Petitioner the opportunity to challenge the
basis for the Agency’s decision.
EPA v. PCB,
138 Ill. App. 3d
550,
551
(3~’
Dist.
1985); Kathe’s
Auto Service Center v. IEPA, PCB 96-102 (Aug.
1, 1996).
To
allow the Agency to base its
decisions concerning rates on a document that cannotbe
subjected to traditional avenues of
~ Another potential source ofbias in the sampling
is its limitation to budgets submitted to
a single consumer, the Agency.
This can have a downward bias if,
for example, a consultant
submits lower rates in order to avoid litigation before the Board.
The more frequently a
consultant lowers rates to appease the Agency, the less the information on rates in the Agency’s
records reflect prevailing market rates.
This bias can only be eliminated by expanding sampling
beyond a single
consumer.
17
adversarial examination would involve nothing less than elevating the rate sheet to the status of a
rule.
The Agency cannot have it both ways
—
it cannot both base its decisions on the rate sheet,
while keeping its details secret.
B.
TECHNICAL REVIEW OF THE
CORRECTIVE ACTION PLAN
1.
The Re~iuirementsof the Act and the Regulations Will Be Met If the
Remedial Investigation Includes Thirteen Direct Push Borings
and Not Merely
Three.
The Agency modified by the corrective action plan with the following condition:
The plan includes
13
additional “direct push” soil borings to better define
and evaluate the extent and relative distribution ofpetroleum contaminants
in
the subsurface.
The plan proposes that only 3
ofthese direct push soil
borings will be
sampled for BTEX concentrations.
Therefore,
it appears
as
though the remaining 10 direct push soil borings would be to classify and log
the subsurface soils
in connection with the 13
direct push groundwater
sampling probes to define groundwater extent.
For the purposes of
reimbursement, as the soils were previously classified at the site
during site
classification
activities, the additional
10
direct push soil borings are in
excess of those necessary to meet the minimum requirements of Title
XVI
of
the Act for corrective action
investigation; costs for
such activities are not
reimbursable (Section 57.5(a) of the Act and 35 IAC 732.606(o)).
(Joint Ex.
at pp.
86-87 (emphasis added)
The Board’s rules recognize that corrective action may include additional soil and
groundwater examination.
(35 Ill.
Admin.
Code
§
732.404(e) (additional investigation activities,
“include, but are not limited to, additional soil borings”)
Additional investigation was deemed
necessary by the project’s professional engineer because ofinformation learned during soil
classification
activities.
As part of soil
classification activities, a licensed professional engineer
18
must verify whether the physical soil
classifications are consistent with the “Berg Circular.”4
(415 ILCS 5/57.7(a)(3)) Here, the Berg Circular indicated that the geologic materials beneath the
site. are designated A2 and/or AX, which consists of“thick permeable sand and gravel within 20
feet ofland surface and/or modern river alluvium consisting ofa mixture ofgravel, sand, silt,
and
clay along streams, variable in composition and thickness.”
(Agency Rec., at p.
8 (emphasis
added)) Such soil conditions pose a high potential for both surface and groundwater
contamination.
(Agency Rec., at p.
8)
Petitioner verified the classifications in the Berg Circular were correct:
The actual geology encountered at the site was representative of “AX” type
stratigraphy, containing assemblages of sand, silt, and
clay in varying
proportions, to a depth of approximately twelve (12) to fifteen (15) feet below
the ground surface at which point clean sands and gravel representative of
~~A2t~
type stratigraphy were encountered.
(Admin. Rec. at p.
9 (emphasis added))
A diagram ofa stratigraphic cross section was included in the corrective action plan
(Admin. Rec. at p.
19), alongwith these discussions ofthe actual soil conditions and the
information drawn from the Berg Circular.
Having verified that site conditions conform to
those
described in the Berg Circular, there was still inadequate information to determine the “the full
extent ofsoil or groundwater contamination and ofthreats to human health and the
environment.”
(35 Ill. Admin. Code 732.404(e))
The Act also requires an investigation and
remediation of natural migration pathways, which the Board defines as “natural routes for the
transport ofmobile petroleum free-liquid or petroleum-based vapors including, but not limited
to
~ The
Illinois Geological Survey Circular (1984) titled “Potential for Contamination of
Shallow Aquifers in Illinois,” by Berg, Richard C. et al.
19
soil, groundwater, sand seams and lenses and gravel seams and lenses.”
(35
Ill. Admin.
Code
§
732. 103)
Because soil conditions at the site were determined to be variable, Petitioner did not have
enough information to
determine the extent ofBTEX contamination.
Joseph Truesdale, a
professional engineer with CSD Environmental,
explained:
The Act requires evaluation of potential natural migration pathways.
