1. ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
      2. Two (2) CopiesTwo (2) CopiesTwo (2) CopiesTwo (2) CopiesTwo (2) Copies
      3. Very tmly yours,
      4.  
      5. NPDES Permit # 1L0029564
      6. NPDES Permit No. 1L0029564September, 2003
      7. Revised RevisedParameter CBOD5 Suspended
  1. Ill.. Quantity & Types of Materials(35 III. Adm. Code i80.202-b-3)
  2. IV. Quantity & Types Emissions(35 lii. Adm. Code 180.202-b-4)
  3. V. Drinking Water Regulations Variance(35 III. Adm. Code i80.202-b-5)
  4. VI. Assessment of Adverse Environmental Impacts,(35 Ill. Adm. Code 180.202-b-6)
  5. VII. Hardship Statement(35 III. Adm. Code i80.202-b-7)
  6. VIII. Description of Compliance Procedures and Timetable
  7. (35 IH. Adm. Code 180.202-b-8)
  8. VIII. Alternative Methods of Compliance
  9. (35 III. Adm. Code 180.202-b-9)
  10. IX. Variance Duration (35 III. Adm. Code 180.202-b-i 0)
  11. X. Previous Variances (35 III. Adm. Code 180.202-b-il)
  12. Xl. Status of Current Permit (35 III. Adm. Code 180.202-b-i2)
      1. & Facilities
      2. II. First analyze capabilities of Blo-roughing side of Treatment Processes~
      3. I. Raw Wastewater Flows and Loadings
      4. A. Compile Present Day Flows and loads

ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
September
11, 2003
City OfLincoln, IL
)
)
Petitioner,
)
)
v.
)
)
IEPA-03-00l
ILLINOIS ENVIRONMENTAL PROTECTION
)
AGENCY,
)
(Provisional Variance- Water)
)
Respondent.
)
).
Re:
Provisional Variance From
35
Ill. Adm.
Code 302.2 12 For Ammonia Nitrogen,
304.120(b) For CBOD5, And 304.141(a) For Suspended Solids
NPDES Permit # 1L0029564
Dear Mr. Eaton:
The Agency has completed its technical review of the aftached provisional variance
request submifted by the City ofLincoln on September 2,
2003.
Based on the re~~iew,
the
Agency GRANTS the requested provisional variance subject to
specific conditions set
forth below for a period of45 days.
The City of Lincoln seeks a provisional variance to allow yard piping modifications
around the aeration basins and tertiary filters as part ofa major upgrade at its wastewater
treatment plant.
Units that will remain in
operation during the term ofthe provisional
variance include: primary clarifiers; trickling filter; secondary clarifiers; excess flow
clarifier; excess flow chlorine tank; and effluent flow measurement/sampling facilities.
Upon completion ofimprovements, the wastewater treatment facility will be equipped to
comply with more stringent effluent limitations for ammonia nitrogen.
In addition, the
current design average flow will be increased
from 3.35 millions gallons per day (MGD)
to4.19MGD.
The Agency’s review ofthe requested provisional variance has concluded the following:
1.
The environmental impact from the proposed activity should be minimal;
2.
No other reasonable alternative appears available;
3.
No public water supplies should be
effected;
4,
No federal regulations will preclude the granting ofthis request; and

5.
The City will face an arbitrary and unreasonable hardship if the request is
not granted.
The Agency hereby GRANTS the City of Lincoln a provisional variance from 35 Ill.
Adm.
Code 302.212 for ammonia nitrogen, from 35 Ill. Adm.
Code 304.120(b) for
CBOD5, and from 304.14 1(a) for total suspended solids
for a period of 45 days beginning
September
15,
2003 subject to the following specific conditions:
A.
During the variance period, the City’s effluent shall meet the monthly
average concentrations of40 mg/l
for CBOD5, 50 mg/i fortotal
suspended
solids, and
15 mg/I for ammonia nitrogen.
B.
The City shall notify Roger Calloway ofthe Agency by telephone at
217/782-9720 when construction starts and again when construction ‘is
completed.
Written confirmation ofeach notice shall be sent within five
days to the following address:
Illinois Environmental Protection Agency
Bureau of Water
Water Pollution Control
Attention:
Roger Callaway
1021
North Grand Avenue East, MC #19
P.O.
Box 19276
Springfield, Illinois 62794-9276
C.
The City shall sign a certificate of acceptance ofthis provisional variance
and forward that certificate to Roger Callaway at the address indicated
above withinten days ofthe date ofthis order.
The certification should
take the following form:
I (We)
,hereby accept and agree to be
bound by all terms and conditions of the provisional variance
granted by the Agency in
_____________
dated
Petitioner
Authorized Agent
Title
Date

