ILLINOIS POLLUTION CONTROL BOARD
    January 8, 2004
     
    ARCHER DANIELS MIDLAND COMPANY,
     
    Petitioner,
     
    v.
     
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
     
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB
    04-114
     
    (Permit Appeal - Air)
    (90-Day
    Extension)
     
    ORDER OF THE BOARD (by J.P. Novak):
     
    On January 2, 2004, the parties timely filed a joint notice to extend the 35-day period
    within which Archer Daniels Midland Company may appeal a December 1, 2003 determination
    of the Illinois Environmental Protection Agency (Agency).
    See
    415 ILCS 5/40(a)(1) (2002); 35
    Ill. Adm. Code 105.206(c), 105.208(a), (c). The Agency approved the application for a Clean
    Air Act Permit Program permit, with conditions, regarding Archer Daniels Midland Company’s
    dry corn mill and ethanol plant at Peoria, Peoria County. The Board extends the appeal period
    until March 30, 2004, as the parties request.
    See
    415 ILCS 5/40(a)(1) (2002); 35 Ill. Adm. Code
    105.208(a). If Archer Daniels Midland Company fails to file an appeal on or before that date,
    the Board will dismiss this case and close the docket.
     
    IT IS SO ORDERED.
     
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
    adopted the above order on January 8, 2004, by a vote of 5-0.
     
     
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board