Since
the soils at the site were specified as variable in composition and thickness
without quantifying that variability across the potential limits ofthe plume,
there would be no way to fully evaluate those identified natural migration
pathways or, as a matter of fact, would not be able to identify those potential
natural migration pathways on off site locations, whatsoever.
(Hrg. Trans.
at p.
72)
In order “to better define and evaluate the extent
and relative distribution ofpetroleum
contaminants in the subsurface,” Petitioner proposed to
advance six on-site “direct-push”
soil
borings and seven off-site “direct-push” soil borings.
(Agency Rec., at p.
6) The location of
these thirteen soil borings would also be used fortaking groundwater samples from each ofthese
thirteen locations.
(~)
Since the groundwater samples are to be taken within two feet of the soil
borings, there are a total of26 borings proposed at 13
locations.
(j~at 68)
Modeling from the
initial site classification work was used to
determine the number and location of the direct-push
borings.
(Pet.’s Ex.
1,
at p. 6) The proposed direct-push boring were identified on a map
submitted with the plan and labeled B-5 through B-17.
(Agency Rec., at p.
16) At the hearing,
Truesdale testified on the location and number of borings:
We proposed a total of 13
direct-push soil
and ground water
sampling
locations, the majority of which were down gradient from the source, some of
which were in the source area.
A single location was up gradient, in order to
characterize potential input of contaminant
mass from an off site location.
20
And the final boring location was placed side gradient to evaluate additional
potential contaminant flux from
a second potential off site location.
As we discussed in the meeting with the Agency personnel, boring B5
was located to evaluate potential source contaminant mass flux from an off
site location located to the east of State Street.
Boring B6
was also located in
order to evaluate flux from a potential
—
a second potential off site
source
located to the south of Fourth Street.
The remaining borings, B17 was
located at that approximate distance based on preliminary
ground water
contaminant transport modeling conducted using TACO equation R26, as
outlined in the application.
The remaining three offsite borings were located
so as to evaluate the lateral spread of the plume across the approximate
center line as estimated, using equation R26.
(Hrg. Trans..
at pp. 4 1-43)
Truesdalé testified that thirteen borings at the described locations is
the minimum that
would be necessary to achieve the Act’s goals, and in fact, more borings may ultimately be
required.
(Hrg. Trans.
at p.
72) He also testified that this plan was prepared in accordance with
generally accepted engineering practices.
(Hrg. Trans.
at p.
97) The investigation approach taken
was
consistent with USEPA guidance entitled “Expedited Site Assessment Tools for
Underground Storage Tank Sites,” a copyofwhich was brought to the Agency’s attention prior
to
filing the subject plan and budget with the Agency.
(Hrg. Trans.
at pp.
65-66;
Pet.’s Ex.
10)
At the locations identified in the map accompanying the plan, Truesdale proposed taking
both soil and groundwater samples
using direct-push technology.
(Agency Rec., at p.
6; Hrg.
Trans.
at p. 35) As the Agency Reviewer previously rejected the use of such technology for
taking water samples (Joint Ex. 6(A) at
¶5),
the nature ofthis emerging technology may need
some explanation.
In April of 2001, the Agency published guidance entitled “Use ofPush-
Driven Technology.”
(Pet.’s Ex. 9) This
document describes push-driven technology as a “useful
21
and cost-effective technology, which yields accurate and representative soil and
groundwater
samples.”
(Id.)
This technology may be used to “investigate contaminant migration along
natural
and man-made pathways.” (j~)
While the corrective action plan states that
13 direct-push soil borings will be advanced,
soil samples will only be taken from three locations for laboratory analysis.
(Agency Rec., at p.
6) Originally, Petitioner proposed that soil samples be taken and tested from
all thirteen
locations, but as a concession, Petitioner would only “log and screen” the soil borings at ten of
the locations without laboratory backup.
(Hrg. Trans. at p.
104) This would be done in
accordance with the Board’s rules at Section 732.308.
(Agency Rec., at p. 68) Even without
quantitative chemical analysis, these soil borings should provide useful qualitative information
concerning soil conditions
and characteristics ofpotential migration pathways, including soil
constituents, consistency, moisture content, nature and extent ofsand or gravel seems and/or
lenses,
visual and olfactory evidence of contamination and volatile organic vapor concentrations
based on field screening with instruments
capable ofdetecting such vapors.
~
35
Ill. Admin.
Code
§
732.3 08(a).
While the Section 732.308(a) rules
are in the subpart dealing with site
evaluation and classification, the purpose ofthese soil borings
is not to re-classify the soil, but
“to better define and evaluate the extent and relative distribution ofpetroleum contaminants in
the subsurface.”
(Admin. Rec. at p.
6)
In summary, initial investigation identified variable soil conditions, which make it
particularly difficult to know the extent and nature of the contamination at the site.