D.
The City shall continue to monitor and maintain compliance with all other
parameters and conditions specified in its National Pollutant Elimination
Permit No. IL 0029564.
Enclosure
CC:
IPCB, Clerk•
Joseph B.
Svoboda
ChiefLegal
Counsel

September
1,
2003
ENVIRONMENTAL
MANAGEMENT
CORPORATION
150 WEST
KICKAPOO
LINCOLN, IL 62656
(217) 732-4030
By
this submittal,
the
City
of Lincoln,
IL is
submitting
an Application for Provisional
Variances
for
the
Wastewater
Treatment Facility.
The
provisional variance
is intended to
allow the
City to
make
required yard
piping
modifications
around
the
existing
Aeration
Basins
and
Tertiaiy
Clariflers
in
conjunction with the
Wastewater
Treatment System Improvements
Project. The City
intends
to begin
the
modifications
on or about
September
15,
2003.
The
intent ofthe project is
more fully described
in the
attached
Application
for Provisional
Variances.
Enclosed please
find
the following
documents
associated with the City’s Application for Provisional
Variances:
1.
Application for Provisional
Variance
2.
AttachmentA
Basis ofDesign
3.
Attachment B
Process Flow Schematic
4.
Attachment C
Facility Plan
5.
Attachment D
-
Yard Piping Plan
Two (2) Copies
Two (2) Copies
Two (2) Copies
Two (2) Copies
Two (2) Copies
The
City
of Lincoln
requests
that
the Agency
issue a Provisional Variance
to the NPDES
permit for
the
referenced project.
If you
have
any
questions
regarding
this
request, please
do
not
hesitate to
contact our consultant
for the project, Joseph Pisula, at Donohue & Associates, Inc. at
217-352-9990.
Please forward a
copy of the variance response documents to
Donohue at the following
office:
115
North Neil
Street,
Suite 213,
Champaign,
IL
61820-4080.
Very tmly yours,
CITY OF LiNCOLN
.~
ii~~~J3
~
Grant
Eaton
WWTF
Facility Operator
SEP
0
2
2003
Illinois Environmental Protection Agency
Division
ofWater Pollution Control
P. 0.
Box
19276
MC #19
Springfield,
illinois
62706
Attention:
Roger
Callaway
Re:
City
ofLincoln, IL
Provisional Variance Application
NPDES Permit #
1L0029564
Dear
Roger:
Cc:
Donohue & Associates,
Inc.

I
Provisional Variance Application
for the
City ofLincoln, Illinois
Wastewater Treatment System Improvements
NPDES Permit No. 1L0029564
September, 2003
L
Applicable Regulations (35
III. Adm. Code 180.202-b-i)
By this Provisional Variance Application, the City of Lincoln formally
requests that
the illinois
EPA
grant
the City
temporary relief from the
CBOD5,
suspended solids,
and
ammonia nitrogen
discharge standards
for the plant as
defined in
35
ill.
Adm. Code 302.
The currentNPDES permit
for
the
facility
stipulates
that
the following
averages
for
CBOD5
and
suspended
solids
to
not
exceed:
Parameter
CBOD5
Suspended Solids
Monthly Average
‘20 mg/!
25 mgfl
Weekly Average
40 mg/I
45 mg/l
The
current NPDES
permit
for
the facility
stipulates
that
the following
averages
for
ammonia
nitrogen to not exceed:
.
I
Under
this
variance,
it
is
proposed
that
during
the
variance
period,
the
monthly
average
for
CBOD5 and suspended solids in
the plant effluent be revised to not exceed the following:
Revised
Revised
Parameter
CBOD5
Suspended
Solids
I Monthly Average
I
40 mg/I
I
50 mg/l
Under
this
variance,
it
is
proposed
that
during
the
variance period,
the
monthly
average
for
ammonia nitrogen in the plant effluent be revised to not exceed the following:
City of Lincoln, illinois
Wastewater TreatmentSystem Improvements
Donohue #10479
4
Monthly Average
3.4 mg/i
5.2
mg/I
Daily Maximum
7.3 mg/I
10.3
mg/I
Monthly Average
15 mg/l
—1—