This
investigation
also revealed the need for further investigation ofnatural migration pathways to be
investigated, remediated and restored.
This information was in the corrective action plan
22
submitted to
the Agency.
Its veracity and
sufficiency was supported from a licensed professional
engineer, Joseph Truesdale, the
only person with such qualifications testifying in these
proceedings.
His resume is
in the record (Pet.’s Ex.
8) and he testified to his qualifications and
his previous experience in direct-push operations.
(Hrg. Trans. at pp.
22-24, 40) There was no
other comparable testimony at the Board’s hearing.
The Agency’s denial is premised on
a number of errors, but particularly,
the falsebelief
that the soil conditions at the site were homogeneous.
The Agency Reviewer’s testimony is
clear:
Q.
So tell me, do you know whether the soils at offsite locations
at this
Beardstown gas station are known to be uniform homogeneous soils?
A..
According to their site classification report, yes, that is what they
found.
Q.
Okay.
And if that were not in the site classification completion report
and that finding were not made, would you change your view that perhaps
they need to do some soil investigation as part of this Phase
1
Plan?
A.
Ifwe had found some layers that seemed to be heterogeneous in
the
site, yes.
However, that was not the case.
Q.
So the fact that the soils at off-site locations were known to be uniform
homogenous soils
—
A.
Regional
soil geology has
been proven to be
uniform at the site.
It can be assumed that it is uniform off-site as well.
‘(Pet.’s Ex.
2, at pp.
2 1-22 (emphasis added))
Q.
And in this particular case you believe that during site
classification
they confirmed that the Berg Circular properly described regional
geology?
A.
If I remember correctly it did.
I
know
it was an AX classification.
23
Essentially what it was
determined it was, it was homogenous
throughout the site.
Q.
That’s what you recall?
A.
Yes.
Q.
And that’s why some of the cuts were recommended by you in
your review letter to the Agency
—
to the client in this case, because they had
already confirmed, and it was
homogenous?
A.
It was not going to give us any additional information that
would be helpful.
Q.
Okay.
A.
I have very sites in Beardstown.
Beardstown is old hat.
I would be very, very surprised to find
something that is not sand there.
I think what are you four blocks from the river?
It’s all sand.
(Pet.’sEx.2,
atpp.
100-101)
Had theAgency Reviewer read the corrective action plan instead ofrelying upon her
recollection ofnearly two years at the Agency, she would have known that the Berg Circular did
not describe soil conditions as homogenous, but as a mixture ofgravel, sand, silt, and clay which
was “variable in composition and thickness.” (Agency Rec., at p.
8) She would have also read
that
the actual geology encountered at the site was, in fact, a mixture ofsand, silt, and clay in
varying proportions.
(Agency Rec., at pp.
9
&
19) Attached hereto as Exhibit A is a stratigraphic
cross section which was included with the corrective action plan.
(Agency Rec. at p.
19)
The primaryreason for reprinting large chunks ofthe Agency Reviewer’s testimony is in
case there
is any doubt as the veracity ofher testimony when she later testified that whether soils
conditions were homogenous or heterogenous was “irrelevant” to her decision.
(Hrg.
Trans. at p.
24
202)
Herprevious
testimony, taken under oath and with multiple opportunities
for her to explain
herself, is quite to the contrary.
In fact, Hawbaker’s testimony that her decision to reject the ten
soil borings based upon her perception ofsoil conditions at the site is a judicial admission which
cannot be withdrawn or rebutted by the Agency.
In re Estate of Rennick,
181
Ill. 2d
395, 406-07
(1998).
Judicial admissions are defined as deliberate, clear, unequivocal statements by a party
about a concrete fact within that party’s knowledge.
Id.
The Agency Reviewer clearly had
personal knowledge ofthe reason for reducing the number ofsoil borings and the lengthy quotes
from her testimony clearly show that her decision was based upon an erroneous assumption about
soil conditions at the site.
Her testimony cannot be changed as a matter oflaw.
Even ifthe Agency Reviewer’s
testimony can be adjusted, the explanation given at
hearing requests this Board to make a highly dubious ruling.
It is the Agency Reviewer’s
contention that regardless of local site or soil conditions, a high priority investigation plan can
never include soil borings without chemical analysis.
(Hrg. Trans. at p.
201) The Board has
never before expressed rigid, inflexible limits on the scope ofinvestigation during corrective
action.
~
35
Ill. Admin.
Code
§
732 .404(e)(”additional investigation activities beyond those
required for the site evaluation and classification maybe necessary”).
Petitioner has proposed
additional
soil borings
at new locations to
obtain information additional to that which was
obtained at the site classification stage.
As the Agency Reviewer explained in her testimony, the
initial site investigation work is merely “an initial
assessment based on the Berg Circular.”
(Pet.’s Ex.