II.
Project
Description
(35 III. Adm.
Code 180.202-b-2)
The City ofLincoln is located in Logan County
approximately
35 miles northwest of Springfield,
illinois.
Lincoln’s
2000 population
was
15,369
persons
based
on
US
Census
data. The project
consists
of an expansion
to
the
City’s
wastewater
plant from its
current flow capacity of 3.35
million gallons per day
(MGD) to
a 4.19 MGD capacity.
Currently the plant receives
an
annual
average of 3.6 MGD of flow. The plant
upgrade is also being implemented in
order to
comply
with more
stringent IEPA
effluent discharge
limits
for ammonia nitrogen that
were imposed in
November 2001. The project will have a useful life of 20 years.
The project consists
of general construction
work,
including the following
additional facilities:
activated sludge
aeration basins, a secondary clarifier
tank, sludge dewatering equipment
and its
building,
and a
new
preliminary
treatment
facility.
Modifications
to
the
existing wastewater
facilities
are
proposed
to
include
code-related
improvements
to
the
existing
buildings
and
tankage, plus associated electrical, mechanical, structural, piping ventilating, and instrumentation
and control systems
upgrades.
The Lincoln Wastewater Treatment Facility discharges to the Salt Creek. The Salt Creek has a 7-
day,
10-year low flow of 33.3
cfs
(21.52 MGD)
upstream of the plant discharge
as
indicated by
data provided by the illinois State Water Survey.

Back to top


Ill..
Quantity & Types of Materials
(35 III. Adm. Code i80.202-b-3)
Not Applicable

Back to top


IV.
Quantity & Types Emissions
(35 lii. Adm.
Code 180.202-b-4)
The
Project
involves
modifying
the
process
piping
around
the
existing
Aeration Basins
and
Tertiary Clarifiers. Additionally the Tertiary Clarifier Flow Splitter Structure (Structure 506) will
be
modified
to
bring
it
into
compliance
with
current environmental
regulations
The
General
Contractor
(Femily
Dickerson)
on
the Project anticipates that
the
Aeration Basins
and Tertiary
Clarifiers
will
need
to
be
bypassed for
22
working days
(30 calendar
days)
to
complete the
required piping modifications. Modifications
to the Tertiary Clarifi~r
Flow
Splitter Structure will
be completed
during the
same time that the piping modifications
are being made.
It
is expected
that
the
concentration
of
CBOD5,
suspended
solids,
and
ammonia
in
the
plant’s
effluent
will
increase
during
the
project,
due
to
bypassing
flows
around
the
Aeration
Basins
and
Tertiary
Clarifiers.
As
the calculations
in
Attachment “A”
indicate,
it expected that the Trickling Filter
and Primary
Clarification
will
achieve
61
removal of the BOD
in
the
raw influent
wastewater.
Effluent
CBOD5
concentrations
are
estimated
at
40
mg/i
based
on
an
assumed
influent
CBOD5
concentration of 118
mg/i.
Effluent
suspended
solids
concentrations
are
estimated
at
50
mg/I
based
on
an
assumed
suspended solids concentration of 170 mg/l
into the trickling filter’s
secondary clarifiers.
City of Lincoln, illinois
Wastewater Treatment System Improvements
Donohue#10479
-2-

Bypassing the
activated
sludge process will result in
the loss of the
nitrification process
in the
Aeration
Basins.
The
1935
era
trickling filters
were
not designed for nitrification
and
will not
reduce the
influent
ammonia concentrations. Based
on
the
significant impacts
to
the
facility’s
nitrification
process
effluent
ammonia
nitrogen concentrations
are estimated at 15
mg/I based on
an assumed influent ammonia nitrogen concentration of 15 ingfl.