3, at p.
100)
There are two fallacies in the Agency Reviewer’s position.
First, it is not true that soil
borings without chemical
analysis can never provide useful information about the extent of
25
contamination.
The Agency Reviewer’s opinion overlooks the fact that even though chemical
analysis is not proposed to
be done on the ten soil borings (the Agency’s own cost-saving
strategy), there will be information on field observations (such
as color and odors) and OVA/PD
readings for petroleum vapors.
~
35
Ill.
Admin. Code
§
732.308.
The second fallacy is that
information specific to soil conditions can never provide useful information as to the extent of
contamination.
The reason local
soil conditions are investigated in the first place is
to obtain
information on the potential for contamination to migrate.
The Act and the Board’s rules require
investigation and remediation ofnatural migration pathways, which requires an understanding of
local soil conditions.
In this case, it requires knowledge oflocal soil conditions beyond knowing
simply that soil conditions vary.
The purpose ofa’technical review ofthe plan is “to determine if the plan is sufficient to
satisfy the requirements ofthe Act and regulations
and has been prepared in accordance with
generally accepted engineering practices.”
(35 Ill. Admin. Code
§
732.505(a))
The thirteen soil
borings
were proposed based upon site-specific conditions which were analyzed in depth by
Petitioner’s professional engineer.
This is the minimum number ofborings that would be
necessary to
achieve the goals ofthe Act and may not ultimately be enough.
The Agency’s
contrary position is based purely on a mistake.
26
C.
FINANCIAL REVIEW OF THE BUDGET
1.
The
Investigation Costs are Reasonable Given the Actual Length of
Time to Perform the Direct Push Investigation.
The Agency eliminated $8,910.72 for Investigation Costs:
As
10 direct push borings are in excess ofthe minimum requirements of Title
XVI, the Direct Push investigation should take 2 days
to complete (8 direct
push borings per day).
Therefore, the costs for the direct push investigation,
drilling labor, utility truck, job trailer, decontamination
activities, and
disposable sampling tubes have been modified accordingly.
Please note that
drilling labor and
utility truck must be included
in the Geoprobe per day
cost.
Job trailer is part of mobilization costs and are included in the
mobilization rate.
Sampling tubes have been modified from 70
to 6.
In
addition, costs for Direct Push investigation, drilling labor, utility truck and
job trailer are not reasonable as submitted (35 IAC 732.606(hh))
(Agency Rec., at p.
90)
The Agency also eliminated $108.00 for the following investigation costs:
Costs for the concrete coring machine and
bentonite chips are unreasonable
and have been
modified accordingly.
(Agency Rec., atp.
91)
Together the investigation costs eliminated from the budget total $9,018.72.
a.
The Reduction to 10 direct-push borings is
erroneous.
The Agency eliminated
10 direct-push borings in its
technical review of the corrective
action plan.
Petitioner restates and reincorporates its
arguments pertaining to that decision here.
b.
The Time the Agency Claims that it Takes to Conduct
the
Direct-push Investigation is Erroneous.
Petitioner proposed 26 borings at
13
locations.
(Agency Rec., at p.
68)
The first boring
would be for direct-push subsurface investigation
and the second boring for direct-push
27
groundwater sampling.
(Id.)
The budget estimated 50 hours
to conduct these 26 borings.
(Ti)
As per the Agency’s forms, this estimate was based upon the number offeet to be bored; since
each boring was to reach 20 feet, then there was a total of 520 feet to be bored.
(j~)
Before further explaining the basis of the 50 hour estimate, Petitioner would like
to point
out that it offered into evidence as a demonstrative exhibit, Truesdale’s calculations that
accompanied his testimony.
(Pet.’s
Ex.
13) This document was not admitted into evidence
because it was redundant, but allowedunder an offer ofproof
(Hrg.
Trans. at pp.
79-81) The
primary issue in admitting demonstrative evidence is whether it will help the trier of fact
understand the issues in the case.
Burke v.
Toledo, Peoria & Western R.R.
Co.,
148
Ill. App.
3d
208,
213
(Pt Dist.
1986).
This exhibit is available if it would help the Board.
Truesdale testified that
in a meeting with the Agency he explained his
figures and drew
diagrams on the dry erase board to help.
(Hrg. Trans. at p. 37) CSD Environmental conducted
fieldtests in order to
develop numbers for estimating the time it would taketo conduct the direct-
push investigation.
(Hrg. Trans.
at p.
40) There were three components to
the analysis: (1) how
long would it take to drill non-stop
on a per-foot basis, (2) how long would it take to draw
groundwater samples, and (3) how long would it take to mobilize on off-site properties.
(Hrg.
Trans. atp. 37)
Truesdale testified that in his experience, a team could drill between 140 to
170 feet in a
ten hour day,
and in this case he estimated 160 feet per-day.