Back to top


V.
Drinking Water Regulations Variance
(35 III. Adm.
Code i80.202-b-5)
The
Project involves
improvements
to
the
City’s
Wastewater
Treatment
System.
No
project
-
activities
are
related
to
the
City’s
public
water
supply.
Therefore
this
portion
of the
Illinois
Administrative
Code is not applicable to this project.

Back to top


VI.
Assessment of Adverse Environmental Impacts,
(35 Ill. Adm.
Code 180.202-b-6)
The
modifications
to
the
yard
piping
around
the
Aerations
Basins
and
modifications
to
the
Tertiary
Clarifier
Splitter Box
(Structure 506)
are
expected to
take place around September
15,
2003, during dry weather conditions.
During these times
it expected
that the influent flows
and
loadings
should be
below
the
original
design
loadings of the plant.
With the
existing Primary
Clarifiers,
Trickling
Filter,
and
Secondary
Ciarifiers
in
operation,
the
project
construction
sequencing attempts to minimize impacts on the facility’s treatment process.
Also
important to
note is that illinois EPA has indicated that the
Salt
Creek is not listed on the
303(d) list as
a protected water ofthe State of Illinois.
Therefore, it is not expected at this time
that any Total Maximum Daily Load (TMDL) limitations will be put in place for this stream.

Back to top


VII.
Hardship Statement
(35 III. Adm. Code i80.202-b-7)
The Project involves yard piping modifications
around the existing Aeration Basins and Tertiary
Clarifiers. Additionally,
the existing Tertiary
Clarifier Flow Splitter Structure will be modified to
bring it into compliance
with current environmental regulations. The yard piping and flow splitter
modifications
are
estimated
by
the
General
Contractor’ (Femily-Dickerson)
to
take 22
working
days (30 calendar days) to complete.
During this time, the facility’s capacity to remove CBOD5,
suspended solids, and ammonia nitrogen will be reduced.
A detailed construction sequencing
schedule was provided
as
part of the
construction documents
for the Project. The construction sequencing schedule required that the Contractor provide bypass
pumping from the Aeration Basins to the Secondary
Clarifiers while the Secondary ClarifierFlow
Splitter (Structure 506) was out of service. The modifications
to the Flow Splitter are
required to
bring
the
structure
in
compliance
with
current
environmental
regulations.
Modifications
to
the
Splitter Structure are
structural in nature and require all flow to the structure to
be shut-off while
the modifications are completed.
The
General Contractor
(Femily
Dickerson) for the project has expressed
concerns regarding the
ability to complete the required yard piping modifications
while the Aeration Basins and Tertiary
City of Lincoln,
Illinois
Wastewater Treatment System Improvements
Donohue#10479

Clarifiers
remain in
operation.
Femily
Dickerson has
stated
that they believe
it is
necessary to
bypass flows
around the entire activated sludge
process while the yard piping
modifications
are
completed. Presently there is no way to isolate the pipes and these pipes must
remain
in service
‘for the
Activated Sludge Process
to operate.
Thus, bypass
pumping
around the Tertiary Clarifier
Flow
Splitter
Box
will not
facilitate the
required yard
piping
improvements necessary for
the
project.
The provision oftemporary wastewater treatment facilities to replace that capacity would place a
severe
hardship
on
the
City.
Such
facilities
could
include
a
temporary
package
wastewater
treatment
plant or the trucking of the City’s wastewater to another wastewater treatment facility.
The cost ofthose options could easily exceed the City’s annual budget for operating the facility.
Therefore, the Implementation ofthese temporary treatment methods is considered not financially
feasible.