(Hrg. Trans.
at p. 37) Given that
there were 520 total feet to be drilled,
this meant it would take 32.5 hours or 3.25 days simply to
do the drilling.
28
The recovery ofgroundwater samples from direct-push technology is not instantaneous.
Enough time must pass in order for groundwater to
accumulate in the screen in order to be
collected.
(Hrg. Trans.
at p. 37) Truesdale testified that it may take anywhere from 20 minutes
to
an hour-and-a-half for the groundwater to
accumulate.
(Hrg. Trans.
at p.
46)
Given local
site
conditions,
Truesdale estimated it would take an average of a
half-hour per groundwater sample.
(FTrg. Trans. at p. 46) Since two groundwater samples were to be taken from each ofthe 13
sites
(for a total of26
groundwater samples), there would be 13 hours in which probing would stop in
order to
allow groundwater to
accumulate.
Furthermore, the direct-push investigation on off-site locations will require an additional
hour to move equipment and setup offsite.
(Hrg. Trans. at p.
37) Since there are five off-site
locations to be investigated, Truesdale
added five hours to his
estimate.
This brings the direct-pushinvestigation to
a total of
50.5
hours (which was rounded
down to 50 hours on the budget).
The Agency’s belief that the work could be done
in 16 hours is
without basis. Even if ten soil probes were eliminated from the corrective action plan, there
would still be 13 hours in which groundwater was being collected.
Since the Agency had
previously denied that direct-push technology can be used to sample groundwater, the
unmistakable impression is that the Agency is not fully familiar with the benefits and limits of
this technology.
The Agency Reviewer admitted that she did not know how long it would take to
conduct
the direct-push investigation,
so she asked Harry Chappel, her unit manager.
(Pet. ‘s Ex. 2, at p.
32) Chappel testified that he was asked his opinion on the number ofdirect-pushborings that
could be done in a day and he responded eight.
(Pet.’s Ex.
3, at p.
27) Chappel was never told
29
any information about the site, was not told that groundwater samples would be taken, was not
told how many feet were to be drilled and was not told about any site or soil conditions.
(Pet.’s
Ex.
2, at pp.
32-33; Pet.’s Ex~
3, at pp. 34-36; Hrg. Trans. at pp.
209-10)
The Agency Reviewer’s conclusion that eight probes per day is reasonable is based upon
the erroneous assumption that all probes are the same.
The Agency Reviewer had no information
that the total number ofhours was unreasonable other than an off-hand question to
her supervisor
that lacked any ofthe details necessary to make an informed decision.
In contrast, Truesdale
testified in depth about his experience and the numerous practical considerations which were
relied upon in reaching the appropriate 50 hour estimate.
c.
Other Investigation Costs Are Reasonable Given These Time
Considerations and the Unrebutted Evidence of the Reasonableness of
the Rates.
The remaining investigation costs were reduced by the Agency based upon the
assumptions that the direct-push investigation would take only two days.
Since the direct-push
investigation will take fifty hours
(5
days), the Agency’s reductions are erroneous.
These costs
are located in the chart on the bottom halfofpage 68
of the Agency Record.
Truesdale testified that the decontamination equipment will be needed for five days in
order to decontaminate equipment between borings, (Hrg. Trans.
at p.
53
& 89), labor will be
needed to run the decontamination equipment (j~at 89), a concrete coring machine is needed for
five days in order to provide an opening in impervious materials (j~at 53), the disposable
sampling tubes
are needed in order to extract the soils to be logged (whether or not a chemical
sample will be taken) (id.), drilling labor is needed to
conduct the work (j~),utility locate is
required before digging on-site (j~),the utility truck and job trailer are required (j4~
at 53-54 &
30
91) and the Bentonite Chips are required to seal the bore holes in order to prevent additional flux
ofcontamination to
the subsurface (id.
at 54).
It is unclear how cuts were made to these investigation costs.
The Agency Reviewer
merely testified that she cut other investigation costs from five days to two
days. (Hrg. Trans.
at
p.
179) In addition, the Agency Reviewer testified that
costs associated with the direct-push
investigation,
drilling labor, utility truck,job
trailer, concrete coring machine and Bentonite chips
were unreasonable based upon her comparison with the rate sheet.
(Hrg. Trans.
at pp.
180-8 1)
For the record, Petitioner was neverprovided those portions of the rate sheet relating to
these
items.
(Pet.’ s Ex.
3, Att. 3) Cindy Davis offered unrebutted testimony as to the reasonableness of
all of these rates.
(Hrg.
Trans. at pp.
144-46)
Since most ofthe reductions for other investigation equipment derive from the Agency
Reviewer’s reduction of the investigation plan from five days to two days, a change that should
be rejected, Petitioner asks that these costs be restored given the evidence that it will take five
days.