Back to top


VIII.
Description
of Compliance Procedures and Timetable

Back to top


(35
IH. Adm. Code 180.202-b-8)
A.
Compliance Procedures
To ensure that proper treatment of the wastewater occurs during the project,
the Contractor will
be required to follow the work sequence detailed in the Project Documents.
The Activated Sludge
Process Facilities will be taken out of operation to make the modifications to it for a period of
22
working days (30 calendar days) in conjunction with the Improvements Project.
All plant
flows
up
to 6.3-MGD
will treated utilizing the existing
Primary Clarifiers, Trickling
Filter, Secondary
Clarifiers,
Excess
Flow
Clarifier,
Excess
Flow
Chlorine
Contact
Tank,
and
Effluent
Flow
Measurement/Sampling
Facilities.
The
Aeration
Basins,
Tertiary
Clarifier
Flow
Splitter
and
Tertiary
Clarifiers
will
be
taken
out
of
operation
to
facilitate the
yard
piping
modifications
necessary for these
structures in
conjunction with the Improvements Project.
Wastewater flows
in
excess of
6.3
MGD
would
be
captured
and
treated
by
the
existing Excess
Flow
Facilities.
Doing
this
will ensure
that the
facility’s
treatment process continues
to
operate
effectively
and
environmental impacts are
minimized.
B.
Timetable
The
Contractor has been
directed
to complete the modifications
to the yard piping
and Tertiary
Clarifier
Flow
Splitter
(Structure
506)
within
22
working
days
(30
calendar
days)
after
commencing work on those modifications.
It is expected that the modifications will begin around
September
15, 2003.

Back to top


VIII.
Alternative Methods of Compliance

Back to top


(35 III. Adm. Code 180.202-b-9)
Alternative
methods of compliance
include
a
temporary
package
wastewater treatment
plant or
the trucking of the City’s
wastewater to another wastewater treatment facility.
The cost of those
City of Lincoln, Illinois
Wastewater Treatment System Improvements
Donohue#10479
4..

options could
easily exceed
the
City’s
annual budget for operating
the
facility.
Therefore,
the
implementation of these alternative methods ofcompliance is considered not fmancially feasible.

Back to top


IX.
Variance Duration (35 III. Adm.
Code 180.202-b-i 0)
The City ofLincoln
formally
requests that the ProvisionalVariance be issued for a duration of45
consecutive calendar days.

Back to top


X.
Previous Variances (35
III. Adm.
Code 180.202-b-il)
The
City
of
Lincoln
has
not
requested,
nor has
received
any
provisional
variances
for
its
wastewater system within the previous calendar year.

Back to top


Xl.
Status of Current Permit (35 III. Adm.
Code
180.202-b-i2)
The
City’s
Wastewater
Treatment
Facility
is
currently
operating
under
NPDES
Permit
No.
1L0029564,
which was made effective on
October
1, 2001.
That permit remains in
effect until
September
30, 2006.
City of Lincoln,
Illinois
Wastewater TreatmentSystem Improvements
Donohue#10479
-5-