Furthermore,
to the extent that the Agency cut rates based upon a secret rate sheet, those
cuts
should be restored because the rate sheet should be given no legal effect in this proceeding.
In summary, Petitioner asks that $9,018.72 in investigation costs be restored.
2.
The Analysis
Cost
Necessary
to Calculate TACO Objectives Should
Be Restored.
The Agency eliminated $490.00 for analysis costs:
The following analyses have cut from the budget: moisture content analysis,
Foc analysis, bulk density, particle density.
In
addition, there is no mention
in the plan that soil cuttings will be transported to a landfill.
Therefore, pH,
paint filter,
flash point
and TCLP lead have been
cut from the budget.
31
(Agency Rec., atp.
91)
The budget contains $3,010.00 in analysis costs.
(Agency Rec., at pp.
70-71) Joseph
rruesdale explained the importance of the analyses the Agency proposes to
cut:
In
order to develop
risk based objectives for subsequent
determination of appropriate clean
up levels, these parameters must be
obtained during investigation in
order to calculate
the appropriate risk based
objectives under TACO.
(Hrg. Trans.
at p.
65)
The Agency Reviewer also
stated that she relied upon the rate sheet in eliminating and/or
reducing the phlORP/temperature meter.
(Hrg. Trans. at p.
184)
Therefore the $490.00 for
analysis costs should be restored as both reasonable and necessary.
3.
The Personnel Costs are Based Upon Reasonable Rates and Work
Necessary to Complete the Corrective Action Plan.
The Agency eliminated $18,450.00 in personnel costs:
The following
job titles have been modified to
a
more reasonable
rate and
time to complete tasks: Professional Engineer, Project Engineer, and Staff
Geologist.
In addition the Job title Field Manager has been cut from the
budget for excessive personnel at the site.
In
addition, as the plan has been
modified, the hours attributed to the above titles exceed the minimums:to
comply with Title
XVI (35
IAC 732.505(c))).
(Agency Rec., atp. 91)
The Agency provided a breakdown ofits
rate and time reductions.
(Pet. ‘s Ex.
11,
at
¶3(d)) The rate reductions are based entirelyupon the illegal rate sheet and should be rejected
outright.
Without waiving said objection, Petitioner states that the rates and time are not
excessive for the following reasons:
32
a.
Professional Engineer.
The Agency appears
to have cut the number ofhours for the professional engineer from
5
hours to 2 hours.
(Pet.’s Ex.
11, at ¶3(d)) Truesdale testified that by law the professional
engineer is required to
oversee all phases ofthe work, which he is signing and certifying.
(Hrg.
Trans. at p.
56;
see 225 ILCS 325/14 (Professional Engineering Practice Act); 68 Ill. Admin.
Code 1380.300(a)(2) (implementing regulations).
“Two
hours is obviously not enough time to
oversee the.
.
.
upward of400 hours that are specified in the plan elsewhere under the other
items.”
(Hrg.
Trans. at p.
56)
In fact, five hours is not enough in Truesdale’s opinion, but he
reducedthe time as a concession to the Agency.
(j~)According to the Agency, all the
professional engineer needs to
do
is thumb threw some documents and sign-offon them.
(Pet.’s
Ex.
3, atp. 67)
Cindy Davis, owner ofCSD Environmental, testified at the hearing as to
the basis ofthe
$150 hourly rate for professional engineer.
(Hrg. Trans.
at pp.
134-42) The rate is arrived at by
considering the employee’s salary, the employer’s tax contributions, and a standard engineering
profit multiplier which takes into consideration employee health insurance, overhead costs and
company profit. (j~at 134) This is the standard way it is done
in the engineering business.
(~
at
142)
She testified that employee salaries are comparable to Agency salaries.
(~
at
135) The
resulting rate of$1 50-per-hour is the company’s usual and customary rate for all services,
including those paid by CSD
Environmental’s customers. (j~at 135-36)
The Agency has also
approved this rate before.
(~)
In fact, the Petitioner attempted to
submit into evidence the
identity ofnumerous
projects in which the Agency had previously approved rates which it now
33
challenges.
(Pet.’s Ex. 19)~
In setting the rate of$150-per-hour,
Cindy Davis was familiar with
rates charges by other companies
in the industry.
(Hrg. Trans. at pp.
136~37)6
Cindy Davis also
purchased a survey that provided standard billing rates for professional engineers in small
Midwest firms at between $132 to
$155
per-hour.
(Hrg. Trans.
at p.
140)
b.
Project Engineer.
The project
engineer’s hours were reduced from
156 hours to
40 hours.
(Pet. ‘s Ex.
11, at
¶3(d)) The project
engineer’s hours are forthe design and development of the corrective action
plan and the corrective action planbudget, correspondence with the Agency and with the client,
coordinating the investigation project, meeting with the Agency and preparing the reimbursement
request.