ATTACHMENT “A”
Basis
ofDesign
Current Conditions
and
Facilities
Client:
Environmental Management
Corporation
Project:
Wastewater Treatment and Sewer System
Improvements
-
Variance Permit
Donohue Project No.
10479
Revised:
May 29,
2003
Task:
Process Calculations-Current Flows
& Facilities
1996-98 Population Equivalent
of plant,
based on BOO
=
1996-98
Population Equivalent of plant, based on SS
=
1996-99 Design Avg.
Flow
=
1996-99 Maximum
Monthly Flow
=
Maximum Weekly
Flow
=
Maximum
Daily Flow
=
Design
Peak Hourly Flow
=
1996-99 BOO load at avg day
=
1996-99 SS
load at avg day
=
1996-99 NH3-N
load at avg. day
=
Est.
1996-99 Avg
Daily TKN
load
=
Est.
1996-99 Avg.
Daily Phos.
load
=
1996-98
Max
Daily BODload
=
1996-98 Max.
Daily SS
load
=
Max
Daily
NH3-N
load
=
Est.
1996-98 Max.
Daily TKN
load
=
Est.
1996-98 Max.
Daily Phos.
load
=
MGD (same as
listed on NPDES permit)
MGD
MGD
MGD (Pump Capacity)
MGD (Pump Capacity)
lb CBOD/day
lb SS/day
lb NH3-N/day
lb TKN/day
lb P/day
lb CBOD/day
lb SS/day
lb NH3-N/day
lb TKN/day
lb
P/day
RESULTING
DESIGN AVG,
RAW
INFLUENT CONCENTRATIONS
118
mg/I
BOD
170
mg/ISS
15
mg/I NH3-N
10
n.~~/l
P
(estimated)
II.
First analyze capabilities of Blo-roughing side of Treatment Processes~
NOTE:
Plant upgrade
in
1977 routes
75
of the flow through Bio-roughing
stage first before discharge into Act.
Sludge
System
Al.
Flow and
loading
split into
Raw Sewage Pumps
inside
“Pump & Service
Bldg’
10479.315
Final Variance Basis of Design.xls
Percentage of split to blo-roughing side
=
100.0
I.
Raw Wastewater
Flows and Loadings
A.
Compile Present Day Flows and
loads
19,412
23,730
3.35
4.19
5.03
6.30
6.30
3,300
4,746
428
570
279
6,635
11,729
871
1,162
647
p.
1
-
1

ATTACHMENT “A”
Basis of Design
Current
Conditions
and
Facilities
Bio-roughing side Current Design iwg. i-low
=
.s.35
MGD
Design
Maximum Monthly Flow
=
4.19
MGD
Maximum Weekly Flow
=
5.03
MGD
Maximum Daily Flow
=
6.30
MGD (Pump Capacity)
Design Peak Hr.
Q to
bio-roughing side
=
6.30
MGD (Pump Capacity)
Peak instantaneous Flow
=
0.00
0
BOO load to bio-rough side at Design
Avg
Flow
=
3,300
lb CBOD/day
SS
load to bio-rough side at Design Avg Flow
=
4,746
lb SS/day
NH3-N
load to bio-rough side
at Design Avg.
Flow
=
428
lb NH3~N/day
BOD load that bypasses bio-rough side at Design Avg Flow
=
0
lb CBOD/day
SS
load
that
bypasses
bio-rough side at Design Avg Flow
=
0
lb SS/day
NH3-N load that bypasses
bio-rough side at Design Avg
Flow
=
0
lb NH3-N/day
BOO load
to bio~roughside at Max.
Daily Flow
=
6,635
lb CBOD/day
SS
load to bio-rough
side at Max.
Daily Flow
=
11,729
lb SS/day
NH3-N load
to bio-rough side
at Max.
Daily Flow
=
871
lb NH3-N/day
BOD that bypasses
bio-rough side at Max.
Daily Flow
=
0
lb CBOO/day
SS that bypasses bio-rough side at Max.
Daily Flow
=
0
lb SS/day
NH3-N that bypasses bio-rough side
at Max.
Daily Flow
=
0
lb NH3-N/day
A-2.
PumpIng Capacity In Pump and Service
Building
Pump #1
=
556
gpm
Pump #2
=
1,042
gpm
Pump #3
=
1,389
gpm
Pump #4
=
1,389
gpm
Pump totalcapacity
=
4,375
gpm
(with no units out ofservice)
6.3
MGD
Pump firm capacity
2985.92
gpm
(with largest unit out ofservice)
4.3
MGD
B-i.
Compute BOD reduction
in Primary
Clarifiers at max. permitted
Design Avg. Flow
BOO load
to bio-rough side at Design
Avg
Flow
=
3,300
lb CBOD/day
Avg Flow to
Primary Clarifiers
=
3.35
MGE~
Total
primaryclarifier surface area
=
2,080
SF
SSR at Design Avg.
Flow
=
1,611
gpd/SF
CBOD removal
in
Primary Clarifiers at Design Avg.
Flow
=
26
from
chart
-
EPA Stds. App.
E,
Fig.
2
BOD
load out of Primaries at max.
permitted
Avg. 0
=
2,442
lb CBOD/day
B-2.
Compute BOO reduction in Primary
Clariflers at Max.
Daily Flow
10479.315
Final Variance Basis of Design.xls
p.
1
-
2

El
=
Wi
=
V=
F=
No. of trickling filter units
Each trickling filter’s diameter
Surface area of one trickling filter unit
Total surface area of both trickling filter units
lb CBOD/day
gpd
SF
gpd/SF
from
chart-
IEPA Stds. App. E,
Fig. 2
lb CBOD/day
ATTACHMENT
“A”
Basis ofDesign
Curreni Conilitions
andFacilities
BOO load to bio-rough
side at ~ax. uaily i-low
=
b,635
Peak Hour Flow to
Primary Clarifiers
=
6,300,000
Total
primary clarifier surface area
=
2,080
SSR at Max. Daily Flow
=
3,029
CBOD removal in Primary Clarifiers at Max.
Daily Flow
=
20.0
BOO load out of Primaries at Max.
Daily Q
=
5,308
C-i.
Flows and
loadings
into Trickling Filters at Daily Average Flow
As per 35
III. Adm.
Code 370.900-h-2,
use NRC formula on page 706 of WEF MOP 8(1992)
Nat’l Research Council (NRC) formula:
P=
R/O
=
BOD load outof Primaries at max. permitted Avg. 0
=
Wi
=
El
=
lOO#(l+O.OO85x(Wl#VF)°~5)
percent
BOO removal efficiency
BOD
loading into trickling filter, ppd
volume ofIF media, acre-ft
number of passes of the organic mat’l
=
(1+R/Q) ÷
(1+(1-P)
x
R/Q~
weighting factor, 0.9 for military TF plants
recirculation ratio (recirc ~
+
plant flow Q)
2,442
lb CBOO/day
2,442
lb CBOD/day
V
=
media area x media depth
=
=
135
feet
=
14,314
SF
=
14,314
SF
0.33
acres
5.00
feet
1.64
acre-feet
0.9
1.20
recirc cap.
is 3.0 MGD when plant ADF
is
2.5 MGD
Depth of each trickling filter’s
media
=
V
(volume of TF media)
=
P=
lR/Q
=
10479.315
Final
Variance Basis of Design.xls
p.
1-3

ATTACHMENT “A”
Basis ofDesign
Current Condit~onsandFaciliti9
~
El
=
69.7
percent BOO removal in trickling filters
REALITY CHECK
Compute applied
BOO load per volume of media
=
W
+
(VF)
847
lb
BOO per day per acre-ft
34.12
lb BOO per 1000 cu-ft
BOO load out of Secondary Clarifiers at Design
Avg. Q
=
739 lb CBOD per day
26
mg/I CBOD
C-2.
Flows
and loadings into Trickling Filters at Max.
Daily Flow
As per 35
Ill. Adm. Code 370.900-h-2,
use NRC formula
onpage 706 of WEF MOP 8(1992)
Nat’l Research Council
(NRC) formula:
El
=
lOO÷(l÷O.OO85x(Wl.z~VF)°~5)
El
=
percent BOD removal efficiency
Wi
=
BOD loading into tricklingfilter, ppd
V
=
volume of TF
media, acre-ft
F
=
number of passes of the organic
mat’I
=
(l÷R/O)
+
(i+(l-P)
x
RJQ~
P
=
weighting factor, 0.9for militaryIF plants
R/O
=
recirculation ratio
(recirc 0÷
plant flow 0)
BOO load out of Primaries at Max.
Daily Q
=
5,308
lb CBOD/day
Wi
=
5,308
lb CBOD/day
V
=
media area x media depth
No
of trickling filter units
=
~
Each trickling
filter’s diameter
=
135
feet
Surface
area of one trickling filter unit
=
14,314
SF
Total surface area of both trickling filter units
=
14,314
SF
0.33
acres
Depth of each trickling filter’s
media
=
5.00
feet
V
(volume of TF
media)
=
1.64
acre-feet
Pr
0,9!,
R/Q=
1.20
Fr
1.75
10479.3 15
Final
Variance Basis of Design.xls
p.
1
4