(Hrg. Trans.
at p. 59) Truesdale testified that
156
hours
is necessary to do the work in
the plan in a way that complies with the Act.
(Hrg. Trans.
at pp.
59-60)
When asked by the
Agency’s attorney to explain how she reached 40 hours, the Agency Reviewer testified that she
“felt” that 40 hours should be ample time.
(Hrg. Trans. at p.
189)
The project engineer’s hourly rate is $114-per-hour.
(Agency Rec., at p. 72) These rates
were also based upon the same standard formula discussed supra with respect to professional
engineers.
(Hrg. Trans.
at p.
141) Moreover, the Agency has previously and repeatedly approved
a rate of$1 14-per-hour for project engineers.
(Hrg. Trans. at p.
137) Furthermore, the survey
~
Petitioner submitted a list ofprojects in which the Agency had previously approved
rates which are now deemed unreasonable.
This information is directly relevant to the issue of
whether or not these rates are reasonable and should have been admitted.
6
Cindy Davis testified to her knowledge of comparable rates in the industry based upon
experience in taking
over projects from other companies, Freedom ofInformation Act queries,
participation in the Consulting Engineers Council, and
annual seminars in which pricing issues
are discussed.
(Hrg. Trans.
at pp.
136-37)
34
purchased by Cindy Davis stated that project engineers in small Midwestern firms
were charging
approximately $120 to $130 per-hour.
(Hrg. Trans.
at p.
140)
c.
Staff
Geologist.
The Staff Geologist’s hours were reduced from 88
hours to
40 hours.
(Pet.’s Ex.
11, at
¶3(d)) The Staff Geologist’s job is to perform the R26 modeling and CAP
design.
(Hrg. Trans.
at
p.
56)
Truesdale
testified that the number of hours were necessary for the described tasks and
were not excessive.
(Hrg. Trans.
at pp.
57-58)
Petitioner submitted a budget in which the Staff Geologist would be paid $72.00 per
hour.
(Agency Rec., at p. 72) Since the rate sheet has a maximum rate of$86 per hour (Pet.
Ex.
2 (Att. 2)), the Agency did not cut this rate.
(Pet.’s Ex.
11, at ¶3(d))
d.
Field
Manager.
All of the Field Manager’s eight hours were cut as excessive.
(Pet.’s Ex.
11, at ¶3(d))
The Field Manger’s job was to collect groundwater samples.
(Agency Rec., at p. 73) A field
technician was also tasked to help collect groundwater samples for the same eight hours.
(~)
If
either ofthese positions was eliminated, it would take twice
as many hours (16) to perform the
task.
(Hrg. Trans.
at p.
56)
Furthermore, the position that would need to be eliminated would not
be the more-experienced Field Manager ($90 per hour), but the less-experienced Field
Technician ($66 per hour).
(Hrg.
Trans. at p.
56)
However, Truesdale testified that OSHA
regulations do not allow one person to perform this function unassisted.
(~.
at
56)
OSHA
35
regulations require the use ofa “buddy system” when handling potentially hazardous materials in
order to provide rapid assistance in the event of an
emergency.
(29 CFR Part
1910)
The Agency did not object to the Field Manger’s hourly rate, and it is
a rate that has been
approved
in the past.
(Hrg. Trans.
at p.
137)
Therefore, there is no
question that the rate is
reasonable.
For the foregoing reasons, all personnel costs must be restored.
4.
The Equipment Costs Are Necessary for the Number of
Days
ofWork
Required and Are Based Upon Reasonable Equipment Rates.
The Agency rejected $849.30 in the following equipment costs:
The following items have been reduced to
2 day’s use:
PID,
ph/ORP/temperature meter, and utility truck for geologist for logging soil
borings.
In
addition, EnCore samplers have been reduced to 6 from 12.
The
following item’s rates was also modified as unreasonable:
pH/ORP/temperature meter (35 IAC 732.606(hh))
(AgencyRec., atp. 91)
In addition, $36.00 for camera costs were also rejected,
(~),
for a total of$885.30 in
equipment costs.
Truesdale explained the necessity for these costs:
As specified on the sheet, the PID and the pH meter were estimated to
be used for five days, which corresponds to the investigation hour estimate
provided on page 68 previously.
The EnCore samplers were estimated based
on the number ofsample
—
the soil samples approved by the Agency
in
accordance with
5035, analysis for BTEX,
two
EnCore samplers must be
submitted to the laboratory for each BTEX sample.
Since we had six
samples that were approved by the Agency,
12 EnCore samplers were
required.
36
A camera was
also reduced.
We had
two
days of camera use instead
of five.