ATTACHMENT
“A”
Basis ofDesign
=
.
.
.61.0
percent BOD removal in trickling filters
Current Concutions andFacilities
BOO load out of Secondary Clarifiers at Max.
Daily Q
=
2,071
lb CBOD per day
39
mg/i
CBOD
C-3.
Flow and
loading Into Secondary Ciarifiers
No. of Secondary Clarifiers
=
2
Secondary Clarifier #1’s diameter
=
40
feet
Surface area of Secondary Clarifier
#1
=
1,257
SF
Percent of total
=
39
Secondary Clarifier #2’s diameter
=
50
feet
Surface area of Secondary Clarifier #2
=
1,963
SF
Percent of total
=
61
Total Secondary Clarifier surface
area
=
3,220
SF
Average Flow to Secondary Clarifiers
=
3,350,000.00
gpd
Existing Surface
Settling Rate (SSR)
=
1,040
gpd/SF
Design Peak
Hr. 0 to bio-roughing side
6.30
MOD
6,300,000
gpd
Existing
Surface Settling
Rate (SSR)
=
1,956
gpd/SF
10479.315
Final Variance Basis
of Design.xls
p.
1
-
5

-
-~
~-~:
...-..
GIN.
siN
l~’~p
/(~
;:?.r
______
GIN
h~
~
L__
“~“
N
FILSE
~
~
~=
N
~
~
~
\
j
L.
SLUDGE
CRYING
I
—REDS
i:,—
It!
4,
I
~.—
~
~
~“
~
~“
~
S~t-_~
.~
“-.=GESUIa
P
POSED
RETO*N SLL~$S~
$,RoPps*Dk
5
0
~
.RmrwN
I
SLqoospRwo~
Cr
MED
511G0’
_____
C5D~
_____
.31
PING
CLUE:
CO.
,~.
/-.
~!I~’DATh
~
o
COMEAçON;
‘..
YOU.
.WIN U
~IOP
.033 N~5
___________
~
:~.R’8’M#W
_________
101033
P15W
-
___________
DOOM
RAW
SE
EARL
gdi,EOUIN
rrR.R.~2tia~
~
oc,.ottE
P1W
___________
_~IS?INO
PARSIIALL
E~II~VACO4TOft
STRUCTIIP.E
\
‘V
.SELUIWP
SIMTOR
EXISTING ~5 PROPOS!O
RAW
3EtUfl
5I.UOGC.-_.,
$
,._-
tpC,LwO
001CR
ErtnvEqr
-_.~.
EXISTING
P1WA
ANAEROBIC
DIGESTER
~OC~7~D
.3100W
DIR
STIR
P
OSED
C1RC0L~.
~
~
-
PUMP
STATiON
‘—‘-3
~
F-”~
,—OWE#S,000
DAM
PPOAOS’CO 3J~
RUBICON
I
CHANNEl
I
~
ir
PROPOSED
/
I
I
UE003’#R1~
EKCESS
~1
I~~~SE~”\
FLOW CHLORINE
CONTACT
~
j1~k~O’POSEb.
SLUORE
/,JI,MEs
\
~ii
/
I
(CESS
FLOW
ORYINT1
GALA
IA.t7G1I0
I
~
~
V~
~
f
NOTE’
ALL SThUCTLINEG
N
PIPING
WEST
OF’ THE,
TiIIBICON
C~0NELN-THE 5L103r
550005 HEOS
CAST
OFT~
CHANNEC
ARE
PRESENTLY
0019110
CONThACT
RUEICON
CHANNEL
~
.-
•~
.-,.
:~TI.
.1
~

Back to top