(Hrg. Trans.
at p. 61)
The reduction of use ofthis equipment to two days is not appropriate given that the work
will take five days.
The Agency Reviewer also indicated that the camera use had been reduced in
light ofthe rate sheet.
All ofthese equipment costs should therefore be restored.
5.
The Field Purchases Are Necessary for
the Number of Days ofWork
Required
and Are Based Upon Reasonable Equipment Rates.
The Agency eliminated $150.00 as “an adjustment in USP
sample shipping,” $50.00 for
“Misc.
Retail Purchases,” and $270.00
as a reduction for the number ofrental days for a
peristaltic pump.
(Agency Rec., at p.
92) These costs total $470.00.
Truesdale
explained the necessity of these items:
Miscellaneous retail purchases includes ice, film, and miscellaneous
parts in the field.
Ice is required for preservation of samples in the field.
We have film.
Obviously;
that is required for documenting photographic
evidence of what is being conducted.
It is
a relatively small cost on
a per day
basis so we don’t charge for disposable gloves
and shovels and spades and
miscellaneous equipment.
We lump it into
a miscellaneous purchase cost
which is
covered on item one.
UPS, shipment of samples to the laboratory.
Soil and ground water
samples are very heavy and are shipped in coolers.
And
$50.00 per sample
per day is probably actually now slightly low.
Our recent costs are actually a
little bit higher than
that.
The ground water sampling pump is obviously required in order to
obtain the ground water samples.
The screen point sampler and the
disposable ground water sampling tube is also required to obtain direct-push
screen point sampler ground water samples.
37
We are required to submit reports to the Agency in duplicate, and as
a result, photocopying is required.
(EIrg. Trans.
at pp.
6 1-62)
These are expenses needed to complete the plan, and which are slightly lower than actual
costs. The Agency reviewer testified that she relied on the rate sheet in determine a reasonable
number of sample shipments and a reasonable rate for the peristaltic pump.
(Hrg. Trans.
at p.
184)
Therefore, these $470 in items
should be restored to
the budget.
6.
.
The Handling Charges Were Reduced Solely Due to Other Cuts
in the
Budget and Therefore
Should Be Restored to the Extent the Budget is
Restored.
The budget included $1,714.76
in handling charges.
(Agency Rec., at p. 78)
There was
no objection to the handling charges themselves,
but once cuts were made elsewhere in the
budget, the $1,714.76 in handling charges exceeded the costs eligible under the statutory
formula.
(Agency Rec., at p.
92) In the event that the Board restores any or all cuts made
elsewhere in the budget, Petitioner asks that the corresponding cuts
in handling charges be
restored as well.
V.
CONCLUSION.
Petitioner gave the Agency a technically sound Phase I High Priority Corrective Action
Plan (Investigation), complying in all respects with the Act and the Board regulations,
and
a
corresponding barebones budget to implement that plan.
Petitioner’s first attempt was rejected,
primarily because the Agency Reviewer mistakenly believed that direct-push soil borings cannot
be used to gather groundwater samples.
Rather than clog the Board’s docket with an appeal,
38
Petitioner sought a 90-day extension for appealing the Agency’s decision, timelymet with
Agency personnel to
explain the direct-push technology (using the Agency’s own fact sheet),
and agreed to make certain concessions in an amended plan and budget.
Without advance
warning, the Agency rejected
10 out of 26 direct-push borings and 58
ofthe reducedbudget.
Recognizing a moving target, Petitioner appealed to
the Board and herebyrespectfully requests
the Board reverse the Agency’s changes in the corrective action plan, reverse the Agency’s cuts
to the associated budget, and provide for such otherrelief as the Board deems meet and just.
Respectfully submitted by
ILLINOIS AYERS OIL COMPANY,
Petitioner,
By its attorneys,
MOHAN,
ALEWELT
By
B~
Fred C. Prillaman
PatrickD.
Shaw
Mohan, Alewelt, Prillaman & Adami
One North Old State Capitol Plaza
Suite 325
Springfield,
IL 62704
217/528-2517
39
&
ADAMI
C
z
-
C
C
~
o
~
o
a-
z
z
C
C
~
(no
CD
z
-4
-I
0
CD
z
=
0
-4
LU
LU
-4
C
C.)
0
LU
C
LU
-J
C
0
C/)
C
I
C)
CD
N-
CO
LCD
~
C)
CN
r
C)
C)
CD
N-
CO
LCD
~
CI
CN
‘
C
C)
C)
C)
C)
C)
C)
C)
C)
C)
C)
C
C
C
C
C
C
C
C
C
C
flq
fl~\
/
o
C)
C
N-
CO
LI
CI
C\J
—
0
C)
C
N-
CO
It)
CI
o
C)
C)
C)
C)
C)
C)
C)
C)
C)
C)
C
C
C
C
C
C
C
C
C
19